A Project Report On Predictive Maintenan
A Project Report On Predictive Maintenan
Project Report On
Submitted By
NILESH GAONKAR
NIKHIL PANBUDE
HARSHAL DESAI
Under the guidance of
PROF M.F.ALVI
Submitted as a partial fulfillment of
Bachelor of Engineering
B.E. (Semester VIII), MECHANICAL
[2013 - 2014]
from
Affiliated to
University of Mumbai
CERTIFICATE
This is certify that the project report entitled
“PREDICTIVE MAINTAINANCE AND OVERHAULING OF ROTARY EQUIPMENTS IN
HPCL REFINERY”
Submitted By
NILESH GAONKAR
NIKHIL PANBUDE
HARSHAL DESAI
of Rizvi College of Engineering, MECHANICAL has been approved in partial fulfillment of require-
ment for the degree of Bachelor of Engineering.
Date:
Acknowledgement
I am profoundly grateful to Prof. Ashwani Sharma and Prof. M.F. Alvi for their expert guidance
and continuous encouragement throughout to see that this project rights its target since its commence-
ment to its completion.
I would like to express deepest appreciation towards Dr. Varsha Shah, Principal RCOE, Mumbai and
Prof. Hussain Jasdanwala, HoD Mechanical Dept. whose invaluable guidance supported me in com-
pleting this project.
I express our heartfelt thanks to Mr V.K. Sinha, Sr. Manager (Training) -HPCL Mumbai Refinery, for
giving us his generous approval to perform In-plant project training.
I am particularly grateful to Mr Deepak Chaudhary (Rotary) -HPCL Mumbai Refinery, who guided
me with my project work in the company.
At last I must express my sincere heartfelt gratitude to all the staff members of Mechanical Department
who helped me directly or indirectly during this course of work.
NILESH GAONKAR
NIKHIL PANBUDE
HARSHAL DESAI
ABSTRACT
Rotary equipments are critical, non-substitutable links in production chains of process industries. And
thus by extension the largest consumers of power. The state of functioning of these determine the ulti-
mate production costs and capacity of these industries.
This project aims to provide us with insight in to the condition monitoring and predictive maintenance
of rotary equipments.
Through this project we would perform the key operations concerning rotating equipment design ba-
sis, maintenance, installation and condition monitoring to enable us to:
• Understand the effect of process and environmental changes on equipment operation, maintenance
and reliability
• Condition monitor equipment on a component basis to optimize up-time, mean time between fail-
ure (MTBF) and mean time to repair (MTTR)
• Select, audit and test the equipment that will produce highest safety and reliability in the field for
the lowest life cycle cost.
Contents
1 Introduction 1
2 Literature Survey 2
2.1 Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
2.2 Predictive or condition-based maintenance. . . . . . . . . . . . . . . . . . . . . . . . . 3
2.2.1 Need for predictive maintenance:- . . . . . . . . . . . . . . . . . . . . . . . . . 3
2.2.2 Benefits of Predictive maintenance:- . . . . . . . . . . . . . . . . . . . . . . . . 3
2.2.3 Predictive Maintenance Techniques:- . . . . . . . . . . . . . . . . . . . . . . . 4
2.3 Condition Monitoring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2.4 Vibration Monitoring and Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2.4.1 What is vibration? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2.4.2 Wave fundamentals:- . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2.5 Vibration terminology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
2.6 Vibration Monitoring for Predictive Maintenance . . . . . . . . . . . . . . . . . . . . . 7
2.7 Domains of vibration analysis:- . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
2.7.1 Time domain:- . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
2.7.2 Frequency domain (Spectrum):- . . . . . . . . . . . . . . . . . . . . . . . . . . 9
2.8 Vibration Measuring Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
2.9 Vibration Sources:- . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
2.10 Vibration data collection by CSI 2130 machine health analyzer:- . . . . . . . . . . . . . 12
2.11 Failure detection by vibration monitoring : . . . . . . . . . . . . . . . . . . . . . . . . 15
2.12 Bearing failure parameters:- . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
2.13 Case Study . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
2.13.1 Case Study of Pump 11P8B . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
2.13.2 Case Study of FD Fan SG9 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
2.13.3 Case Study 12Fan1B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
2.14 Rotating Unbalance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
2.14.1 Static unbalance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
2.14.2 Couple unbalance:- . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
2.14.3 Dynamic Unbalance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
2.15 Shaft Alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
3 Proposed Work 33
3.1 Overhauling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
3.2 Pump Overhauling Procedure: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
3.3 Overhauling of mechanical seal:- . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
3.4 Dynamic balancing of the rotor using Abro balancing machine . . . . . . . . . . . . . . 53
3.5 Hydrotest of seals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58
3.6 Shaft Misalignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
3.6.1 Shaft Alignment using Laser kit (ROTALIGN PRO) . . . . . . . . . . . . . . . 60
3.6.2 Shaft Alignment using Dial gauge indicator . . . . . . . . . . . . . . . . . . . . 63
3.7 Dye Penetration test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
6 Conclusion 82
APPENDICES 83
A Project Hosting 84
List of Figures
3.1 Overhauling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
3.2 Steaming of pump . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
3.3 Seal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
3.4 removing casing coverl . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
3.6 hydraulic press . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
Chapter 1 Introduction
Chapter 1
Introduction
Primary purpose of rotary equipments is to pump fluids. Any failure or malfunctioning causes partial or
complete halt of production which is highly undesirable.
System used in industries keep alternate or standby lines ready in such an eventuality. Thus the purpose
of predictive maintenance is to foresee the malfunctioning and thus to repair the equipment before com-
plete failure while using standby line.
HPCLs Mumbai refinery, one of the most complex refineries in the country, is a Lube based refinery
with the highest lube production capacity in India. It employs more than 1500 pumps as well as vari-
ous other rotary equipments. Hence we chose HPCL for performing our project as it would provide us
access to varied types of rotary equipments. Also HPCL has dedicated condition monitoring unit and
maintenance workshop with advance equipments which would provide us with required resources.
Modes of failure of rotary equipments are numerous, few of them are component specific while others
are common. So it is daunting task to determine the exact cause of failures. Also failure is the most ex-
treme stage in equipment lifecycle. Hence the deterioration is to be arrested before this stage, to reduce
repair time and repair cost.
Chapter 2
Literature Survey
2.1 Maintenance
• Breakdown or run to failure maintenance.
• Preventive or time-based maintenance (TBM).
• Predictive or condition-based maintenance.
• Proactive maintenance.
1. Frequency (cycle):-
At point E, the wave begins to repeat with a second cycle, which is completed at point I, a third cycle at
point M, etc. The peak of the positive alternation (maximum value above the line) is sometimes referred
to as the top or crest, and the peak of the negative
Alternation (maximum value below the line) is sometimes called the bottom or trough. Therefore, one
cycle has one crest and one trough.
Units of frequency:-
CPS - cycles per second (Hz)
CPM - cycles per minute (1Hz = 60 cpm)
RPM - revolutions per minute
Orders - multiples of Turning Speed
2.Wavelength :-
A wavelength is the distance in space occupied by one cycle of a transverse wave at any given instant.
If the wave could be froze and measured, the wavelength would be the distance from the leading edge
of one cycle to the corresponding point on the next cycle.
3.Amplitude (A or Xo):-
The height of a wave crest above the reference line is called the amplitude of the wave. The amplitude
of a wave gives a relative indication of the amount of energy the wave transmits.
4.Phase (φ):-
If we consider the two waves as depicted, we find that the waves are identical in amplitude and frequency
but a distance of T/4 offsets the crests of the waves.
This lag of time is called the phase lag and is measured by the phase angle.
• Vibration analysis is one of several predictive maintenance techniques used to monitor and analyze
critical machines, equipment, and systems in a typical plant. As indicated before, however, the use of
vibration analysis to monitor rotating machinery to detect budding problems and to head off catastrophic
failure is the dominant technique used with maintenance management programs.
• Vibration monitoring and analysis are the primary diagnostic tools for most mechanical systems that
are used to manufacture products. When used properly, vibration data provide the means to maintain
optimum operating conditions and efciency of critical plant systems. Vibration analysis can be used
to evaluate uid ow through pipes or vessels, to detect leaks, and to perform a variety of nondestructive
testing functions that improve the reliability and performance of critical plant system.
• In HPCL refinery we are interested in vibration monitoring and analysis of centrifugal pumps,
screw and lobe pumps, compressors, turbines, blowers, motors and fans.
This waveform is so complex that it becomes difficult to study it for detecting a particular failure in the
pump. Hence it is necessary to convert this waveform into frequency spectrum. The example is given
below.
• Frequency-domain data are obtained by converting time-domain data using a mathematical technique
referred to as a fast Fourier transform (FFT).
• FFT allows each vibration component of a complex machine-train spectrum to be shown as a dis-
crete frequency peak. The frequency-domain amplitude can be the displacement per unit time related to
a particular frequency, which is plotted as the Y-axis against frequency as the X-axis. This is opposed to
the time-domain spectrum, which sums the velocities of all frequencies and plots the sum as the Y-axis
against time as the X-axis.
1. All common machinery problems and failure modes have distinct vibration frequency components
that can be isolated and identied.
2. A frequency-domain vibration signature is generally used for the analysis because it is comprised of
discrete peaks, each representing a specic vibration source.
3. There is a cause, referred to as a forcing function, for every frequency Component in a machine-trains
vibration signature.
4. When the signature of a machine is compared over time, it will repeat until some event changes
the vibration pattern (i.e., the amplitude of each distinct vibration component will remain constant until
there is a change in the operating dynamics of the machine-train).
Figure 2.4: The Above fig. shows the relationship of time domain and frequency domain
• Rotor Imbalance:-
While mechanical imbalance generates a unique vibration prole, it is not the only form of imbalance that
affects rotating elements.
rotor-support system (i.e., bearing and bearing pedestals) determine the vibration level.
Rotor-support stiffness is important because unbalanced forces resulting from ow instability can deect
rotating elements from their true centerline, and the stiffness resists the deection.
• Cavitation:-
When the pump suction pressure becomes less than the vapour pressure of the liquid then the liquid
starts to evaporate and hence small air bubbles are formed which when go to high pressure zone of the
pump implodes and hence cause pitting and corrosion of the rotor. Due to the imploding of the bubbles
vibration of very high frequency is created.
The probe mounting techniques are given in the increasing order of their sensitivity towards
high frequency vibrations.
• The displacement, velocity and acceleration characteristics of vibration are measured to determine
the severity of the vibration and these are often referred to as the amplitude of the vibration.
• The relationship between acceleration, velocity and displacement with respect to vibration amplitude
and machinery health redefines the measurement and data analysis techniques that should be used. Mo-
tion below 10 Hz (600 cpm) produces very little vibration in terms of acceleration, moderate vibration
in terms of velocity and relatively large vibrations in terms of displacement.
Hence, displacement is used in this range.
• In the high frequency range, acceleration values yield more significant values than velocity or displace-
ment. Hence, for frequencies over 1000 Hz (60 kcpm) or 1500 Hz (90 kcpm), the preferred measurement
unit for vibration is acceleration.
• It is generally accepted that between 10 Hz (600 cpm) and 1000 Hz (60 kcpm) velocity gives a good
indication of the severity of vibration, and above 1000 Hz (60 kcpm), acceleration is the only good in-
dicator.
• Since the majority of general rotating machinery (and their defects) operates in the 101000 Hz range,
velocity is commonly used for vibration measurement and analysis.
• Sub synchronous:-
These are the vibration frequencies of the order less than the shaft rpm. I.e. for example 0.5x, 0.35x etc.
Failures:-
• Another component in the machine
• Another machine
• Belt drives
• Hydraulic instability
• Oil whirl, oil whip
• Rubs (rotor, shaft, wheel)
• Cage (fundamental train - rolling element brgs)
• Synchronous:-
These vibration frequencies are in the integral order of the shaft rpm. For ex.1x, 2x, 5x, 1000x etc.
Failures:-
• Imbalance
• Misalignment
• Bent shaft
• Looseness
• Blade / vane pass
• Gears
• Non synchronous:-
These frequencies are in the non-integral order of the shaft rpm and are more than shaft rpm. For
ex. 1.25x, 5.3x 11.5x etc. Failures:-
• Another machine
• Belt multiples
• Bearings
• Resonances
• Electrical
• Chains
• Compressor surge
• Sliding surfaces
• Force Unbalance:-
• Couple Unbalance:-
• Dynamic Unbalance:-
2) Misalignment:-
• Angular misalignment:-
• Offset misalignment:-
3) Rotor Rub:-
4) Mechanical Looseness:-
It is defined as the no. of rolling elements i.e. balls passing by any point on the inner race.
For ex: - if BPFI is 5.2 then in one revolution of the shaft, 5.2 balls are passed through a point on the
inner race.
Usually BPFI values are in the range of (4.8x to 11X).
If any defect is there on the inner race then it will be shown in the harmonics of BPFI value.
It is defined as the no. of rolling elements passing by any point on the outer race.
For ex: - if BPFO is 3.5 then in one revolution of the shaft, 3.5 balls are passed through a point on the
outer race.
Range of BPFO values (2.5X to 6X).
If any defect is there on the outer race then it will be shown in the harmonics of BPFO value.
It is defined as the no.of revolutions a ball makes about its own axis in one revolution of the shaft.
For ex: - if BSF is 2.3 then in one revolution of the shaft, every ball makes 2.3 revolutions about its own
axis.
Range of BSF values (2X to 3X).
If any defect is there on the rolling elements then it will be shown in the harmonics of BSF value.
• For bearing failure detection, peak view frequency readings are analyzed.
• Peak view readings are based on the Envelope Acceleration Technology.
• Peak view readings are used to detect bearing failures and cavitation problems, as both occur at high
frequencies.
• Peak view readings are collected only at bearing locations such as bearing housings.
• Peak view frequency > 60,000 RPM.
6) Bent shaft:-
• Turbulent flow:-
• Cavitation:-
Fasteners had entered the impeller. They got stuck on the impeller causing imbalance.
Impeller was pulled out and after cleaning was installed back. Vibration came down to 3 mm/sec.
Types of Unbalance:-
1. Static Unbalance
2. Couple unbalance
3. Dynamic unbalance
Effects of Unbalance:-
• Vibration
• Noise
• Decrease life of bearings
• Unsafe work conditions
• Reduced machine life
• Increased maintenance
1. Offset misalignment:-
• Parallel horizontal misalignment:-
It occurs when the motor shaft is moved horizontally away from the pump shaft, but both shafts are still
in the same horizontal plane and parallel.
2. Angular misalignment:-
• Angular horizontal misalignment:-
The motor shaft is under an angle with the pump shaft but both shafts are still in the same horizontal
plane.
• LOST PRODUCTION
• LEAKING SEALS
• INCREASED VIBRATION
• BEARING FAILURE
• SHAFT BREAKAGE
• COUPLING WEAR
• QUALITY PROBLEMS
Chapter 3
Proposed Work
3.1 Overhauling
The typical overhauling process of centrifugal pump involves checking the:-
• Pump shaft is straight and true to the bearings & seal housing.
• Bearing housing & fits are within tolerance.
• Wear ring clearances are within tolerance.
• Surface finish to shaft sleeves & their fits on the shaft.
• Impeller for erosion, cavitation, corrosion & the fit on the shaft.
• Condition & fit of all keys and keyways.
• Condition of stationary and rotating seals.
• Condition of bearings and lubricants.
• Casing for erosion, cavitation & corrosion.
• Condition of all fastners, seal-faces & gaskets.
• Balance of rotating assembly.
• Condition of the foundations and the holding down bolts.
• Pump , motor & pipe work alignment.
1. Isolate pump electrical circuit breaker on main switch board and attach a warning notice.
2. Switch off and lock pumps supply at its local supply panel.
3. Close suction and discharge valves, chain and lock hand wheels.
4. Open pump suction and discharge pipe drain valves to bilge and when water ceases to flow; crack
open the pipes / pump flange joints carefully to ensure that pump has drained off and is safe for opening.
5. Fix a shackle to lifting pad eye above pump and hang chain block; ensuring SWL of block, slings and
shackles are satisfactory.
6. Use a center-punch to match/mark coupling and casing, then remove the coupling bolts.
7. Disconnect, fix i/d tag and remove motor supply cables; taping over bare ends with insulating tape.
8. Connect shackle and sling to motor eyebolt and lift motor clear of pump using overhead chain block.
Lay motor on its side out of harms way, protecting machined surfaces on both pump and motor coupling
halves against damage. (Cardboard and masking tape is quick and efficient method.)
9. Disconnect all external fittings from pump casing e.g. cooling pipe, pressure gauge, oil reservoirs and
air cock.
10. Remove bolting from top cover and remove cover. Scrape off old gasket and check mating surfaces,
and renew gasket on assembly. (Light smear of grease on gasket / faces)
11. The pump shaft with impeller can be lifted out of casing.
12. Dismantle the impeller, and remove the wear ring.
17. Replace the Wear rings & throat bush if clearances are found more than desired value.
18. Lock the wear ring & maintain the clearance as specified by the vendor.
19. Refer to vibration report and carry out balancing of rotor if suggested.
20. Install the bearings using magnetic induction heater.
21. Install the shaft along with the bearings & tighten the covers.
22. Now check the axial float of the rotor. It should be within 0.002 i.e. (2 Thou).
23. Assemble the seal assembly insert on the shaft.
24. Assemble the impeller & stuffing box.
25. Tighten the impeller with torque wrench. Use the torque as specified by the vendor.
26. Insert the casing gasket & tighten the casing.
27. Hydro test the seal & casing for any leakage.
28. Attach the coupling.
29. Check all the casing nuts are tight.
30. Shift the pump at site.
31. Carry out housekeeping.
Removing the coupling & removing the rotor from pump casing:-
• The coupling should be removed using hydraulic puller. These pullers come with different pres-
sure capacities and different lengths of the forks. Choosing the right puller is also important. Attach the
forks on the coupling flange and position the center piston on the center of the shaft so that after pushing
the piston by hydraulic force, the forks will pull the coupling out.
• Lock nut with lock washer is used to prevent the bearings from sliding over the shaft.
• The lock washer is also called as star washer as it has protrusions all over its circumference.
• The lock nut also has a corresponding groove so that one of the protrusions of the washer can fit into
the groove.
• When one of the protrusions is fitted in the groove, it is bent down to lock the nut & washer assembly.
• It is to be noted that the lock nut is loosened by rotating it in the same direction of the shaft .This is
due to the fact that whenever an obstruction comes between the shafts the lock nut tends to tighten itself
there by justifying its purpose.
Wear rings:-
Clearance measurement:-
Clearances are measured in HPCL using two methods:
• Using shim gauge
• Using Plastic gauge
Shim gauge:-
Shims are very thin but precisely made metal strips .These are used to measure clearances & adjustment
of motors in alignment procedure.
The above fig. shows the usage of plastigauge for checking clearance in split bearing of a fan.
Clearance less than 1 Thou or greater than 1.5 Thou is not acceptable.
This is due to the fact that, for proper working of bearing and long life of bearing, the bearing clearance
is very critical parameter.
Less or more clearance than the specified range may results into
• If the clearance is more, the outer race will tend to rotate inside the upper bearing cover.
• Due to less clearance, there is a pressure on the whole bearing which results in the rubbing of rolling
balls against inner and outer race which not only decreases bearing life but also generates heat.
• If the clearance is more then there is a space for bearing vibration.
• If the clearance is less then, this may result into the ovality of the bearing due to pressure exerted by
bearing cover.
Results of split bearing clearance between I.D of bearing cover and O.D of outer race of the bear-
ing = Clearances of both the bearings are found to be (0.25 Thou)less than 1 Thou which is not
acceptable.
Solution= adding 2 thou shims under the bearing cover to increase the clearance. This method
for checking the clearance is especially used for checking the clearance of split bearings & in the
situation where shim gauges cannot be inserted.
This method is useless where there is no place for the plastigauge to attach or where its not possible
to detach one of the mating surfaces without disturbing the plastigauge. For example: - checking the
clearance between casing wear ring and impeller wear ring.
There are countless variants of shaft seals, reflecting the diversity of the pump industry, and the need for
specific solutions for individual situations. In its most basic form, a shaft seal combines a rotating part
with a stationary part. When properly designed and installed, the rotating part rides on a lubricating film,
only 0.00025 mm in thickness. Should the film become too thick, the pumped medium will leak. If the
film becomes too thin, the friction loss increases and the contact surfaces overheat, triggering seal failure.
Sleeve:-
It is a hollow cylindrical component which fits on
the shaft and protects the shaft from rubbing.
It is the rotating component of the seal.
It also supports collar and retainer to hold fixed
mating surface.
when the seal is disembled for inspection, first the
sleeve along with all rotating components are re-
moved from the gland.
Collar is a hollow thin cylindrical component which is mainly used to attach the sleeve with the shaft
with the help of grub screws. Grub srew grabs the sleeve with the rotating shaft.
Retainer is a cup shaped component which is used to hold the carbon face (Rotating face) pressed against
the helical springs or leaf springs attached in the retainer. The sleeve properly sits inside the retainer on
the step provided on both.
In small pumps , the retainer is replaced by bellows.
During overhauling, the springs are checked for their good condition and stiffness.
In some of the pump seals, we found these springs are broken down by over use and corrosion.
Case study:-
1. The sleeve is damged severly hence it cant be used anymore.Hence it is replaced and checked for
proper clearance.
2. Both the seal faces (hard face and carbon face) are replaced.
3. All wear rings are replaced.
4. Collar and retainer are not damaged hence no need to replace.
5. All scrub screws are intact.
6. Some of the retainer springs were found broken hence they are replaced.
7. All the components are properly cleaned,checked for proper fit and then assembled.
8. Hydrotest is done on both the seals and they were ready for the use.
9. Installed the seals on the pump and assemble the pump.
10 . Install the pump properly in the plant and laser alignment is done.
11 . It was make sure that while starting the pump, all the procedure is strictly followed under the super-
visor.
• First set up the balancing m/c . For that measure the diameters of the regions of the shaft where
the rotor will rest on the rollers of the m/c. Now with the help of adjusting mechanism set up the rollers
on both sides according to the diameters so that the rotor wil remain perfectly horizontal while testing.
• Loosen the alen bolts and adjust the distance between the rollers on which the rotor will rest.
• After the m/c set up, tighten all the bolts properly.
• Now lift the rotor with E.O.T and weigh it.
• Position the rotor on the rollers on the m/c properly.
• Put down the supporting roller members , adjust its position accordingly and lock it.
• Now position the driving belt on the rotor and set up the belt by adjusting the positions of idle pulleys
with the help of adjustment mechanism provided.
• Now circumferentially stick a completely black tape on the smooth (without any obstruction) and free
surface of the rotor.
• Also stick a very thin strip about (0.5 cm thick) radium tape at only one position on the black tape.
• Set up the optical laser sensor at appropriate position above the tape.
• Now taking the current point as 00 mark angular positions (900,1800,2700) on the outer surface of the
rotor using chalk.
• Start the abro software and i/p all the required parameters.
• After inputing all the values, start the m/c.
• Slowly go on increasing the rpm upto operating rpm of the rotor.
• Let the unbalance values be steady.
• Note down the values.
• It is general practice to add balancing weights on rotor of the motor where as to remove the material
from the outer surface of the impeller in case of the pump. Exceptionally, if very large amount of weight
is to be removed then we have no choice than adding the equal amount of weight on the opposite side in
the flow area (Inner surface)of the impeller so as to compensate for the extra weight on the other side.
• After adding or removing the weights, carry out the balancing again and again till the unbalance comes
in the range of acceptable limits.
Rotor type =7
A= 0 mm
B= 1190 mm
C =0 mm
RL= 290 mm
RR=290 mm
Balancing speed =800 rpm
Rounf off (L)= 0.01
Round off(R)=0.01
Tolerance (L)=10.7 gm
Tolerance (R)=10.7gm
Offset angle = 00
Correction method= Remove
(L,R)
Correction mode= Polar (L,R)
Reading no. 1
After removing some material with the help of portable grider.
Reading no.2
As weight to be removed is more hence we decided to add weight of 35.58 gms on opposite side
i.e 289-180= 1090
we added approx. 36 gms
Reading no.4 :-
Now instead of adding 11
gms it is easier to remove it
at 2590 by grinding.
Final Reading:-
Since the unbalance reading is in tolerance hence the rotor is said to be balance.
Leakage Sources:-
In most cases, the seal leakage comes from the sealing interface. However, in some situations, leakage
may come from the secondary sealing area, such as O-rings. This could be due to O-ring degradation
caused by chemical attack, overheating and loss of resilience from compression set. In rare occasions,
the sealing rings are porous and fluid leaks through the bodies. The above leakage problems can be
identified with static pressurization.
Laser alignment coupling results for F.D. (Forced draft) Fan of new boiler house:-
In HPCL Refinery ,the acceptable range for alignment of shaft for coupling readings: -
-5 Thou to +5 Thou
The sum of dial indicator readings of top and bottom is equal to the sum of dial indicator readings
of two sides.
This rule proves to be very helpful in the cases in which there is an obstruction in turning of
dial indicator 360◦.
1. Install the pump properly on the foundation and make sure all the foundation bolts of pump are
properly tight.
2. Two types of shaft misalignments are removed by this method.
3. Always angular alignment of shaft is done first and then radial (Offset) misalignment is done.
4. Initially shaft coupling is not attatched.
5. Position the magnetic base of the dial gauge on the coupling flange of the pump shaft.
6. The base should rest on the front surface where the coupling will attach afterwards.
7. Now touch the pointer of the indicator to the corresponding surface of the flange of the motor shaft.
8. Set the current position as 0 in the dial.
9. Rotate the shaft slowly and mark the readings at 90◦, 180◦ and 270◦.
10. Thses are total indicator readings(TIR).
11. For adjusting flange surface of motor with that of pump,
the thickness of shims to be added or removed = 3 * bottommisalignment reading. 12. Add or remove
required amout of shims thus remove angular misalignment.
13. Now position the base of the dial gauge on the circumference of the the coupling flange of the pump
shaft.
14. Touch the pointer of the dial gauge to the corresponding surface of the flange of the motor shaft.
15. At top position, set the dial at zero.
16. Rotate the pump shaft through 360◦ and mark dial readings at 90◦, 180◦ and 270◦.
17. Add or remove the required amount of shims thus removing the radial misalignment.
The given fig. shows the Aixial (angular) and Radial (offset) misalignment values of an asphalf pump.
• Top:- 0
• Bottom:- -6
• Right:- -7
• Left:- +1
• Top:- 0
• Bottom:- +60
• Right:- -10
• Left:- +70
Pressurized spray cans are the most commonly used package. The cans are easily Carried to the part
to be inspected. There are no brushes to clean; no spillage. Plus, Spray cans protect inspection materials
from contamination. Dye penetrant can be sprayed on a limited area of a part, such as a weld or critical
Section. It can be removed by wiping with a dry towel or a towel dampened with Cleaner/Remover. In
the case of water-washable dye penetrant, it can be removed with A water-dampened towel or by water
spray. The developer is always applied by spraying.
1. Cleaning:-
A clean surface is essential for successful dye penetrant inspection. The surface to Be examined and
adjacent area should be free of such contaminants as ultrasonic Welding flux, weld spatter, scale, rust,
paint, oil and grease. Organic soils, Such as oil and grease, clog cracks and prevent or retard dye pene-
trant entry.
Important -
Following the cleaning process, allow sufficient time for the Cleaner/Remover to evaporate completely
from cracks or other surface Openings before applying Double-Check Dye Penetrant. The evaporation
rate Depends on ambient temperature and humidity.
Spray dye penetrant on clean, dry surface; let stand 5 Minutes or more. If especially tight cracks are
suspected, if there is reason to believe defects are contaminated and not free of soil, or if the substrate is
cold (below 60F), the dye Penetrant should dwell on the surface for a longer time.
4. Developer Application:-
• Before applying developer, vigorously shake the spray can to restore fully the white developer particle
suspension. Spraying is the ONLY recommended method of applying developer.
• The goal is to spray a light, even coat which is slightly damp when it contacts the surface. It should
be slightly damp, so the volatile solvent will couple the flaw-entrapped dye penetrant to the powder and
speed the penetrants return to the surface for viewing.
• But, it should not be so damp as to dilute and over spread the small amount of dye penetrant retained
in the flaw. A too damp developer application results in weak, blurred indications.
Inspection results:-
Chapter 4
Chapter 5
Chapter 6
Conclusion
• The methods undertaken in this project are industry intensive. They help us obtain fairly ac-
curate inferences about the state of the system. It is possible that instrument of measurement
improve with time but not the method of performing analysis, diagnosis and repair, as they have
remained more or less the same over last 50 years.
• The methodology and technology is an exact science, but engineering isnt hence quality of work
depends upon the skill and experience of the performer of monitoring and maintenance operation.
• There are times when different tests produce varying inferences. Under those circumstances,
the diagnosis and repair of fault depends solely on the wit of the maintenance professionals.
• The field of monitoring is heavily sensor dependent hence there is much scope for automation
which would;
⋆ Remove the necessity of monitoring personnel going into difficult or hazardous locations for
monitoring the system.
• As automation gets cheaper it would be more widely used for monitoring purposes.
• The life of a rotary equipments depends upon the coating of internal surfaces and fluid pump.
The proper choice of such coats depends upon the expertise of maintenance professionals.
• Leakage of seals is very hazardous and polluting in petroleum industry hence they require criti-
cal attention. Again, improvements in sensor have improved the quality of inspection.
References
Hand book on Pumps, Exchangers & Fired heaters, HPCL Mumbai Refinery
Appendix A
Project Hosting
The project is hosted at Google Code. The complete source code along with the manual to operate
the project and supplementary files are uploaded.
QR CODE: