Open navigation menu
Close suggestions
Search
Search
en
Change Language
Upload
Sign in
Sign in
Download free for days
0 ratings
0% found this document useful (0 votes)
27 views
6 pages
PP July 2023
Uploaded by
Awangku Muhammad Khaidir
AI-enhanced title
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here
.
Available Formats
Download as PDF or read online on Scribd
Download
Save
Save Pp July 2023 For Later
Share
0%
0% found this document useful, undefined
0%
, undefined
Print
Embed
Report
0 ratings
0% found this document useful (0 votes)
27 views
6 pages
PP July 2023
Uploaded by
Awangku Muhammad Khaidir
AI-enhanced title
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here
.
Available Formats
Download as PDF or read online on Scribd
Carousel Previous
Carousel Next
Download
Save
Save Pp July 2023 For Later
Share
0%
0% found this document useful, undefined
0%
, undefined
Print
Embed
Report
Download
Save Pp July 2023 For Later
You are on page 1
/ 6
Search
Fullscreen
CONFIDENTIAL, [ 2 CFIJUL 2023/BQS659/QSM659/QSB669 UNIVERSITI TEKNOLOGI MARA. FINAL EXAMINATION COURSE : PROFESSIONAL PRACTICE III COURSE CODE BQS659/QSM659/QSB669 EXAMINATION JULY 2023 INSTRUCTIONS TO CANDIDATES 1 ‘This question paper consists of four (4) questions. 2. Answer ALL questions in the Answer Booklet. Start each answer on a new page. 3, Do not bring any material into the examination room unless permission is given by the invigitator, 4 Please check to make sure that this examination pack sonsists of ) the Question Paper il) an Answer Booklet - provided by the Faculty ii) Form of Contract PWD 203A (Rev. 1/2010) - provided by the Faculty iv) Form of Contract PAM 2018 — provided by the Faculty vi Interim Certificate JKRE6 (pin.4/2000) ~ provided by Faculty v) Final Certificate — provided by Faculty 6 ‘Answer ALL questions in English DO NOT TURN THIS PAGE UNTIL YOU ARE TOLD TO DO SO This examination paper consists of 6 printed pages (© Hak Cipta Universiti Teknologi MARA, CONFIDENTIAL,CONFIDENTIAL 2 CFIJUL 2023/BQS659/Q5M659/QSB669 QUESTION 1 The following particulars are extracted from a contract for the Construction and Completion of 9 Storey Office Building in Putra Height, Selangor. ‘a__| Contract Sum Ri 10,925,000.00 |b. | Date for Possession ‘ist February 2022 ©. Date for Completion 30th March 2023 d. Liquidated and Ascertained Damages __ RM 3,200.00 per day e. | Period of honouring certificates 30 days f. | Performance Bond (The Contractor opted for | 5% of Contract Sum Performance Guarantee Sum) g._| Prime Cost Sum RM 1,800,500.00 h__|_ Provisional Sum _ RM_ 300,990.00 ‘Summary of valuation of the progress of the works, Interim Valuation No. 1 Work Done RM 525,000.00 Materials on Site (Main Contractor) RM 110,000.00 Interim Valuation No. 2 Work Done - RM 720,750.00 Materials on Site (Main Contractor) - RM 260,000.00 Variation (Addition) - RM — 49,000.00 Variation (Omission) RM — 35,000.00 Interim Valuation No. 3 Work Done (Main Contractor) = RM 1,100,990.00 Work Done (Sub-Contractor) - RM 290,280.00 Materials on Site (Main Contractor) - RM 320,000.00 Provisional Sum - RM 50,000.00 a) Calculate the amount of Advance Payment for the following: i) Main Contractor ii) Nominated Sub-Contractor (both of P.C works awarded to tie same Nominated Sub-Contractor at awarded amount RM 1,700,000.00) (5 marks) b) Prepare the interim certificates for the above valuation showing all calculations based on the following: i) Based on PWD 203A (Rev.1/2010) Standard Form of Contract ii) Based on PAM 2018 (With Quantities) Standard Form of Contract (20 marks) {© Hak Cipta Universiti Toknolog! MARA CONFIDENTIALCONFIDENTIAL, QUESTION 2 (CF/JUL 2023/8QS659/QSM659/QSB669 The following are particulars of 2 newly completed project for the construction and Completion of a 15-storey office building at Bandar Bahar Bukit Raja, Klang, Selangor. PARTICULARS OF CONTRACT Contract Sum RM 45 251,000.00 Date of Possession 1 February 2020 Date for Completion 31% January 2022 Date of Practical Completion 15% February 2022 Extension of Time. Nil Liquidated and Ascertained Damages RM 2.550.00/day ‘Amount paid to date RM 11,575,000.00 [Retention Fund RM 762,550.00 ‘Type of Contract PAM Standard Form of Contract 2018 SUMMARY OF CONTRACT SUM [tem] Description ‘Amount (RM) 1 Preliminaries 763,000.00 [2 ‘Administration Block 11,950,000.00 3.___| Guard House 0,500.00 4. External Works 457,500.00 5 P.C. & Provisional Sums 2,030,000.00 TOTAL RM 16,251,000.00 PROVISIONAL SUM Item | Description “Amount allowed in BQ - (RM) i Builtin Fumiture 20,000.00 2 “TNB Sub-station 100,009.00 CB Landscaping 220,000.00 PRIME COST SUM Item | Description ‘Amount allowed in BQ (RM) 7 Curtain Walling 430,000.00 Profit 3% 12,900.00 Attendance 42,900.00 z Air Conditioning installation 350,00C.00 Profit 3% 10,500.00 | Attendance 40,500.00 3 Electrical installationProfit 3% 90,000.00 Attendance 2,700.00 2,700.00 (© Hak Cipta Universiti Teknologi MARA CONFIDENTIAL,CONFIDENTIAL 4 __CFIJUL 2023/8 QS859/ASM659/QSE669 4. | Lift Installation 550,000.00 Profit 3% 13,500.00 Attendance 18,500.00 5 Firefighting system Profit 3%) 80,000.00 Attendance 2,400.00 __ 2,400.09 ‘SUMMARY OF VARIATIONS i Building Works Item | Description. Omission (RM) ‘Addition (RM) 1. Ceiling Finishes 185,000.00 75,000.00, 2. Floor Finishes [25,000.00 26,000.00) 3. Doors and Windows €5,000.00) 3€,000.00 ii) External Works Item_| Description ‘Omission (RM) ‘Aadition (RM) 1 Water Reticulation 20,500.00 35,000.CO 2 Surface Water Drainage 20,700.00 15,700.CO (3. Hardstanding 25,000.00 '35,000.C0 ii) Provisional Sums Item | Description ‘Amount (RM) 1 Built in Furniture 700,009.00 2. TNB Sub-station 420,009.00 3 Landscaping 215,009.00 iv) Prime Cost Sums Description Omission (RM) | Addition (RM) Curtain Walling Accepted tender| figure:RM 400,350.00 V.0. No. 1 25,250.00 40,500.00 2 ‘Air-Conditioning Installation Accepted tender figure’ RM 370,500.00 V.0. No. 1 15,00€.00 25,250.00 3. Electrical Installation Accepted tender figure:RM 85,000.00 V.0. No. 1 V.0. No. 2 12,500.00 18,C00.00 40,000.00 12,500.00 4. Litt Installation Accepted tender figure:RM 520,000.00 No variation 0.00 0.00 © Hak Cipta Universiti Teknologi MARA CONFIDENTIAL,‘CONFIDENTIAL 5 ____CF/JUL 2023/BQS659/QSM659/QSB669 | | Fire Fighting System Accepted tender figure:RM 90,000.00 No variation 0.00 0.00 Based on the information provided, prepare a draft Statement of the Final Account complete with Summary of Variations and Final Certificate for the project, (25 marks) QUESTION 3 2) During the course of carrying out a contract for the construction of a 12-storey high condominium block in Petra Jaya, the Architect/S.O instructed the Contractor to change the layout of the top floor to accommodate an outdoor ‘swimming pool. The whole structure of that floor together with the finishes to the floor and walls must be changed and the Contractor requested the Architect/S.0 to issue instructions to accommodate all the changes. The Architect/S.O was too busy to issue a written order for this work, but the Contractor nevertheless carried on with the work as required by the Architect/S.O. On completion of the work, the Contractor was not aid for the extra work, although he contended that the changes were extra, and he was entitled to additional payrrent based ‘on the variation works. i) Define variation based on PWD and PAM Standard Form of Contract ( marks) ii) Discuss the contractual legality of the above situation. (10 marks) b) The S.0 issued an instruction to the contractor to provide three (3) additional shelters for the student's convenience. The instruction was issued out two (2) weeks after the contractor had been awarded the Certificate of Practical Completion (CPC) as fulfil a new requirement by the Kementerian Pendidikan Tinggi (KPT) Malaysia. In response to the instruction, the contractor has written back to the S.O/Architect stating tha’ he would only agree to carry out the works if the S.O agrees to pay all the additioral costs incurred to him. Advise the S.O/Architect regarding the contractor's response. (10 marks) © Hak Cipta Universiti Teknologi MARA CONFIDENTIALCONFIDENTIAL 6 CFIJUL 2023/BQS659/QSM659/QSB669 QUESTION 4 Loss and expense claims are often associated with delays or any disruption on the contractor's progress of work where the Contractor incurs loss due to the failure of the Employer. a) Referring to the PWD203A (Rev. 1/2010) and PAM 2018 (With Quantities) standard forms of contract, discuss the procedure involved for a successful claim for direct loss and/or expense, (45 marks) b) Briefly explain the probable head of claims that the contractor could validly submit. (10 marks) END OF QUESTION PAFER (© Hak Cipta Universiti Teknologi MARA CONFIDENTIAL,
You might also like
BQS659 Final Account Work Example
PDF
100% (1)
BQS659 Final Account Work Example
10 pages
2015 LAM Part 3 Exam Paper 2
PDF
No ratings yet
2015 LAM Part 3 Exam Paper 2
8 pages
Quanity Surveying Interview Questions - 1
PDF
No ratings yet
Quanity Surveying Interview Questions - 1
15 pages
Interim Payment
PDF
No ratings yet
Interim Payment
42 pages
Faculty - Architecture, Planning, and Surveying - 2022 - Session 1 - Degree - bqs609
PDF
No ratings yet
Faculty - Architecture, Planning, and Surveying - 2022 - Session 1 - Degree - bqs609
5 pages
BQ 230809
PDF
No ratings yet
BQ 230809
49 pages
Bqs659 Fa Latest Jan2022
PDF
No ratings yet
Bqs659 Fa Latest Jan2022
7 pages
Faculty - Architecture, Planning, and Surveying - 2022 - Session 1 - Diploma - dqs359
PDF
No ratings yet
Faculty - Architecture, Planning, and Surveying - 2022 - Session 1 - Diploma - dqs359
4 pages
Task1 - PP Interim Payment
PDF
100% (1)
Task1 - PP Interim Payment
5 pages
3 Hours / 70 Marks: Seat No
PDF
No ratings yet
3 Hours / 70 Marks: Seat No
3 pages
2023 Winter Question Paper (Msbte Study Resources)
PDF
No ratings yet
2023 Winter Question Paper (Msbte Study Resources)
4 pages
Assign 4
PDF
No ratings yet
Assign 4
3 pages
BQ+ Harbour+City+Blank+June+ (Tao 2021
PDF
No ratings yet
BQ+ Harbour+City+Blank+June+ (Tao 2021
383 pages
3 Hours / 100 Marks: Seat No
PDF
No ratings yet
3 Hours / 100 Marks: Seat No
3 pages
CT1 Nov2022 Maf201 Q
PDF
No ratings yet
CT1 Nov2022 Maf201 Q
5 pages
CT MAF201 - Q - Nov2020
PDF
No ratings yet
CT MAF201 - Q - Nov2020
4 pages
Tutorial 2 - BTQS3024 - Answer
PDF
No ratings yet
Tutorial 2 - BTQS3024 - Answer
2 pages
Ctnov22 - Maf201 Q
PDF
No ratings yet
Ctnov22 - Maf201 Q
5 pages
CT Maf201 May2022 - Q
PDF
No ratings yet
CT Maf201 May2022 - Q
5 pages
Assignment 2 Final Account May 2025
PDF
No ratings yet
Assignment 2 Final Account May 2025
4 pages
Sop Sampleforms
PDF
No ratings yet
Sop Sampleforms
13 pages
Tutorial Final Payment
PDF
No ratings yet
Tutorial Final Payment
5 pages
Section D: Track Record (For CW, CR, Me, FM and MW Workheads)
PDF
100% (1)
Section D: Track Record (For CW, CR, Me, FM and MW Workheads)
3 pages
T250 MBW Front End
PDF
No ratings yet
T250 MBW Front End
9 pages
Assignment A
PDF
No ratings yet
Assignment A
9 pages
Workshop 4 Solution
PDF
No ratings yet
Workshop 4 Solution
7 pages
BUIL1287 Assignment QUESTION ONLY (2020)
PDF
No ratings yet
BUIL1287 Assignment QUESTION ONLY (2020)
4 pages
PP July 2022
PDF
No ratings yet
PP July 2022
6 pages
Monthly Commercial Report:: Emmar Properties (PJSC)
PDF
100% (1)
Monthly Commercial Report:: Emmar Properties (PJSC)
9 pages
2023 Mar Paper 2
PDF
No ratings yet
2023 Mar Paper 2
9 pages
EOT Sample
PDF
85% (13)
EOT Sample
22 pages
Question 1 (25 Marks)
PDF
No ratings yet
Question 1 (25 Marks)
5 pages
BQS659 Ap2246a Assignment 3-1
PDF
No ratings yet
BQS659 Ap2246a Assignment 3-1
5 pages
BFC31602
PDF
No ratings yet
BFC31602
7 pages
Contract and Estimation Finals BFC31602
PDF
No ratings yet
Contract and Estimation Finals BFC31602
6 pages
22601-Sample-Question-Paper (Msbte Study Resources) PDF
PDF
100% (1)
22601-Sample-Question-Paper (Msbte Study Resources) PDF
4 pages
PP Past Year Dec 2015-July 2017-Jan 2018
PDF
100% (1)
PP Past Year Dec 2015-July 2017-Jan 2018
30 pages
PP Feb 2022
PDF
No ratings yet
PP Feb 2022
8 pages
3 Hours / 100 Marks: Instructions: (1) All Questions Are Compulsory
PDF
No ratings yet
3 Hours / 100 Marks: Instructions: (1) All Questions Are Compulsory
4 pages
Tutorial 3 Answer
PDF
No ratings yet
Tutorial 3 Answer
2 pages
1045 Deannamuhidi (Contract Ass1)
PDF
No ratings yet
1045 Deannamuhidi (Contract Ass1)
7 pages
Assignment PP
PDF
No ratings yet
Assignment PP
6 pages
5 LT CONSTRUCTION CONTRACT Handout
PDF
No ratings yet
5 LT CONSTRUCTION CONTRACT Handout
2 pages
Afar 6
PDF
No ratings yet
Afar 6
5 pages
2017 Summer Question Paper
PDF
No ratings yet
2017 Summer Question Paper
3 pages
Construction Accounting
PDF
No ratings yet
Construction Accounting
60 pages
Sime Darby Properties Realty Sdn. BHD.: Declaration
PDF
No ratings yet
Sime Darby Properties Realty Sdn. BHD.: Declaration
31 pages
pp2 Coursework 2 - 201808
PDF
No ratings yet
pp2 Coursework 2 - 201808
2 pages
Preliminaries
PDF
No ratings yet
Preliminaries
8 pages
PC No.19 Updated 1
PDF
No ratings yet
PC No.19 Updated 1
661 pages
Dqs 359 Final Assessment - August 2022
PDF
No ratings yet
Dqs 359 Final Assessment - August 2022
7 pages
Tutorial 6 Answer
PDF
0% (1)
Tutorial 6 Answer
3 pages
Criteria Comments Achievement (Y / N)
PDF
No ratings yet
Criteria Comments Achievement (Y / N)
7 pages
8 CE Laws Final Examination Questionaires
PDF
100% (1)
8 CE Laws Final Examination Questionaires
4 pages
Griha Rating Booklet - Dec12
PDF
No ratings yet
Griha Rating Booklet - Dec12
21 pages
3333 OCW L6-Preparation of Final Account
PDF
No ratings yet
3333 OCW L6-Preparation of Final Account
13 pages