0% found this document useful (0 votes)
342 views

Critical Path Method Exercise Question With Solutions

The document provides three questions and solutions for calculating early start (ES) and early finish (EF) dates, late start (LS) and late finish (LF) dates, free float (FF) and total float (TF) for three construction project networks. The questions include precedence diagrams showing activities and their dependencies. The solutions show the calculations for the ES, EF, LS, LF, FF and TF for each network.

Uploaded by

Jay L
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
342 views

Critical Path Method Exercise Question With Solutions

The document provides three questions and solutions for calculating early start (ES) and early finish (EF) dates, late start (LS) and late finish (LF) dates, free float (FF) and total float (TF) for three construction project networks. The questions include precedence diagrams showing activities and their dependencies. The solutions show the calculations for the ES, EF, LS, LF, FF and TF for each network.

Uploaded by

Jay L
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

CONS0009 Construction Planning and Control

CPM Exercise Questions (Solutions)

Question 1
(a) Plot a precedence diagram for the list of activities shown in the table:

Activity Predecessors Duration


A - 5
B A 3
C B 2
D C 3
E B 4
F D 8
H B 5
G H 2
J H,E 3
I F,G,J 2

Solution:
C D F
2 3 8

A B E J I
5 3 4 3 2

H G
5 2
(b) Calculate the above network (Find early start & finish date, late start &
finish date, free float and total float)

Solution:

8-10 10-13 13-21


0 0 0 0 0 0
8-10 10-13 13-21

C D F
2 3 8
0-5 5-8 8-12 13-16 21-23
0 0 0 0 1 6 5 5 0 0
0-5 5-8 14-18 18-21 21-23

A B E J I
5 3 4 3 2
8-13 13-15
0 5 6 6
13-18 19-21
H G
5 2
Question 2
Calculate the ESD, EFD, LSD, LFD, FF and TF of the following project:

0–4 4–8 8 – 15
0 1 0 1 1 1
1–5 5–9 9 – 16

A C D
4 4 7
8 – 13
0–0 3 3 16 – 16
0–0 11 – 16 16 – 16

START E FINISH
5
0–7 7 – 16
0 0 0 0
0–7 7 – 16

B F
7 9

ES – EF
FF TF
LS – LF
Question 3
Calculate the ESD, EFD, LSD, LFD, FF and TF of the following project:
0–3 3–6 6–8 8 – 15 24 – 32
0 1 0 1 0 5 9 9 0 0
1–4 4–7 11 – 13 17 – 24 24 – 32

A D G I L
3 3 2 7 8
0–7 7 – 13 13 – 24
0–0 0 0 0 0 0 0 32 – 32
0–0 0–7 7 – 13 13 – 24 32 – 32

START B E J FINISH

7 6 11
0–7 7–9 13 – 18 18 – 22 22 – 30
0 6 4 6 0 2 0 2 2 2
6 – 13 13 – 15 15 – 20 20 – 24 24 – 32

C F H K M
7 2 5 4 8

ES – EF
FF TF
LS – LF

You might also like