Appendix 2 - Installation and Commissioning Schedule

This document provides a master schedule for the HMAN 018-SAT10 project from March 2009 to December 2009. It outlines key milestones and tasks such as engineering packages, procurement, fabrication of structural components, workshop sub-assemblies, system testing, and delivery documentation. The schedule is 93% complete overall and shows the duration, start and finish dates for each task.

Uploaded by

nguyenhoang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
60 views1 page

Appendix 2 - Installation and Commissioning Schedule

This document provides a master schedule for the HMAN 018-SAT10 project from March 2009 to December 2009. It outlines key milestones and tasks such as engineering packages, procurement, fabrication of structural components, workshop sub-assemblies, system testing, and delivery documentation. The schedule is 93% complete overall and shows the duration, start and finish dates for each task.

Uploaded by

nguyenhoang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

HMAN018- SAT10 MASTER SCHEDULE PAGE 1 /1

VERSION 1.0 Prepared By: Hans Erlangga

ID Task Name Duration Start Finish % Complete 2010


Mar '09 Apr '09 May '09 Jun '09 Jul '09 Aug '09 Sep '09 Oct '09 Nov '09 Dec '09 Jan '10
eb 1 eb 2 Mar 2 Mar 9 ar 1 ar 2 ar 3 Apr 6 pr 1 pr 2 pr 2 May ay 1 ay 1 ay 2 Jun 1 Jun 8 un 1 un 2 un 2 Jul 6 ul 1 ul 2 ul 2 Aug 3 ug 1 ug 1 ug 2 ug 3 Sep 7 ep 1 ep 2 ep 2 Oct 5 ct 1 ct 1 ct 2 Nov 2 Nov 9 ov 1 ov 2 ov 3 Dec 7 ec 1 ec 2 ec 2 Jan 4 an
1 250.94 days?
MASTER SCHEDULE FOR HMAN 018- SAT 10 Wed Mar 4, '09 Wed Dec 30, '09 93%

3 PROJECT KICK OFF DATE 1 day? Wed Mar 4, '09 Wed Mar 4, '09 100%

4 ENGINEERING PACKAGES 106.81 days? Thu Mar 5, '09 Sat Jul 11, '09 96%

5 Design Packages 9 days? Thu Mar 5, '09 Mon Mar 16, '09 97%

6 Drawing Packages 16.94 days? Tue Apr 7, '09 Mon Apr 27, '09 97%

7 Modification Drawings 5.94 days? Tue Apr 28, '09 Tue May 5, '09 97%

8 Class Review & Approval 62.88 days? Tue Apr 28, '09 Sat Jul 11, '09 95%

9 PROCUREMENT PROCESS 53.94 days? Thu May 7, '09 Sat Jul 11, '09 98%

10 STRUCTURAL/MAIN COMPONENTS FABRICATION 154.81 days? Wed Mar 4, '09 Sat Sep 5, '09 93%

11 Hydraulic Winch (Shipneeds) 136.81 days? Mon Mar 23, '09 Wed Sep 2, '09 100%

18 Chamber Fabrication (LSWE) 121 days? Wed Mar 4, '09 Mon Jul 27, '09 100%

96 Complete System Interface (Final inspection) 3 days? Tue Jul 21, '09 Thu Jul 23, '09 100%

97 Packing for Delivery 2 days? Fri Jul 24, '09 Mon Jul 27, '09 100%

98 MAIN CHAMBERS COMPONENT DELIVERABLES 1 day? Mon Jul 27, '09 Mon Jul 27, '09 100%

99 Life Support Equipment (UTS & Rex Marine) 131.5 days? Wed Apr 1, '09 Sat Sep 5, '09 75%

107 Control Containers (JMS & Hardy House) 100.06 days? Wed Apr 1, '09 Thu Jul 30, '09 100%

112 WORKSHOP SUB-ASSEMBLIES 114.63 days? Thu Jul 2, '09 Tue Nov 17, '09 97%

113 Electrical Sub-Assemblies 66.88 days? Wed Jul 29, '09 Sat Oct 17, '09 98%

144 Mechanical Sub-Assemblies 47.44 days? Wed Jul 29, '09 Thu Sep 24, '09 97%

160 SAT Chambers 78.5 days? Fri Aug 14, '09 Tue Nov 17, '09 98%

161 DDC/TUP Chamber 54.25 days? Wed Sep 2, '09 Fri Nov 6, '09 98%

232 HRC Chamber 60.75 days? Fri Sep 4, '09 Tue Nov 17, '09 99%

277 Dive Bell 42.63 days? Fri Aug 14, '09 Mon Oct 5, '09 98%

345 Dive/SAT Control Container 77.5 days? Tue Aug 4, '09 Wed Nov 4, '09 98%

346 Internal Fit Outs 49.06 days? Mon Sep 7, '09 Wed Nov 4, '09 98%

393 External Fit Outs 32 days? Tue Aug 4, '09 Thu Sep 10, '09 100%

399 Fly Away Container 28.56 days? Thu Jul 2, '09 Wed Aug 5, '09 99%

400 Internal Fit Outs 28.56 days? Thu Jul 2, '09 Wed Aug 5, '09 100%

420 External Fit Outs 16.75 days? Mon Jul 6, '09 Fri Jul 24, '09 98%

429 Umbilical Basket 30 days? Fri Aug 28, '09 Fri Oct 2, '09 93%

430 Mechanical Fit Out 30 days? Fri Aug 28, '09 Fri Oct 2, '09 98%

434 Electrical Fit Out 7.81 days? Mon Aug 31, '09 Tue Sep 8, '09 91%

440 Life Support Container 19 days? Wed Sep 16, '09 Thu Oct 8, '09 16%

441 Mechanical Fit Out 3.63 days? Wed Sep 16, '09 Sat Sep 19, '09 0%

444 Electrical Fit Out 18.94 days? Wed Sep 16, '09 Thu Oct 8, '09 31%

449 System Test 59.94 days? Tue Oct 20, '09 Wed Dec 30, '09 41%

450 HRC Thermal Test (3rd Party & ABS) 4 days? Tue Oct 20, '09 Fri Oct 23, '09 100%

451 HRC Floating & Towing Test 0 days? Mon Oct 26, '09 Mon Oct 26, '09 45% 10/26

452 IMCA Audit- Internal 5 days? Tue Oct 27, '09 Mon Nov 2, '09 0%

453 Load test for A Frame and winches 3 days? Wed Nov 4, '09 Fri Nov 6, '09 0%

454 Life Support Container Hook up & Test 4 days? Mon Nov 9, '09 Thu Nov 12, '09 0%

455 Chamber Alignment, hook up & pressure Test 10 days? Mon Nov 16, '09 Thu Nov 26, '09 100%

456 Final Acceptance Test 2 days? Fri Nov 27, '09 Mon Nov 30, '09 0%

457 System final checking & verification 7 days? Mon Nov 30, '09 Tue Dec 8, '09 0%

458 Packing & Delivery 2 days? Wed Dec 9, '09 Thu Dec 10, '09 0%

459 Delivery Documentation 13 days? Tue Dec 15, '09 Wed Dec 30, '09 50%

Project Manager : Hans Erlangga Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline
Approved By : Kishore K. (SPM)
Sunil Uchil ( GM)

Page 1