BLDG2023 Tutorial Answer

The document provides a precedence diagram and network calculations for a project with 11 activities (A to J). It includes: 1) The precedence diagram showing the logical relationships and durations of each activity. 2) Calculations of the earliest start and finish dates, latest start and finish dates, and total float for each activity. 3) An explanation that total float is calculated as the late finish date minus the early finish date or late start date minus the early start date. Free float is the minimum of the early start date of following activities minus the early finish date.

Uploaded by

Jay L
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views33 pages

BLDG2023 Tutorial Answer

The document provides a precedence diagram and network calculations for a project with 11 activities (A to J). It includes: 1) The precedence diagram showing the logical relationships and durations of each activity. 2) Calculations of the earliest start and finish dates, latest start and finish dates, and total float for each activity. 3) An explanation that total float is calculated as the late finish date minus the early finish date or late start date minus the early start date. Free float is the minimum of the early start date of following activities minus the early finish date.

Uploaded by

Jay L
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 33

Week2 Tutorial

Solutions
Kevin Yang
Question 1
(a). Plot a precedence diagram for the list of activities shown in the table:
Activity Predecessors Durations
A - 5
B A 3
C B 2
D C 3
E B 4
F D 8
H B 5
G H 2
J H, E 3
I F, G, J 2

(b). Calculate the above network (Find early start & finish date, late start & finish
date, free float and total float)
Question 1-Answer (a)
Activity Predecessors Durations

A - 5

B A 3

A C B 2
5
D C 3

E B 4

F D 8

H B 5

G H 2

J H, E 3

I F, G, J 2
Activity Predecessors Durations

A - 5

B A 3

A B C B 2
5 3
D C 3

E B 4

F D 8

H B 5

G H 2

J H, E 3

I F, G, J 2
Activity Predecessors Durations

A - 5
C B A 3
2
C B 2

D C 3
A B E

5 3 4 E B 4

F D 8
H
H B 5
5
G H 2

J H, E 3

I F, G, J 2
Activity Predecessors Durations

A - 5
C D B A 3
2 3
C B 2

D C 3
A B E

5 3 4 E B 4

F D 8
H
H B 5
5
G H 2

J H, E 3

I F, G, J 2
Activity Predecessors Durations

A - 5
C D F B A 3
2 3 8
C B 2

D C 3
A B E

5 3 4 E B 4

F D 8
H
H B 5
5
G H 2

J H, E 3

I F, G, J 2
Activity Predecessors Durations

A - 5
C D F B A 3
2 3 8
C B 2

D C 3
A B E

5 3 4 E B 4

F D 8
H G
H B 5
5 2
G H 2

J H, E 3

I F, G, J 2
Activity Predecessors Durations

A - 5
C D F B A 3
2 3 8
C B 2

D C 3
A B E J

5 3 4 3 E B 4

F D 8
H G
H B 5
5 2
G H 2

J H, E 3

I F, G, J 2
Activity Predecessors Durations

A - 5
C D F B A 3
2 3 8
C B 2

D C 3
A B E J I

5 3 4 3 2 E B 4

F D 8
H G H B 5
5 2
G H 2

J H, E 3

I F, G, J 2
Question 1-Answer (b)
Step1: Calculating earliest start & finish date
C D F
2 3 8

A B E J I
5 3 4 3 2

H G
5 2

ES Task EF
FF D TF
LS LF
Step1: Calculating earliest start & finish date
8 C 10 10 D 13 13 F 21

Max {EF} =ES+Duration 2 3 8

0 A 5 5 B 8 8 E 12 13 J 16 21 I 23
5 3 4 3 2

8 H 13 13 G 15
5 2

ES Task EF
FF D TF
LS LF
Step2: Calculating Latest start & finish date
8 C 10 10 D 13 13 F 21
2 3 8

0 A 5 5 B 8 8 E 12 13 J 16 21 I 23
5 3 4 3 2

8 H 13 13 G 15
5 2

ES Task EF
FF D TF
LS LF
Step2: Calculating Latest start & finish date
8 C 10 10 D 13 13 F 21

Min{LS}=LF-Duration 2 3 8
8 10 10 13 13 21

0 A 5 5 B 8 8 E 12 13 J 16 21 I 23
5 3 4 3 2
0 5 5 8 14 18 18 21 21 23

8 H 13 13 G 15
5 2

ES Task EF 13 18 19 21

FF D TF
LS LF
Step3: Calculating the Total float
8 C 10 10 D 13 13 F 21
2 3 8
8 10 10 13 13 21

0 A 5 5 B 8 8 E 12 13 J 16 21 I 23
5 3 4 3 2
0 5 5 8 14 18 18 21 21 23

8 H 13 13 G 15
5 2

ES Task EF 13 18 19 21

FF D TF
LS LF
Step3: Calculating the Total float
8 C 10 10 D 13 13 F 21
Total Float= LF-EF or LS-ES
2 0 3 0 8 0
8 10 10 13 13 21

0 A 5 5 B 8 8 E 12 13 J 16 21 I 23
5 0 3 0 4 6 3 5 0 2 0
0 5 5 8 14 18 18 21 21 23

8 H 13 13 G 15
5 5 2 6

ES Task EF 13 18 19 21

FF D TF
LS LF
Step4: Calculating the Free float
Free Float= Min(ESD(Following activity)-EFD) 8 C 10 10 D 13 13 F 21
2 0 3 0 8 0
8 10 10 13 13 21

0 A 5 5 B 8 8 E 12 13 J 16 21 I 23
5 0 3 0 4 6 3 5 2 0
0 5 5 8 14 18 18 21 21 23

8 H 13 13 G 15
5 5 2 6

ES Task EF 13 18 19 21

FF D TF
LS LF
Step4: Calculating the Free float
Free Float= Min(ESD(Following activity)-EFD) 8 C 10 10 D 13 13 F 21
0 2 0 0 3 0 0 8 0
8 10 10 13 13 21

0 A 5 5 B 8 8 E 12 13 J 16 21 I 23
0 5 0 0 3 0 1 4 6 5 3 5 0 2 0
0 5 5 8 14 18 18 21 21 23

8 H 13 13 G 15
0 5 5 6 2 6

ES Task EF 13 18 19 21

FF D TF
LS LF
Question 2
Calculate the ESD, EFD, LSD, LFD, Ff and TF of the following project ES Task EF
FF D TF
4 4 7 LS LF
A C D

START E FINISH
5

B F
7 9
A C D
4 4 7

E
Start 5 Finish

B F
7 9
Step1: Calculating earliest start & finish date

Max {EF} =ES+Duration

0 A 4 4 C 8 8 D 15
4 4 7

8 E 13
Start 5 Finish

0 16

0 B 7 7 F 16
7 9
Step2: Calculating Latest start & finish date

Min{LS}=LF-Duration

0 A 4 4 C 8 8 D 15
4 4 7
1 5 5 9 9 16

8 E 13
Start 5 Finish
11 16
0 16

0 B 7 7 F 16
7 9
0 7 7 16
Step3: Calculating the Total float
Total Float= LF-EF or LS-ES

0 A 4 4 C 8 8 D 15
4 1 4 1 7 1
1 5 5 9 9 16

8 E 13
Start 5 3 Finish
11 16
0 16

0 B 7 7 F 16
7 0 9 0
0 7 7 16
Step4: Calculating the Free float
Free Float= Min(ESD(Following activity)-EFD)

0 A 4 4 C 8 8 D 15
0 4 1 0 4 1 1 7 1
1 5 5 9 9 16

8 E 13
Start 3 5 3 Finish
11 16
0 16

0 B 7 7 F 16
0 7 0 0 9 0
0 7 7 16
Question 3
Calculate the ESD, EFD, LSD, LFD, Ff and TF of the following project ES Task EF
FF D TF

3 3 2 7 8 LS LF
A D G I L

START B E J FINISH
7 6 11

C F H K M
7 2 5 4 8
A D G I L
3 3 2 7 8

B E J
Start 7 6 11 Finish

C F H K M
7 2 5 4 8
Step1: Calculating earliest start & finish date

0 A 3 3 D 6 6 G 8 8 I 15 24 L 32
3 3 2 7 8

0 32
0 B 7 7 E 13 13 J 24
Start 7 6 11 Finish

0 C 7 7 F 9 13 H 18 18 K 22 22 M 30
7 2 5 4 8
Step2: Calculating Latest start & finish date

0 A 3 3 D 6 6 G 8 8 I 15 24 L 32
3 3 2 7 8
1 4 4 7 15 17 17 24 24 32

0 32
0 B 7 7 E 13 13 J 24
Start 7 6 11 Finish
0 7 7 13 13 24

0 C 7 7 F 9 13 H 18 18 K 22 22 M 30
7 2 5 4 8
6 13 13 15 15 20 20 24 24 32
Step3 & 4: Calculating the Free float and Total float
0 A 3 3 D 6 6 G 8 8 I 15 24 L 32
0 3 1 0 3 1 0 2 9 9 7 9 0 8 0
1 4 4 7 15 17 17 24 24 32

0 32
0 B 7 7 E 13 13 J 24
Start 0 7 0 0 6 0 0 11 0 Finish
0 7 7 13 13 24

0 C 7 7 F 9 13 H 18 18 K 22 22 M 30
0 7 6 4 2 6 0 5 2 0 4 2 2 8 2
6 13 13 15 15 20 20 24 24 32