Cost
Cost
DEFINITION
Cost management plan is a component of a
project management plan that describes how
costs will be planned, structured and controlled
1
Cost Management Plan Content
Units of measure
Control thresholds
Reporting formats
3
Common Estimate Types
Phased
estimate
Project Cost
4
Estimating Techniques –
Advantages and Disadvantages
5
Lessons Learned
Register
ü Use during and after projects.
6
Project Budget
Governance
7
GUIDELINES
Estimate Costs
• Gather estimates for individual work packages.
• Check with the resource supplier to validate assumptions.
• Choose a suitable estimating technique according to context.
• Look for alternative costing options.
• Determine which units of measure to use.
• Consider impact of risks on cost.
• Ensure that cost estimates are assigned to the right account.
• Ensure estimates include resource costs, level of estimate, and a list of
assumptions.
8
Cost Baseline
DEFINITION
The cost baseline is the approved version of the
time-phased project budget, excluding any
management reserves.
9
Cost Baseline Project Budget
Cost baseline:
ü Monitors and measures cost
performance
ü Includes a budget contingency
o n t r o l a cc ounts
ü Is tailored for each project c
activitmanagement
y cont
reserve
Other components of the project ingenc
y rese
budget are depicted at right.
control accounts rve
e s ti m a te
ti v i ty c ost
ac contingency reserve
work package estimates
10
GUIDELINES
Estimate Budget
11
GUIDELINES
• Gather inputs to establish the baseline e.g. WBS, project schedule, cost
estimates, and risk management plan.
• Assign work to dates on project schedule and allocate funds for each
activity or work package for assigned time period.
• Consider a contingency reserve to cover expenses associated with risks.
• Total the costs for each time period, then plot these on a chart to create an
S-curve of the baseline.
• Publish and distribute the cost baseline to the appropriate project
stakeholders.
12
GUIDELINES
Determine a Budget
• Review:
− Cost management plan
− Scope baseline for project scope statement, WBS, and WBS dictionary
− Risk register to consider any risks that may impact cost estimation
• Check the project schedule for type, quantity, and duration of resources.
• Use appropriate tools and techniques.
• Document the project budget, creating a cost baseline.
• Understand project funding requirements or cash flow to enable the project.
• Update project documents, as needed.
13
Budget Challenges
ü Ideally, budget is set during project
planning and does not change.
14
Response to Budget
Challenges
When changes or challenges occur, you
must tailor:
ü Budget or funding
ü Cost
ü Schedule
ü Scope
15
Funding Limit Reconciliation
DEFINITION
The process of comparing the planned
expenditure of project funds against any limits
on the commitment of funds for the project to
identify any variances between the funding limits
and the planned expenditures.
16
Funding Limit Reconciliation
Keep in mind:
• Most budgets assume
steady incoming and
outgoing flows.
• Large, sporadic
expenditures are usually
incompatible with
organizational operations.
• Funding limits help regulate
A Guide to the Project Management Body of Knowledge
the outgoing capital flow to
(PMBOK® Guide) – Sixth Edition, Project Management Institute,
Inc., 2017, Page 255.
protect against
overspending.
Ongoing Progress Based on Methodology
Traditional - Measure project progress
according to schedule by:
• Monitoring project status to update the schedule.
• Managing changes to schedule baseline.
18
Performance Tracking Techniques
Tool
Based on the Japanese management method of pulling cards to
*Scrum/Agile/Kanban
various stages as they are worked on, physical or electronic boards
boards
can track work as it progresses across various stages or categories.
Measurement of the team’s work that has moved from one stage to
*Throughput Metrics
another stage over a certain time.
Measurement of work that has progressed all the way from plan to
*Cycle Time
completed or delivered.
Various measurements to track quality deliverables, defects, and
Quality Metrics
acceptable output.
Earned Value Tracking cost and effort performance against a planned value.
Bar Charts (Gantt) Using the project schedule to track performance over time.
Measurement of total output from an iteration to attempt to predict
*Velocity
future iteration outputs.
19
Variance Analysis – WHY?
DEFINITION
A methodology that combines scope, schedule,
and resource measurements to assess project
performance and progress.
22
Earned Value Management (EVM)
In projects that use earned value management, the cost baseline is referred
to as the performance measurement baseline.
Planned Value
PV • The authorized budget assigned
to scheduled work.
PV
AC
EV
Earned Value
• The measure of work performed
expressed in terms of the
EV
budget authorized for that work.
Actual Cost
AC • The realized cost incurred for
the work performed on an
activity during a specific time
period.
Schedule
And
Cost Variance
23
Earned Value Management (EVM)
Planned Value
PV The authorized budget
EV = % work complete to date x budgeted cost
assigned to scheduled work.
400
Earned Value
EV The measure of work
performed expressed in
terms of the budget 300
authorized for that work.
$ (K)
24
Estimate to Complete Analysis
Estimate To Complete (ETC) - The amount of money needed to
complete the project.
26
EVM Measures for Cost Control
27
Estimate at Completion Analysis
Estimate At Completion (EAC) - The current projected final cost of the project.
Schedule Cost
*Information Radiators Big visual boards to display in high traffic public locations about the project and the
advancement of the project. The aim is to radiate information to all about the project
work.
*Burndown Chart A graph to show the progress by plotting the burning down of work during an iteration or
other time period.
*Burnup Chart A graph to show the progress and gains made by the project team over time.
Earned Value Management Graphs and values based on the earned value management (EVM) equations.
Reports
Variance Analysis Reports Graphs and their analysis comparing actual results to planned or expected results.
Work performance The physical or electronic representation of work performance information compiled in
reports project documents, intended to generate decisions, actions, or awareness.
Quality Reports Charts and reports based on the quality metrics collected.
**Dashboards Physical or electronic summaries of the progress, usually with visuals or graphics to
represent the larger data set
*Task Boards Physical or electronic depictions of the work that must be done and their current state.
30
Iteration Burndown Chart
Tracks the work to be completed in the iteration backlog
Used to analyze variance to ideal burndown of work committed to during planning
Diagonal line is ideal burndown against which daily actual remaining is charted
31
(Release) Burnup Chart
Visually shows accumulated progress of work completed against plan
Updated after each iteration
Known as ‘Feature Complete Graph’ in Feature Driven Development (FDD)
32
GUIDELINES
33
34
Cost
You are a project manager on a large project that would involve work being
performed across multiple continents. Which of the following factors are most likely
to be the greatest cost risk to the project?
A project manager was successful in his ability to obtain the three most skilled craftsmen within his company
to join the project team in completion of a large industrial turbine overhaul project. The skill and experience
of the craftsmen have manifested positive results. The team has been able to complete the project work faster
than defined in the schedule and at a better cost efficiency rate. The project manager expects the current
conditions to continue throughout the remainder of the project. Which equation should the project manager
use to calculate the estimate at completion value?
Your project sponsor has sent you an email questioning why the project budget and cost baseline
are different. He insists that you have made a mistake in your calculations and that you promptly
adjust the two numbers so that they match. What action should you take?
A. Politely inform the Sponsor that the numbers are correct and that it is normal for the budget and
baseline to be different
B. Increase the cost baseline to match the project budget
C. Compare the project budget and project baseline to determine where the error in calculation was
made
D. Decrease the budget to match the project baseline
Question No: 05 COST MANAGEMENT
A. Estimate Costs
B. Control Costs
C. Plan Cost Management
D. Determine Budget
41
End of
Module 3
42