Sunny Deol Vs Suneel Darshan - 16 - Apr - 2015
Sunny Deol Vs Suneel Darshan - 16 - Apr - 2015
Sunny Deol Vs Suneel Darshan - 16 - Apr - 2015
doc
Suneel Darshan )
carrying on his sole proprietary )
business under the name and style of, )
“Shree Krishna International”, )
132, Park Street-2, S.V.P. Nagar, )
Andheri (West), Mumbai- 400 053. ) .. Petitioner
Vs.
Ajay Singh (Sunny) Deol )
residing at Plot No.22, Road No.11, )
Juhu-Vile Parle Development Scheme, )
Mumbai – 400 049. ) .. Respondent
---
Mr.G.R.Joshi, Senior Advocate a/w Ms.Neeta Jain a/w Mr.Sunil Gangal
a/w Mr.Jayesh Mistry i/by M/s.RMG Law Associates for the petitioner
in Arb. Petn. No.819 of 2011 & for the respondent in Arb. Petn.908 of
2011.
Mr.Ajit Kapadia a/w Mr.Shyam Kapadia i/by Mr.Aditya Chitale for the
petitioner in Arb. Petn.908 of 2011 & for the respondent in Arb. Petn.
No.819 of 2011.
---
ppn 2 arbp-819.11 & 908.11(j).doc
JUDGMENT :
. By these two petitions filed under Section 34 of the
Arbitration and Conciliation Act, 1996 (for short “the said Arbitration
Act), both the petitioners have challenged part of the impugned award
dated 6th June 2011 passed by the learned arbitrator rejecting the claim
made by Mr.Suneel Darshan-petitioner in Arbitration Petition No.908 of
2011 however, awarding arbitration costs of Rs.12,00,000/- (Rs. Twelve
Lacs only) against Mr.Ajay Singh (Sunny) Deol-the petitioner in
Arbitration Petition No.819 of 2011 who was the original respondent.
The respondent in the said petition was the original claimant in the
arbitral proceedings. Mr.Suneel Darshan is described as the claimant and
Mr.Ajay Singh (Sunny) Deol is described as the respondent in this
judgment. Some of the relevant facts for the purpose of deciding these
two petitions are as under :
5. On 29th April 2008, the writer of the script Mr. Robin Bhat
along with Mr.Kartike Singh narrated the script “Good Morning India”
to the respondent. The respondent liked the subject of the said script
but wanted to know the exact dialogues in order to understand his role
as a lead star in the film. The respondent also wanted to know about
music director in the film.
ppn 4 arbp-819.11 & 908.11(j).doc
7. By letter dated 28th May 2008, the respondent denied all the
allegations made by the claimant and informed that he had accepted the
subject of the film “Good Morning India”, however, without hearing the
dialogues, he could not proceed with the venture. He also placed on
record that Mr.Kartike Singh had informed him that he would revert
back with the dialogues.
10. The dispute arose between the parties. The said dispute
was referred to a former Judge of the Supreme Court of India. The
claimant filed a statement of claim demanding a sum of
Rs.20,00,00,000/- (Rs.Twenty Crores only) with interest and costs. The
respondent denied the said claim and lodged a counter claim. Both the
parties examined witnesses. By an award dated 6 th June 2011, the
learned arbitrator dismissed the claim of the claimant and the counter
claim of the respondent. Learned arbitrator, however, awarded costs of
Rs.12,00,000/- (Rs.Twelve Lacs only) in favour of the claimant and
against the respondent. Both the parties have challenged part of the award
rendered by the learned arbitrator in these two petitions.
11. By the said arbitral award dated 6th June 2011, the learned
arbitrator though rendered various findings of facts in favour of
Mr.Darshan-original claimant, the learned arbitrator has held that the
claimant had not able to prove that he has suffered any damages much
less damages in the sum of Rs.20 crores. The learned arbitrator held
that the claimant was ready and willing to perform and that the
respondent committed breaches of the agreement and the consent terms.
ppn 6 arbp-819.11 & 908.11(j).doc
The claimant had not able to prove that he had suffered any loss or
damages as a result of the breaches. It is held that the claimant thus
would be only entitled to costs of arbitration quantified at Rs.12 lacs
from the respondent.
14. In the impugned award, the learned arbitrator held that the
respondent had committed breach of consent terms by keeping on
varying his demands on how the subject was to be agreed upon and
answered the said issue in the affirmative accordingly. However, in so
far as the claim for damages dealt with by the learned arbitrator while
dealing with issue nos.(vi) and (vii) is concerned, he rendered a finding
that there was no evidence on record to show that the agreement marked
as exhibit ‘C-31’ was the agreement which had been entered into by
ppn 7 arbp-819.11 & 908.11(j).doc
18. Learned counsel for the claimant then submits that though
ppn 9 arbp-819.11 & 908.11(j).doc
21. Learned counsel for the claimant then submits that there
was no market price of the said movie available. The claimant had
claimed compensation for loss of profit on the premise that if the said
movie would have been released, the claimant would have earned profit
which the claimant was deprived of in view of the breach of the contract
committed by the respondent. He submits that in this case, the
consideration which the claimant was entitled to receive from the said
M/s. Gemini for the said film was proved and was known to both the
parties. The expenses required to be incurred on production of the
film would not be ascertained as the same was not incurred upto the
stage of production. Even if the revenue was uncertain in view of no
market for the film available, certain expenses were required to be
incurred which could not be disputed. The claimant was producing the
film for commercial exploitation. The respondent was fully aware of the
said fact. He submits that the respondent was fully aware that since he
had committed breaches, the claimant was not able to produce a film
and had suffered financial loss.
22. Learned counsel for the claimant then submits that the
claimant had produced the accounts for three years. The claimant had
produced three movies prior to the execution of the agreement with the
ppn 11 arbp-819.11 & 908.11(j).doc
23. Learned counsel for the claimant submits that though there
was adequate material produced by the claimant before the learned
arbitrator to prove that the claimant had suffered loss of profit, the
learned arbitrator has rejected the said claim without considering the
evidence produced by the claimant. The claimant had also produced a
letter from another producer exchanged with the respondent in respect
of the movie “Goli” which indicated that the respondent would have
charged a sum of Rs.5 crores for the said movie. He submits that as far
as this case is concerned, the consideration amount was of Rs.50 lacs
and thus the claimant would have at least made a profit of Rs.4.5 crores.
24. Learned counsel for the claimant then submits that even the
counter claim of the respondent for Rs.5 crores would also suggest that
there was loss of profit of Rs.5 crores suffered by the claimant. The
learned arbitrator thus would have considered at least the said
undisputed position and would have granted the claim for loss of profit
in favour of the claimant.
ppn 12 arbp-819.11 & 908.11(j).doc
26. Learned counsel for the claimant submits that the learned
arbitrator is required to make guess work while determining the loss of
profit as claimed by the claimant. The learned arbitrator was not bound
by the strict provisions of the Evidence Act. He submits that inspite of
ppn 14 arbp-819.11 & 908.11(j).doc
28. Learned counsel for the claimant submits that the finding of
the learned arbitrator that two letters relied upon by the claimant were
procured and fabricated is totally illegal. He submits that if, according
to the learned arbitrator, the documents were not sufficiently stamped,
the learned arbitrator was bound to refer to the said documents to the
Collector for adjudication. In support of this submission, learned counsel
placed reliance on the judgment of the Supreme Court in the case of
ppn 15 arbp-819.11 & 908.11(j).doc
prove his readiness and willingness to perform his part of the obligation
all throughout which the claimant failed in this case. In support of this
submission, learned counsel placed reliance on the judgment of the
Privy Council in the case of Abdullah Bey Chedid and Ors. Vs.
Tenenbaum, reported in AIR 1934 Privy Council 91.
35. Learned senior counsel for the respondent submits that the
claimant in his evidence had deposed that he was ready to make the film
if finance was given to him by the respondent. He submits that even
profit and loss account and balance sheet produced by the claimant
would also indicate that there was huge loss suffered by the claimant
in the years 2006, 2007 and 2008. Capital account of the claimant was
in negative. In reply to question nos.318 to 321, the claimant had
admitted that he had suffered loss.
36. In so far as the MOU between the claimant and M/s. Gemini
alleged to have been executed on 2nd November 2007 is concerned, the
learned senior counsel submits that on the date of execution of the said
agreement, it was not the case of the claimant that the respondent had
committed any breach of the said MOU. He submits that since one
cheque, out of four cheques, was dishonoured and other two cheques
alleged to have been issued in favour of the claimant were not deposited
by the claimant, the said alleged agreement even otherwise would not
have been survived. The learned arbitrator has rightly rendered finding of
ppn 18 arbp-819.11 & 908.11(j).doc
fact that the claimant had failed to prove the said documents. He
submits that in any event, the said document was terminated by the said
M/s. Gemini with immediate effect.
41. Learned senior counsel for the respondent submits that the
said writing entered into between the claimant and the said M/s.
Gemini was required to be stamped in accordance with Article 5(iv)(a)
of the Maharashtra Stamp Act whereas the said writing was alleged to
have been executed on the stamp paper of Rs.100/- only. He submits
that merely because the said agreement was marked as exhibit, the
ppn 20 arbp-819.11 & 908.11(j).doc
43. Learned senior counsel submits that the claimant has been
cross-examined on the accounts relied upon by the claimant. The
claimant failed to prove the entries in the accounts. The claimant did
not examine any Chartered Accountant.
arbitrator could not have awarded any sum on the basis of any guess
work. The claimant failed to prove the revenue as well as expenditure.
No claim for nominal damages was made by the claimant. The learned
arbitrator did not decide that there was no mitigation of loss as the
claimant did not raise such plea of alternate method of computation of
damages. Learned senior counsel placed reliance on the commentary of
Mulla on the Contract Act on the issue of proof of damages.
raised by the claimant before the learned arbitrator. Each film may have
a different quantum of profit or loss.
the said M/s.Gemini had already paid Rs.3 crores to the claimant under
the said agreement. Further amount at that stage was not required to be
paid to the claimant. He submits that since the film was not complete in
all respect, the amount received by the claimant from M/s.Gemini was
rightly shown as refundable advance in the books of account of the
claimant.
learned counsel. Both the parties have impugned part of the arbitral
award dated 6th June 2011 made by the learned arbitrator. The learned
arbitrator framed 9 issues for consideration. It is held by the learned
arbitrator that he had jurisdiction to decide the disputes arising out of the
consent terms and to decide whether the parties had orally agreed on the
number of subjects to be put to the respondent and whether the forty dates
were to be allotted consecutively. The respondent did not seriously
dispute the finding of the learned arbitrator holding that he had
jurisdiction to decide the disputes arising out of the consent terms.
57. Insofar as the issue raised by the respondent that the consent
terms were a mere 'Agreement to agree' and was not a concluded contract
is concerned, the learned arbitrator rejected the said submission of the
respondent. It is held by the learned arbitrator that in the said agreement
the parties had provided that a subject would be agreed upon within three
months and the respondent should give forty shooting dates. The consent
terms further provided that the film should be made within seven months
from the date the parties agree upon the subject. It is held that there was
thus a concluded contract on that aspect. The learned arbitrator held that
merely because the subject was to be subsequently decided and/or an
Actor Producer Agreement in the usual form was to be subsequently
signed, and/or the fact that it was not set out how the forty shooting dates
had to be alloted did not make it an 'Agreement to agree.'
58. It is held that merely because the name of the actress was to
be decided later did not detract from the fact that there was a concluded
contract. All these matters were the matters of working of the binding
ppn 27 arbp-819.11 & 908.11(j).doc
contract. The learned arbitrator thus decided the said issue in favour of
the petitioner. In my view the learned arbitrator has interpreted the terms
of the contract and has rightly come to the conclusion that the consent
terms and the articles of agreement were not 'Agreement to agree' as
canvassed by the respondent. The interpretation of the learned arbitrator
on this issue is a possible interpretation and thus cannot be substituted by
another interpretation by this court under section 34 of the Arbitration
Act.
perverse and does not warrant any interference. There is no merit in this
submission of the learned senior counsel for the respondent on this issue.
admit that the meeting had taken place but he then claimed that it was for
the narration of the story.
62. The learned arbitrator held that on one hand the respondent
had claimed that he could not agree upon a subject without the script
being first narrated to him and on the other hand in his letter dated 22 nd
April 2008, he claimed that he did not read scripts before approving the
subject of the film. The learned arbitrator rendered a finding of fact that
the respondent was reiterating that the script would only follow an
approval of a subject and that the script would not be sent without the
subject being discussed or approved. However his evidence in paragraph
14 of his affidavit was contrary to the said case and was belied by his
own letters. The learned arbitrator has held that when the parties had
provided that the subject of the film was to be mutually agreed upon
within a period of three months, they did not intend that script with
dialogues to be first narrated by the writer in the presence of the director
and thereafter, the script to be read by the respondent before he would
accept the subject.
65. The learned arbitrator has held that the respondent never
allowed the consent terms to get past the first stage of agreeing upon the
ppn 31 arbp-819.11 & 908.11(j).doc
subject of the film and thus a party in breach could not be heard to say
that the other party was not willing to comply with the terms which were
to be fulfilled later. It is held that even if the claimant was not ready and
willing, at the highest he would not be entitled to damages and that would
not preclude the learned arbitrator from holding that respondent was in
breach. It is held that there was no substance in the contention that the
claimant was not ready and willing.
start to carry out his obligation under the agreement and was on one or
the other ground refusing to comply with his part of the obligation. The
judgment of the Privy Council in case of Abdullah Bey Chedid (supra)
thus relied upon by the respondent does not assist him.
72. It is held that the only first cheque of Rs.3 crores was
honoured. The second cheque dated 13 th November, 2007 was
dishonoured for the reason 'payment countermanded by the Drawer'. The
claimant did not give any explanation as to why the said payment had
been countermanded. The other two cheques were admittedly not
deposited by the claimant. The learned arbitrator held that the claimant
did not give any explanation as to why payment of the second cheque was
ppn 34 arbp-819.11 & 908.11(j).doc
claimant could not give any explanation about the alleged consideration
mentioned in the said alleged agreement and could not produce the
original cheques though called upon by the respondent. In my view the
findings rendered by the learned arbitrator that the claimant could not
produce any evidence on record to show that the said agreement was the
agreement which had been entered into by the claimant with Gemini
Industries and Imaging Limited is not perverse and the contents thereof
had not been proved by anybody is not perverse but in my view is based
on the oral as well as documentary evidence led by the parties and thus
no interference with such finding of fact is warranted.
The full bench of this court case in of Hemendra Rasiklal Ghia (supra)
has held that a question as to admissibility of document should be
decided when it arises and should not be reserved till the judgment of the
case is given. There is no provision enabling the court to postponing the
objection regarding admissibility of the proof of the document. I am
respectfully bound by the judgment of the Full Bench of this court which
applies to the facts of this case. The respondent not having raised any
objection about the mode and manner of execution of the document when
the said document was tendered could not be allowed to raise that issue at
the time of hearing of the matter.
which was subject matter of the agreement entered into between the
parties, the claimant would have incurred expenditure of of Rs.13 crores
and accordingly claimed loss of profit in the sum of Rs.20 crores. The
respondent had disputed this claim for loss of profit on the ground that
the respondent had not committed any breach and in the alternative that
the claimant had not proved any such loss of profit. The respondent also
placed reliance on various parts of the cross examination of the claimant
and also the documentary evidence produced by the claimant himself in
support of the submission of the respondent that the claimant had
suffered losses even in past when produced other movies and never made
any profit.
had suffered any damages much less damages in a sum of Rs. 20 crores.
In my view the learned arbitrator has rightly rendered such finding of fact
while rejecting the claim for loss of profit which finding is not perverse
but is based on oral as well as documentary evidence led by the parties
and thus no interference with such finding of fact is permissible.
suffered losses. Though the claimant proved that the respondent had
committed breaches however could not prove that the claimant suffered
any loss of profit.
evidence in support of his claim for loss of profit and had failed to prove
such loss of profit, the learned arbitrator could not have awarded any
compensation on the basis of guess work.
89. In my view if a party has not suffered any losses, even if the
respondent has committed breaches, such party cannot be awarded any
compensation under Section 73. When loss in terms of money is prayed,
the party claiming compensation has to prove such loss or damages
suffered by him. The division bench of this court in case of Maharashtra
State Electricity Board (supra) has held that section 73 of Contract Act
does not give any cause of action unless and until any damages or loss
was actually suffered otherwise section 73 would become nugatory and
party would be penalised though the other party suffered no loss. In my
view, if the party who has not suffered any loss is awarded any
ppn 49 arbp-819.11 & 908.11(j).doc
that the learned arbitrator has rendered most of the findings in favour of
the claimant while holding that the respondent had committed breaches of
the agreement and had since inception had no intention to comply with
his part of the obligation under the agreement. The learned arbitrator
however has rejected the claim for loss of profit on the ground that the
claimant had failed to prove such loss of profit. In my view though the
claimant had incurred arbitration cost much more, the learned arbitrator
has only awarded the cost at Rs.12 lacs. In the facts and circumstances of
this case the learned arbitrator was thus justified in awarding cost of
Rs.12 lacs in favour of the claimant. In my view there is thus no merit in
this submission of the learned senior counsel for the respondent and thus
that part of the award is upheld. In my view both the arbitration petitions
are devoid of merits.
R.D. DHANUKA, J.
R.D. DHANUKA, J.