Project Management Lecture
Project Management Lecture
CEE 501A
Course Teacher
Dr. Muhammad Saiful Islam
Associate Professor
Dept. of CEE, SUST
1
About Me
Ph.D. (2019), Construction and Project Management, Australia
2
Unit Aim and Learning Outcomes
Aim
• To provide knowledge and develop skills of understanding basic project
management principles and practices.
Learning outcomes
• Apply project management tools and techniques for successful project completion
• Develop skills to project time, cost, quality, and safety (KPIs) management
• Understanding project risks and uncertainties and their management strategies
• Introduce with the PMBOK and the project management manual
3
Approaches to Teaching and Learning
4
Schedule & Content
Lecture week Date Content
Week 1 18/07/19 Introduction on Project Management
Week 2 25/07/19 Project cost management
Week 3 01/08/19 Project cost management
Week 4 08/08/19 Public holiday
Week 5 15/08/19 Public holiday
Week 6 22/08/19 Project schedule management
Week 7 29/08/19 Project schedule management
Week 8 05/09/19 Term test and mid-submission
Week 9 12/09/19 Project quality management
Week 10 19/09/19 Project quality management
Week 11 26/09/19 Project safety management
Week 12 03/10/19 Public holiday
Week 13 10/10/19 Public holiday
Week 14 17/10/19 Contract management (project delivery systems)
Week 15 24/10/19 Project risk management & Stakeholder
management
Week 16 31/10/19 Final submission & presentation, and Review class
5
Assessment
The total (=100) marks are distributed as follows:
1. Class attendance = 10%
2. Project submission (group) = 10%
3. Term test = 10%
4. Final exam = 70%
6
Making Group and Rules of working in a group
7
Academic honesty/integrity
8
Academic honesty/integrity
9
Reference books/research papers
10
Introduction to Project Management
Project??
A project is a temporary endeavour undertaken to create a unique
product or service.
It is
• performed by people
• constrained by limited resources
• planned, executed and controlled
11
Introduction to Project Management
A project is temporary ? As it has:
12
Introduction to Project Management
A Project is (cont..):
Progressive elaboration
➢ A project occurs step by step to define the product or
service, in a so called “progressive elaboration” process.
➢ for instance, the development of a chemical processing
plant begins with the process engineering to define the
characteristics of the process, and ends with the final
assembly.
13
Introduction to Project Management
Examples of projects:
The development of software for an improved business
process, the construction of a building or bridge, the relief
effort after a natural disaster, the expansion of sales into a
new geographic market — all are projects.
14
Project Life-cycle
Cost and
Intermediate
Staffing
Phases (one
level
or more) Final
Initial
Phase Phase
Time
Start Finish
Milestones :
• defined state of the project
• decision point
15
Project Management: Definition and scope
Project management, then, is the application of knowledge, skills,
tools, and techniques to project activities to meet the project
requirements.
17
Why Project Management- 10 reasons:
1. Defines a plan and organizes chaos – projects are naturally
chaotic. The primary business function of project management is
organizing and planning projects to cultivated this chaos. A clear
path mapped out from start to finish ensures the outcome meets
the goals of your project.
18
Why Project Management- 10 reasons:
4. Maximizes resources – Resources, whether financial or human,
are expensive. By enforcing project management disciplines such
as project tracking and risk management, all resources are used
efficiently and economically.
19
Why Project Management- 10 reasons:
6. Controls cost – some projects can cost a significant amount of
money so on budget performance is essential. Using project
management strategies greatly reduces the risk of budget
overruns.
20
Why Project Management- 10 reasons:
9. Retain and use knowledge – projects generate knowledge or at
least they should. Knowledge represents a significant asset for
most businesses. Left unmanaged knowledge tends to quickly
fade. Project management ensures that knowledge is captured and
managed.
Failure in terms of cost (i.e. cost overrun), time (delay), and quality,
the three basic constraints.
21
Project management broadly covered --
• project,
• program, and
• portfolio management.
And more companies are clearly seeing the payoff from investing
time, money and resources to build organizational project
management expertise to: Why will
✓ lower costs, you hire a
✓ greater efficiencies, PM??
✓ improved customer and stakeholder satisfaction, and
✓ greater competitive advantage.
Sylhet
23
Portfolio Management
A portfolio- refers to projects, programs, subportfolios, and
operation managed as a group to achieve strategic objectives.
24
Portfolio Management
25
Portfolio, Program and Project
26
Absence of proper or no project management
Loss of reputation
27
Project management knowledge draws on
ten areas:
Integration, Scope, Time, Cost, Quality, Procurement, Human
resources, Communications (information management), Risk
management, and Stakeholder management.
29
Project Charter
• The key word in this definition is “authority.” It authorizes both the project and
the project manager.
Kick-off
meeting
30
Project Charter
The PMBOK® Guide lists specific information that the charter should provide,
either directly or by reference, including:
Lecture week 2
Project Scope Definition and Management
Course Teacher
Dr. Muhammad Saiful Islam
Associate Professor
Dept. of CEE, SUST
1
Lecture Content
• Scope definition
• Scope management steps
• WBS details
2
Triple Constraints and Trade-off
3
Scope definition?
4
Project scope management
(PMI chap 5)
Project Scope Management.
5
Project scope definition and management steps
6
Project scope definition and management steps
Need identification
7
Project scope definition and management steps
8
Define Scope- Statement of Work (SoW)
✓ Description of the project, the purpose of the project, with clear actionable
and measurable project objective/s
✓ Project budget/cost estimates (detail the forecasted budget and all sources of
funding)
✓ Major milestones
9
Define Scope- Statement of Work (SoW)-cont..
✓ Acceptance criteria
✓ Project constraints
12
13
WBS?
✓ Support effective project management
o Assessing responsibilities
✓ Representation of WBS
14
Graphical
view
Source: PMI (2006). Practice standard for work breakdown structures (2nd ed.) 15
Outline view
17
18
CRTC-CEE
project
19
WBS Dictionary
✓ It defines, details and clarifies the various elements of the WBS and will help
to develop the detailed schedule
20
21
Khadim Project
22
23
Org. WBS
24
25
WBS development: the 100% rule
26
27
Project scope definition and management steps
28
Project scope definition and management steps
29
Recall your memory
30
Project Management
CEE 501A
Lecture week 3
Course Teacher
Dr. Muhammad Saiful Islam
Associate Professor
Dept. of CEE, SUST
1
Project Cost Management
Safety Moment??
Did anyone cycle to
university today?
2
Project Cost Management
3
Project Cost Management
4
Project Cost Management
5
Project Cost Management
6
Project Cost Management
7
Project Cost Management
8
Project Cost Management
• Depends on the type of project and the level of design detail available.
9
Project Cost Management
10
Project Cost Management
11
Project Cost Management
According to PMBOK:
7.1 - Estimate Costs, developing an approximation of the monetary
resources needed to complete the project activities.
7.2 – Determine Budget, aggregating the estimate costs of individual
activities or work package to establish and authorised cost baseline.
7.3 – Control Costs, monitoring the status of the project to update the
project budget and manage changes to the cost baseline.
12
Project Cost Management
• Should be refined during the course of the project to reflect additional detail
as it becomes available.
• Costs are estimated for all resources that will be charged to the project. This
includes, but is not limited to, labour, materials, equipment, services, and
facilities, as well as special categories such as an inflation allowance or
contingency costs.
• A cost estimate is a quantitative assessment of the likely costs for resources
required to complete the activity
13
Project Cost Management
14
Project Cost Management
15
Project Cost Management
16
Project Cost Management
Estimating Methodologies:
• Job Costing (Labour, Plant, & Materials)
• Factoring (%)
• Inflation
• Economies of Scale (non linear)
• Unit Rates (PWD work schedule)
• Day Work (Hourly / Daily Rates)
17
Project Cost Management
Contingencies:
Fixed %
Risk & Opportunities (Monte Carlo )
Client & PM Contingency
Incl / Exclude accuracy
18
Project Cost Management
19
Project Cost Management
20
Project Cost Management
22
Project Cost Management
Cost Estimating
Cost estimating is the process of developing an approximate
value of the funding needed to complete all activities associated
with the delivery of the project.
This section should explain the procedure for achieving that cost
estimate and provide some details on the accuracy of the
estimate along with what has informed the estimate, units of
measure, inclusions, exclusions and risks.
23
Project Cost Management
Drawings:
Which should at least include plans and elevations in sketch
form. Then you as the estimator can get an idea about
quantitative data about physical product. That is useful to
allocate money for elements.
Materials/Quality:
Clients requirement of the Quality of the project.
Depend on quality requirements and allows you as the
estimator to forecast costs for the materials for the overall
project.
Then you can allocate money from the cost plan.
24
Project Cost Management
Contractual information:
Such as the method of securing tenders, bonds and guarantees,
contract period etc this allowing the allocation of funds.
If, available, a comparable cost analysis from a previous
project:
This is important information.
Having this type of information enables you as the estimator to
review and determine a suitable method for preparing the cost
plan and subsequently forecasting for some budget for items.
25
Project Cost Management
26
Project Cost Management
Market condition:
Reference materials should be considered in regard to
comparable markets / economic climates and project types.
27
Project Cost Management
Market condition:
Reference materials should be considered in regard to
comparable markets / economic climates and project types.
28
Project Cost Management
29
Project Cost Management
30
Project Cost Management
Other Factors
Other factors that may affect cost include: market conditions,
locality, climate, building criteria, site, construction time, existing
buildings, procurement methods, codes and specification,
currency exchange fluctuation.
31
Project Cost Management
32
Project Cost Management
33
Project Cost Management
34
Project Cost Management
35
Project Cost Management
36
Project Cost Management
Types of Costs
Variable Costs: Changes with the amount of production / work (eg: material,
supplies & wages)
Fixed Costs: Does not change with production or project changes (eg: rental,
site establishment)
Direct Costs: Directly attributable to the work of the project (eg: team travel,
wages)
Indirect Costs: Overhead of costs incurred for benefit of more than one project
(eg: taxes, fringe benefits)
37
Project Cost Management
38
Project Cost Management
39
Project Cost Management
Cost Estimate
Cost Management Plan should include a Cost Estimate, the WBS
should form the basis of this Cost Estimate (cost all activities
and works packages associated with levels 1 – 3).
40
Project Cost Management
41
Project Cost Management
42
Project Cost Management
Cost Estimate Allocated cost
Construction (WBS Level 2)
Site Preparation, Demolition, Repairs etc (WBS Level 3) $??
Earthworks (m2 rate) (WBS Level 3) $??
Building Works (m2 rate) (WBS Level 3) $
Finishing (m2 rate) (WBS Level 3) $
External Site Works (m2 rate) (WBS Level 3) $
SUB - TOTAL $
Preliminaries, Management Fees & Overheads (assume %) $
Client Costs (incl descriptions) $
Project Contingency (assume %) $
TOTAL $
43
Project Cost Management
44
Project Cost Management
45
Project Cost Management
46
Project Cost Management
48
Project Cost Management
49
Project Cost Management
50
Project Cost Management
51
Project Cost Management
52
Project Cost Management
53
Project Cost Management
54
Project Cost Management
Cost Baseline
is a time-phased budget that will be used to measure and monitor cost
performance on the project. It is shown as an S curve. The difference
between maximum funding and the end of the cost baseline is
Management Reserve in the S curve.
55
Project Cost Management
56
Project Cost Management
Cost
Baseline is
usually
represented
through an
S Curve
https://www.projectsmart.co.u
k/what-is-earned-value.php
57
Project Cost Management
58
Project Cost Management
59
Project Cost Management
60
Project Cost Management
61
Project Cost Management
62
Project Cost Management
63
Project Cost Management
64
Project Cost Management
65
Project Cost Management
66
Project Cost Management
68
Project Cost Management
69
Project Cost Management
70
Project Cost Management
71
Project Cost Management
72
Project Cost Management
73
Project Cost Management
74
Project Cost Management
EVM Definitions:
Budget Plan (Resource loaded schedule)
Planned Value (PV) / Budgeted Cost for Work Scheduled
(BCWS) - The value of the resources planned and
scheduled for the work packages
Earned Value (Accomplishment)
Earned Value (EV) / Budgeted Cost for Work Performed
(BCWP) - The value of the work completed in terms of the
budgeted values for the work packages
Actual Costs
Actual Cost (AC) / Actual Cost of Work Performed (ACWP)
- The Costs incurred and recorded in the accounting system
for the work packages
75
76
Project Cost Management
AC = $50,000
PV = $100,000 EV = $30,000
77
Project Cost Management
78
Project Cost Management
79
Project Cost Management
80
Project Cost Management
ASSIGNMENT DISCUSSION
Brief description about project:
At least this description should clearly mention about scope of
the project, project details such as:
o Address
o Duration
o Budget
Next class:
o Cash flow analysis
o Earned value approach
Reading material
..\Architectural programming.pdf
81
Project Management
CEE 501A
Lecture week 4
Course Teacher
Dr. Muhammad Saiful Islam
Associate Professor
Dept. of CEE, SUST
1
Project Cost Management
ASSIGNMENT REVIEW
Brief description about project:
At least this description should clearly mention about scope of
the project, project details such as:
o Address
o Duration
o Budget
2
Cash Flow
3
Cash Flow Diagram
4
Cash Flow Diagram
5
Simple and Compound Interest
6
Simple and Compound Interest
7
Cash Flow and Cash Flow Diagram
8
Common terminologies and Symbols
9
Common terminologies and Symbols
10
Example of cash flow diagram
11
Example of cash flow diagram
12
Cash flow diagram-another example
13
Cash flow diagram- Exercise for home
14
Time Value of Money
15
Time Value of Money: Relation between present worth and
future worth
16
Time Value of Money: Relation between present worth and
future worth
17
Time Value of Money: Relation between present worth and
future worth
18
Time Value of Money: Relation between present worth and
future worth
19
Example
20
Example of Net Present Worth (NPW)
21
Example of Net Present Worth (NPW)
22
NPW calculation for the example project
23
Decision Making
24
Rate of Return (ROR)
25
Investment decision based on Rate of Return (ROR)
26
Rate of Return (ROR)
27
28
Project Evaluation and Control System
• Measures project progress and performance against a project plan to
ensure that the project is completed on time, within budget, and to the
accepted quality requirements
• Designing, implementing, and maintaining an accurate monitoring and
control systems is perhaps one of the most difficult challenges on projects.
✓ Cost Variance
✓ Schedule Variance
✓ Scope Changes
✓ Risk
29
Project Evaluation and Control System
30
Project Cost Control: Big Picture
31
Cost baseline and S-curve
The Cost Baseline or Cost Performance Baseline is an authorized time-phased
budget.
It is developed as a summation of the approved budgets by time period
and is typically displayed in the form of an S-Curve
32
Development of an S-curve
33
Development of an S-curve
34
Development of an S-curve
35
Development of an S-curve
36
mobilization
37
Monitoring the Status of a Project using S-curve
38
Earned Value Management
39
Earned Value Management
40
Earned Value approach
41
Earned Value approach
42
Earned Value approach
43
Earned Value approach
A negative value indicates that the project is behind the schedule as the
value of work performed is less than that scheduled.
A positive value indicates that the project is ahead of schedule.
44
Earned Value approach
45
Earned Value approach
% SV = 100xSV/BCWS
% CV = 100xCV/BCWP
47
Earned Value approach
48
Earned Value approach
Information on the cost index and how it has changed over time can be used
to forecast what the costs will be at the end of the project, referred to as
Estimated at Completion (EAC).
EAC = ACWP + (BAC-BCWP), this is the latest revised estimate of the total cost
of the project and can be compared t the BAC (original estimated project
cost).
49
Earned Value approach
50
Earned Value approach
51
Example of an Earned Value Analysis
52
Example of an Earned Value Analysis
53
Example of an Earned Value Analysis
54
Example of an Earned Value Analysis
55
Earned Value approach
Difficulties in Integrating Cost and Schedule Systems
56
Earned Value approach
57
Earned Value approach
58
Earned Value approach
Difficulties in Integrating Cost and Schedule Systems
• Front end loading could mislead this earned value approach for
integrating schedule and cost.
• For example, once the roofing work is done, the project is
considered 47.4% completed on the basis of work-hour, but is
considered 57.9% completed on the basis of costs.
59
Earned Value approach
Some Important Issues in the Effective Use of EVM
60
Project Management
CEE 501A
Lecture week 5
Project Planning and Scheduling
Course Teacher
Dr. Muhammad Saiful Islam
Associate Professor
Dept. of CEE, SUST
1
Project Planning and Scheduling
• Project schedule is
developed from the
project scope
statement and
WBS.
6
Network Diagram Development Rules
7
Network Diagram Types
Activity on node or
precedence diagram
method (PDM)
8
Activity on node (AON) or precedence diagram method
(PDM)
9
Activity on node (AON) or precedence diagram method
(PDM)
10
Different notations are used to draw a precedence diagram
11
Common Relationship Types
12
Common Relationship Types
13
Common Relationship Types
14
Common Relationship Types
15
Common Relationship Types
16
Some Definitions
• Early Start (ES) – Earliest time that the activity can possibly
start
• Early Finish (EF) – Earliest possible time that the activity can
be completed
• Late Start (LS) – Latest possible time that the activity can be
started
• Late Finish (LF) – Latest time that the activity can be finished
• Lag – A minimum amount of time a dependent activity must
be delayed to begin/start or end.
• Lead – A minimum amount of time a dependent or successor
activity must be accelerated to begin or end.
17
Some Definitions
• Total Float
–The amount of time that a schedule activity may be delayed
from its early start date without delaying the project finish
date, or violating a schedule constraint. It is the difference
between the early finish dates and late finish dates.
• Free Float
–The amount of time that an activity can be delayed without
delaying the early start date of any immediately following
schedule activities. Free float can NEVER be negative.
18
Some Definitions
• Critical Path
–The longest activity path(s) through the network.
• Critical Path Method
–A schedule network analysis technique used to determine
early & late activity dates, floats, and the minimum total
project duration.
• Forward Pass
–The calculation of the early start and early finish dates of the
schedule activities in the project network.
• Backward Pass
–The calculation of late finish dates and late start dates of
schedule activities. It is determined by working backwards from
the project’s end date in the network diagram.
19
Forward Pass- Earliest Times
Source: Larson, E.W., & Gray, C.F. (2008). Project Management : The managerial
process, 5th edition, McGraw Hill
20
Forward Pass- Earliest Times
Source: Larson, E.W., & Gray, C.F. (2008). Project Management : The managerial
process, 5th edition, McGraw Hill
21
Backward Pass- Latest Times
Source: Larson, E.W., & Gray, C.F. (2008). Project Management : The managerial
process, 5th edition, McGraw Hill
22
Backward Pass- Latest Times
23
Determining Total Float, Critical Path, Critical Activities
24
Determining Total Float, Critical Path, Critical Activities
• After Total Float for each activity is computed, the critical path
(s) (are) can be easily identified
• When the LF = EF for the end project activity, the critical path
becomes the one traversing the activities that have zero total
float (LF = EF, or LS = ES)
• When the EF of the end activity differs from LF, the critical
path becomes the network path that has the least total float in
common
26
Example Precedence Diagram for Developing a New
Business Centre
27
Example Precedence Diagram for Developing a New
Business Centre
28
Forward Pass Calculation
29
Backward Pass Calculation
30
Backward Pass Calculation
31
Class Exercise
32
Exercise problem (at home).
Compute the early and late activity times, and total float and free float for the
following network diagram. Identify the critical path. How many days will the project
take?
33
Use of Lags
34
Use of Lags
35
Use of Lags
36
Use of Lags
37
Use of Lags
38
Use of Leads
39
Schedule Calculation with Lag, Lead and FF, FS, & SS
Relationships
40
Identify One Example each Involving the Following
Relationships with or without a Lag
• Finish to Start
• Finish to Finish
• Start to Start
• Start to Finish
41
Assignment
Compute the early and late activity times, and total float and free float for the
following network diagram. This is the same diagram as in the tutorial activity 2,
there are, however three finish to start lags. Has the critical path changed? How
many days will the project take to complete?
42
Activity on Arrow (AOA)
43
Activity on Arrow (AOA)
44
Additional Points on Activity on Arrow (AOA) method
45
Example of Activity on Arrow (AOA) method
46
Example of Activity on Arrow (AOA) method
47
Example of Activity on Arrow (AOA) method
48
Some graphical representations of project scheduling
49
50
51
Project Management
CEE 501A
Lecture week 6
Project Procurement and Contracting
System
Course Teacher
Dr. Muhammad Saiful Islam
Associate Professor
Dept. of CEE, SUST
1
Lecture Outlines
• Procurement Methods
• Payments arrangements with different types of
contracts
• Cash flow profiles
• Strategies to optimize cash flows
2
3
Scope
• The portion of the major tasks- design, construction, and finance-
that is assigned to or for which the service is sought.
Organization
• The business entity with whom the owner holds contract, such as
head contractor, construction manager
Contract
• The arrangement of how the owner/contractor will pay the
organization for work performed such as fixed price, reimbursable
contracts
Award
• The method used to select contractor and/or the price, such as
competitive bidding or negotiation
Gordon (1992)
4
Project Delivery Methods in Construction
• Design-Bid-Build
• Design and Build
• Construction Management Contract
– Construction Management as Owner’s Agent
– Construction Management at Risk
• Alliancing
• Public Private Partnership (PPP or P3)
5
6
7
8
9
Australian Government Dept. of Infrastructure and Regional Development (2015)
10
11
12
13
Finnerty (2013)
14
15
16
17
18
Different types of commonly used
construction contracts
19
Contract Types
• Lump sum
• Unit price
• Cost Plus or Cost Reimbursable
• Guaranteed Maximum Price (GMP)
20
Lump Sum
Gordon (1992)
21
Unit Price
Gordon (1992)
22
23
24
Selecting an Award
25
26
Payment Arrangement
27
28
29
30
Payment Arrangement with different
types of contracts
31
32
33
34
35
36
37
38
39
40
41
Cash Flow Profiles
42
Venkataraman, & Pinto (2008)
43
44
46
Cash Flow Optimization Strategies
47
48
49
50
51
Project Management
CEE 501A
Lecture week 7
Project Quality Management
Course Teacher
Dr. Muhammad Saiful Islam
Associate Professor
Dept. of CEE, SUST
1
Lecture Outlines
• Definition of Quality
• Deming’s 14 points
• The Taguchi approach
• ISO 9000
• Quality management Concept
• The cost of quality
• The seven quality control tools
• Quality leadership
• Total Quality Management
• PMBOK PMI Quality Management
2
Definition of Quality
3
4
In past, quality was viewed as:
o The cost of quality
o Zero-defect programs
o Reliability engineering
o Total quality control
5
The most influential contributor in the quality movement is W. Edwards
Deming. He proposed a quality improvement cycle, which is called Deming
Cycle for Improvement. Deming’s definition of quality is “continuous
improvement.”
6
Deming’s 14 Points for
Management
• The System of Profound Knowledge generates an interrelated
set of 14 Points for leadership in the Western world.
• These 14 Points provide guidelines, or a road map, for the
shifts in thinking required for organizational success.
• They form a highly interactive system of management; no one
point can be studied in isolation.
1. Quality should be designed into the product and not inspected into it.
2. Quality is best achieved by minimizing the deviation from a target. The product
42
Taguchi built on Deming’s observation that 85 percent of poor quality is
attributable to the manufacturing process and only 15 percent to the worker.
According to Taguchi’s first concept:
• the better way to improve quality was to design and build it into the
product
• quality improvement starts at the very beginning, that is, during the
design stages of a product or a process, and continues through the
production phase.
• poor quality cannot be improved by the process of inspection,
screening, and salvaging
• quality concepts should be based upon, and developed around, the
philosophy of prevention.
• the product design must be so robust that it is immune to the influence
of uncontrolled environmental factors on the manufacturing processes.
43
His second concept deals with actual methods of effecting quality.
44
• His third concept calls for measuring deviations from a given design
parameter in terms of the overall life-cycle costs of the product.
• These costs would include the cost of scrap, rework, inspection, returns,
warranty service calls, and/or product replacement.
45
ISO 9000
46
ISO 9000: This defines the key terms and acts as a road map for the other
standards within the series.
ISO 9001: This defines the model for a quality system when a contractor
demonstrates the capability to design, produce, and install products or services.
ISO 9002: This is a quality system model for quality assurance in production and
installation.
ISO 9003: This is a quality system model for quality assurance in final inspection
and testing.
ISO 9004: This provides quality management guidelines for any organization
wishing to develop and implement a quality system. Guidelines are also available
to determine the extent to which each quality system model is applicable.
Becoming ISO 9000 certified does not guarantee that your organization will
produce quality products or services. Instead, it confirms that the
appropriate system is in place.
47
ISO 9000 is actually a three-part, never-ending cycle including planning,
controlling, and documentation.
Controlling is required to ensure that the goals and objectives are met, and that
problems are anticipated or averted through proper corrective actions.
48
QUALITY MANAGEMENT CONCEPTS
The project manager has the ultimate responsibility for quality management
on the project.
Quality management has equal priority with cost and schedule management.
However, the direct measurement of quality may be the responsibility of the quality
assurance department or the assistant project manager for quality.
49
From a project manager’s perspective, there are six quality
management concepts that should exist to support each and every
project. They include:
● Quality policy
● Quality objectives
● Quality assurance
● Quality control
● Quality audit
● Quality program plan
50
Quality Policy
51
Quality Objectives
52
Quality Assurance
Quality assurance is the collective term for the formal activities and
managerial processes that attempt to ensure that products and services
meet the required quality level.
Quality assurance also includes efforts external to these processes that
provide information for improving the internal processes.
It is the quality assurance function that attempts to ensure that the project
scope, cost, and time functions are fully integrated.
53
Quality Assurance
54
Quality Control
55
Quality Control
56
Quality Audit
57
Quality Plan
The quality plan is created by the project manager and project team
members by breaking down the project objectives into a work breakdown
structure.
Using WBS the project activities are broken down into lower-level
activities until specific quality actions can be identified.
The project manager then ensures that these actions are documented and
implemented in the sequence that will meet the customer’s requirements and
expectations.
This enables the project manager to assure the customer that he has a road
map to delivering a quality product or service and therefore will satisfy the
customer’s needs.
58
Quality Plan
59
The Cost of Quality
The costs can be classified as “the cost of conformance” and “the cost of
nonconformance.”
60
The Cost of Quality
Trying to save a few project dollars by reducing conformance costs could prove
disastrous.
The Japanese returned all 10,000 components to the American supplier stating
that this batch was not acceptable. In this example, the nonconformance cost
could easily be an order of magnitude greater than the conformance cost. The
moral is clear: Build it right the first time.
61
The Cost of Quality
Prevention costs are the up-front costs oriented toward the satisfaction of
customer’s requirements with the first and all succeeding units of product
produced without defects. Included in this are typically such costs as design
review, training, quality planning, surveys of vendors, suppliers, and
subcontractors, process studies, and related preventive activities.
Appraisal costs are costs associated with evaluation of product or process to
ascertain how well all of the requirements of the customer have been met.
Included in this are typically such costs as inspection of product, lab test,
vendor control, in-process testing, and internal–external design reviews.
62
The Cost of Quality
Internal failure costs are those costs associated with the failure of the
processes to make products acceptable to the customer, before leaving the
control of the organization. Included in this area are scrap, rework, repair,
downtime, defect evaluation, evaluation of scrap, and corrective actions for
these internal failures.
External failure costs are those costs associated with the determination by
the customer that his requirements have not been satisfied. Included are
customer returns and allowances, evaluation of customer complaints,
inspection at the customer, and customer visits to resolve quality complaints
and necessary corrective action.
63
The Cost of Quality
64
The Cost of Quality
As the process going the over long appraisal costs will go down as
the need to inspect in quality decreases.
The biggest savings will come from the internal failure areas of
rework, scrap, reengineering, redo, and so on.
The external costs will also come down as processes yield first-time
quality on a regular basis.
65
The Cost of Quality
This is not always the case. Prevention costs actually decrease without
sacrificing the purpose of prevention if we can identify and eliminate the
costs associated with waste, such as waste due to
66
The Cost of Quality
67
Total Quality Management (TQM)
68
Total Quality Management (TQM)
The most common primary strategies to obtain TQM are listed below
69
Total Quality Management (TQM)
70
Project Management
CEE 501A
Lecture week 8
Project Risk Management
Course Teacher
Dr. Muhammad Saiful Islam
Associate Professor
Dept. of CEE, SUST
1
Lecture Outlines
❑ Risk definition
❑ Risk management process
• Plan for risk management
• Risk identification
• Risk analysis
o Qualitative and quantitative risk analysis
• Planning for Risk response
• Monitoring and control risk
2
Risk
Risk can be defined as the combination of the probability of an event
and its consequences (ISO/IEC Guide 73) on project performance.
3
Risk management is a central part of any organisation’s strategic
management.
Its objective is to add maximum sustainable value to all the activities of the
organisation.
It increases the probability of success, and reduces both the probability of
failure and the uncertainty of achieving the organisation’s overall
objectives.
4
Risk management should be a continuous and developing process which runs
throughout the organisation’s strategy and the implementation of that strategy.
Risk Management is increasingly recognised as being concerned with both
positive and negative aspects of risk. Therefore this standard considers risk
from both perspectives.
The risks facing an organisation and its operations can result from factors both
external and internal to the organisation.
5
6
Risk Management Process
7
Risk Management Process
Risk management protects and adds value to the organisation and its
stakeholders through supporting the organisation’s objectives by:
• providing a framework for an organisation that enables future
activity to take place in a consistent and controlled manner
• improving decision making, planning and prioritisation by
comprehensive and structured understanding of business activity,
volatility and project opportunity/threat
• contributing to more efficient use/allocation of capital and
resources within the organisation
• reducing volatility in the non essential areas of the business
• developing and supporting people and the organisation’s knowledge
base
• optimising operational efficiency
8
Risk Management Process
It is important that a risk management strategy be established early in a project
and that risk be continually addressed throughout the project life cycle. Risk
management includes several related actions(Numbers refer to section
numbers in the 4th edition of the PMBOK Guide.):
9
Risk Management Process
• Plan Risk Response (11.5): The process that identifies, evaluates, selects, and
implements one or more strategies in order to set risk at acceptable levels given
program constraints and objectives. Response options for risks include
acceptance, avoidance, mitigation (also known as control), and transfer.
• Monitor and Control Risks (11.6): The process that systematically tracks and
evaluates the performance of risk response actions against established metrics
throughout the acquisition process and provides inputs to updating risk
response strategies, as appropriate.
10
Plan for Risk Management
Plan for risk management (risk planning) is the detailed formulation of a
program of action for the management of risk. It is the process to:
11
Plan for Risk Management (RMP)
12
Risk Identification
13
Risk Identification
Common practice is to classify project risk according to its
source, which is typically either objective or subjective:
Objective sources: recorded experience from past projects and
the current project as it proceeds
• Lessons learned files
• Program documentation evaluations
• Current performance data
14
15
Risk Identification
Sources of information:
• Assumption analysis
• Baseline cost estimates
• Brainstorming
• Checklists
• Cost analysis
• Decision drivers
• Diagramming techniques (e.g., influence diagrams)
• Earned value analysis
• Expert judgment
• Lessons learned files
16
Risk Identification
Sources of information contd.:
• Life-cycle cost analysis
• Models
• Plan/WBS decomposition
• Root cause investigations
• Schedule analysis
• Strengths, weaknesses, opportunities, and threats (SWOT)
• Systems engineering documentation
• Technical performance measurement (TPM/) planning/analysis
• Technology analysis
• Technology development/insertion projects
• Trade studies/analyses
17
Risk Identification
18
Risk Identification
19
Risk Analysis
21
Risk Analysis
22
Risk Analysis
23
Risk Analysis
24
Risk Analysis
25
Risk Analysis
26
Qualitative Risk Analysis
27
Qualitative Risk Analysis
• Ordinal scales are commonly used in risk analyses. Such scales and a
corresponding risk mapping matrix can be a helpful methodology for estimating
risk.
• Another type of scale is based on subjective estimates assigned to different
probability statements (e.g., high), termed here estimative probability.
• Estimative probability scales can either be ordinal (more common) or cardinal (less
common) in nature, depending upon the source of the underlying data and the
structure of the scale.
• In the best case the probability estimates are derived from a statistical analysis of
survey data from a substantial number of respondents and include point estimates
and ranges around the estimate for each probability statement.
28
Qualitative Risk Analysis
A single “probability” of occurrence scale, related to technology maturity is used,
and given in Table 17–6. (Note: Since ordinal probability scales almost never
represent true probability but only an indicator of probability, scores derived
from such scales are indicated as “probability” values.)
(e.g., low scale levels A and B, medium scale level C, and high scale levels D
and E for both probability and consequence of occurrence scores), or five
resulting risk levels (low, low medium, medium, medium high, and high)
29
Qualitative Risk Analysis
Three consequence of occurrence scales—for cost, schedule, and technical—are
used and given in Table 17–7. For each of the three consequence of occurrence
scales, assume that low scale levels A and B, medium scale level C and D, and
high scale level E.
Project
Management: A
Systematic
Approach 30
Qualitative Risk Analysis
Project
Management: A
Systematic
Approach 31
Qualitative Risk Analysis
• In this example, the resulting probability of occurrence score from Table 17–6 is
level C (preprototype maturity), and from Table 17–7 Cc level C, Cs level B, and Ct
level D. Given this information and the risk mapping matrix in
• Table 17–8, the risk level relative to cost, schedule, and technical is medium, low,
and medium, respectively.
• Taking the maximum of the three risk scores yields an overall medium risk level for
CCD low-light performance.
Project Management: A
Systematic Approach
32
Quantitative Risk Analysis
Project Management: A
Systematic Approach
33
Payoff Matrix
Risk can be viewed as outcomes (i.e., states of nature) that can be described within
established confidence limits (i.e., probability distributions). These probability
distributions should ideally be either estimated or defined from experimental data.
The best choice of strategy is, therefore, the strategy with the largest expected
value, where the expected value is the summation of the payoff times and the
probability of occurrence of the payoff for each state of nature. In mathematical
formulation,
34
Payoff Matrix
35
Payoff Matrix
Ei is the expected payoff for strategy i, 𝑃𝑖,𝑗 is the payoff element, and 𝑝𝑗 is
the probability of each state of nature occurring. The expected value for
strategy 𝑆1
Repeating the procedure for strategies 2 and 3, we find that E2 55, and E3
20. Therefore, based on the expected value, the project manager should
always select strategy S1. If two strategies of equal value occur, the
decision should include other potential considerations (e.g., frequency of
occurrence, resource availability, time to impact).
36
Tree Diagram
Consider the following problem. A product can be manufactured using machine A or
machine B. Machine A has a 40 percent chance of being used and machine B a 60
percent chance. Both machines use either process C or D. When machine A is
selected, process C is selected 80 percent of the time and process D 20 percent.
When machine B is selected, process C is selected 30 percent of the time and
process D 70 percent of the time. What is the probability of the product being
produced by the various combinations?
37
Tree Diagram
38
Planning for Risk Response
• Planning risk responses (risk handling) includes specific methods and
techniques to deal with known risks and opportunities, identifies who is
responsible for the risk or opportunity, and provides an estimate of the
resources associated with handling the risk or opportunity, if any.
• It involves planning and execution with the objective of reducing risks to
an acceptable level and exploiting potential opportunities.
• There are several factors that can influence our response to a risk or
opportunity, including but not limited to:
– Amount and quality of information on the actual hazards that caused
the risk descriptive uncertainty)
– Amount and quality of information on the magnitude of the damage
(measurement uncertainty)
39
Planning for Risk Response
40
Planning for Risk Response
• Personnel that evaluate candidate risk response strategies
may use the following criteria as a starting point for
evaluation:
– Can the strategy be feasibly implemented and still meet the user’s needs?
– What is the expected effectiveness of the response strategy in reducing
program risk to an acceptable level?
– Is the strategy affordable in terms of dollars and other resources (e.g., use of
critical materials and test facilities)?
– Is time available to develop and implement the strategy, and what effect does
that have on the overall program schedule?
– What effect does the strategy have on the system’s technical performance?
41
Planning for Risk Response
42
A brief discussion of the four response options for risks follows:
● Acceptance (i.e., retention): The project manager says, “I know the risk exists
and am aware of the possible consequences. I am willing to wait and see what
happens. I accept the risk should it occur.”
● Avoidance: The project manager says, “I will not accept this option because of
the potentially unfavorable results. I will either change the design to preclude
the issue or requirements that lead to the issue.”
● Control (e.g., mitigation): The project manager says, “I will take the necessary
measures required to control this risk by continuously reevaluating it and
developing contingency plans or fall-back positions. I will do what is expected.”
● Transfer: The project manager says, “I will share this risk with others through
insurance or a warranty or transfer the entire risk to them. I may also consider
partitioning the risk across hardware and/or software interfaces or using other
approaches that share the risk.”
43
A brief discussion of the four response options for opportunities follows:
● Exploit: The project manager says, “This is an opportunity. How can we make
the most of it? Will assigning more talented resources allow us to get to the
marketplace quicker?”
44
Planning for Risk Response
45
Planning for Risk Response
46
Monitoring and Control Risk
47
Monitoring and Control Risk
• Some techniques suitable for risk monitoring and control that can be used
in a program-wide indicator sys
– Earned Value (EV): This uses standard cost/schedule data to evaluate a program’s cost
performance (and provide an indicator of schedule performance) in an integrated
fashion. As such, it provides a basis to determine if risk response actions are achieving
their forecasted results.
– Program Metrics: These are formal, periodic performance assessments of the selected
development processes, evaluating how well the development process is achieving its
objective. This technique can be used to monitor corrective actions that emerged from
an assessment of critical program processes.
– Schedule Performance Monitoring: This is the use of program schedule data to evaluate
how well the program is progressing to completion.
– Technical Performance Measurement (TPM): TPM is a product design assessment that
estimates, through engineering analysis and tests, the values of essential technical
performance parameters of the current design as effected by risk response actions.
48