D11 vs. D11T Performance Report
D11 vs. D11T Performance Report
Performance Report
May 2019
Objectives: Evaluate the productivity and the fuel efficiency of the D11T vs. the new D11.
Abstract
The new D11 demonstrated 5%-9% improvement in productivity and 7%-10% in fuel efficiency over the D11T. These
improvements aligned with predictions based on the machine performance analysis and provided confidence in the
production study results. The improvements on the new D11 result from optimized hydraulics for better system efficiency,
extended pitch tilt cylinder option for greater load capacity and productivity, the new stator clutch torque divider for
improved drivetrain efficiency, high-horsepower reverse for faster return speed on grade, and improved retarding for
faster cycle times. The results show that across a wide range of applications, the new D11 is more efficient and productive
than the D11T.
• Day 1: The test area was approximately 320 ft (98 m) wide and 275 ft (84 m) long at the start. Each slot was staked
out to be approximately 25 ft (7.6 m) wide, with 15 ft (4.6 m) between slots, enabling each tractor to push 4 total slots
with as little mixing of the fill volume as possible. The slope on the first day was an average of 8% downhill.
• Day 2: The space limited the testing to only 1 slot for each tractor. The slope was on average 30% downhill and the
length of the slot was approximately 250 ft (76 m). The material on Day 2 had not been blasted and required more
material be pulled from the top rather than front-to-back dozing, however each tractor used the same technique.
• Day 3: The test area was approximately 250 ft (76 m) wide and 365 ft (111 m) long at the start, with the first 2/3 flat.
The machines were able to load the blades on the flat using front-to-back dozing, then push uphill on an average of
18% slope. Each tractor pushed 3 slots, then the area was surveyed, and the berms were removed overnight.
• Day 4: The test area was approximately 180 ft (55 m) wide and 450 ft (137 m) long at the start, with the first 6/10 flat.
The machines were able to push uphill on an average of 19% slope. Each tractor pushed 2 slots before surveying.
The test area was surveyed at the beginning and end of each day, providing a clear definition of both the cut and fill areas.
The material was measured before and after each set of slots were pushed, prior to berm removal. Because there was
some mixing of the fill volumes, the cut volume was used for all production calculations, which are therefore reported as
bank volume.
Time Measurement
Study time was recorded in 2 segments, Dozing and Return. The time spent performing unproductive tasks, such as ripping
and prying out large obstructions impeding the normal cycle, was removed from the total production time. The data was
recorded with both digital stopwatches, as well as via a GPS-based cycle tracking system. The two methods were then
compared to validate the accuracy of the data and to enable more granular analysis of the test results.
Volume Measurement
Test areas were drone surveyed before and after each series of tests. Pit volumes and centroidal push distances were
calculated for each pit in the test. The survey, centroid and volume calculations were done be an independent third party.
The cut volumes were used for all production calculations, and the unproductive working time was excluded for direct
comparisons of hourly production rates between tractors.
Image 2: Day 1 cut and fill areas, as reported from survey results
Figure 3: Sample actual centroidal push distance measurements for first 2 slots on Day 1
Fuel Measurement
Fuel measurement was simplified for the purposes of this testing because both machines are running the same fuel
system. The onboard computers on each tractor calculates a total fuel burn in real time as fuel is delivered to the engine.
The fuel burn totals were recorded at the start and stop of each pit. The fuel burn rate was then calculated for the total
testing time, excluding any idle time/delays for communicating with operators that was recorded during the study period.
The time spent performing work, such as prying out large rocks, was included in the testing time for the calculation of fuel
burn rate, but excluded from the production rate calculations, as stated above.
CAT, CATERPILLAR, LET’S DO THE WORK, their respective logos, “Caterpillar Yellow”, the “Power Edge” and Cat “Modern Hex” trade dress as well
as corporate and product identity used herein, are trademarks of Caterpillar and may not be used without permission.
May 2019
© 2019 Caterpillar
All Rights Reserved