Project Schedule For P&S System 090919

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Summit Park View Hotel - Project Schedule for Plumbing and Sanitary System

ID Task Task Name Duration Start Finish August September October November December January February March April May
Mode E B M E B M E B M E B M E B M E B M E B M E B M E B M
1 PLUMBING AND SANITARY WORK 130 days Mon 19/11/4 Thu 20/4/2
2 Procured, Delivery, Preparation Fri 19/10/4
3 Lower Ground Floor 15 days Mon 19/11/4 Wed 19/11/20
4 Underground/Concealed Piping 3 days Mon 19/11/4 Wed 19/11/6
5 1st Fix Piping & Hanger Support Installation Works LG 8 days Thu 19/11/7 Fri 19/11/15
6 (Included external) Works
Final Fix Installation 7 days Sat 19/11/16 Sat 19/11/23
7 Upper Ground Floor 15 days Mon 19/11/11 Wed 19/11/27
8 Concealed Piping UG 3 days Mon 19/11/11 Wed 19/11/13
9 1st Fix Piping & Hanger Support Installation Works UG 9 days Thu 19/11/14 Sat 19/11/23
10 (Included
Final external) Works (Sanitary Wear, Basin)
Fix Installation 6 days Tue 19/12/17 Mon 19/12/23
11 1st Storey 15 days Thu 19/12/5 Sat 19/12/21
12 Concealed Piping 1 3 days Thu 19/12/5 Sat 19/12/7
13 1st Fix Piping & Hanger Support Installation Works 1 10 days Thu 19/12/5 Mon 19/12/16
14 Final Fix Installation Works (Sanitary Wear, Basin) 5 days Fri 20/1/10 Wed 20/1/15
15 2nd Storey 15 days Mon 19/12/30 Wed 20/1/15
16 Concealed Piping 2 5 days Mon 19/12/30 Fri 20/1/3
17 1st Fix Piping & Hanger Support Installation Works 2 9 days Mon 19/12/30 Wed 20/1/8
18 Final Fix Installation Works (Sanitary Wear, Basin) 6 days Tue 20/2/4 Mon 20/2/10
19 3rd Storey 15 days Mon 20/1/20 Wed 20/2/5
20 Concealed Piping 3 3 days Mon 20/1/20 Wed 20/1/22
21 1st Fix Piping & Hanger Support Installation Works 3 8 days Mon 20/1/20 Tue 20/1/28
22 Final Fix Installation Works (Sanitary Wear, Basin) 7 days Thu 20/2/20 Thu 20/2/27
23 4th Storey 15 days Wed 20/2/12 Fri 20/2/28
24 Concealed Piping 4 3 days Wed 20/2/12 Fri 20/2/14
25 1st Fix Piping & Hanger Support Installation Works 4 8 days Wed 20/2/12 Thu 20/2/20
26 Final Fix Installation Works (Sanitary Wear, Basin) 7 days Wed 20/3/11 Wed 20/3/18
27 5th Storey 10 days Tue 20/3/3 Fri 20/3/13
28 Concealed Piping 5 3 days Tue 20/3/3 Thu 20/3/5
29 1st Fix Piping & Hanger Support Installation Works 5 6 days Tue 20/3/3 Mon 20/3/9
30 Final Fix Installation Works (Sanitary Wear, Basin) 4 days Thu 20/4/2 Mon 20/4/6

Task Inactive Summary External Tasks


Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Project Schedule f Summary Manual Summary Rollup Progress
Date: Mon 19/9/9 Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only

Page 1
Summit Park View Hotel - Project Schedule for Plumbing and Sanitary System
ID Task Task Name Duration Start Finish August September October November December January February March April May
Mode E B M E B M E B M E B M E B M E B M E B M E B M E B M
31 6th Storey 10 days Tue 20/3/24 Fri 20/4/3
32 Concealed Piping 6 3 days Tue 20/3/24 Thu 20/3/26
33 1st Fix Piping & Hanger Support Installation Works 6 6 days Tue 20/3/24 Mon 20/3/30
34 Final Fix Installation Works (Sanitary Wear, Basin) 4 days Wed 20/4/22 Sat 20/4/25
35 Roof 6 days Sat 20/4/4 Fri 20/4/10
36 1st Fix Piping & Hanger Support Installation Works 6 days Sat 20/4/4 Fri 20/4/10
37 Major Equipment Installation 131 days Mon 19/11/11 Fri 20/4/10
38 Sump Pump Installation 3 days Wed 19/11/13 Fri 19/11/15
39 Transfer Pump Installation 5 days Mon 19/11/11 Fri 19/11/15
40 Heat Pump C/W Calorifier Installation(LG) 5 days Mon 19/11/11 Fri 19/11/15
41 Concrete Water Tank Installation 3 days Wed 19/11/13 Fri 19/11/15
42 FRP Tank Installation 3 days Wed 19/11/13 Fri 19/11/15
43 Fresh Water Treatment Plant 6 days Sat 19/11/9 Fri 19/11/15
44 Grease Trap Installation 2 days Thu 19/11/14 Fri 19/11/15
45 Petroleum Interceptor Installation 2 days Thu 19/11/14 Fri 19/11/15
46 Tube-well Installation 5 days Mon 19/11/11 Fri 19/11/15
47 Storm Water Storage Tank Installation 2 days Thu 19/11/14 Fri 19/11/15
48 Water Meter Compartment 2 days Thu 19/11/14 Fri 19/11/15
49 Septic Tank Installation 30 days Mon 20/4/6 Tue 20/5/12
50 Booster Pump Set Installation 3 days Wed 20/4/8 Fri 20/4/10
51 Overhead Tank Installation 3 days Wed 20/4/8 Fri 20/4/10
52 Heat Pump C/W Calorifier Installation(Roof) 5 days Mon 20/4/6 Fri 20/4/10

Task Inactive Summary External Tasks


Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Project Schedule f Summary Manual Summary Rollup Progress
Date: Mon 19/9/9 Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only

Page 2