MOS Structure Lifting Plan
MOS Structure Lifting Plan
Method Of Statement
(Lifting and Installation Plan for Column Structure)
Ref:
Rev: 01
TABLE OF CONTENT
1.Purpose
2.Scope
3.References
4.Definitions / Abbreviations
5.Responsibilities
6.Equipment
7.Procedure
8.Attachment
9.Appendix
Method Statement for (Lifting Doc No:
and Installation Plan for
Date: 29/2/2024
Column Structure)
1.0 PURPOSE
This method of statement defines the procedures for the safe control and operation of crane
rigging at the plant and crane erection activities for all these distillation setup tanks:
A. Equipment List
Method Statement for (Lifting Doc No:
and Installation Plan for
Date: 29/2/2024
Column Structure)
Method Statement for (Lifting Doc No:
and Installation Plan for
Date: 29/2/2024
Column Structure)
Method Statement for (Lifting Doc No:
and Installation Plan for
Date: 29/2/2024
Column Structure)
2.0 SCOPE
This specification requires all parties involved or concern to plan for safety to receive, load,
transport, offload, lift and lower any load. This may include site survey on access road to
provide a well prepare working area for the crane before it arrives at the plant.
Main job activities are to use 1 unit 85 ton mobile cranes to lift and erect the followings.
Note:
-All the cranes deliver to the job site shall comply with the local regulations with valid PMA
issue by DOSH department and competent riggers and signalman.
-The crane operator is a qualified / competent person who is authorized by the lift supervisor
to operate the controls of the crane and meets all the requirements of local regulations.
-The manufacturer capacity chart includes lifting capacities, operating conditions, operating
radius, and boom length shall accompany the crane at the cabin.
-All cranes shall have a load moment indicator and gear lifting appliances shall be inspected
before work.
3.0 REFERENCES
5.0 RESPONSIBILITIES
5.1.1 Qualified Rigging and Lift Supervisor - An individual, with documented training
and experience that has demonstrated proficiency in the skills and abilities
necessary to inspect and certify lifting and rigging equipment.
5.1.3 Qualified Rigger An individual with training and experience that has successfully
completed an appropriate rigging training course and a rigger skills training
course.
5.1.4 Qualified Crane Operator - An individual with training and experience who has
success- fully completed an appropriate rigging and qualified crane operator
crane skills training course. The qualified crane operator shall hold a qualification
card for the type and capacity of crane that they are operating.
6.0 EQUIPMENT
a. Lifting gears –
1. Belt (Sling)
- 10-ton – 10 meter – 2 set (spare)
- 12-ton – 10 meter – 2 set
c. Lorry /Container
d. Forklift
f. Hand tools
7.0 PROCEDURE
7.1.1 Prepare and submit to WKL/Biocon MOS, Lifting Plan attached with JSA.
7.1.2 Ensure WKL/Biocon review, accept, and approve all the related submitted
documents.
7.1.3 Confirm with WKL/Biocon work schedule to carry out the lifting work and apply
for Permit to work.
7.1.4 Display a copy of the Permit to Work at the site work area.
7.1.5 All tools & equipment are subject to inspection by the WKL Safety
Representative.
7.1.6 Mobilization of tools, equipment, and people to setup the lifting work.
Method Statement for (Lifting Doc No:
and Installation Plan for
Date: 29/2/2024
Column Structure)
7.1.7 The main structure for the column was erected earlier on preparation site due to
space issue and for easy maneuver and resume installation. The weight for the
main structure which need to be lifted is 6 ton, while the total weight of the
structure is 12 ton.
7.1.8 On the day of the lifting works, cranes parking location to be decided by lifting
supervisor and crane operator. They will ensure the crane is able to reach the
location. Basically, the 85-ton mobile crane parked location are as per the
respective “PART A: CRANE ARRANGEMENT & MATERIAL
LOADING/UNLOADING” drawings.
7.1.9 Thereafter the 85-ton mobile crane shall park in front of SRP beside the erected
column structure. The working radius for the boom already per-calculated earlier for crane
to pick counterweight and working area. The boom can only be extended when the
operator cab and boom already in position to lifting the structure and materials. Then hoist
the equipment and move to the designated structure and materials for installation.
7.1.10 Rotate and align the structure orientation to the correct and matching angle
alignment to the anchor bolting on the concrete foundation. Please refer to
drawing “PART C: DRAWING FOR COLUMN STRUCTURE” for the
orientation.
7.1.11 Upon completion of successful lifting and installation conduct final inspection
with WKL/Biocon.
a. Proper PPE
b. Safe and proper access
c. Proper lifting slings and belt arrangement
d. Lifting activity follows requirements.
e. Barricade the work area.
f. Practice proper housekeeping
Method Statement for (Lifting Doc No:
and Installation Plan for
Date: 29/2/2024
Column Structure)
7.1.14 Bolt and nut work for structure installation at SRP (top level)
a. Lift the structure and structure materials (platforms, bolts and nuts,
staircases, handrails, etc.) to SRP top level and unpack the cover to
identify the structure materials correctly by parts and functional.
c. After marking, fixed the structure using bolt and nuts using hand tools.
d. The bolt is placed through a pre-cut hole in the structure, after which a
nut is twisted and secured onto the mating thread at the end of the bolt.
e. The steps are repeated till fixed all the structure onto the platform.
f. Final bolt and nut securing was done at the marking floor.
g. The work may need some hand tools and ladder for working purposes.
7.1.15 A-Frame erection, modification, and dismantling work at SRP (Top Level)
a. The A- Frame erected at the structure installation site for accessing high level.
b. The WKL EHS shall be fully responsible for ensuring that all work carried out at
the site meets the Safety, Health & Environment Standards.
d. There is safe access provided for worker to assemble and dismantle A-Frame.
8.0 ATTACHMENT
PART D:
1. CRANE PMA CERTIFICATE, MANUAL & OTHER CRANE DETAILS
(ROADTAX, INSURANCE ETC)
2. CRANE OPERATOR DOSH OYK CERTIFICATE
3. RIGGER AND LIFTING SUPERVISOR COMPETENCIES
4. LIFTING PLAN
9.0 APPENDIX
The picture below showing the lifting method for structure column:
Method Statement for (Lifting Doc No:
and Installation Plan for
Date: 29/2/2024
Column Structure)
Step D: Assemble
the platform and
Step E: Installing the joint member at
hand rail at main main structure.
structure.
Step B: The
structure materials
lifted up to the
installation site
Method Statement for (Lifting Doc No:
and Installation Plan for
Date: 29/2/2024
Column Structure)