Appendix 2 - Installation and Commissioning Schedule
Appendix 2 - Installation and Commissioning Schedule
3 PROJECT KICK OFF DATE 1 day? Wed Mar 4, '09 Wed Mar 4, '09 100%
4 ENGINEERING PACKAGES 106.81 days? Thu Mar 5, '09 Sat Jul 11, '09 96%
5 Design Packages 9 days? Thu Mar 5, '09 Mon Mar 16, '09 97%
6 Drawing Packages 16.94 days? Tue Apr 7, '09 Mon Apr 27, '09 97%
7 Modification Drawings 5.94 days? Tue Apr 28, '09 Tue May 5, '09 97%
8 Class Review & Approval 62.88 days? Tue Apr 28, '09 Sat Jul 11, '09 95%
9 PROCUREMENT PROCESS 53.94 days? Thu May 7, '09 Sat Jul 11, '09 98%
10 STRUCTURAL/MAIN COMPONENTS FABRICATION 154.81 days? Wed Mar 4, '09 Sat Sep 5, '09 93%
11 Hydraulic Winch (Shipneeds) 136.81 days? Mon Mar 23, '09 Wed Sep 2, '09 100%
18 Chamber Fabrication (LSWE) 121 days? Wed Mar 4, '09 Mon Jul 27, '09 100%
96 Complete System Interface (Final inspection) 3 days? Tue Jul 21, '09 Thu Jul 23, '09 100%
97 Packing for Delivery 2 days? Fri Jul 24, '09 Mon Jul 27, '09 100%
98 MAIN CHAMBERS COMPONENT DELIVERABLES 1 day? Mon Jul 27, '09 Mon Jul 27, '09 100%
99 Life Support Equipment (UTS & Rex Marine) 131.5 days? Wed Apr 1, '09 Sat Sep 5, '09 75%
107 Control Containers (JMS & Hardy House) 100.06 days? Wed Apr 1, '09 Thu Jul 30, '09 100%
112 WORKSHOP SUB-ASSEMBLIES 114.63 days? Thu Jul 2, '09 Tue Nov 17, '09 97%
113 Electrical Sub-Assemblies 66.88 days? Wed Jul 29, '09 Sat Oct 17, '09 98%
144 Mechanical Sub-Assemblies 47.44 days? Wed Jul 29, '09 Thu Sep 24, '09 97%
160 SAT Chambers 78.5 days? Fri Aug 14, '09 Tue Nov 17, '09 98%
161 DDC/TUP Chamber 54.25 days? Wed Sep 2, '09 Fri Nov 6, '09 98%
232 HRC Chamber 60.75 days? Fri Sep 4, '09 Tue Nov 17, '09 99%
277 Dive Bell 42.63 days? Fri Aug 14, '09 Mon Oct 5, '09 98%
345 Dive/SAT Control Container 77.5 days? Tue Aug 4, '09 Wed Nov 4, '09 98%
346 Internal Fit Outs 49.06 days? Mon Sep 7, '09 Wed Nov 4, '09 98%
393 External Fit Outs 32 days? Tue Aug 4, '09 Thu Sep 10, '09 100%
399 Fly Away Container 28.56 days? Thu Jul 2, '09 Wed Aug 5, '09 99%
400 Internal Fit Outs 28.56 days? Thu Jul 2, '09 Wed Aug 5, '09 100%
420 External Fit Outs 16.75 days? Mon Jul 6, '09 Fri Jul 24, '09 98%
429 Umbilical Basket 30 days? Fri Aug 28, '09 Fri Oct 2, '09 93%
430 Mechanical Fit Out 30 days? Fri Aug 28, '09 Fri Oct 2, '09 98%
434 Electrical Fit Out 7.81 days? Mon Aug 31, '09 Tue Sep 8, '09 91%
440 Life Support Container 19 days? Wed Sep 16, '09 Thu Oct 8, '09 16%
441 Mechanical Fit Out 3.63 days? Wed Sep 16, '09 Sat Sep 19, '09 0%
444 Electrical Fit Out 18.94 days? Wed Sep 16, '09 Thu Oct 8, '09 31%
449 System Test 59.94 days? Tue Oct 20, '09 Wed Dec 30, '09 41%
450 HRC Thermal Test (3rd Party & ABS) 4 days? Tue Oct 20, '09 Fri Oct 23, '09 100%
451 HRC Floating & Towing Test 0 days? Mon Oct 26, '09 Mon Oct 26, '09 45% 10/26
452 IMCA Audit- Internal 5 days? Tue Oct 27, '09 Mon Nov 2, '09 0%
453 Load test for A Frame and winches 3 days? Wed Nov 4, '09 Fri Nov 6, '09 0%
454 Life Support Container Hook up & Test 4 days? Mon Nov 9, '09 Thu Nov 12, '09 0%
455 Chamber Alignment, hook up & pressure Test 10 days? Mon Nov 16, '09 Thu Nov 26, '09 100%
456 Final Acceptance Test 2 days? Fri Nov 27, '09 Mon Nov 30, '09 0%
457 System final checking & verification 7 days? Mon Nov 30, '09 Tue Dec 8, '09 0%
458 Packing & Delivery 2 days? Wed Dec 9, '09 Thu Dec 10, '09 0%
459 Delivery Documentation 13 days? Tue Dec 15, '09 Wed Dec 30, '09 50%
Project Manager : Hans Erlangga Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline
Approved By : Kishore K. (SPM)
Sunil Uchil ( GM)
Page 1