Tigist Tsegaye
Tigist Tsegaye
Advisor:
I certify that this research work titled “Study on Construction Cost Accounting System of
State Owned Road Contractors: A Case Study on Ethiopian Construction Works
Corporations – Transport Infrastructure Sector” is my own work. The work has not been
presented elsewhere for assessment. Where material has been used from other sources, it
has been properly acknowledged /referred.
_________________________________
TIGIST TSEGAYE MOLLA | GSR/4447/10
DATE:
M.Sc. Thesis A.Y. 2020
ACKNOWLEDGEMENT
First and foremost I would like to thank the almighty God and his mother for supporting
me to accomplish this research. Then I would like to give my full heartiest gratitude to
my advisor, Abraham Assefa (PhD.) for his guidance and suggestion. Finally, I am most
grateful to all members of my family and friends for their understanding and support.
AAiT | SCEE i
M.Sc. Thesis A.Y. 2020
ABSTRACT
This research investigated the cost accounting system of state-owned road contractor by
taking Ethiopian Construction Works Cooperation‟s transport infrastructure sector as a
case study. The construction industry consumes different resources such as, material,
manpower and equipment which have to be managed properly to ascertain the profit. The
research is based on the problem of ascertaining the cost of each cost object in order to
evaluate the project status and helps the decision makers to make corrective measure on
time. The proper implementation of costing system is necessary to determine the
profitability of each cost object whereby management can identify whether the cost
object is contributing profit or loss. Both primary and secondary data collection were
used in this research. The primary data were obtained from the company using a
questionnaire and secondary data were obtained from company cost records, reports, and
cost accounting implementation manuals. Desk studies by randomly selecting three
ongoing projects were done for detail study on current system. Based on the collected
data, the detailed analysis has been conducted to find answers for the research question
and modified costing system was proposed.
The study found out that the organization does not have a structured and typical cost
accounting system. The respondents revealed that the company‟s current system is weak
when evaluating based on different requirements of the costing system. According to the
research, the ability of the current system in providing relevant information to decision-
makers for future planning and decision making is poor. Lack of training on updated cost
accounting techniques, difficulties in data collecting and gathering, and lack of adequate
information on cost data are the mostly occurred problem during implementing costing
system in the organization. It is recommended that the company should use the proposed
system of cost accounting to overcome the shortcoming of the current system based on
the data findings. The proposed costing system is expected to improve responsibility
center identification, cost determination, indirect cost allocation, variance analysis at
activity and resource level and data presenting format.
AAiT | SCEE ii
M.Sc. Thesis A.Y. 2020
ABBREVIATION
ECWC : Ethiopian construction works corporation
TICS : Transport infrastructure construction sector
ABC : Activity based costing
TC : Traditional costing
IGPG : International Good Practice Guidance
IFAC : International Federation of Accountants
PVA : Process Value Analysis
ICAI : The Institutes of cost accountants of India
PAVIC : Productivity Analysis with Video and Computer
TABLE OF CONTENTS
ACKNOWLEDGEMENT ................................................................................................. i
ABSTRACT ....................................................................................................................... ii
ABBREVIATION ............................................................................................................ iii
TABLE OF CONTENTS ................................................................................................ iv
LIST OF FIGURES ........................................................................................................ vii
LIST OF TABLES ........................................................................................................... ix
1. INTRODUCTION....................................................................................................... 10
1.1 Background ............................................................................................................. 10
1.2 Problem statement ................................................................................................... 11
1.3 Aim and Objective .................................................................................................. 12
1.4 Research question .................................................................................................... 12
1.5 Significance of the study ......................................................................................... 12
1.6 Scope and limitation of the study ............................................................................ 13
1.7 Structure of the research .......................................................................................... 13
2. LITERATURE REVIEW ....................................................................................... 14
2.1 Definition of cost ..................................................................................................... 14
2.2 Classification of cost ............................................................................................... 15
2.3 Accounting .............................................................................................................. 19
2.3.1 Financial accounting ......................................................................................... 20
2.3.2 Management accounting ................................................................................... 20
2.3.3 Cost accounting ................................................................................................ 20
2.4 Difference between cost accounting and financial accounting ............................... 21
2.5 Objectives of Cost Accounting ............................................................................... 22
2.6 Importance of cost accounting ................................................................................ 23
2.7 Method of costing.................................................................................................... 24
2.7.1 Job Costing ....................................................................................................... 24
2.7.2 Process Costing................................................................................................. 25
2.8 Process of cost accounting ...................................................................................... 26
2.8.1 Performance data recording .............................................................................. 26
2.8.2 Data processing................................................................................................. 28
2.8.3 Evaluating the performance .............................................................................. 28
2.8.4 Corrective decision making .............................................................................. 31
2.9 Overheads ................................................................................................................ 31
2.9.1 Overhead distribution ....................................................................................... 32
2.10 Cost Assignment ................................................................................................... 37
2.11 Costing systems ..................................................................................................... 38
2.11.1 Traditional costing system .............................................................................. 39
2.11.2 Activity-based costing .................................................................................... 40
2.12 Evaluating and improving costing in organizations .............................................. 42
2.12.1 Key Principles of Evaluating and Improving Costing in Organizations ........ 43
AAiT | SCEE iv
M.Sc. Thesis A.Y. 2020
AAiT | SCEE v
M.Sc. Thesis A.Y. 2020
AAiT | SCEE vi
M.Sc. Thesis A.Y. 2020
LIST OF FIGURES
Figure 1: Cost Assignment Method (Drury, 2012) ........................................................... 38
Figure 2: Costing System Classification ........................................................................... 39
Figure 3: Cost systems – Levels of sophistication (Drury, (2012)) .................................. 40
Figure 4: Types of research (Kumar, 1999) ...................................................................... 52
Figure 5: Method of data collection (Kumar,2011) .......................................................... 59
Figure 6: Respondents year of experience ........................................................................ 65
Figure 7: Costing system of the company......................................................................... 67
Figure 8: Allocation of project overhead .......................................................................... 68
Figure 9: Level of using computer tools ........................................................................... 69
Figure 10: Determination of Cost ..................................................................................... 71
Figure 11: Providing of relevant cost data for decision-makers ....................................... 72
Figure 12: Performance evaluation ................................................................................... 73
Figure 13: Efficiency controlling of the current system ................................................... 74
Figure 14: Ascertainment of the profit.............................................................................. 75
Figure 15: Serving as an effective information system .................................................... 75
Figure 16: Identifying the profitable and unprofitable activity ........................................ 76
Figure 17: Ability to forecast ............................................................................................ 77
Figure 18: Satisfaction of staff with the current system ................................................... 77
Figure 19: Costing system of the company....................................................................... 81
Figure 20: Determination of cost ...................................................................................... 84
Figure 21: Providing Relevant Cost Data ......................................................................... 85
Figure 22: Performance Evaluation .................................................................................. 85
Figure 23: Efficiency controlling ...................................................................................... 86
Figure 24: Ascertainment of profit ................................................................................... 87
Figure 25: Serving as an effective information system .................................................... 87
Figure 26: Identifying profitable and unprofitable activity .............................................. 88
Figure 27: Ability to forecast ............................................................................................ 89
Figure 28: Satisfaction with the current system ................................................................ 89
Figure 29: Corporate Structure of ECWC ........................................................................ 93
Figure 30: TICS Organizational Structure ........................................................................ 94
Figure 31: Cost accounting manual implementation procedure of ECWC TICS ............. 96
Figure 32: Cost accounting analysis flow chart ................................................................ 97
Figure 33: Data collection procedure ............................................................................. 101
Figure 34: Daily activity actual cost analysis ................................................................. 103
Figure 35: Summary of activity actual Cost ................................................................... 104
Figure 36: Variance Analysis.......................................................................................... 106
Figure 37: Proposed cost accounting system structure ................................................... 111
Figure 38: Actual cost and earned value variance analysis for Dulecha –Awash Arba
project ............................................................................................................................. 122
Figure 39: Variance analysis for site clearing for Dulecha –Awash Arba project ........ 125
Figure 40: Variance analysis for cut and borrow to fill for Dulecha –Awash Arba project
......................................................................................................................................... 126
Figure 41: Variance analyses for Rock fill in embankment for Dulecha –Awash Arba
project ............................................................................................................................. 127
Figure 42: Variance analyses for sub-base layer construction for Dulecha –Awash Arba
project ............................................................................................................................. 128
Figure 43: Variance analyses for base- course layer construction for Dulecha –Awash
Arba project .................................................................................................................... 128
Figure 44: Variance analyses for asphalt concrete surfacing construction for Dulecha –
Awash Arba project ........................................................................................................ 129
Figure 45: Variance analyses for class 'B' stone masonry construction for Dulecha –
Awash Arba project ........................................................................................................ 130
Figure 46: Variance analyses for class 'C' concrete construction for Dulecha –Awash
Arba project .................................................................................................................... 130
Figure 47: Variance analyses for backfill with selected material construction for Dulecha
–Awash Arba project ...................................................................................................... 131
LIST OF TABLES
Table 1: The Difference between Financial Accounting and Cost Accounting (ICAI,
(2012))............................................................................................................................... 22
Table 2: Common problems in implementing costing, (Nangan 2012)............................ 46
Table 3: Cost accounting implementers (experts) ............................................................ 57
Table 4: Management Staffs ............................................................................................. 57
Table 5: List of Responses ................................................................................................ 63
Table 6: Educational Background of Respondents ........................................................... 64
Table 7: Objectives of implementing cost accounting ...................................................... 66
Table 8: Problems Encountered ........................................................................................ 69
Table 9: Respondents comment ........................................................................................ 78
Table 10: Respondent Profile............................................................................................ 79
Table 11: Respondents' Experience .................................................................................. 79
Table 12: Objectives of implementing cost accounting .................................................... 80
Table 13: Encountered problems during implementation ................................................. 82
Table 14: Respondents' Suggestion .................................................................................. 90
Table 15: Comparison between ECWC TICS system and ICAI or IFAC ...................... 108
Table 16: Comparison between the existing system and proposed system .................... 112
Table 17: List of consumed resource, Dulecha – Awash Arba road project .................. 115
Table 18: List of responsibility centers for Dulecha –Awash Arba project ................... 117
Table 19: List of cost allocated to support center for Dulecha –Awash Arba project .... 118
Table 20: List of cost allocated to product centers Dulecha –Awash Arba project ........ 119
Table 21: Allocation of cost to cost objects for Dulecha –Awash Arba project............. 121
Table 22: Cost Variance Analysis for Dulecha –Awash Arba road project .................. 123
Table 23: Cost variance at resource level for Dulecha –Awash Arba project ................ 124
Table 24: List of responsibility center for Dimma-Rad road construction project ......... 132
Table 25: List of cost allocated to support center for Dimma-Rad road construction
project ............................................................................................................................. 133
Table 26: List of cost allocated to support center for Dimma-Rad road construction
project ............................................................................................................................. 134
Table 27: List of cost allocated to cost objects for Dimma-Rad road construction project
......................................................................................................................................... 135
Table 28: Variance analysis at activity level for Dimma-Rad road construction project 136
Table 29: Variance analysis at resource level for Dimma-Rad road construction project
......................................................................................................................................... 137
Table 30: List of responsibility center for Jinka Mender project.................................... 138
Table 31: List of cost allocated to support center .......................................................... 139
Table 32: List of cost allocated to product center ........................................................... 140
Table 33: List of cost allocated to cost objects for Jinka - Mender project .................... 141
Table 34: List of variance analysis at activity level for Jinka- Mender project .............. 142
Table 35: List of variance analysis at resource level for Jinka- Mender project ............ 143
AAiT | SCEE ix
M.Sc. Thesis
1. INTRODUCTION
1.1 Background
The construction industry is one of the foremost industries of today that has a great
impact on the economy of any nation. The industry has a huge contribution to sustainable
economic development by satisfying some of the basic objectives of development
including output generation, employment creation, and income generation and re-
distribution (Serdar & Syuhaida, 2012). It has also a significant role in satisfying basic
physical and social needs, including the production of shelter, infrastructure, and
consumer goods.
The industry is a complex business sector where the need for accurate costing systems is
more vital than any other since competitive bidding is deeply rooted in its tradition
whereby the lowest bidder wins the contract (Lehtonen, 2001). If a contractor wants to
involve in a competitive bid, maintaining proper costing systems is needed with sound
mechanisms for accurate cost allocation, apportionment and performance measurement.
Lehtonen,(2001) also argues that to produce performance information, a cost build-up for
each project must be done, after which the profitability of each project can be accurately
determined and management can identify which projects are contributing profits and
which are making losses.
Construction costs are classified based on traceability to cost objects as a direct and
indirect cost. These costs have to be allocated to each activity to obtain the total cost of
each cost object. Evanse,(2015) indicate that direct costs are those costs that can be
linked or traced to the final product or service offered, whereas indirect costs are
representing the consumption of company resources that are shared by its products. These
costs can be allocated to cost objects either by using a traditional costing system or
activity-based costing system.
In order to ascertain the profit and give relevant information to the managers cost
accounting system is very essential. Cost accounting aims to give management the basis
for decision making, improved efficiency and how to enhance the performance of
organization. From a managerial point-of-view, the effort to develop, implement and
AAiT | SCEE 10
M.Sc. Thesis
operate a cost system is justifiable only when the cost information provides effective
support for decision making (Evanse, 2015). Cost accounting measures, analyzes, and
reports financial and non-financial information relating to the costs of acquiring or using
resources in an organization (Charles, Srikant, & Madhav, 2015). It classifies, records,
allocates and appropriation expenses for the determination of cost of products or service
and the presentation of suitably arranged data for control and guidance of management
(Horngern, 1978).
This research aims to give some relevant understanding about the Ethiopian Construction
Works Corporation Transport Infrastructure Construction Sector (ECWC TICS) current
practice of cost accounting system, encountered problems during the implementation and
finally proposes a modified costing system. The proposed system is prepared to
overcome the shortcoming of the current system based on the data findings.
AAiT | SCEE 11
M.Sc. Thesis
leading to project cost overruns. This research will study on the overall system, method
and problems encountered in the actual implementation of cost accounting in ECWC
TICS and propose a modified costing system in order to fill the gap in the current system.
AAiT | SCEE 12
M.Sc. Thesis
prerequisites of a successful cost accounting procedure and the importance of such cost
control practices and processes.
AAiT | SCEE 13
M.Sc. Thesis
2. LITERATURE REVIEW
The terms „Cost‟ and „Expenditure‟ are used interchangeably to mention the same thing
in the field of business. Costs that are incurred for the production of a product or service
have to be determined, the techniques and process of ascertaining costs are known as
costing. Costing includes classifying, recording, allocation and appropriation of expense
to determine the cost of product or service and for the presentation of arranged data for
control and guidance of management (ICAI, Cost and managment accounting, 2012).
Terminology
A cost object is any activity, product, service or job order for which the cost is assigned.
Drury (2012) defines cost objects as any activities for which a separate measurement of
cost is desired. Carefully identifying the cost object is very crucial for a sound costing
system.
A cost pool is assembling the cost in a meaningful group in an organized manner. A cost
pool is defined by CIMA (2005), as a grouping of costs relating to a particular activity in
an activity-based costing system. In the case of a manufacturing organization, as regards
stores, cost of classification, cost of issue of store requisitions, inspection costs, etc. can
be pooled under the heading „stores‟ (ICAI, Cost and managment accounting, 2012). In
another word, it is the sum of the total cost assigned to an activity. (Charles, Srikant, &
Madhav, 2015)
Cost drivers are any factors that have the effect of changing the level of total cost.
Chales, Srikant, & Madhav, (2015) defines cost drivers as a variable, such as the level of
activity or volume that causally affects costs over a given period.
AAiT | SCEE 14
M.Sc. Thesis
Cost accumulation is a process of collecting cost data in some organized way (Charles,
Srikant, & Madhav, 2015). The accumulated cost is then assigned to designate the cost
object.
Cost assignment is a general term that encompasses both tracing direct costs to a cost
object and allocating indirect costs to a cost object. . Chales, Srikant, & Madhav, (2015)
defines cost assignment as gathering a cost in a cost pool and assigning it to a specific
cost object.
Cost allocation is the process of assigning costs when a direct measure does not exist for
the quantity of resources consumed by a particular cost object (Drury, 2012). It is a form
of cost assignment of indirect cost to a cost pool and cost object through the use of cost
drivers.
Cost sheet is a statement that shows various components of the total cost or per unit cost
in a systematic manner (ICAI, Cost and managment accounting, 2012). It is important for
ascertaining cost, fixing of selling price, cost control and facilitating managerial
decisions. The cost sheet can be prepared based on historical and estimated costs. In
historical cost basis, the cost sheet is prepared after the actual cost is incurred. Whereas
the estimated costs sheet is prepared before the commencement of production.
Depending upon the traceability of expenditure to cost object, cost can be classified into
the direct and indirect cost. Direct costs are an expense that is related to a particular cost
object and can be traced to it in a cost-effective (economically feasible) manner (ICAI,
Cost accounting, 2018). Otherwise, the cost component can be termed as an indirect cost.
For example, the costs of rock material in rock fill activity in construction considered as
AAiT | SCEE 15
M.Sc. Thesis
direct cost because it can be easily traced or identified with the rock fill activity. Whereas
the cost of the store, safety facility, workshops, offices, parking facilities can be
considered as an indirect cost because these costs are not particularly done for the rock
fill activity rather it is required to support the working crew all activity.
Costs should be gathered together in their natural groupings such as material, labor,
equipment and other expense. Material costs are any cost of material which are used for
the production of a product or provide a service. Labor cost indicates the payment made
to the permanent or temporary employees for a production of a product or rendering of
service. Equipment cost means the cost of machinery or any other equipment which are
used for the production of a product. For example, in construction firms activities use
different types of machinery and equipment, it is important to accurately estimate the
equipment cost as part of the total cost of the construction project. Expenses are other
than material, labor and equipment which are involved in an activity.
A company performs several functions like manufacturing, selling, research, etc. In this
case, costs may be required to be determined for each of these functions. For example,
functional cost for a manufacturing sector can be classified as production and
manufacturing cost, administration cost, selling and distribution cost, research and
development cost.
Based on the behavior in response to the change in the activity levels costs can be
classified as a fixed cost, variable cost, and semi-variable cost. Identifying these costs
provides valuable information for making management decisions and evaluating the
performance. Fixed cost is an expense that a company is obligated to pay which doesn‟t
vary with the change in the volume of activity. These costs are not affected by temporary
fluctuation in the activity of an enterprise and it is usually time-related. For example,
rent, depreciation, etc. Variable cost is an expense that changes or directly varies with the
total activity or volume of output produced. For example, direct material, piece-rate
AAiT | SCEE 16
M.Sc. Thesis
labor, etc. Semi-variable costs contain fixed and variable elements they are partly
affected by the fluctuations in the level of activities. Maintenance and supervision are a
good example.
1. Batch cost is total cost related to a cost unit which consists of a group of similar
courses which maintain its identity through one or more stage of production (ICAI,
Cost accounting, 2018).
2. Process cost
Some products are produced from a sequence of the continuous or repetitive process the
cost incurred during a period is considered as a process cost. This type of costing is
applied in industries where continuous manufacturing is carried out and the unit costs are
identified by dividing the process cost by the number of units produced during the period
(ICAI, Cost accounting, 2018).
The main purpose of ascertaining the cost is to provide relevant data for management to
make the decision-making process reasonable. For managerial decision making, cost data
can be analyzed keeping in view the following cost concepts:
Marginal costing is variable costs which indicate the rate at which the total cost of a
product increases or decreases due to the production increase by one unit (ICAI, Cost
accounting, 2018). Since fixed costs don‟t change with the change in the volume of
product the marginal cost is only influenced by the change in the variable cost.
Differential cost also known as incremental cost, is the difference between the total costs
because of the selection of one alternative to the other (Drury, 2012). It has a similar
principle with the marginal cost but the main difference is that the marginal costing
represents the increasing or decreasing of cost due to adding one extra unit of output,
AAiT | SCEE 17
M.Sc. Thesis
whereas incremental cost represents the additional cost/revenue resulting from a group of
additional units of outputs.
Opportunity cost is the cost that measures the revenue forgone or sacrificed because of
not making the best alternatives or choosing one option over the other (Charles, Srikant,
& Madhav, 2015). It refers to the return expected from an investment other than the
present one.
Replacement cost is the expense of an asset in the current market for the purpose of
replacement (ICAI, Cost accounting, 2018). It is useful in determining the optimum time
of replacement of an asset.
Relevant cost is costs which are relevant for a specific purpose and pertinent for making
a decision. Those costs can be changed by a decision whereas the other cost which is not
affected by the decision is irrelevant.
Imputed cost also known as „implicit cost‟ are a hypothetical cost that a firm forgoes by
taking one action or strategy over another. According to Drury (2012), this type of costs
isn‟t involving cash outlay computed only for the purpose of decision making. It is a type
of opportunity cost that cannot be recorded in the books of account but significant for
making a decision.
A sunk cost is the costs that have been incurred before where the decision will be
unaffected. These costs are irrelevant made in the past can‟t be changed by any decision
that will be made in the future (Drury, 2012).
Normal/Abnormal cost normal costs are the expenses that are usually incurred or
expected to incur at a given level of output (CIMA, 2005). Unusual or unexpected costs
occur due to abnormal situation of production is called abnormal cost.
Avoidable/unavoidable cost
Avoidable costs are those cost which can be kept by under a given performance
efficiency or by not adopting a given alternative, whereas unavoidable costs can‟t be
saved. Unavoidable costs are fixed cost which can‟t be eliminated or escape because they
are essential to be incurred to acquire the product.
AAiT | SCEE 18
M.Sc. Thesis
Historical costs are the actual costs of product or service which are determined after the
event. Those costs are ascertained after they have been incurred and they represent the
cost of actual operational performance.
Predetermined costs are computed based on the specification of all factors affecting the
cost and cost data which can be standard or estimated.
Standard cost is planned unit cost of a product, component or service (CIMA, 2005).
The predetermined calculation of the amount of cost from an assessment of the value of
cost elements correlates technical specifications and the quantification of materials, labor
and other costs, that will occur under the specified working condition. It is useful in
providing bases for controlling costs and efficiency.
Estimated cost is forecasting a cost based on the past performance which focuses on the
level of costs not to be exceeded. It is also used in price fixation and tendering.
2.3 Accounting
Accounting is a tool that transfers economical information to people who have an interest
in an organization such as the managers, shareholders, investors, and even for the
government (Drury, 2012). It is an art that focused on keeping records of receipts and
payments as well as income and expenditure (ICAI, Cost and managment accounting,
2012). Many kinds of literature named it as a “language for financial decision”. In any
business after gaining a sound knowledge on different types of cost which can occur in
the business, it is also crucial to have the proper format of recording the costs for the
future and present decisions. For accounting information to be appropriate for decision
making, the accountant who process the data must be conscious about for what is the
purpose the information be used and by whom (Sharma B. , 2007). There are many
groups of users of this information and each of these groups will have different needs for
accounting information (Atrill, 2009). According to ICAI (2012), it can be broadly
divided into 3 categories namely:
Financial Accounting,
AAiT | SCEE 19
M.Sc. Thesis
AAiT | SCEE 20
M.Sc. Thesis
Cost accounting differs from other types of accounting in such a way that it focuses on
the computation of cost on a scientific basis and thereafter controlling and reduction of
cost. One of the main objectives of cost accounting is to collect records and measure
numbers that describe economic activity such as amounts, prices, values, and other
quantities. Another main task of cost accounting is to create and use reports and
calculations based on these numbers for decision-making, to reduce the company's costs
and to improve profitability.
AAiT | SCEE 21
M.Sc. Thesis
Table 1: The Difference between Financial Accounting and Cost Accounting (ICAI, (2012))
AAiT | SCEE 22
M.Sc. Thesis
AAiT | SCEE 23
M.Sc. Thesis
1. Job Costing
2. Process Costing
AAiT | SCEE 24
M.Sc. Thesis
unit or multiple units of a distinct product or service called a job (Charles, Srikant, &
Madhav, 2015). For industries, when the production is not on a continuous basis, rather it
is only when order from customers is received as per the specifications and with a
different product in such type of business, organizations use Job Costing or Job Order
Costing. This creates the need for the cost of each unit to be calculated separately (Drury,
2012). A job may be a product, unit, batch, sales order, project, contract, service, specific
program or any other cost objective that is distinguishable clearly and unique in terms of
materials and other services used (ICAI, Cost and managment accounting, 2012). The
cost of a completed job will be the materials used for the job, the direct labor employed
for the same and the production overheads and other overheads if any charged to the job.
Job costing includes batch costing and contract costing
Batch Costing: is the extension of the job costing, used where units of a product
are manufactured in batches and used in the assembly of the final product. Thus
components of products like television, radio sets, air conditioners, and other
consumer goods are manufactured in batches to maintain uniformity in all
respects (ICAI, Cost and managment accounting, 2012). The cost per unit is
determined by dividing the costs of the batch by the number of units produced in
a batch.
Contract Costing: is a method used when the job is big and spread over a long
period (ICAI, Cost and managment accounting, 2012). Contract costing is used by
concerns like construction firms, civil engineering contractors, and engineering
firms.
AAiT | SCEE 25
M.Sc. Thesis
AAiT | SCEE 26
M.Sc. Thesis
entailed video recording of work operations and analyzing the film by connecting it to a
specially coded computer which was programmed to imprint time marks on the sound
track of the videotape and transform the recorded information into statistics such as
means, maxima, minima and standard deviation for each operation studied. Abubakhar
(1992), states three methods of performance data capturing that appear to be particularly
for construction projects are card recording system, computer-generated turn around the
system and graphical method.
1. Card recording system
In this system all items of expenditure on-site should be captured systematically and
progressively such as; labor operational time and cost, materials consumption and
wastage, equipment utilization, breakdown and idle time, overhead expenses, and costs
of subcontractors, subcontractor's . Depending on the activities to be carried out, a
foreman collects the relevant forms for labor, materials, plant, and attendance before
starting time each day and enters the relevant data through the day as the operations
proceed (Abubakhar, 1992). At the end of the day, he signs and drops the completed
forms at the site office where all the forms for that day will be processed. Clough, Searse,
& Koki (2008), have identified designed forms or cards as the most popular means of
capturing data on construction sites. Such forms include time sheets for labor, plant and
subcontractors, site diary, equipment utilization register, work quantity summaries, and
stores forms.
2. Computer-generated Turnaround Document
As the name indicates it is a communication tool of primary significance for conveying
information between the office environment and the job site. The turnaround document is
not much different from the card system. Each foreman picks up an exception printout of
his expected activities for the day from the (site) computer room and returns the
completed document at closing time for feeding into the computer. Strictly speaking, the
turnaround document is simply a case of the card system linked to the computerized
database and with automated processing and evaluation
3. Graphical method
This method of data capturing can be applied into generally small projects with very
simple schedules, repetitive projects and on management contracts where a main
AAiT | SCEE 27
M.Sc. Thesis
contractor schedules and monitors the activities of subcontractors. The foreman gets a
copy of the project schedule in bar charts or networks and shades the progress of his
operations on a daily, weekly or monthly basis and reports regularly to the management.
As Abubakhar, (1992) states this method is not effective in monitoring actual costs even
though it provides a good focus on the project schedule.
AAiT | SCEE 28
M.Sc. Thesis
1. Performance ratio
Performance ratio provides a more pragmatic approach to the evaluation of performance
data and involves direct matching of data on an activity by activity basis to provide a
basis for corrective decision-making (Abubakhar, 1992) . The formula for calculating
performance ratios is:
Performance Ratio (PR) = Actual performance (AP) x100%
Planned Performance (PP)
If PR> 1, something has gone wrong to warrant corrective action; or that as long as PR <
1, there is nothing wrong with the project, and that conditions are all favorable.
2. Variance analysis
Constriction project works are usually planned to ensure that work is carried out
according to the budget, to the desired quality and in the allowed time. Mostly
divergences from plans occur. Nevertheless, such divergences are expected because of
the nature of the work and uncertainties associated with it. So the progress of the project
is required to be monitored and compared as the work proceeds to be able to identify and
measure cost and time variances. Variance analysis helps to monitor the project at every
level of an organization. Kabiru and Abuh, (2013) states the basic concept of variance is
simply the difference between actual costs incurred and standard or budgeted costs
applied to an activity or service process in a period. When practical or realistic standards
of performance are put in place, taking into consideration wastage and other losses, and
the actual performance deviates positively or negatively from the predetermined level of
performance, then there will be a question of why cost variance has occurred.
Kabiru I. and Abuh A,(2013) states that when the variance occurs first, the management
should recognize that the variances are only a starting point, a clue for investigation and
secondly, from the viewpoint of control, these variances should be measured as soon as
possible. The longer the delay, the staler would be the data and the fewer the
opportunities for corrections (Horngern, 1978).
The analysis of variance will be based on the various elements of costs in a process,
usually into material, labor, equipment, and overheads. It is the analysis and comparison
AAiT | SCEE 29
M.Sc. Thesis
of the variables that had caused the variation between the standards and actual
performance to highlight and prevent wastes in whatever form. Dandago K.I and Tijjani
B, (2005), states material variance could arise from the instability of prices, a supply of
material and management lapses such as inefficient purchasing policy, the uncertainty of
required materials and mistakes, reversal of specification and inadequate resources. Labor
variances are said to be caused mainly by management lapses like the improper
determination of internal rate, provision for labor turnover and idle time, quality of labor
and poor conditions of the machine. And variances from overheads are due to changes in
production volume, labor disputes, poor production scheduling, poor production quality
and major shifts in demand for products. Abubakhar, (1992) state the general formula for
calculating variance as;
V = (A-P) R
Abubakhar, (1992), states different types of variances that have to be computed but not
limited for construction for each cost code or center. Such as:
1. LRV = labour rate (price) variance
2. LEV = labour efficiency variance
3. MPV = materials price variance
4. MUV = materials utilization variance
5. MYV = materials yield variance
6. EEV = equipment efficiency variance
7. ERV = equipment rate variance
8. OHV = overhead variance
9. TCV = total cost variance
AAiT | SCEE 30
M.Sc. Thesis
2.9 Overheads
As discussed earlier, based on the nature costs are classified as a direct and indirect cost.
Direct costs are those which are identifiable and traceable to the cost object while indirect
costs are not traceable to the cost object. If the company manufactures or produce only
AAiT | SCEE 31
M.Sc. Thesis
one product all cost is direct and easily traceable to the product but if more than one
product is offered by the firm the indirect costs are not traceable with a particular
product. This indirect or supplementary cost which cannot be wholly debited to a
particular job is called Overhead cost (ICAI, Cost and managment accounting, 2012). As
per CIMA,(2005) overheads comprise costs of indirect materials, indirect employees and
indirect expenses which are not directly identifiable or allocable to a cost object in an
economically feasible manner. Thus all indirect material, indirect labor and indirect
expense are called overheads. For example, rent, tax, depreciation, maintenance repairs,
supervision, etc.
After the overhead costs have been collected it is advisable to classify them according to
their category. Classification is defined by CIMA (2015) as, „the arrangement of items in
logical groups having regard together nature (subjective classification) or the purpose to
be fulfilled (Objective classification. Classification of cost in an accurate manner is a
prerequisite to any form of cost analysis and control system. It can be made according to
the following basis:
AAiT | SCEE 32
M.Sc. Thesis
Indirect material: can be defined as the costs of materials that cannot be directly
attributed to a particular product unit (ICAI, Cost accounting, 2018). For example,
lubricants used in a machine are indirect material.
Indirect Labour: These are indirect employee cost which cannot be directly attributed to
a particular cost object. Wages and salaries paid to indirect workers, i.e. workers who are
not directly engaged in the production are examples of indirect wages (ICAI, Cost and
managment accounting, 2012).
Indirect Expenses: are expenses, which cannot be directly attributed to a particular cost
object. For example, expenses such as rent and taxes, printing and stationery, power,
insurance, electricity, marketing and selling expenses, etc.
Administrative overhead these are costs that are incurred for running the general
management and administration of the organization (ICAI, Cost and managment
accounting, 2012). The expense may be for policy formulation, directing the organization
and controlling the operation of the organization. These costs are incurred for the benefit
of the organization as a whole.
Selling and distribution overheads are all indirect expenses related to sales
management for the organization. An expense incurred for getting an order from the
consumers is called selling expense whereas costs incurred for the execution and
handling of order from the time it is ready for dispatch until it reaches the consumers are
called distribution expense (ICAI, Cost and managment accounting, 2012). This overhead
AAiT | SCEE 33
M.Sc. Thesis
in the total cost would depend on many factors such as the nature of the product, type of
customers, spread of market, statutory restrictions, etc.
III. Classification based on behavior or variability
Fixed overheads also known as period cost are constant expenditures incurred during a
period without regard to the volume of production during that period (Maharshi
Dayanand university, 2004). These costs are not affected by the outputs of production
only when the change in output is not substantial. If the change in the output is
substantial these will increase and remain constant.
Variable overheads are costs that fluctuate in the same ratio to the volume of output. For
example, power, and selling commission.
Semi- variable overheads these are costs which are partly fixed and partly variable. For
example telephone costs. There are two types of semi-variable overhead, the expense
which changes with the change in the volume of output and the cost which remains
constant with a certain range of output, then jump up and remain constant for another
range and so on (Maharshi Dayanand university, 2004).
2. Departmentalization of overhead
The term departmentalization of overheads refers to creating the department in the firm
so that the overhead expense can be easily allocated and apportioned to the departments
like fabrication, assembling, maintenance, test room, etc (ICAI, Cost and managment
accounting, 2012). The process helps in the ascertainment of cost of each department and
control of expense. This involves the following stages:
AAiT | SCEE 34
M.Sc. Thesis
Absorption refers to charging of overheads of cost centers to different cost units in such a
way that each cost unit bears an appropriate portion of its share of overheads (Maharshi
Dayanand university, 2004). This is done by means of overhead rates. An overhead rate
refers to the rate at which the overheads are to be charged to different cost units. It can be
in the form of a rate per unit or percentage (Maharshi Dayanand university, 2004). ICAI,
AAiT | SCEE 35
M.Sc. Thesis
(2012) indicates several methods in determining the overhead rates such as actual,
predetermined overhead, blanket, and multiple rates.
Actual overhead rate is obtained by dividing the overhead expenses incurred during the
accounting period by actual quantum on the base selected (ICAI, Cost and managment
accounting, 2012). Assuming that the rates are worked out on a monthly basis the
formula is:-
Blanket overhead rates this may be absorbed either based on one single rate (known as
a blanket rate) computed for the factory or based on separate rates for each individual
department or cost center (ICAI, Cost and managment accounting, 2012). It is applied
where one product is manufactured or where work performed in different departments is
more or less on a uniform pattern.
Multiple overhead rates this method is most commonly used to determine the multiple
overhead rates, i.e. separate rates: for each producing department, for each service
department, for each cost center and for each product line (ICAI, Cost and managment
accounting, 2012). The multiple rates are worked out according to the below formula:
AAiT | SCEE 36
M.Sc. Thesis
AAiT | SCEE 37
M.Sc. Thesis
AAiT | SCEE 38
M.Sc. Thesis
overhead, absorption costing system, it can be divided into divided into traditional
costing system and activity-based costing system.
Direct
costing
Costing
System Traditional
costing
Absorption
costing
Activity
based costing
AAiT | SCEE 39
M.Sc. Thesis
There should be a linkage between the activities and the costs. Similarly, the
information should be available simultaneously which means that information
should be made available while the activities are going on. The information
available after the activity is over will not be of much use (Charles, Srikant, &
Madhav, 2015).
AAiT | SCEE 40
M.Sc. Thesis
CIMA, (2005) defines activity based costing as cost attribution to cost units based on
benefit received from indirect activities e.g. ordering, setting up, and assuring quality.
Activity-Based Costing has been introduced to overcome the limitations of traditional
costing systems.
AAiT | SCEE 41
M.Sc. Thesis
concept of a cost center. The cost pool is the point of focus or in other words, it is
the total cost assigned to an activity. It is the sum of all the cost elements
assigned to an activity.
Cost Drivers: - is any factor which causes a change in the cost of an activity.
(CIMA, 2005). Thus a cost driver is an activity that generates cost. Activity-
based costing is based on the belief that activities cause costs and therefore a link
should be established between activities and products. The cost drivers thus are
the link between the activities and the cost (ICAI, Cost and managment
accounting, 2012).
Identification of costs with the products: - The final stage in Activity based
costing is to identify the cost with the final products which can also be called as
cost objects. Cost objects include products, services, customers, projects and
contracts. As mentioned earlier, direct costs can be identified easily with the
products but the indirect costs can be linked with the products by identifying
activities and cost drivers. Thus Activity Based Costing is the process of tracing
costs first from resources to activities and then from activities to specific products
(ICAI, Cost accounting, 2018)
For effective implementation of an activity-based costing system, there is a need for
involvement of the staff and their training on a continuous basis (Maharshi Dayanand
university, 2004). Similarly, there is a need to review the working of the system at
periodic intervals and keep a follow up of the feedback received. These actions will
ensure the effective implementation of the system. Support of top management is also
required for the effective implementation of this system. Activity based costing system is
definitely a better system but much depends on the implementation of the same (ICAI,
Cost and managment accounting, 2012). Traditional cost systems tend to report less
accurate costs because they use cost drivers where no cause-and-effect relationships exist
to assign support costs to cost objects (Drury, 2012).
AAiT | SCEE 42
M.Sc. Thesis
be measured, accumulated and assigned to various processes and outputs to allow the
structure and operation of the organization to explained, understood and improved.
Costing, the accounting term that embraces these processes and expresses them using
money as a common language lies at the heart of managerial accountancy and, exercised
intelligently. Costing contributes to an understanding of how profits and value are
created, and how efficiently and effectively operational processes transform input into
output (IFAC, 2009). The information available in costing can be used to provide
feedback on past performance and motivate to change the future performance. IFAC,
(2009) states that costing for decision support is valuable for performance improvement,
value creation, “what if” analysis, and the effective and efficient application of an
enterprise‟s resources and processes.
AAiT | SCEE 43
M.Sc. Thesis
AAiT | SCEE 44
M.Sc. Thesis
The lack of top management support in the implementation of costing is one of the
common problems encountered in the implementation of the costing system. Wessels
S.and Shotter M(2000: 222) states that the intensity of the lack of management support
increases especially when the top management is more concentrated or focused on other
priorities in the firm, as being more important than the costing initiative or when costing
initiative is not aligned with the company strategy. Also, a key-related problem cited by
Wessels and Shotter,(2000) is that the implementation of costing is too time-consuming
for operational managers.
Marivic, (2004) quoted in Nangan, (2012), states that the difficulties in implementing
costing are technical and complex since the steps involved need detailed records of the
costs associated with producing products and services. Marivic, (2004), also observes that
employees lack of basic knowledge and skill of costing techniques. Sartorius, (2007)
states that other technical or resource obstacles include a difficult definition of cost
centers and cost drivers, a lack of adequate information or technology system, a difficult
accumulation of data needed for costing and a difficult integration of costing data with
another system. Also, Majid and Sulaiman, (2008) argue that the high cost of the
implementation, especially the cost of IT (purchasing and updating specific software) are
one of the resource constraints encountered by companies during the implementation of a
costing system. A study by Wessels and Shotter (2000), indicates that the lack of
adequate employee resources is also one of the resource constraints.
AAiT | SCEE 45
M.Sc. Thesis
According to Wessels and Shotter, (2000) the problems relating to a lack of coherence
with the organization‟s goal and culture are the incompatibility of costing with company
strategy, and inadequate training of managers, and inadequate training of implementers,
inadequate training of users and resistance to change in organizational culture.
Difficulty in identifying and defining cost centers and suitable cost drivers
AAiT | SCEE 46
M.Sc. Thesis
AAiT | SCEE 47
M.Sc. Thesis
set of processes and methodologies which can eradicate and minimize the waste from the
production process”.
The concept of lean construction is the application of lean concepts to the construction
industry. According to Kramer, Henrich, Koskela, and Kagiolou (2002) quoted in
Evanse, (2015) lean construction tries to manage and improve construction processes at
low cost and with maximum value through a consideration of customer value. Similarly,
ABC aims to add value and reduce wastage by eliminating non-value adding activities
(Evanse, 2015). Both lean construction theory and ABC systems emphasize customer
value additions and product quality.
Using the traditional cost account information has become mostly irrelevant and even
dangerous for managerial purposes (Kaplan & Cooper , 1997). According to Johnson &
Kaplan (1987) cited in Evanse, (2015), states that traditional management accounting
information tends to be too late, too aggregated and too distorted to be relevant for
production planning and control. According to Marchesan, and Formoso, (2013) the
AAiT | SCEE 48
M.Sc. Thesis
According to Marchesan, and Formoso, (2013) some alternatives for traditional cost
accounting systems have been developed, aiming to regain the managerial relevance of
cost information. One of these alternatives is the activity-based costing (ABC) method,
which has been suggested as the leading contender to replace traditional cost accounting
methods due to its capability to make the processes and activities performed in an
organization transparent and observable. The information produced by ABC cost systems
can increase process transparency, guiding to identify non-value adding activities and
take the necessary corrective actions (Kaplan & Cooper , 1997).
According to Kim & Ballard, (2002), traditionally construction companies use resource-
based costing (RBC) and volume-based allocation to deal with the problem of allocating
indirect costs to cost objects. The system of allocating overheads directly to cost objects
by the resource is known as resource-based costing, whereas volume-based allocation
refers to a system of cost allocation in which costs are assigned to products or services
using direct labor hours consumed or contract value. The difficulty with the current
system is that companies do not obtain accurate project costs because they fail to allocate
overhead costs, or they use a uniform cost driver to assign overhead costs to work
divisions (Kim & Ballard, 2002).
This makes it difficult to find where the money is being made or lost because progress
payments for each work division contain overhead costs (Kim & Ballard, 2002).
Therefore, using the current system of overhead allocation, contractors may be unable to
reduce or influence profitability since the system does not pinpoint how much the
contractor has spent on each section of the project (Evanse, 2015). ABC was chosen as
AAiT | SCEE 49
M.Sc. Thesis
the conceptual basis of the proposed system for its capability to provide a better
understanding of the processes and the activities performed, as well as for its affinity with
the new operations management ideas.
Donizetti, (2015) classifies the cost accounting system for manufacturing industry into
three main parts chart of account, responsibility center, and allocations system. A chart of
account is related to the acquirement of resources. This resource has to be classified
based on destination to the responsibility centers; each center contains costs related to
activities done in that center. Responsibility centers are classified as a support center and
product center. Support centers are a department or a section that is not directly involved
in performing the activity but it gives support to the production department or unit.
Whereas product centers are a subdivision of cost objects which has a direct relationship
with the final product or service. Finally, the costs which are classified as a support
center and product center have to be allocated to the product or cost objects.
AAiT | SCEE 50
M.Sc. Thesis
3. RESEARCH METHODOLOGY
3.1 Introduction
Kothari (2004), defines research as the systematic method consisting of enunciating the
problem, formulating the hypothesis, collecting the facts or data, analyzing the facts and
reaching certain conclusions either in the form of the solution toward the concerned
problem or in a certain generalization for some theoretical formulation. Singh (2006),
stated that research is simply the process of arriving as a dependable solution to a
problem through a planned and systematic collection, analysis and interpretation of data.
AAiT | SCEE 51
M.Sc. Thesis
From the above classification, this research is descriptive and analytical, applied and
quantitative research. It is analytical as it uses the company‟s existing cost accounting
reports to study the overall system; It is applied as it tries to find the solution for the
problem areas in implementing the system and propose a modified cost accounting
system for the company; It is descriptive as it tries to describe and find out the facts about
the cost accounting system of the company; It is quantitative as it tries to quantify the
response of the company employees through questionnaires.
AAiT | SCEE 52
M.Sc. Thesis
previous research. The research is designed to collect data through questionnaires and
desk study and then the collected data will be analyzed by using computer tools and
statistics. Finally, conclusion and recommendation will be made based on the
research findings.
AAiT | SCEE 53
M.Sc. Thesis
1. ECWC TICS undertakes most of the large and complex projects all over the country
that are given to local contractors; hence, the impact of any improvement achieved will
significantly contribute to the overall improvement of the contractor‟s performance.
AAiT | SCEE 54
M.Sc. Thesis
2. ECWC TICS has many types of machinery and human resources in addition to
organizational and financial capability than private contractors; hence they are better
suited for studying the costing system.
3. The contractor is handled by the state and constructs different governmental projects.
To ensure that the public properties are used efficiently their costing system has to be
studied.
By considering the above methods, this research purposively selects the Ethiopian Road
Construction Corporation Transport Infrastructure Construction Sector (ECWC TICS) to
study longitudinally the company‟s costing system. After identifying the sample size of
the research, the respondents were selected purposively gather the desired information
through questionnaires. Then from those ongoing road construction projects for an in-
depth study of the actual system, 3 projects have been randomly selected and a detailed
study has been undertaken.
AAiT | SCEE 55
M.Sc. Thesis
AAiT | SCEE 56
M.Sc. Thesis
Number of Total
questionnaire number of Total number
Respondent to be distribute project in of Remark
per each the questionnaire
project organization
Project One project
1
Manager manager &
18 36 counterpart
Counterpart engineer for each
1
Engineer project
Project
For all 4 team
management
1 4 4 leaders of the
Team
company
leaders
Engineering
For all 6 team
service and
1 6 6 members of the
marketing
company
team
Therefore, there are a total of 82 respondents for this research, 36 from implementers and
46 from management staff.
AAiT | SCEE 57
M.Sc. Thesis
As we can see from the above table there are 86 populations in this study. Yamanes,
(1967) provides a simplified formula to calculate the sample size.
n = ___ N ___
1+N(e)2
Where, n is the sample size, N is the total population size and e is the margin of error.
Therefore, by using Yamanes, (1967) formula the sample size for implementers survey,
where N is 36, 95% confidence level and 5% margin of error is:
n = ___ 36 ___
1+36(0.05)2
= 33 peoples
Using same formula the sample size for management staff survey, where N is 50, 95%
confidence level and 5% margin of error is:
n = ___ 46 ______
1+46(0.05)2
= 42 peoples
Therefore, 75 sample size shall be used in this research.
AAiT | SCEE 58
M.Sc. Thesis
the first time and thus happen to be original. The secondary data, on the other hand, are
those which have already been collected by someone else and which have already been
passed through the statistical process. Kumar (2011), states that primary data are the data
collected from primary sources such as observation, interview and questionnaire, and
secondary data are collected from secondary sources like government publication, earlier
research, census, personal records, client histories and service records.
This research uses both primary and secondary data collection. The primary data refers to
the data which was obtained from the company by using questionnaires. Both open and
close-ended questionnaires were used as a primary data collection method for this
research. Secondary data was obtained from the company‟s existing records, reports, and
cost manuals. In the secondary data collection, the real information about how the
companies are implementing the cost accounting system, the methods and overall
practice were gathered.
AAiT | SCEE 59
M.Sc. Thesis
Furthermore, a literature review was used as one of the secondary data collection
methods to gather information about the concept, method, techniques, and practice of
cost accounting in construction and other businesses. Depending on the information
obtained from this review then used to evaluate the current system of costing, identify
which method of costing was used and modifying the existing system from other
countries experience. Thus, the study made use of several sources of literature such as
relevant books, journals, related websites on the internet, and other documents that are
related to the topic used under study.
AAiT | SCEE 60
M.Sc. Thesis
schedule and the respondent or the investigator ticks the category that best describes the
respondent‟s answer. It is usually wise to provide a category „Other/please explain‟ to
accommodate any response not listed. In this research, the questionnaire was addressed to
company experts, management staffs and marketing department.
According to (Kumar, 2011) there are three types of validity face and content, concurrent
and predictive, and construct validity. When each question or item on the research
instrument has a logical link with objective face validity will be established. Content
validity assesses the extent to which the measurement covers all aspects of the concept
being measured. Predictive validity is judged by the degree to which an instrument can
forecast an outcome. And concurrent validity is judged by how well an instrument
compares with a second assessment. Construct validity is based up on statistical
procedure and is determined by ascertaining the contribution of each construct to the total
variance observed in a phenomenon. In this research the face validity has been
maintained.
The reliability and validity of a research results depends on creating strong research
design, choosing appropriate methods and samples, and conducting the research carefully
and consistently. To ensure the validity and reliability, this research use a standardized
questionnaire based on established theories or findings of previous studies which is
targeted to measure exactly what the research wants to find out. Also this research uses
AAiT | SCEE 61
M.Sc. Thesis
AAiT | SCEE 62
M.Sc. Thesis
4.1 Introduction
This chapter analyzes the data gathered through questionnaire and desk study from the
cost accounting system implementers and decision-makers of the ECWC TICS. A total of
75 questionnaires were distributed to both implementers and decision-makers or
management staff. The document refereed during desk study includes cost accounting
reports, manual and cost data records of the company. In this chapter, the response rate,
research findings from the analysis of responses and the desk study results will be
discussed. The complete survey questions are presented in the Appendix B and C.
Table 5 indicates that the total questionnaires distributed in the study for both the cost
accounting implementers and for management staffs 56 or 74% out of 75 questionnaires
were fully completed and returned, while the remaining 9 or 12% were returned
incomplete and 10 or13% unreturned. The completed questionnaires were analyzed in the
AAiT | SCEE 63
M.Sc. Thesis
following sections in accordance with the content classification. This response was
considered adequate for the purpose of the statistical analysis to be carried out.
Figure 6 indicates that out of 27 respondent 37% of the respondents have experience
within zero up to 5 years, 52% have five up to ten years and 11% have above ten years of
experience.
AAiT | SCEE 64
M.Sc. Thesis
60%
52%
50%
40% 37%
0-5
30%
6-10
20% Above 10
11%
10%
0%
Year of Experiance
The above table and figure indicate that the respondents were adequately trained,
experienced and positioned to provide credible answers to the research inquiries.
Furthermore, they would be capable of understanding and implementing any proposals
arising out of the investigations.
AAiT | SCEE 65
M.Sc. Thesis
other 2 7%
AAiT | SCEE 66
M.Sc. Thesis
As indicated in the Figure 7 11% of the 29 respondents revealed that the organization
uses direct costing system followed by 4% traditional costing system and the remaining
30% don‟t know about their organization costing system. These different answers on the
organization costing system indicate that there is a lack of training and knowledge on
different cost accounting systems and techniques in the company. This result indicates
that the company has to work more in training the staffs about cost accounting.
60% 56%
50%
40%
30%
30%
AAiT | SCEE 67
M.Sc. Thesis
project cost object. This result shows that the cost data that are presented for the decision-
makers are incorrect. This can lead the managers to make the wrong decision and
evaluating the performance based on unreliable data which finally faces the project to
unexpected cost overruns.
90%
78%
80%
70%
60%
50%
30%
22%
20%
10%
0%
Yes No
AAiT | SCEE 68
M.Sc. Thesis
80%
70%
70%
60%
52%
50%
40%
Technical constraint
AAiT | SCEE 69
M.Sc. Thesis
Resource constraint
Lack of adequate number of employee
resource in the cost accounting team 17 63% 7
Lack of implementation software or computer
tools 21 78% 3
Other 1 4%
The survey result revealed a lack of training on updated cost accounting techniques
selected mostly by the cost accounting implementers of the company as a problem
encountered during the implementation of the system. Out of 27 respondents, 93% of the
respondents choose a lack of training on updated cost accounting techniques. Difficulties
in data collecting and gathering selected by 89% of the respondent. The respondents also
revealed that lack of implantation software and difficulties in identifying and defining
cost drivers are selected as a problem by 78% and 74% respectively. Out of 27
respondents, 4% of them revealed that there is another problem encountered during the
implementation of the system. The problem which is not listed in the list is the lack of
raw materials for print out and present the relevant data.
AAiT | SCEE 70
M.Sc. Thesis
1. Cost determination
Determination of the cost of a product is one of the primary aims of the costing system.
The respondents were asked to rate the effectiveness of their costing system in
determining the costs of a product on per unit basis or total cost such as, cost per kg, cost
per meter, cost per liter, cost per ton etc. In figure10 it is indicated that 48% of the
respondent revealed the cost determination of the company costing system is good and
4% choose excellent. Out of 27 respondents, 22% rated the cost determination of the
current system as poor. In this regards most of the respondents are impressed with their
system in determining the costs of products per unit basis.
60%
50% 48%
40%
Poor
10%
4%
0%
Determination of cost
AAiT | SCEE 71
M.Sc. Thesis
The costing system should provide cost data in a systematic manner and actual
information about the cost to the management for the evaluating, future planning and
decision making. Providing relevant cost data for decision-makers is one of the
requirements of a costing system. As indicated in figure 11 out of 27 respondents 44%
rated the current costing system as poor in assisting the management or decision-makers
for planning and decision making by providing relevant cost data. Also, 30% and 19% of
the respondents revealed satisfactory and good. Out of 27 respondents 4% rate the system
with regarding to providing the relevant cost data for decision-makers as very good and
excellent.
50%
44%
45%
40%
35%
30%
30%
25%
Providing of cost data
20% 19%
15%
10%
4% 4%
5%
0%
Poor Satisfactory Good Very good Excellent
3. Performance evaluation
Evaluating the performance of the project based on the standards is one of the costing
system tasks. From the response, 37% of respondents revealed that the ability of their
costing system in allowing to evaluating and analyzing the performance was poor. Out of
27 respondents 26% thoughts, it was satisfactory, 30% of respondents choosing it was
good and the remaining 4% choose as very good and excellent. Figure 12 summarize the
AAiT | SCEE 72
M.Sc. Thesis
res
4%
4%
37% Poor
30% Satisfactory
Good
Very good
Excellent
26%
Different resources like labor, material, and machineries have to be used efficiently. To
control the cost of products the efficiency has to be controlled by avoiding
underutilization, idle time and spoilage of material. As summarized in the figure 13 37 %
of the respondents rated their costing system as poor in controlling the efficiency by
locating wastages, inefficiencies and other loopholes in the production processes.
Secondly, 26% of them rated as satisfactory and 33% of them rated good. This indicates
that the management is not impressed by the costing system of the company with regard
to efficiency controlling.
AAiT | SCEE 73
M.Sc. Thesis
40% 37%
35% 33%
30%
26%
25% Poor
20% Satisfactory
Good
15%
Very good
10%
5% 4%
0%
Conrolling the efficency
AAiT | SCEE 74
M.Sc. Thesis
60%
52%
50%
40%
10%
4%
0%
0%
Poor Satisfactory Good Very good Excellent
45%
41%
40% 37%
35%
30% Poor
25% Satisfactory
20% Good
15% Very good
15%
Excellent
10% 7%
5%
0%
0%
Serving as an effective information system
AAiT | SCEE 75
M.Sc. Thesis
Identifying the profitable and unprofitable activities in the costing system assists to
reduce wastage and give special consideration for an unprofitable activity. The
respondent rated the company costing system for identifying profitable and unprofitable
activities which help to reduce or eliminate wastages and inefficiencies such as
underutilization, idle time, spoilage of material, etc. As figured below out of the total
respondent 37% & 30% of the respondents rated poor and satisfactory respectively. The
remainder 26% ,4% and 4% of respondents rated as good, very good and excellent.
40% 37%
35%
30%
30%
26%
25%
10%
5% 4% 4%
0%
Poor Satisfactory Good Very good Excellent
8. Ability to forecast
The cause and effect relation of activities are useful for forecasting or predicting future
costs. The respondents were asked to rate the ability of the current costing system to
forecast from the past cause and effect relation. Out of 27 respondents, 48% of
respondents revealed that the ability of their costing system to forecast the future cost of
an activity was poor. The remainder 37%, 11%, and 4% were rated as satisfactory, good
and very good respectively.
AAiT | SCEE 76
M.Sc. Thesis
60%
50% 48%
11% Excellent
10%
4%
0%
0%
Ability to forcast
11%
Yes
No
89%
AAiT | SCEE 77
M.Sc. Thesis
The respondent also suggests different issues that have to be amended or added in the
current system which are listed as follows (Table 9).
AAiT | SCEE 78
M.Sc. Thesis
Table11 indicates that out of 29 respondent 55% of the respondents have experience of
zero up to 5 years, 34% have five up to ten years and 10% have above ten years of
experience. So they would be capable of understanding and implementing any proposals
arising out of the investigations.
AAiT | SCEE 79
M.Sc. Thesis
Eighteen of 29 respondents (62%) choose to determine the cost of an activity and cost
control and reduction as an objective of implementing cost accounting. Also, efficiency
control and profit ascertainment are selected by most of the respondents as 55% and 52%
respectively.
AAiT | SCEE 80
M.Sc. Thesis
Respondents suggested that there were other objectives of implementing cost accounting
such as to predict the profit and loss of the project and to capture the total cost of
production by assessing the variable and fixed costs of each step of production.
60% 55%
50%
40%
30%
24%
17% Costing system
20%
10%
3%
0%
0%
Direct costing Traditional Activity based I don’t know Other
system costing costing
system system
AAiT | SCEE 81
M.Sc. Thesis
The respondents were asked about the common problems they faced in cost accounting
reports during the decision-making process and their answer are summarized as table13.
Technical constraints
Incorrect assigning and allocation of cost
to each activity 12 41% 8
Difficulties in identifying the actual
project and head office overhead cost
16 55% 4
Using approximate data rather than
collecting the actual cost
13 45% 6
Absence of presenting easy and
understandable cost accounting reports 10 34% 9
As indicated in the survey result lack of adequate information about the cost data is the
most occurred problem in the system. Out of 29 respondents, 79% choose the lack of
adequate information about cost data as a problem in cost accounting reports. As
AAiT | SCEE 82
M.Sc. Thesis
discussed in the literature cot accounting aims to ascertain and control the cost of the
product. Table 13 revealed that 69% of the respondents chose late reporting of cost
accounting reports as a common problem of the system. Incorrect perception about cost
accounting doing it just for the purpose of reporting takes the third position, which is
selected by 66% of the respondent. Respondents were suggested that there were other
problems commonly faced in the decision-making stage. The problems which are not
listed in the question are incorrect data collection, using incomplete cost data and lack of
concern about the report.
AAiT | SCEE 83
M.Sc. Thesis
60%
50% 48%
40%
30% 28%
24% Determination of cost
20%
10%
0%
0%
Poor Satisfactory Good Very good
Providing relevant cost data for decision-makers is one of the requirements of a costing
system. The costing system should provide cost data in a systematic manner and actual
information about the cost to the management for the evaluating, future planning and
decision making. As indicated in figure21 out of 29 respondents 41% of them rated poor
when they are asked about the ability of the system in assisting the management for
planning and decision making.
AAiT | SCEE 84
M.Sc. Thesis
45% 41%
40% 38%
35%
30% Poor
25% Satisfactory
5% 3%
0%
0%
Providing relevant cost data
3. Performance evaluation
As discussed in the literature the performance evaluation of the project based on the sited
standards is an important task. From the response, 45% of respondents revealed that the
ability of their costing system in allowing to evaluating and analyzing the performance
was satisfactory. 28% of respondents thoughts it was poor, and 14% of respondents
choose it was good. Figure 22, summarize the result.
14%
28%
Poor
14% Satisfactory
Good
Very good
45%
AAiT | SCEE 85
M.Sc. Thesis
The efficiency or proper usage of different resources like labor, material, and machinery
is one of the main issues that the management staffs have to be highly concerned. To
control the cost of products the management should control the efficiency by avoiding
underutilization, idle time and spoilage of material. As summarized in the figure 23 41%
of the respondents rated their costing system as poor in controlling the efficiency by
locating wastages, inefficiencies and other loopholes in the production processes.
Secondly, 34% of them rated satisfactory. This indicates that the management is not
impressed by the costing system of the company with regards of efficiency control.
45% 41%
40%
34%
35%
30% Poor
25% Satisfactory
21%
Good
20%
Very good
15%
Excellent
10%
5% 3%
0%
0%
controlling the efficency
AAiT | SCEE 86
M.Sc. Thesis
of the company as poor in ascertaining the profitability in division wise, activity-wise and
unit wise.
40% 38%
35%
31%
30%
25%
20% 17%
Ascertainmnet of profit
15%
10%
10%
5% 3%
0%
Poor Satisfactory Good Very good Excellent
40%
34%
35%
Poor
30% 28%
Satisfactory
24%
25%
Good
20%
Very good
14%
15%
Excellent
10%
5%
0%
0%
serving as an effective information system
AAiT | SCEE 87
M.Sc. Thesis
Proper identifying of the profitable and unprofitable activities in the costing system
assists the managements to reduce wastage and give special consideration for an
unprofitable activity. The respondent rated the company costing system for identifying
profitable and unprofitable activities that help the management to reduce or eliminate
wastages and inefficiencies such as underutilization, idle time, spoilage of material, etc as
figured below. Out of the total respondent, 34% & 41% of the respondents rated poor and
satisfactory respectively. The remainder 17% and 7% of respondents rated as good, very
good and excellent.
45% 41%
40%
34%
35%
30%
Poor
25%
Satisfactory
20% 17%
Good
15% Very good
10% 7%
5%
0%
Identifying the profitable and unprofitable activities
8. Ability to forecast
The respondents were asked to rate the ability of costing system to forecast from the past
cause and effect relation. Out of 29 respondents, 45% of respondents revealed that the
ability of their costing system to forecast the future cost of activity was poor. The
remainder 21%, 17%, and 17% were rated as satisfactory, good and very good
respectively.
AAiT | SCEE 88
M.Sc. Thesis
50%
45%
45%
40%
35%
30% Poor
25% Satisfactory
21%
20% 17% 17% Good
3%
Yes
No
97%
AAiT | SCEE 89
M.Sc. Thesis
Finally, the management was asked to suggest what they would like to add or amend in
the current costing system of the company which is summarized in the Table14.
AAiT | SCEE 90
M.Sc. Thesis
ECWC acquire, own and administer irrigation dams, deep water wells and as may be
necessary water supply canals constructed and to be constructed by the federal
government budget and collect charges from the beneficiaries of such dams. The
Purposes for which the corporation is established are
AAiT | SCEE 91
M.Sc. Thesis
To make studies and forward proposals in line with directions given by the
ministry of public enterprises to get financial, technological and modern
administrative inputs (including attracting investment or to engage in investment )
to be competitive and profitable in domestic and overseas works ;
To sell and pledge bonds and to negotiate and sign loan agreements with local and
international financial sources in line with the directive issued by the Ministry of
Finance and Economic Co-operation and in accordance with policy direction
given by the Ministry of public enterprises ;
To undertake any other related activities necessary for the attainment of its
purposes.
AAiT | SCEE 92
M.Sc. Thesis A.Y. 2019/2020
AAiT | SCEE 93
M.Sc. Thesis A.Y. 2019/2020
AAiT | SCEE 94
M.Sc. Thesis
The cost accounting manual of the company stated that the implementation of the system
involving different personnel ranging from the general manager, deputy general
managers, division managers to road construction project manager and road maintenance
project manager to initiate, plan, evaluate and monitor the implementation of cost
accounting at road construction and road maintenance projects. It is facilitated by
preparing a document and giving training about cost accounting procedures to give a
clear image to all levels of management members about the benefits and advantages of its
implementation. The cost accounting manual implementation procedure is shown in the
Figure 31.
AAiT | SCEE 95
M.Sc. Thesis
AAiT | SCEE 96
M.Sc. Thesis
office Engineer, one accountant, one quantity surveyor and data encoder under
engineering service team leader. The cost accounting analyzing team is responsible for
the weekly computation of actual cost and weekly analysis of variance after properly
collecting data of labor, material, equipment, and overhead for a given road construction
or maintenance activity. The cost accounting analysis flow chart of the company is shown
in Figure 32.
AAiT | SCEE 97
M.Sc. Thesis
However, most projects don‟t have the cost accounting team as per the manual. They
consist of data collectors to collect data, office engineers to analyze and engineering
service team leaders to check the overall analysis process. Since the office engineer is
appointed for additional tasks of the project, this could influence the office engineer‟s
work in cost accounting reports.
In the cost accounting manual, it is stated that indirect expenses incurred from a project
which are associated with the construction of road project activities are summarized as
actual overhead cost of that particular project. The computation of actual overhead cost is
the summation of the project actual overhead cost & head office actual overhead cost for
assisting the given project. The project‟s head office overhead costs are being supplied
by the head office finance department. The computation of actual overhead cost should
be worked out at the project, based on the actual recorded data, by the cost accounting
analyzing team on a monthly basis. Project actual overhead cost is different from project
to project and which is highly dependent on project performance, location, topography,
weather, security, and size and type.
The head office overhead cost includes three costs; the cost of the head office supporting
department, cost of head office road construction and maintenance division and the cost
of equipment maintenance and administration department. Costs other than road
construction and road maintenance divisions are allocated to project costs depending on
the level of support that the head office provided to the respective projects. Road design
& construction division overhead costs are allocated to the various road construction
projects and the road maintenance division overhead costs are allocated to the various
road maintenance costs. The overhead costs of equipment maintenance and
administration costs are allocated to various projects (construction and maintenance).
AAiT | SCEE 98
M.Sc. Thesis
As per the manual, the computation of actual overhead cost should be worked out by the
project cost accounting analyzing team on weekly basis by computing the project actual
overhead costs based on the daily recorded data and estimates the actual overhead costs
incurred by the head office for supporting that particular project in the week.
In ECWC TICS, mostly head office overhead costs were not considered in the
computation of the actual cost and in some reports the head office overhead cost included
but the allocation percentage was constant through all the time which leads to incorrect
computation of cost. In order to know the actual costs of projects and profit, the actual
head office overhead costs of each project have to be calculated and allocated fairly to
each project. Otherwise, it is difficult to know the financial status of the project so that
the managements make an incorrect decision based on false information. Head office
overhead costs have to be calculated based on the accurate costs which are incurred by
the head office in order to provide supports to that specific project. This cost can vary
from time to time so instead of using the constant amount of cost, the company has to use
the actual calculated overhead amount in order to determine the actual cost of the project.
In ECWC TICS project overhead percentage rates are calculated by summing up the total
overhead cost and dividing it to the expected revenue to allocating it for each activity.
Some reports indicate that they consider the same amount of cost or predetermined
overhead cost but the calculated amount of overhead cost has to be used in order to get
correct cost information.
AAiT | SCEE 99
M.Sc. Thesis
activity-based costing is cost attribution to cost units based on benefit received from
indirect activities e.g. ordering, setting up, and assuring quality. As a researcher can
observe ECWC TICS uses the ABC system. The overheads are charged to each cost
object or activity fairly accurately based on the benefit received from the indirect
activities.
ECWC TICS cost accounting manual states that the data collection for actual cost
accounting is accomplished by the work execution team leader. And this team is
responsible for assigning data collectors for each road activity and establish a network for
proper flow of recorded daily resource utilization data for labor, equipment, manpower,
and overhead data to cost accounting analyzing team during executing a given road
activity. Project site data collection activities involve personnel of data collectors,
foremen, site engineers, work execution team leader, and engineering service team
leader.
ECWC TICS had been capturing performance and cost data using the card recording
system. The daily cost and performance data are recorded by the data collector in the
daily data recording formats of the company. The format includes the crew of manpower
which are involved in such activity, material consumed and operated equipment for
performing an activity. Then the raw data collected by the data collectors are signed by
the foremen and approved by the work execution team leader, then send to the office
engineer for further analysis. Work Execution team leader is responsible for the daily
field data collection of resource utilization of labor, equipment, material and site
overhead for actual cost accounting.
In ECWC TICS the captured raw data were classified, accumulate and analyzed in order
to give meaningful information for the decision-makers and evaluating the performance.
Beliveau (1984) and Clough, (1979) suggested that data processing on construction sites
be carried out in a standardized format, preferably similar to the data capture approach.
The raw cost data gathered from the data collector are inserted in a different excel
spreadsheet to calculate the direct cost and total cost including the overhead cost. First,
the daily activity cost data including labor, material and equipment cost were inserted in
the daily actual cost analysis sheet. In this sheet, the direct cost for the executed quantity
for each day and each activity was analyzed. Figure 34 indicates the direct cost analysis
format of the company.
The summary of daily executed activity and their corresponding cost are listed in the
summary of the daily activity cost sheet. In this sheet, the total cost of each executed
activity (cost center) including the overhead cost are calculated to get unit cost of each
activity.
The next step is collecting the executed quantity and costs of each day. The summary of
the executed activity together with its actual unit cost are listed in this sheet. This sheet
differs from the previous one by its calculation of actual cost. The total executed quantity
of each activity is summed up and their earned cost for corresponding activity was
summed and then the summed cost divided by the summed total executed quantity.
Finally, the overhead cost percentage rate will be allocated by multiplying with the total
direct cost. Figure 35 shows the format of the sheet.
Actual
Actual Equipment Actual Material Actual Overhead
Item Activity Actual Labor Cost(A) ActivityCostE=A+B+
Cost(B) Cost(C) Cost(D)
C+D
2100 CLEARING AND GRUBBING
21.01 Clearing and grubbing 2493.56 17435.31 0.00 3696.80 23625.67
32.02(b) Backfilling using imported selected material 51.07 144.32 127.39 56.64 379.42
32.07 Cast In Situ Concrete and Formwork
32.07(f) Class "C" Concrete (C-20) 696.26 2730.29 1592.96 903.51 5923.03
34.03 STONE MASONRY WALLS
34.03(b)iii Class 'B' Masonry for town Ditch 803.90 2096.59 238.50 565.02 3704.01
4000 EARTHWORKS
Cut and Borrow to fill with unlimited hauling distance
42.01(a)ii i) Compacted to 95% of modified AASHTO Density 4.42 54.05 26.90 15.37 100.75
42.01 (c) Rock fill in embankment 3.91 22.81 193.09 39.56 259.37
5100 SUBBASES
51.01 Gravel
275mmsub-base layer, 97%
max. thickness MDD,
Gravel AASHTO
sub-base T-180
layer, 97% MDD,
51.01(a)ii AASHTO T-180 32.93 48.34 103.43 33.25 217.95
5200 ROAD BASES
52.01 Base layer
Crushed construction
stone base, compacted in layers of maximum
52.01(b) ii 200mm thickness, to 100% compaction 16.36 33.37 543.19 106.73 699.64
61.01 Prime Coat
64.02 Asphalt Sufacing
50mm thick Asphalt Concrete Surfacing, 60/70 Penetration
8.55 232.40 10.32 45.23 296.48
64.02 (a) (ii)Grade Bitumen, Continously Graded, Medium Grade.
standard cost of an activity is the acceptable cost for a unit activity based on the market
price of resources, overhead and updated CMS manual & procedures. CMS is a standard
that has road construction activities together with their crew formation and expected
productivity. The company uses the CMS manual prepared by the company itself based
on the previously completed projects productivity experience and crew formation.
Establishing of road construction activity standard costs is used as target costs or basis for
comparison with the actual costs.
ECWC TICS uses CMS to evaluate the performance of a crew and its productivity. The
CMS manual consists of different activity and their allowable crew formation. Every
project has to form the working crew based on the manual and then the actual executed
quantity will be compared with the expected productivity as per the standard. Currently,
the company uses this standard for an effective measuring of productivity. If the
productivity is less than the expected it is maybe because of inefficient uses of resources
including labor, material, and machinery so the management can justify its loss and take a
corrective decision.
Even if the literature puts the different types of variance analysis in construction such as;
LRV = labour rate (price) variance, LEV = labour efficiency variance, MPV = materials
price variance, MUV = materials utilization variance, MYV = materials yield variance,
EEV = equipment efficiency variance, ERV = equipment rate variance, OHV = overhead
variance and TCV = total cost variance, the company perform only the total cost variance
at an activity and serious level. The following figure represents the variance analysis
formats at the serious and activity level in ECWC TICS.
8/20/2019-9/19/2019
Day works
Sub-Base,Road-
Site Clearance
BITUMINOUS
base&Gravel
Earth Works
SURFACING
AND ROAD
Structures
Drainage
Ancillary
Wearing
General
Course
Works
BASE
Activity Reference Total Cost
Series 11000
Series
Series
Series
Series
Series
Series
Series
Series
1000
2000
3000
4000
5000
6000
8000
9000
A Performance achieved per standard(BOQ)rate 10,232.07 89,476.17 2,713,600.30 723,741.23 464,245.60 4,001,295.38
B Actual cost incurred based on actual Cost rate 11,340.32 158,297.57 3,231,594.63 671,691.75 539,601.98 4,612,526.25
The variance is calculated by summing up the labor, material and equipment cost of each
activity, then by the total cost from the budget cost. The calculated variance may be
negative or positive depending on the cost. If the variance is negative something has gone
wrong and if it is positive then nothing is wrong but it doesn‟t mean that the project is
safe to get the planned profit. Since the company computes variance analysis only for
total cost at an activity and serious level the cause for variance can‟t be determined so it
is complicated to take a proper corrective measure on the result.
The cost accounting manual of the company states that the analysis report should be sent
weekly to the head office for project management purposes. Furthermore, the
summarized monthly cost accounting analysis report should be compiled with a monthly
progress report and submitted to the road maintenance and road construction project
management teams located at the head office. Accordingly, each project‟s cost
accounting analysis reports are evaluated at the head office management staffs by
referring the variances concerning actual costs and standard costs (BOQ rates). Then after
feedback based on the analysis evaluation is forwarded to each project so that the project
incorporates the suggested comments and manages project costs. However, the projects
are sending the cost accounting reports on 15days and a monthly basis. This will leads to
a lack of making corrective decisions on time. The project manager together with other
project management staff has to be the primary user of the cost accounting reports so that
they will decide on the time it will prevent the loss occurred during the time until the
feedback has come from the head office.
During the case study, the researcher can observe that mostly in the cost accounting
reports the comments or reasons out from the project management staffs are the negative
variance of the cost stated as that it is occurred because of over expected productivity of
standard or underestimation of the unit rate of the activity.
The researcher can observe that in the company taking corrective measures and decisions
are less practiced. This is because of the less detail computation of the variance and the
late reporting of the cost analysis. Mostly the cost accounting reports are prepared after
15days or a month of the completed activities. This can preserve the managers to make a
decision on time. And due to less detailed computation of the variance, it is unable to
know whether the variance is because of labor cost, material cost or equipment cost.
Identifying the cause of variance will lead to take the corrective decision so that restoring
the performance to the desired level or correct the standard can be done. If a positive
variance occurs in the analysis, the profitability analysis has to be done. Because
sometimes there might be positive variance while there is the desired profit variance. In
the ECWC TICS when there is a positive variance it simply took as the planned
performance achieved but the profitability has to be done.
After reviewing the cost accounting report the feedback about the overall reports sent to
the project from the head office. This feedback control comments about the variance,
crew formation together with their productivity, costs of labor, material and equipment
and overhead. The feedback is done to correct the action and overall system in the project
for the future.
Table 15: Comparison between ECWC TICS system and ICAI or IFAC
Currently the company has practiced cost accounting system by focusing on the
identification of the actual cost incurred for each cost object or activity during the
production. It is done by identifying the direct costs incurred and allocating the indirect
cost or overhead cost to the cost object. The direct cost is determined by summing up the
costs which are incurred particularly to that activity or cost object such as; labor, material
and equipment cost. Since the direct cost has a direct relation with the cost object it is
easy to trace the cost to each cost object, whereas indirect cost are shared to each cost
object by percentage allocation bases. The percentage value are taken from the estimated
overhead sets in the fixed unit rate or calculated by dividing the total indirect costs to the
expected revenue then the indirect costs are allocated by multiplying by the total direct
cost of each cost object. From the investigation evidence the existing system has two
main problems such as ignoring different expenses which are incurred and misallocate
the cost to the cost objects.
The proposed approach classifies the cost accounting system into three main parts
resource, responsibility center and cost objects. The system indicates that first all costs
incurred with in a specific reporting period has to be list out and then identify the
responsibility centers for the entire project. Depending up on their task the responsibility
centers can be divided in to support center and product center then the costs will be
allocated to each cost objects. Figure37 indicates the proposed cost accounting system
structure.
After identifying the total acquired cost the next step is assigning those cost to the
responsibility centers and grouped in cost pool. The responsibility center can be a unit or
department in an organization for which the resources are acquired. Basically
responsibility centers are classified as support center and product center. Support center
are a department or a section which is not directly involved in performing the activity but
it gives support to the production department or unit. For example, administrative
department, equipment maintenance department, procurement and supply management
team, etc. whereas product center has a direct relationship with the product or service
such as, borrow material production, asphalt placing, sub base material production, etc.
Table 16: Comparison between the existing system and proposed system
allocation.
Variance analysis
The variance analysis is done at Variance analysis is done to the
serious and general activity activity and resource level in order
level. to evaluate the performance of the
project. The resource cost variance
of labor, material, equipment and
overhead from the standard is
computed in order to ascertain
which resource is the cause for the
negative or positive variance
Data presentation
Cost data is presented only in The arranged cost data are presented
table format which is to the concerned body in easy and
complicated and difficult to understandable way. In addition to
understand. the table presentation format the cost
variance of each activities and
resources are presented graphically
in order to easily indicate the varied
activity and resource from the
standard.
The reference of Dulecha-Awash Arba , Dimma-Rad and Jinka Mender road construction
projects cost data is taken to test the proposed system.
4.6.2.1 Resources
The analysis of all the project cost incurred during the specified period is the first task
that has to be occurred. This is important firstly to identify the consumed resources in the
project and then to classify them into direct and indirect which is fundamental for the
configuration of costs. In addition it also prevents the chance of cost ignorance which is
one of the problems of current system. Table17 shows all the resources or cost incurred in
the project during the specified period
Table 17: List of consumed resource, Dulecha – Awash Arba road project
Table 18: List of responsibility centers for Dulecha –Awash Arba project
Table 19: List of cost allocated to support center for Dulecha –Awash Arba project
Table 20: List of cost allocated to product centers Dulecha –Awash Arba project
Table 21: Allocation of cost to cost objects for Dulecha –Awash Arba project
4,500,000.00
4,000,000.00
3,500,000.00
3,000,000.00
2,500,000.00
2,000,000.00
1,500,000.00
1,000,000.00
500,000.00 Actual Cost
-
Earned value
Figure 38: Actual cost and earned value variance analysis for Dulecha –Awash Arba project
During the specified period a total of 3,236,488.35 birr loss is incurred. This result
indicates the project is performing its work below the specified unit rate. The loss can be
because of the work methodology, ideal hours of man power and machineries or poor
productivity of the crews. For decision maker the result shown in table 22, is not enough
to identify the real cause of the loss. The cause of the loss can be occurred on labor,
material, equipment and overhead cost. Therefore, further detailed variance analysis is
necessary.
Table 22: Cost Variance Analysis for Dulecha –Awash Arba road project
8 Class 'C' concrete m3 3.78 30,384.95 8,038.35 3,581.38 30,384.95 13,537.62 (4,456.97) (16,847.34)
9 Backfill using selected material m3 268.00 128,273.02 478.63 232.99 128,273.02 62,441.32 (245.64) (65,831.70)
Total Cost 21,777.80 7,237,957.94 7,237,957.94 4,001,469.59 (3,236,488.35)
Table 23: Cost variance at resource level for Dulecha –Awash Arba project
I/N Cost Total cost Labour cost Material cost Equipment cost Overhead cost
35,000.00
30,000.00
25,000.00
20,000.00
Actual cost
15,000.00
Estimated cost
10,000.00
5,000.00
-
Total cost Labour cost Material Equipment Overhead
cost cost cost
Figure 39: Variance analysis for site clearing for Dulecha –Awash Arba project
160.00
140.00
120.00
100.00
40.00
20.00
-
Total cost Labour cost Material Equipment Overhead
cost cost cost
Figure 40: Variance analysis for cut and borrow to fill for Dulecha –Awash Arba project
500
450
400
350
300
250 Actual cost
200 Estimated cost
150
100
50
0
Total cost Labour cost Material cost Equipment Overhead
cost cost
Figure 41: Variance analyses for Rock fill in embankment for Dulecha –Awash Arba project
300
250
200
50
0
Total cost Labour cost Material Equipment Overhead
cost cost cost
Figure 42: Variance analyses for sub-base layer construction for Dulecha –Awash Arba project
1000
900
800
700
600
500 Actual cost
400
Estimated cost
300
200
100
0
Total cost Labour cost Material cost Equipment Overhead
cost cost
Figure 43: Variance analyses for base- course layer construction for Dulecha –Awash Arba project
the decision makers have to give a method to minimize the overhead and increase the
productivity.
450
400
350
300
250
Actual cost
200
Estimated cost
150
100
50
0
Total cost Labour cost Material Equipment Overhead
cost cost cost
Figure 44: Variance analyses for asphalt concrete surfacing construction for Dulecha –Awash Arba project
6000
5000
4000
1000
0
Total cost Labour cost Material Equipment Overhead
cost cost cost
Figure 45: Variance analyses for class 'B' stone masonry construction for Dulecha –Awash Arba project
9,000.00
8,000.00
7,000.00
6,000.00
5,000.00
Actual cost
4,000.00
Estimated cost
3,000.00
2,000.00
1,000.00
-
Total cost Labour cost Material Equipment Overhead
cost cost cost
Figure 46: Variance analyses for class 'C' concrete construction for Dulecha –Awash Arba project
600
500
400
100
0
Total cost Labour cost Material Equipment Overhead
cost cost cost
Figure 47: Variance analyses for backfill with selected material construction for Dulecha –Awash Arba project
B. Summary of results
The above results show that Dulecha-Awash Arba project has incurred negative variance
during the specified reporting period. Most of the variances are caused by
underestimation of the cost of resource and very high overhead cost. The contractual unit
rates of most activities are not well considering manpower and material availability in the
project. Most materials are available in the project far from the expected location and also
the actual equipment rental rates are higher than the expected. As indicated in the above
variance result overhead costs are the main causes for loss in all activities. The overhead
is estimated to be 10% of the direct cost but the actually calculated rate is 60% of the
direct cost. The cause for this high cost of overhead is the presence of large number of
unnecessary manpower hired to create work chance for the society. In order to minimize
loss the project should either reduce the overhead or increase the volume of executed
quantity.
By the same procedure the system was tested for Dimma- Rad and Jinka- Mender road
projects. The system result for both projects is described below.
Table 24: List of responsibility center for Dimma-Rad road construction project
Table 25: List of cost allocated to support center for Dimma-Rad road construction project
2
Contract employees payment 327,744.70
3 Overtime Payment 423,252.28
4 Deseret allowance 160,689.41
5 Housing allownace 18,142.46
6 Communication expense
7 Fuel 153,354.49
8 Oil & lubricant 3,979.97
9 Spareparts 51,834.19
10 Tyre & tubes
Electrical Supplies
11
12 Equip. Rent expense
13 Entertainment
14 clothing and linen supplies 132,965.28
15 Food & Supplies 4,210.00
16 Medical supplies
Table 26: List of cost allocated to support center for Dimma-Rad road construction project
Excuted
I/N Product center Quantity (m3) Cost per m3 Total cost
1 Borrow material production 36.32 151,962.88
Cost allocation to cost object for Dimma –Rad road construction project.
Table 27: List of cost allocated to cost objects for Dimma-Rad road construction project
Variance analysis at the activity level for Dimma- Rad road project.
Table 28: Variance analysis at activity level for Dimma-Rad road construction project
275mm max.thickness gravel sub-base m3 519.00 153,287.69 295.35 246.64 153,287.69 128,006.16
4 layer, 97% MDD,AASHTO T-180 (48.71) (25,281.53)
Overhead
I/N Cost Labour cost Material cost Equipment cost cost
Summary of cost for cut and borrow to fill
1 Actual cost 9.91 84.34 38.98 91.93
2 Estimated cost 5.82 96.09 21.10 30.75
Variance (4.09) 11.75 (17.88) (61.18)
Summary of cost for capping layer
1 Actual cost 10.79 99.01 50.48 110.59
2 Estimated cost 10.16 105.03 33.75 37.24
Variance (0.63) 6.02 (16.73) (73.36)
Summary of cost for sub-base layer construction
1 Actual cost 14.91 91.97 67.39 120.25
2 Estimated cost 12.79 125.12 44.78 45.67
Variance (2.12) 33.15 (22.61) (74.57)
Summary of cost for base- course layer construction
1 Actual cost 14.79 433.61 62.53 352.54
2 Estimated cost 12.96 393.07 47.85 113.47
Variance (1.83) (40.54) (14.68) (239.07)
Summary of cost for Asphalt concrete surfacing construction
1 Actual cost 2.34 206.96 8.80 150.49
2 Estimated cost 1.27 260.34 3.70 66.33
Variance (1.07) 53.38 (5.10) (84.16)
Summary of cost for Stone masonry walls in check dams, retaining walls, end wall,
1 Actual cost 1,284.07 458.09 1,202.09
2 Estimated cost 920.11 869.03 125.29 478.61
Variance (363.96) 410.94 125.29 (723.48)
Summary of cost for cast in situ concrete construction
1 Actual cost 812.15 1,879.90 1,140.21 2,644.26
2 Estimated cost 569.38 2,792.83 511.56 968.44
Variance (242.77) 912.93 (628.65) (1,675.82)
Summary of cost for cement-mortared stone masonry walls (Class 'B' stone masonry)
1 Actual cost 1,018.97 575.91 832.29 1,674.75
2 Estimated cost 920.11 869.03 125.29 478.61
Variance (98.86) 293.12 (707.00) (1,196.14)
11 Asphalt surfacing
Stone production & hauling for retaining
12 wall
Stone masonry construction for retaining
13 wall
Stone production & hauling for town
14 ditch
Stone masonry construction for town
15 ditch
16 Curb stone material production
4 Deseret allowance
6 Housing allowance -
8 Fuel 301,372.81
10 Spareparts 28,572.69
12 Electrical Supplies -
15 Entertainment 7,172.99
23 Miscellanous 189,814.54
Excuted
I/N Product center Quantity Cost per unit Total cost
AAiT | SCEE
Excuted Total cost Actual Unit Budgeted
Quantity (DC+IC) rate Rate Actual cost Earned Value Variance
Rate Cost
I/N Cost objects Unit (A) (B) (C=B/A) (D) (E=A*C) (F=A*D) (G=D-C) (H=F-E)
1 Cut and borrow to fill m3 2,375.00 411,084.23 173.09 123.29 411,084.23 292,818.50 (49.80) (118,265.73)
2 Common Excavation m3 11,701.00 572,829.78 48.96 41.70 572,829.78 487,955.10 (7.25) (84,874.68)
9 Curb stone consruction m3 333.50 227,351.54 681.71 360.00 227,351.54 120,058.67 (321.72) (107,292.87)
Total Cost 29,231.00 10,988,679.99 10,988,679.99 6,295,782.79 (4,692,897.20)
Table 34: List of variance analysis at activity level for Jinka- Mender project
142
A.Y. 2019/2020
M.Sc. Thesis A.Y. 2019/2020
Overhead
I/N Cost Labour cost Material cost Equipment cost cost
Summary of cost for cut and borrow to fill
1 Actual cost 3.59 29.00 69.91 70.59
2 Estimated cost 3.51 58.26 33.07 18.97
Variance -0.08 29.26 -36.84 -51.62
Summary of cost for common excavtion
1 Actual cost 0.86 0.00 28.13 19.97
2 Estimated cost 1.74 0.00 30.74 6.50
Variance 0.88 0 2.61 -13.47
Summary of cost for Rock fill in embankment
1 Actual cost 1.47 203.00 26.30 128.42
2 Estimated cost 13.66 149.70 36.63 40.00
Variance 12.19 -53.3 10.33 -88.42
Summary of cost for sub-base layer construction
1 Actual cost 6.87 0.00 14.80 14.93
2 Estimated cost 0.00 0.00 0.00 0.00
Variance -6.868958276 0 -14.80156342 -14.93
Summary of cost for base- course layer construction
1 Actual cost 8.71 845.47 161.16 699.27
2 Estimated cost 2.82 441.06 27.29 94.23
Variance -5.89 -404.41 -133.87 -605.04
Summary of cost for Asphalt concrete surfacing construction
1 Actual cost 3.02 191.96 17.61 146.41
2 Estimated cost 0.74 231.42 5.19 47.47
Variance -2.28 39.46 -12.42 -98.94
Summary of cost for retaining wall construction
1 Actual cost 474.24 436.70 52.84 663.76
2 Estimated cost 307.96 880.48 99.44 257.58
Variance -166.28 443.78 46.6 -406.18
Summary of cost for town ditch
1 Actual cost 355.18 615.78 35.64 693.25
2 Estimated cost 307.96 880.48 99.44 257.58
Variance -47.22 264.7 63.8 -435.67
Summary of cost for curb stone construction
1 Actual cost 39.07 185.32 179.29 278.02
2 Estimated cost 21.39 251.09 4.44 55.38
Variance -17.68 65.77 -174.85 -222.64
4.6.3 Summary
This section presented about the summary of proposed system of cost accounting for the
company. The survey and desk study analysis revealed that the current system is unable
to ascertain the cost which is the primary aim of implementing the system. This incorrect
presentation of cost data will expose the managers to face unexpected cost overrun of the
project without any chance to take corrective measures. Therefore proposing of the
modified costing system is necessary to overcome those problems. The proposed system
was focused on avoiding inconsideration of cost data and proper allocation of the cost to
the eligible cost objects. The implementation of the proposed system is tested in three
ongoing projects of the organization named as, Dulecha-Awash Arba, Dimma-Rad, and
Jinka Mender road construction project. These three projects are similar as they are
asphalt concrete road construction projects. However, their location, climate condition
and contract delivery system are different. Dulecha –Awash Arba and Dimma-Rad
projects are located in Afar and Gambella Regional state respectively and has a design
bid build contract delivery system. Whereas, Jinka Mender road construction project are
located in South nation and nationalities regional state which has a high rainy weather
condition and use design build delivery system. The result from the proposed system
revealed that Dulecha –Awash Arba road project has incurred 3,236,488.35birr loss
during the reporting period. However, the result from the current system indicates only
611,230.87 birr loss. For Dimma-Rad road project has incurred 1,074,760.49birr loss
while the current system indicates 190,177.73birr profit. This distorted system result will
let the mangers to think that the project financial status is safe. For Jinka- Mender road
project the current system indicates the project has incurred 3,234,628.57 birr loss but the
result from the proposed system indicates the project loss is 4,692,897.20 birr. This high
difference of the result between the current and proposed system arises from the lack of
current system in considering head office overhead cost and computing and allocating of
actual project overhead costs of the specified period.
The research established that professional staffs don‟t have adequate knowledge
about cost accounting. There was a different answer from the respondent about
the company's current costing system. 24% and 30% of the respondent from
decision-makers and implementers responded that they don‟t know about which
costing system is they currently use in the company.
The finding indicates that the company doesn‟t have a structured and typical cost
accounting system. 78% of the respondent responded that they allocate project
overhead and the remaining 22% didn‟t allocate the project overhead cost when
determining the cost of the project cost object. Most of the respondents, 59%
don‟t allocate head office overhead to the project and 41% allocate. This result
indicates the company has a lack of an organized cost accounting system in all
projects. Also, the desk study findings revealed that the company uses the wrong
overhead allocation bases. Therefore, the findings indicate that the company is not
properly implementing an activity-based costing system.
This research found that the implementation of cost accounting in the company is
weak. The respondents were asked to evaluate the effectiveness of the company
current system based on the different requirements of the costing system. The
implementer rate the current system as poor in providing relevant data for
decision-makers, performance evaluation, efficiency controlling, profit
ascertainment, and forecasting ability. And also the response from 97% of the
decision-makers revealed that they are not satisfied by the current. This poor
implementation will make the system unfit for the intended purpose.
The result from questionnaires confirms the findings of Nangan 2012, about
different common problems which can occur in the implementation of cost
accounting. The respondent identified several problems encountered during the
implementation. The top three problems selected by cost accounting implementers
are lack of training on updated cost accounting techniques, difficulties in data
collecting and gathering and lack of implantation software. Decision-makers
responded that most three problems as lack of adequate information about cost
data, late reporting and incorrect perception about cost accounting. As Sartorius
(2007) state the lack of implantation software and difficulties in identifying and
defining cost drivers are selected as a problem by 78% and 74% respectively.
The research revealed the ability of the current system in providing relevant
information to the decision-makers for future planning and decision making was
poor. The literature indicates that the costing system should provide cost data in a
systematic manner and actual information about the cost to the management for
the evaluating, future planning and decision making. Also IFAC, 2009 selects as
one of the requirements of a good costing system. However, 44% and 41% of
respondents from implementers and decision-makers rated the current costing
system as poor in assisting the management or decision-makers for planning and
decision making by providing relevant cost data.
5.2 Recommendations
Based on the findings of the study the following recommendations are made;
The company should train the staffs about the different cost accounting systems
and its different techniques to get certain cost results which will help the decision-
makers to make decisions and corrective measures based on reliable data.
An independent cost accounting team should be organized at the project level to
execute clear and detailed costing reports to present for management staffs to take
corrective measures on time.
The cost accounting implementer team should include accountants in order to
solve the problem of overhead cost computation and allocation.
The company should use a structured and typical costing system for all projects.
The lack of a standardized costing system will lead the decision-makers to
evaluate the performance of the project based on unequal bases.
The reporting period should be reduced to 15day in order to enable the decision-
makers to take corrective measures timely.
The project managers have to be the primary user of the cost accounting report
and immediate corrective measures have to be done at the site level in order to
ascertain the healthiness of the project's financial status.
The feedback system should get more attention to use the cost accounting results
for a better profit.
The cost data acquires from the cost accounting reports should be used in project
pricing and bidding to fix rates based on the actual performance.
The company should create a proper and uniform cost sheet format for all
projects.
The company should avoid using a predetermined overhead rate. The updated
actual overheads rate should be allocated to the cost objects by using the correct
allocation bases.
The company should use the proposed cost accounting system in this study which
tries to overcome the problems with the current system.
REFERENCES
Abdelhak, C., & Mohammed, T. (2012). The design of cost estimating model for
construction project. Open journal of accounting.
Ahmad, Y. B., Ezanee, M. E., & Hishamuddin, D. (2012). Construction cost control.
College of Buisness university of Malysia.
Akyol, D., Tuncel, G., & Bayhan, G. (2005). A comparative analysis of activity-based
costing and tarditional costing. World academy of science engineering and
technology.
Ali A.S , & Kamaruzzaman, S. (2010). Cost performance for building construction
projects. Journal of Building Performance.
Arora, M. (2004). Cost accounting principles and practice. New Delhi: Vikas publishing
house.
Barry, C., & Brooke, L. (2005). Essential of research design and methodology.
NewJersey: John Wiley & sons.
Chao, S. (2013). A Study of Cost Accounting Practices, Through Germany, Japan, and
the United States (Master's thesis). Retrieved from https://lup.lub.lu.se/student-
papers/search/publication.
Charles, T., Srikant, M., & Madhav, V. (2015). Cost Accounting a managerial emphasis.
United states of America: Pearson Education .
Clough, H., Searse, G., & Koki, S. (2008). Construction project management; a practical
guide to field construction management. John Wiley & sons.
Cooper, R., & Kaplan, R. (1988). How cost accounting distorts product cost. Managment
accounting.
Dandago, K., & Tijiani, B. (2005). Cost and management. Gidan Dabino.
Derya , E. A., Gonca , T., & G.Mirac, B. (2007). A comparative analysis of activtity -
based costing and Traditional costing. International journal of Industrial and
Manufacturing Engineering.
Edward J., V. (2010). Principles of cost accounting. United staes of America: Cengage
Learning Custmer.
Evanse, M. (2015). A cost accounting system for the construction industry in South Africa
(Master's thesis). Retrieved from https://www.semanticscholar.org/.
Fayek, A. R. (2001). Activity based job costing for integrated estimating,schedule, and
cost control. Cost Engineering, Vol.43/No8.
G., J. (2015). The impact of information in cost accounting (Master's thesis). Retrieved
from http://www.diva-portal.se/.
G.W, P. (1990). Cost manufacturing: drawn of a new era. London: Production planning
and control .
Garrison, R., Noreen, E., & Brewer, P. (2011). Managerial accounting. Boston:
MCGraw-Hill Irwin.
Howell, G., & Ballard, G. (n.d.). Implementing lean construction: understanding and
action. Proceedings of the international group for lean construction. Guaruja.
ICAI. (2012). Cost and managment accounting. Mumbai: The Institute of cost
Accountants of India.
ICAI. (2018). Cost accounting. Mumbai: The institutes of cost accountants of India.
Jake, S., Brian , L., & Jeff , S. (2017). An Analysis of construction Overhead expenses.
53rd Annual International Conference Proceedings. The Associated School of
construction.
JFMIP. (1998). Managerial cost accounting system requirments. Washington DC: Joint
Financial Management Improvment program.
Jouni, K. (2009). Cost accounting methods for construction projects in North -West
Russia (Master's thesis).
Kabiru, I., & Abuh , A. (2013). The relevance of variance analysis in managerial cost
control. Journal of finance and investment analysis, Vol.2.
Kaplan, R., & Cooper , R. (1997). Using integrated cost system to drive profitability and
performance. Boston: Harvard buisness school press.
Khataie, A., & Bulgak, A. (2013). A cost of quality decision support model for lean
manufacturing: ABC application. International journal of quality and reliability
managment.
Kim, Y., & Ballard, G. (2002). Overhead cost analysis. Proceedings international group
for lean construction.
Kothari, C. (2004). Research Methodology Methods and Techniques. New Delhi: New
age international Ltd.
Kramer, K., Heinrich, G., Koskela, l., & Kagiolou, M. (2002). How construction flows
have been understood in lean construction. 7th Annual conference of the
international group for lean construction.
Lucie, H., & Tomas, H. (2017). An Emperical anlysis of overhead cost managment in
Czech construction industry. Technical Journal.
Maharshi Dayanand university. (2004). Advanced cost accounting. New Delhi: Excel
books PVT.
Maher, M. (1997). Cost Accounting Creating Value for Managment. California: The
MCGraw-Hill companiies.
Majid, J., & Sulaiman, M. (2008). Implementation of activity- based costing in Malaysia.
Asian review of accounting.
Marchesan, P., & Formoso, C. (n.d.). Cost managment and production control for
construction company.
Marivic, V. (2004). Activity- based costing vs. traditional cost accounting system among
top 500 corporations in the Pjilippines.
McCaffer, R., Thorpe, A., & James, M. (1990). A site-based data capturing and
information system. Building economics and construction management.
Montana, P., & Charnov, B. (1993). Management. New York: Barron's business review
series.
Nabil I., E.-S., & Ahmed, E.-R. (2015). An overhead costs assessment for construction
projects at Gaza strip. American journal of civil engineering.
National computing center, N. (1979). Project planning and control. Manual papers.
P.R.C, M., & Formoso, C. (2014). Cost management and production control for
construction companies (Master's thesis). Retrieved from
http://vietnamsupplychain.com.
Potts, K. (2008). Construction cost managment. New York: Taylor & Francis group.
Rasdorf, W., & Abudayyeh, O. (1991). Cost and schedule control integration. Journal of
construction engineering and mangement.
Reeve, J., & Duchan, J. (2012). Principles of financial and managerial accounting.
Canada: Cengage Learning.
Sandra, C., & Efrosini, K. (2009). Cost accounting system structure and information
quality. Journal of applied accounting research.
Sartorius, K., Eitzen, C., & Kamala, P. (2007). The design and implementation of
activity-based costing: a South African survey. Meditari Accountancy research.
Serdar, D., & Syuhaida, I. (2012). Role of the construction industry in economic
Development. Energy science and Research.
Singh, A., & Masuku, M. (2014). Smapleing Techniques & Determination of Sample
Size in Applied Statistics Research. International Journal of
Economics,Commerce and Managment.
Takim, R., Akintoye , A., & Kelly, J. (2003). Performance measurnment system in
construction. Greenwood,D 19th Annual ARCOM conference.
Tunji-Olayeni, Timothy, O. M., Olabosipo, I. F., Ignatius, O. O., & Opeyemi, J. (2016).
Evaluating construction project perfromance.
V.V Morajkar, & Suhas, M. (2015). Advanced cost accounting. Dr. Prakash Atkare,
Registrar, Y.C.M.Open University, Nashik - 422 222.
Yong, W. K., & Glenn, B. (2001). Activity based costing and its application to lean
coonstruction . National university of singapore.
Zewdu, Z. T., & G. T. (2015). Causes of contractors cost overrun in construction projects.
International journal of buisness and economics research, 180-191.
Dear Participant:
My name is Tigist Tsegaye Molla and I am a graduate student at Addis Ababa University
School of civil and Environmental Engineering doing a research entitled „A study on the
cost accounting system of state owned Road contractors a case study on Ethiopian
construction works Corporation Transport infrastructure construction sector in fulfillment
of Msc. Program in construction technology and management. I have designed this
questionnaire which I request you kindly take a time to complete.
Please note that you do not need to divulge your name to this questionnaire and your
response to this question shall be treated confidentially. Please be assured that the
information you give will be used for this research and will not be passed to any parties.
Sincerely,
Researcher’s address
Name: Tigist Tsegaye
Phone: +251921402694
E-mail: [email protected]
Yes � No �
2. Do you think cost accounting system useful for your company?
Yes � No �
3. As a decision maker (management staff) what is your objective of implementing cost
accounting?
Please choose all your objectives.
Yes � No �
5. Which costing system does your company use?
Yes � No �
Only answer this question if the answer for question #6 was '„Yes'
________________________________________________________________________
________________________________________________________________________
_______________________________________.
�Difficulties in identifying the actual project and head office overhead cost
�Using of approximated data rather than collecting the actual cost data
�Incorrect perception about cost accounting doing it just for the purpose of
reporting
9. Please rate the effectiveness of your company current cost accounting system based
on the following requirement.
Please choose the appropriate response by marking the appropriate box.
After rating your company costing system based on the above cost accounting system
requirement please answer the following question.
10. Are you satisfied with the current cost accounting system?
Yes � No �
Only answer this question if the answer for question #10 was '„Yes'
QUESTIONNAIRE
Please give your response for the following questions either by writing your answers in the
space provided or by putting X” or””marks at your choice rectangle shown for questions
having choice.
Yes � No �
2. Do you think cost accounting system useful for your company?
Yes � No �
3. What is your objective of implementing cost accounting?
Yes � No �
6. Do you allocate project overhead to the works (project) section?
Yes � No �
Only answer this question if the answer for question #6 was '„Yes'
7. What are basis of allocating project overheads to works
� Value of section
�Direct labor
� ABC system
� Other ________________________________________________________
Yes � No �
9. Does your organization have a standard cost sheet that used to provide the cost data of
the project?
Yes � No �
10. Are computer application software or tools used in implementing the cost accounting
system? Yes � No �
Only answer this question if the answer for question #10 was '„Yes'
11. Write type of computer software or tools used in applying the cost accounting
system?
Please write your answer here:
________________________________________________________________________
________________________________________________________________________
_______________________________________.
12. In which level of cost accounting system that you use computer application
software or tools?
Please choose all levels that you use the software or tools
�Incorrect perception about cost accounting, doing it just for the purpose of reporting
Technical constraints
� Lack of basic knowledge and skill on cost accounting and its different techniques
�Difficulties in identifying the actual project and head office overhead cost
� Difficulties in the assigning and allocation of cost to each activity (cost object)
14. Pleases rate the effectiveness of your company current cost accounting system
based on the following requirement.
Please choose the appropriate response by marking the appropriate box.
After rating your company costing system based on the above cost accounting system
requirement please answer the following question.
15. Are you satisfied with the current cost accounting system?
Yes � No �
Only answer this question if the answer for question #15 was '„Yes'