Project Execution plan-PEP
Project Execution plan-PEP
00 13/02/2024
Revision Report:
TABLE OF
CONTENT
1. PEP Presentation.............................................................................................................................4
1.1. PEP Objective........................................................................................................................................4
1.2. Responsibilities associated to the PEP................................................................................................4
1.3. PEP Transmission and implementation..............................................................................................4
1.4. PEP Modification..................................................................................................................................4
1.5. Applicable documents...........................................................................................................................4
1.6. Definitions and abbreviations...............................................................................................................5
2. Project Presentation........................................................................................................................5
2.1. Project General presentation...............................................................................................................5
2.2. PEP objectives........................................................................................................................................5
2.3. Project Scope of Work...........................................................................................................................5
2.3.1. Mobilization and demobilization..................................................................................................................6
2.3.2. Mechanical (Prefabrication works)..............................................................................................................6
2.3.3. Piping works...................................................................................................................................................6
2.3.4. Inspection and testing....................................................................................................................................6
2.3.5. Painting works................................................................................................................................................6
2.3.6. Civil works......................................................................................................................................................6
2.3.7. Material management....................................................................................................................................7
2.3.8. Warehouse management...............................................................................................................................8
3. Project Controls................................................................................................................................9
3.1. Project milestones identification.....................................................................................................9
3.2. Preparation of the project schedule................................................................................................9
3.3. Control of planning........................................................................................................................10
3.4. Project costs Management............................................................................................................10
4. Project Quality Management.........................................................................................................10
5. Project Health, Safety and Environment (HSE) Management.................................................11
6. Resources Plan...............................................................................................................................12
7. Construction equipements and special tools...............................................................................12
8. Logistics and site mobilization plan.............................................................................................12
1. PEP Presentation
2. Project Presentation
Painting all recently installed or modified pipe works, as well as production units incorporated
during facility modifications and upgrades.
2.3.6. Civil works
Excavating the earth and building a new concrete foundation base for a new installation.
002/ AP XX/ 10/14
XX
NOAPxx
PROJECT EXECUTION PLAN Rev. 00
PAGE 7 of 11
The arrangement of all reinforcement shall match the specifications outlined in the approved
AFC drawings.
The construction of formwork for pouring the concrete foundation must follow the guidelines
outlined in COMPANY DEPs.
The storage location will be logged into the material management system/software.
All movements of materials will be closely monitored, documented, and updated as
necessary.
Ensuring safe storage practices is the responsibility of the contractor and this to prevent
accidents and damage to materials or other stored items.
Hazardous materials will be appropriately labeled and stored separately, with relevant
Material Safety Data Sheets accessible in the Warehouse.
3. Project Controls
6. Resources Plan
PROJECT site team will be mobilized after the readiness of the base camp and according to the
starting dates of scheduled construction activities.
The project Human Resource Manager prepares the mobilization schedule, project organization
chart, and job descriptions for all key personnel.
Only execution manpower & machinery will be sub-contracted.
Contractor will manage, coordinate and supervise the work of subcontractors, to ensure that the
work is performed on schedule and in accordance to quality and safety requirements, including
preparing detailed schedules for the work in accordance with the project schedule, regular
monitoring of this schedule and making appropriate adjustments to obtain efficient usage of
resources.
With regards to local personnel, after fulfilling all recruitment requirements (medical check,
contract signature…), the whole documentation of the personnel will be transmitted to the
security manager in order to apply for temporary or permanent security clearance.
Regarding working hours, will be fixed according project schedule and standard working
hours. Please refer to Attatchement1: Organisation chart.