MGMT 5205
MGMT 5205
Cohort: MBAG/22A/PT
Duration : 3 Hours
Instructions to Candidates:
1. This question paper consists of Section A and Section B.
2. Section A is compulsory.
3. Answer any four (4) questions from Section B.
4. Always start a new question on a fresh page.
5. Total Marks: 100
Sbmf-Aug/Sept2023Ex-PM
Project Management (MGMT5205) Page 1 of 5
SECTION A: COMPULSORY
(i) Draw a network for the project using the activity on node approach. You may use an
algorithm to determine the graphical logical dependencies among the activities.
(10 marks)
(ii) Outline the main skills that a Project Manager should possess. (9 marks)
(iii) Using brief notes explain the difference between a project and an operation.
(9 marks)
.
Sbmf-Aug/Sept2023Ex-PM
Project Management (MGMT5205) Page 2 of 5
SECTION B: ANSWER ANY FOUR (4) QUESTIONS
QUESTION 2: (18 MARKS)
A Project has adopted Earned Value Method for the management of cost. The forecasted
duration of the Project is 10 months and the following cumulative planned value (PV) of
project cost are available:
End of 1 2 3 4 5 6 7 8 9 10
Month
Cumulative 100 200 300 400 500 600 700 800 900 1000
PV (000)
(ii) At end of Month 5 the actual cost of the project was Rs 575 000 and 55 % of the
project was completed. Determine EV, CV, SV, CPI, SPI and EAC for this project.
Assume that for this project cost performance will not change in the future.
(12 marks)
Sbmf-Aug/Sept2023Ex-PM
Project Management (MGMT5205) Page 3 of 5
QUESTION 4: (18 MARKS)
(i) Explain the different types of organizational structures and compare how projects are
tackled differently in these different organizations. (9 marks)
(ii) As a project Manager what are the tools and techniques that you can consider
available to you to estimate activity duration for any particular project. Give a fully
detailed answer. (9 marks)
Sbmf-Aug/Sept2023Ex-PM
Project Management (MGMT5205) Page 4 of 5
Activity Dependency Normal Crash Normal Crash
duration duration cost cost
(days) (days) Rs Rs
A - 2 1 22000 22750
B - 3 1 30000 34000
C A,B 2 1 26000 27000
D C 4 2 48000 49000
E D 4 2 56000 58000
F B 3 2 30000 30500
G F 5 2 80000 84500
H E,G 2 1 16000 19000
(ii) Comment on the 3 point estimate technique used in Program Evaluation and Review
Technique (PERT). (9 marks)
(ii) Explain the functioning of Pareto analysis as a tool for the control of quality.
(9 marks)
Sbmf-Aug/Sept2023Ex-PM
Project Management (MGMT5205) Page 5 of 5