5 6282548229238162396
5 6282548229238162396
5 6282548229238162396
me/dailytarget2020
Read the data given in table carefully and answer the question given below.
The table given below shows the cost price (in rupees), selling price (in rupee)s, marked
price (in rupees), percentage profit/loss and percentage discount of 6 different novel A, B,
C, D, E and F in a shop.
Note: In percent profit/loss column, ‘ + ’ shows profit percent and ‘-‘ shows the
loss percent.
Q. 1) If Ali went to the shop and purchase 1 unit of Novel Q and 1 unit of Novel U.
If shopkeeper of the shop marked both the novel 15% above of its CP, then what
is the overall approximate percent profit or loss of Ali in this transaction?
(a) Profit 17.75% (b) Loss of 17.5% (c) Profit of 3.15%
(d) Profit of 8.85% (e) Loss of 3.15%
Q. 2) If shopkeeper of the shop marked novel R by 10% above its cost price and
novel S by 20% above its cost price. Cost price of novel S is half of the cost price of
novel R, then what is the total amount of discount offered by shopkeeper on novel
S?
(a) Rs. 250 (b) Rs. 350 (c) Rs. 300 (d) Rs. 400 (e) None of these
Q. 4) Shopkeeper marked up the price of novel P by 25% above its cost price. If he
offers two successive discounts of 5 % each instead of a single cumulative
discount of 10%, then profit amount when two successive discounts are applied is
how much more or less than the profit amount when single cumulative discount is
applied?
(a) Rs. 14 (b) Rs. 7 (c) Rs. 70 (d) Rs. 17 (e) None of these
Q. 5) What is the ratio of total discount amount offered by the shopkeeper of the
shop on novel T to the total discount amount offered on novel U if shopkeeper
marked novel U up by 18% above its cost price?
(a) 1 : 2 (b) 2 : 3 (c) 4 : 7 (d) 1 : 5 (e) None of these
Set 2
Given below is the bar graph shows the number of days taken by five (A, B, C,
D and E) different machines to complete a certain work. While table shows the
ratio of efficiency of machine D to the efficiency of three men, five women and
eight children in completing the same work. Read the data carefully and
answer the questions.
1) Machine A and E together worked for three days initially, then both
machines stop working due to technical problem. If remaining work completed
by one man & one woman alternatively, starting with man, then in ________
days ______ hours whole work will be completed? (2 Marks)
a. 4 days 25/7 hour
b. 5 days 24/7 hour
c. 3 days 2/3 hour
d. 4 days 27/13
e. None of these
2) The ratio of time taken by one man, one woman and one child alone to
complete the work is ______________ respectively? (2 Marks)
a. 3 : 4 : 12
b. 6 : 5 : 24
c. 5 : 6 : 22
d. 6 : 8 : 21
e. 5 : 6 : 24
3) If ratio of efficiency of the given three men is different and it is in the ratio 5
: 4 : 1 respectively, then number of days taken by least efficient man in
completing the work alone is _______ percent more than number of days taken
by machine A in completing the work alone.
a. 140%
b. 80%
c. 125%
d. 150%
e. 90%
SET 3
It is known that the efficiency of a man, a woman and a child is in the ratio of 6 : 5 : 3
2) Project D is 3/4 of the size of project C . If both the projects get completed
in the same time, what is the number of men allotted to project D?
A. 11
B. 8
C. 15
D. 12
E. None of these
1) If 85% of applicants selected from applicants called for an interview, then how
many non-selected applicants are there who applied for full-time work?
A) 331 B) 341 C) 351 D) 361 E) 371
2) If number of applicants not selected during interview are 6 more than the
number of females selected for full time work but not for shift 1, then find the
value of D.
A) 12.4% B) 15.8% C) 18.6% D) 13.2% E) 16.8%
3) If applicants selected for full time work are 28.6% of number of mails received,
then how many males are selected for full time work?
A) 168 B) 184 C) 170 D) 192 E) 206
4) If number of mails received for full time work are 100 more than the number of
mails received for freelancing work, then applicants selected for freelancing work
are approximately what percent of applicants applied for freelancing work?
A) 29.56% B) 44.82% C) 33.43% D) 41.29% E) 38.67%
5) If 48% applicants did not call for interview, then what is the value of
1) MP of Q = Rs. 4830
SP of Q = 92% of 4830 = Rs. 4443.60
CP of Q = 4830 × (100/115) = Rs. 4200
CP of U = Rs. 1000
SP of U = 92% of 1000 = Rs. 920
Total CP = 4200 + 1000 = Rs. 5200
Total SP = 4443.6 + 920 = Rs. 5363.60
Required profit percent = [(5363.6 – 5200)/5200] × 100 = 3.15% (Approx)
where
∴ Number of men
3)
That means a man can do 6a units of work in a given time
A woman can do 5a units of work in the given time
The child can do 3a units of work in the same time
Women contribute 28%
Number of women = 7
SET 4
Data given in all individual question for the given
graph is interrelated, so, we will determine the
value of all unknown variables by using data
given in respective questions.
From first question:
85% of 780 = C + applicants selected for
freelancing work ...(i)
From second question:
780 - C - applicants selected for freelancing work
= 6 + D% of (A + B) - 126 ...(ii)
From third question:
28.6% of (A + B) = C ...(iii)
From fourth question:
B = A + 100 ...(v)
From (i) and (ii), we get
D% of (A + B) = 237 ...(vi)
From fifth question:
(100 - 48)% of (A + B) = 780
A + B = 1500 ..(vii)
Then, from (v) and (vii), we get
1500 - A = A + 100
A = 700, B = 800
From (vi) and (vii), we get
D% of 1500 = 237
D=15.8
From (iii) and (vii), we get
28.6% of 1500 = C
C = 429
Then, 85% of 780 = 429 + applicants selected for freelancing work
2) Value of D = 15.8%