1. Learning
2. Learning Library
Share
Abstract
One of the project manager’s key responsibilities is to be aware of the status of the project at
any given time. In order to do that, status meetings become a critical tool throughout the
lifecycle of the project. Too often, unfortunately, these critically important meetings become
unbearably inefficient, ineffective, and at times almost painful! The good news is that there
are simple techniques that project managers can employ to improve the overall efficacy of
these sessions.
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) defines status
review meetings as follows:
Status review meetings are regularly scheduled events to exchange information about the
project. On most projects, status review meetings will be held at various frequencies and on
different levels. For example, the project management team can meet weekly by itself and
monthly with the customer. (PMI, 2004, p. 233)
Indeed, virtually all project managers are familiar with the status meeting. This is one tool
that the project manager uses to “check in” on the project. Typically, the project manager
wants to assess the status of each of the following elements during a status meeting:
Task updates
Schedule status update (Are we behind or ahead of schedule?)
Budget status update (Are we under or over budget?)
Quality/scope status update (Are we maintaining desired scope/quality levels?)
Current or anticipated issues (e.g., changes, risks, resource issues, client
satisfaction issues, vendor issues, etc.)
Next steps
Because the project manager should be able to report up-to-date information to project
sponsors or clients at any time, it’s imperative for the project manager to conduct status
meetings regularly. The frequency of these status meetings will vary depending on several
factors, including (but not limited to) the following:
Project complexity
Number of team members
Level of information required by project sponsor, clients, and others
Project manager’s level of task involvement
Effective status meetings not only benefit the project manager, by providing timely task
updates, but also benefit the entire team, by providing a venue for recognizing milestone
achievements, sharing information, and bringing problems/issues to the team. Unfortunately,
too often these important meetings are ineffective and fail to benefit the project in the manner
intended.
Interestingly, project status meetings that fail invariably seem to possess similar dysfunctions.
Common project status meeting dysfunctions include the following:
Ill-prepared team members – Unfortunately, some team members feel that all they need to do
for a status meeting is show up and participate. When this happens, the entire team wastes
valuable time. Invariably, when a team member is unable to provide feedback on an issue
because of not being prepared, the team typically wastes time speculating about it and
someone is tasked with following up after the meeting and reporting back at the next meeting.
These sorts of delays are not just frustrating; they can actually delay the project!
Poor time management – One of the biggest frustrations team members have with project
meetings is that they often drone on too long (without much getting accomplished). When
time isn’t managed well, additional meetings are often required, which decreases team
member morale and often rushes decisions. All of these can negatively impact not just the
project timeline but also the quality of the project’s product or service. When time isn’t
managed appropriately during status meetings, team members often become tempted to skip
the meeting because they suspect it will be a waste of time and their time will be better spent
other ways. Once team members start missing status meetings, their overall effectiveness
begins to fundamentally break down.
Allowing discussions to veer off topic – This is an extremely common dysfunction during
project status meetings. Quite frequently, topics or issues arise during the sessions that are
outside the intended scope of that meeting. When participants spend more and more time on
topics outside the scope of the meeting, less and less time is available for intended topics.
This often means that the intended agenda topics are rushed or not addressed at all, resulting
in poor quality decisions, delays, communication breakdowns, and the like.
Not getting balanced input from team members – One of the most difficult tasks any project
manager has is dealing with different personalities on the team. More aggressive personalities
can tend to dominate project meetings while more passive types tend to contribute much less
to discussions and tend to be much less vocal about their opinions on a given issue. We’ve all
heard that the squeaky wheel gets the oil, and that’s unfortunately often true during project
meetings. Too often a project manager or team leader will be overly influenced by a team
member with an aggressive personality. When certain team members dominate while others
sit passively (without providing critical input on an issue), the quality of the team’s decisions
suffer. Another major problem with this particular dysfunction is that the project manager
often develops a skewed view of important project issues because one or two people may
voice very strong opinions. Those opinions may not be representative of the group at all, but
without balanced input from the group, he/she may leave the project status meeting with an
inaccurate perspective of the team’s views on a particular issue.
Ineffective handling of action items – One of the important parts of any project meeting is
effective handling of action items. Often, issues come up during the meeting that must be
addressed after the meeting. Too often these action items are casually mentioned verbally,
which often results in meeting déjà vu (where no one follows up on the issue and the issue
continues to resurface in future meetings). Another result of poor handling of action items is
poor follow-up on critical project issues. Action items are the vehicle project managers use to
assign follow up tasks after the meeting. When that process is ineffective, those follow-up
tasks suffer. It becomes much easier for team members to complain that they didn’t know
about the action item, they didn’t understand it, or they didn’t have time to complete it. When
action items aren’t completed in a timely manner, project progress is stalled.
Clearly, these common project status meeting dysfunctions have significant negative impacts
on the progress of the project. While the impacts on schedule, cost, and quality may be
obvious, a more subtle impact is the erosion of the project manager’s credibility with his or
her team. Team members view the project manager as the person responsible for running
smooth, relevant, efficient status meetings. When that doesn’t happen, often the project
manager is deemed to be weak and ineffective. Indeed, the project manager’s ability to run
effective status meetings not only directly impacts the progress of the project but also
influences how he or she is perceived by others.
Indeed, effective meetings need both a leader and a facilitator. Often, the meeting leader is
the project manager, senior manager, or subject matter expert. Most project managers are
very familiar with this role, as they have the legitimate authority on the project. They’re often
less familiar with the role of facilitator. A meeting facilitator is someone who helps guide the
group toward its goals during the meeting by focusing primarily on the processes the group
will use to achieve desired outcomes. Status meetings require both a facilitator and a leader to
run optimally. While project managers sometimes designate someone else as a facilitator for
their meetings, more likely the project manager wears both hats.
Exhibit 1 – Leader versus Facilitator Comparison
In short, the meeting leader is often focused on the “what,” while the facilitator is often
focused on the “how”. Both are necessary for an optimally effective meeting.
Because many project managers are leading status meetings, they tend to focus exclusively
on their role as meeting leader and ignore their role as meeting facilitator. The good news is
that they are not solely responsible for the facilitator role. Many project managers ensure that
the meeting is appropriately facilitated by inviting an outside facilitator or asking team
members to play the role of facilitator. Team members should be actively engaged in all
facets of project success and having them perform key facilitation activities is one way to
encourage more involvement. Because the facilitator should be constantly observing and
prodding the group from the sidelines, they’re somewhat “detached” from much of the
meeting content. In this case project managers may not want to ask any of the team
members/subject matter experts to fully take on this role (as their contribution to meeting
discussions is key). In this case, the project manager may want to assign specific facilitation
tasks to certain team members. Key facilitation tasks that he/she may want to delegate
include the following:
Seasoned facilitators use specific techniques to avoid common meeting management pitfalls.
In particular, project managers should implement the BLISS strategy to enhance the
effectiveness of their project status meetings.
Be Efficient
Meeting efficiency refers to accomplishing as much as possible in the shortest amount of time
with the smallest number of people participating in the meeting. Running efficient meetings
is important because it respects everyone’s time and provides team members more time to
focus on task completion, encourages team members to participate in project meetings, and
builds goodwill for the project manager.
To run efficient project status meetings, project managers can employ several specific
techniques:
Look back – look forward refers to reviewing the previous immediate timeframe and the
immediately upcoming timeframe as well (e.g., +/- 2 weeks). During a status meeting,
“looking back and looking forward” encourages the team to focus on a current snapshot of
the project and zero in on issues relevant to the current period. This approach provides a brief
historical view that offers context for the “current state” project discussion. The brief review
also affords important opportunities to recognize team members for recent accomplishments.
Insist on Accountability
Project managers rely on subject matter expert team members to complete tasks in a timely
manner. Throughout the course of the project, additional items will arise requiring follow-up
by various team members. Team members must be accountable for tasks that they take on if
the project is to reach its objectives within the parameters set. When team members are not
held accountable, it creates a myriad of problems for the project:
Sounds good? Well, the obvious question becomes how does the project manager encourage
this culture of accountability in the project team during status meetings? Consider these
techniques to encourage that dedication to accountability in the team:
Write all action items with a task owner and due date on a flip chart in real time
during the meeting
Repeat the action items to the owner and confirm his/her understanding of it
Ask action item owners to suggest due dates (do not mandate due dates)—
negotiate dates if needed.
Maintain a database of action items that task owners are responsible for updating
Begin all status meetings with a review of previous action items
Consider using electronic tools to provide automatic reminders of action items
Discuss importance/consequences for missing action items during project kickoff
Address repeat offenders offline to explore potential causes
Team members are certainly influenced by the behavior of and reactions from other team
members. Project managers should capitalize on this to foster a team that is highly
accountable.
The agenda is your roadmap for the meeting. It should include not just topics but also
timings, topic owners, and possibly even facilitation techniques for each section. A well
developed agenda helps the project manager keep the team on track, makes preparation easier
for team members, reduces meeting time, and provides a sense of focus for the meeting.
For project status meetings, agendas should be simple and consistent. The project manager
should clearly indicate what topics should be covered at each regularly scheduled status
meeting—no surprises! Project managers should get consensus on the status meeting agenda
early in the project cycle, then circulate that agenda as a reminder prior to each meeting. A
sample status meeting agenda might include the following topics:
Stay Focused
One of the biggest dilemmas project managers face during project status meetings is keeping
focused on the topic at hand. Everyone seems to have their favorite soap box issue that they’d
love to discuss extensively, whether it’s on the agenda or not! These tangents not only take
the group off topic but also tend to take up critical time during the meeting and cause
meetings to run late. Another problem with tangents is that they tend to cause the meeting to
bounce from topic to topic without facilitating true resolution of the intended topic at hand. In
short, getting sidetracked impacts both the efficiency and effectiveness of the status meeting.
Project managers should consider a few simple techniques to help maintain focus during their
status meetings:
Ask someone on the team to “raise a flag” or otherwise point out when the
discussion is veering off topic
Question whether the issue raised can be taken offline
Use an egg timer or similar device to “time box” discussions about issues not on
the agenda (but the team agrees should be discussed)
Redirect the issue to the parking lot
Develop ground rule about keeping the group on topic (e.g., ELMO—“Everyone,
Let’s Move On)
Maintaining focus during status meetings is critical to keep meetings within the allotted time.
The key for implementing any of these techniques successfully is surfacing the issue with the
team early in the project cycle and identifying techniques that the team will support to
address this common problem.
Conclusion
Project status meetings are a critical tool in the project manager’s tool box. Unfortunately, too
few project managers have adopted methods and techniques to ensure that these sessions are
succinct, productive, and valuable. It’s not uncommon for project managers to conduct at
least one 90-minute status meeting per week. For a team of six, that’s an investment of nearly
40 hours in just one month! Too many project managers assume that a status meeting means
sending out a meeting invitation and just showing up. In reality, effective status meetings
require so much more! The good news is that when project status meetings are effective and
efficient, the results are tremendous! Productive project status meetings increase team
morale, provide timely information on project status, uncover potential risks, provide a forum
for timely issue resolution, and encourage relevant information sharing.
References
Project Management Institute. (2004). A guide to the project management body of knowledge
(PMBOK® Guide) (2004 ed.). Newtown Square, PA: Project Management Institute.
This material has been reproduced with the permission of the copyright owner. Unauthorized
reproduction of this material is strictly prohibited. For permission to reproduce this material,
please contact PMI or any listed author.
© 2008, Dana Brownlee
Originally published as a part of the 2008 PMI Global Congress Proceedings – Denver,
Colorado USA
ADVERTISEMENT
ADVERTISEMENT
Related Content
WHITE PAPER Teams , Organizational Culture May 2022
By Gardiner, Paul | Alkhudary, Rami | Druon, Marie This report presents the results of
an SLR conducted to collect and synthesize the extant literature on EDI in the field of
project management.
By Manata, Brian | Miller, Vernon D. | Mollaoglu, Sinem | Garcia, Angelo J. This study
examines the influence of project managers’ communication behaviors in integrated
project delivery (IPD) projects.
ADVERTISEMENT
This site uses cookies to provide you with a better browsing experience, improve
performance, for analytics, and to show you relevant advertisements. By using this website
you agree to the use of cookies. See our privacy and cookie policy for more information.
OK
Quick Links
Webinars
PMBOK® Guide
Online Courses
Events
Store
Explore PMI
Certifications
Project Management Professional (PMP)®
Agile Certifications
Report PDUs
Community
Latest from the Community
Discussions
Templates
Blogs
Volunteering
Membership
Membership Overview
Become a Member
Student Membership
Local Chapters
Membership FAQs
Organization
About Us
Our Leadership
Careers
Project Management Institute
Stay Connected
Support
Contact Us
Store Help
Privacy
Sitemap
Terms of use
Purchasing Terms
Advertising & Sponsorship