Truth, Excellence, Service
Adique, John Vic A. Project Management Plan
Angeles, Francisco Jr. S. «Date Submitted»
Bautista, Micah Rianna S.
R2-M2-05
Project Title: Assessing the Physical Properties of a Composite Made from Abaca
Fibers and High-Density Polyethylene (HDPE) as a Potential Alternative to Commercial Plywood
PROJECT MANAGEMENT PLAN
NETWORK CHART
Paste figure of network chart here. Put appropriate caption. As early as the network chart, you may use landscape layout.
EST/ECT/LST/LCT TABLE
Task Immediately Estimated Earliest Start Earliest Completion Latest Start Latest Completion
Code Preceding Tasks Duration Time (EST) Time (ECT) Time (LST) Time (LCT)
A — 10 0 10 0 10
B 7 0 7 3 10
—
C A,B 1 10 11 10 11
D C 25 11 36 11 36
E — 5 0 5 38 43
F D,E 7 36 43 36 43
G — 7 0 7 36 43
H — 21 0 21 22 43
I F, G, H 5 43 48 43 48
J — 7 0 7 41 48
K I, J 3 48 51 49 52
L I, J 3 48 51 49 52
M I, J 4 48 52 48 52
N I, J 3 48 51 49 52
O K, L, M, N 7 52 59 52 59
GANTT CHART
Paste the Gantt chart screenshot from Excel or create your own table here. Remember to properly place tasks and use a different color
for the critical tasks AND indicate them using a legend. Use a ray with broken and solid lines depending on the duration to indicate
the slack time.
MODIFIED GANTT CHART
Same instructions; note that the MGC is the Gantt Chart with any task movement along the slack. If there are no movements (MGC is
same as previous), provide a short explanation why no tasks are moved.
MANPOWER TASK LIST
Task Task Description Researcher Immediately Estimated Earliest Start Date2 Target Start Date2 Latest Start Latest
Code in-charge1 Preceding Duration Date2 Completion
Tasks (in days) Date2
A
B
C3
..
1 Equitably distribute work among members. You can always assign “all”, but equitable distribution is recommended to ensure someone is in-charge of a task.
2 Note that these are now CALENDAR DATES instead of the day 0, day 1, etc. that was used in the computation from the network chart. You still need those
values (like task duration, primarily) to count days. Include weekends in counting days.
3 If the task is critical, highlight the entire row.