Mk8-MM-Manual-19.05.2020 - ENG - 238-316
Mk8-MM-Manual-19.05.2020 - ENG - 238-316
Mk8-MM-Manual-19.05.2020 - ENG - 238-316
12.7 Faults
The table below show the faults which are directly related to the Bottom Blowdown function.
13 DRAUGHT CONTROL
Draught control is used to manage the excess draught from stacks, in both fire-tube and water-tube
applications, so heat transfer from the hot gases to the boiler tubes can be optimised. Both heat transfer rate
and combustion rate depend on the motion of the flue gases; any changes in boiler pressure can affect the
amount of combustion air entering the burner, possibly resulting in unburnt fuel. An excess of unburnt fuel
can lead to unsteady combustion with dangerous consequences. A tall stack is susceptible to a changing
pressure which is caused be stack temperature and wind velocity. The main benefits of maintain stack
pressure through draught control include:
The Autoflame draught control stores the pressure conditions at the commissioning stage and modulates
with the firing curve to maintain this, irrespective of changing firing rate and stack conditions. Normally there
is a vertical main stack which has a horizontal cross connection from the boiler flue gas outlet; this is then
connected into the main stack.
The boiler only works at optimum efficiency when all the conditions that affect its operation are held at good
commissioned values. Therefore, under the new arrangement, a butterfly valve driven by a positioning
motor, is placed in the horizontal back flue typically two or three metres from the boiler. A differential
pressure sensor is then inserted into the flue that is between the boiler outlet and the butterfly valve. As
stack energy alters, the suction or pressure would vary at this point. It can be seen that by measuring the
pressure of the draught at the position of the damper could be adjusted to bring the pressure or suction back
to its commissioned value, the complete system would then be operating at optimum efficiency again.
After commissioning is completed, every fuel and air position will have a stack damper position together with
a stored draft pressure. The stack pressure is controlled by air pressure sensor, stack damper and PI loop.
When the system is in run mode the stack damper will be positioned according to the stored commissioning
pressure. If the stack pressure reading measured by the differential air pressure sensor reads a different
condition to the stored value, then the stack damper butterfly valve will be adjusted to ensure that the stack
pressure is brought back to its commissioned value.
Depending on the setup, Draught Control may require the following parts:
• Air Pressure Sensor – please see Autoflame Sensors Guide.
A siphon loop must be fitted on the flue for air sensor.
• Positioning Servomotor, this may also require a mounting kit if used with a third-party damper –
please see Autoflame Valves and Servomotors Guide.
• Draught Damper – Available upon request with the servo mounting fitted as standard, please contact
Autoflame for sizes and availability.
The table below shows the Expansion Options used for Draught Control configuration.
The draught servomotor can be set on the Mk8 MM for servomotor movement only or draught control with a
pressure sensor to maintain the stack pressure.
The draught control trim functionality follows the same ideology to the EGA, where corrections are made to
air damper to compensate for the changes in exhaust gas values from their commissioned values, caused by
fluctuations in ambient conditions. For Autoflame draught control, corrections are made to the stack damper
to compensate for changes in wind and ambient conditions which cause the stack pressure to differ from the
commissioned stack pressure along the fuel curve.
Once the burner starts up and the main flame stabilised, there is a time delay where no draught control
operation occurs, set in expansion option 85. After this time delay elapses, as the air going into the burner is
increased from low fire to high fire, the boiler pressure may change, and the draught servomotor will move to
follow these changes as commissioned. If the atmospheric or stack pressures have changed from their
commissioned values along the curve, the air damper will either move in the open, or close direction to
adjust the air pressure in the stack back to its set value.
The smallest angle that the draught damper can drive to while running is defined by expansion option 83;
when the burner turns off, the draught damper will go to commissioned closed position to maintain heat
within the boiler.
If draught control is optioned off after being commissioned, then the draught servomotor will continue to
move to its commissioned angular position as the burner fires.
There is a deactivation window, outside of which no trim occurs, and the air damper remains at the
previously trimmed position until back within the window and trim is required. This deactivation window is
defined by expansion options 85 - delay before compensation and 86 – commissioned angle variation
tolerance. If the draught servomotor has moved more than the set angular degrees “x”, within the time period
set “y”, than no trim functionality will operate, if trim has been performed prior to this deactivation then the
trim is carried forward.
For example, when the burner is first switched on, if the burner comes out of warming in lead-lag control or is
switched from low flame hold to auto mode, there is a high load demand. In these situations the firing rate
may ramp up quickly to meet load demand, at this point if the draught servomotor is required to move greater
than the commissioned angle variation tolerance and quicker than the delay before compensation then no
trim functionality will occur and any trim % will be carried forward.
If within the trim window, the trim functionality is controlled by the maximum forward or backward trim set in
expansion option 84 maximum compensation, and also by the PI settings in expansion options 90
proportional band and 91 integral time. The maximum compensation set in expansion option 84 is the
maximum percentage of the commissioned draught servomotor angle to which the stack damper will trim
negative or positive.
Figure 13.3.3.ii shows the draught trim operation to maintain the commissioned draught pressure.
13.4.1 Configuration
The draught control servomotor positions, and the stack pressure if using draught control is enabled, is set
during the burner commissioning procedure.
Due to softened error checking, it is recommended to use an industrial UNIC servomotor for the draught
channel; however, a small/large servomotor can be used for smaller applications. The servomotor will need
to be sized according to the torque requirements of the stack damper. If draught control is enabled in
expansion 82, then a Mk8 air pressure sensor is also required, part number MM80005.
For information on installing the draught servomotor and air pressure sensor, please see section 13.1. For
dimensions and technical specification for the draught servomotor, please refer to Autoflame Valves and
Servomotors manual.
The table below shows the MM terminals for the draught servomotor and Mk8 air pressure sensor.
Terminal Description
DT+ Digital communication connections from draught control pressure sensor
DT- Digital communication connections from draught control pressure sensor
DP- 0V supply to draught control pressure sensor and draught control servomotor
DP+ +12V supply to draught control pressure sensor and draught control servomotor
DPW Signal from draught control servomotor, indicating position
DCI Switched neutral – drives draught servomotor clockwise
DCD Switched neutral – drives draught servomotor counter clockwise
When wiring the air pressure sensor, the screen is connected through the casing of the lead and through the
sensor; therefore, the flying lead should be connected to the MM without a screen. The screen should be
carried through until the connection to the MM; the screen should not be connected to the S terminal.
The table below shows the expansions options to be set when using draught control.
The draught servomotor can be used for draught control trim with an air pressure sensor, or as a draught
servomotor which drives to commissioned positions along the firing curve.
Figure 13.4.2.i shows the draught servomotor enabled without draught control trim.
Important Note: Prior to commissioning, the fuel and air servomotors must be calibrated to ensure that the
position of the valves and damper correspond to the potentiometer feedback signal as displayed on the MM.
When the valve is fully closed, the MM should display zero degrees. If it does not, please adjust the
servomotor potentiometer.
If the MM is commissioned without an EGA then a combustion analyser is required to check the exhaust
gases. If the system does have an EGA, then a combustion analyser is not necessary as the EGA performs
all normal exhaust gas measurements. When burning oil, a smoke detection device is also necessary to
check that the smoke generated is within safe limits.
To implement commissioning efficiently, arrange for a substantial load on the boiler. The commissioning
procedure can be interrupted due to excess temperature or pressure, causing the burner to turn off; the
commissioning data entered so far is not lost, provided power is not lost to the MM. When the burner is
called back on, the system starts automatically, and commissioning can proceed from where it was left.
Once a start position has been entered, the high fire position is entered next, then descending fuel/air
positions are entered consecutively until finally the low fire position is entered. CH1 and CH2 positions must
always be less than the ones previously entered; however, CH3 to CH7 can be set lower or higher than the
previous position. CH7 is used for the draught servomotor (unlockable expansion feature).
On a newly installed system the following procedures should be carried out as listed:
1. Check all interconnecting wiring between the MM and external components is correct.
2. Set options, parameters and expansion options required.
3. Commission bottom blowdown module if optioned.
4. Commission water level probes and external level sensor if optioned.
5. Set up servomotors.
6. Program fuel/air positions.
On a previously commissioned system is it possible to omit steps 1 to 5.
In addition to the CH7, a draught pressure tab is available on the MM screen whilst commissioning if draught
control is enabled rather than draught servomotor. Use CH7 to change the draught damper angle to maintain
the boiler’s ideal stack pressure throughout the commissioning curve.
Note: If on the day of commission, there are extreme conditions such as heavy wind, the stored angles for
the draught damper along the commissioned curve may not be relevant for a day with average wind speed
over the stack.
Go through the burner commissioning process as described in section 3.4 and entered the draught
servomotor positions as required. The draught servomotor cannot be set at a position lower than the
minimum angle set in expansion option 83, all positions except for the closed which can be set lower.
13.6 Faults
The table below show the faults which are directly related to the draught control function.
14 DIRECT MODBUS
14.1 Overview
The Mk8 MM can be accessed remotely in one of the following two ways:
If Direct Modbus is used on the Mk8 MM (for example connecting the MM directly to a Building Management
System - BMS), then neither Autoflame Intelligent Boiler Sequencing (IBS) nor the DTI can be used on that
MM. A Mk8 DTI is required if IBS and Modbus are required at the same time.
There are a limited number of Modbus addresses available on the Mk8 MM which can be accessed directly
without using a DTI.
The table below shows the Expansion Options used for configuring Direct Modbus.
Up to 10 MMs can be linked together and connected to any Management System that supports Modbus
protocol via terminals 27 and 28. Each Mk8 MM needs to be set with an individual Modbus Device ID in
expansion option 104.
The following expansion options need to be set on the Mk8 MM for to configure Direct Modbus.
The MM communicates using an RS485 data link from terminals 27 (-ve) and 28 (+ve), the connection must
be screened from the MM side only. Belden 9501 data cable is recommended for the communication.
Terminal Description
27 RS485 -
28 RS485 +
S Screen
The maximum block of addresses the MM can read and write to is 127, as per Modbus having a built-in limit
of 255 byte packets.
If the MM does not receive any Modbus commands for 60 seconds, the Modbus goes ‘offline.’ You can keep
the Modbus ‘online’ with a simple instruction, such as polling or setting a single value to that individual MM. If
the Modbus is ‘offline’ then remote setpoint and firing rate set via Modbus will be disabled. The only
exception is the enable/disable burner which changes the enable/disable button on the MM on the home
screen, as this change will last until the Modbus state is changed again or the enable/disable button is
pressed again.
If the MM is powered off or the communications is lost, the Modbus address values from the unit will not be
true.
Please check the Modbus settings on your Modbus device before configuring it with the Mk8 MM.
15 FIRST OUTS
When the control circuit has a long series chain of various thermostats and switching elements, it can be
difficult to identify which element has opened the control circuit. With First Outs expansion feature it is
possible to monitor up to 15 different inputs in a series control circuit on the Mk8 MM. Each input responds to
a signal voltage of between 110V to 230Vac.
The First Outs can be configured for active input state low or high. When the active input state is set to low,
the first out is triggered when the input is low, and when it is set for high, it will be triggered when the input is
high. The table below shows the functions that can be set for the first outs.
The First Out logs can be displayed by pressing in the Home screen, which gives information on
the First Out number, trigger time and the time it was reset.
The table below shows the Expansion Options used for configuring First Outs.
The burner will shut down when the MM detects a First Out trigger for the non-recycle and recycle functions.
Local codes may require the First Outs to be tied into the burner run circuit, and it is recommended that they
are connected to terminal 53 on the Mk8 MM. A break in circuit will cause the burner to turn off but will not
cause a lockout.
On the First Outs log screen, the MM will display which first out has failed.
Note: Do not tie in first outs to terminal 54 (air proving switch) to turn the burner off as the MM will lockout
with no air pressure, rather than indicating which First Out has failed.
The schematic below shows an example of wiring First Out to terminal 53 on the Mk8 MM.
First outs can be configured either in Commission mode or Online Changes. Press in
Commission mode or press in Online Changes to access the First outs screens.
In the First Outs screen, press on the First Out number to be configured and select the function of first out
when upon the active state set for high or low. Please see section 8.1 for more information on the first out
functions and active input state.
On the Configure First Out screen, press the First Out label highlighted in blue under Touch Label to Edit,
use the on-screen keyboard to edit the name as required, once finished press to save the
change.
The First Outs can be directly and automatically connected to the stat circuit on the Mk8 MM without the
need to physically connect the First Outs to terminal 53 on the MM.
The table below shows the settings which must be set for First Out Interlock.
For Option 145 setting 1 (Enabled), the First Outs will be tied to the burner safety stat circuit T53.
First Out Interlock only allows the First Outs to be configured as:
• Non-recycle or recycle
• Active low
16 HEAT FLOW
16.1 Overview
The purpose of Heat Flow Metering is to measure the amount of steam or hot water being produced and to
check the amount of heat this is delivering. The majority of steam plants require Heat Flow Metering to check
how much steam is being generated and used and at what cost, so the overall plant efficiency can be
determined.
Steam or hot water flow meters are very expensive to procure and complex to install, however, Autoflame
Mk8 MM offers a simple, accurate and cost-effective steam/hot water flow metering solution integrated into
the MM.
Autoflame has been granted a worldwide patent on the Heat Flow Metering function on the Mk8 MM.
Note: Fuel flow metering is required for steam/hot water flow metering.
The table below shows the Expansion Options used for configuring Heat Flow Metering.
16.3 Wiring
The table below shows the terminals used for the steam flow metering.
MM Terminal Description
- Common for terminals T1, T2 and T3
T1 Signal input from T1 temperature sensor
T2 Signal input from T2 temperature sensor
T3 Signal input from T3 temperature sensor
F- Common for terminals MF and CF
MF Current input, 4-20mA for cold water make up flow meter
CF Current input, 4-20mA for condensate return flow meter
Heat Flow Function set in Expansion Option 120 can be configured and used in different ways.
• The commissioned Fuel Flow Metering on the MM, enabled in option 57.
• The standing losses are set as a fixed percentage in Expansion Option 121
• The total blowdown losses are set as a fixed percentage in Expansion Option 122
• The stack losses are set as a default fixed percentage value in the MM. If an EGA is enabled then
the stack losses are taken from the EGA rather than using a default value for the calculation.
T1 Not Used
T2 Not Used
T3 Spare Input (Temperature Expansion Feature)
2. Steam Flow
A temperature sensor is used to measure the feed water temperature and the value is taken into the
calculation for greater accuracy.
To be used in boilers with an economiser. The temperature of the water going in and out of the economiser
is measured.
The Economiser screen can be accessed by pressing from the main MM screen.
Can be used for systems with deaerators. The temperature of the make up water and the condensate
temperature is measured and used in the heat flow calculation.
T1 Make Up Temperature
T2 Spare Input (Temperature Expansion Feature)
T3 Condensate Temperature
This function is used for systems with a dearator. The flowrate of the make-up water, feedwater and
condensate has to be measured using a flow meter.
The MM Dearator screen displays the live values as well as a history graph for the dearator data.
T1 Make Up Temperature
T2 Feed Water Temperature
T3 Condensate Temperature
MF Current input, 4-20mA for cold water make up flow meter
CF Current input, 4-20mA for condensate return flow meter
• The commissioned Fuel Flow Metering on the MM, enabled in option 57.
• The standing losses are set as a fixed percentage in Expansion Option 121
• The total blowdown losses are set as a fixed percentage in Expansion Option 122
• The stack losses are set as a default fixed percentage value in the MM. If an EGA is enabled then
the stack losses are taken from the EGA rather than using a default value for the calculation.
T1 Not Used
T2 Not Used
T3 Not Used
A temperature sensor is used to measure the feed water temperature and the value is taken into the
calculation for greater accuracy.
Hot Water Flow with Economiser on a vertical condenser hot water boiler
T1 Not Used
T2 Not Used
T3 Spare Input (Temperature Expansion Feature)
11. Steam Flow from Feed Water Meter and Feed Sensor
T1 Not Used
T2 Not Used
T3 Spare Input (Temperature Expansion Feature)
By the addition of one temperature detector it is possible to extrapolate steam flow from a boiler both as an
instantaneous value and a totalised amount over time. A full Steam Flow Metering package is available with
just the addition of one temperature sensor to the system, avoiding the cost of an expensive steam flow
meter and orifice plate that is typically accurate at the higher firing rates only.
The fuel flow metering has been set in option 57 and commissioned for gas. The standing losses are set
default as 1% in expansion option 121. The total blowdown losses are set default as 1% in expansion option
122. The stack losses are set as default in the MM as 15% for oil and 19% for gaseous fuels.
From fuel flow metering, in the screen above the burner is currently firing at 88% with a flow rate of
24.6MMBtu/hr. The net calorific value of the fuel into the wet side of the boiler can be determined by taking
away the losses from the flow rate:
Note: If an EGA is optioned, then the stack losses are taken from the EGA data rather than default system
values, this provides greater accuracy.
Therefore, the net calorific value of the fuel (wet) is 19,434,000 Btu/hr.
19,434,000 𝐵𝐵𝐵𝐵𝐵𝐵/ℎ𝑟𝑟
𝐵𝐵𝐵𝐵𝐵𝐵𝐵𝐵𝐵𝐵𝐵𝐵 𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒 =
24,600,000 𝐵𝐵𝐵𝐵𝐵𝐵/ℎ𝑟𝑟
Therefore the current boiler efficency is 79.0%, which is seen on the Steam Flow Status screen.
The Steam Flow status screen shows that the feed water temperature is currently at 180.0°F, with steam at a
pressure of 51 PSI and 298.7 °F.
Note: Feed water temperature sensors can be used for greater accuracy.
The amount of heat needed to change the feed water to steam is found by the amount of heat needed to
raise 1 lb of feed water at 180.0°F to steam at 51 PSI and 298.7 °F. The standard steam tables are built in
within the steam flow metering on the MM, and this is then calculated as 1032 Btu/lb. This figure is the latent
heat of liquid into steam (gas) plus the sensible heat components.
19,434,000 𝐵𝐵𝐵𝐵𝐵𝐵/ℎ𝑟𝑟
𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆 𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 =
1032 𝐵𝐵𝐵𝐵𝐵𝐵/𝑙𝑙𝑙𝑙
A common practice in steam generation is the use of a “deaerator” to remove the oxygen from the feed water
and hence reduce the incidence of oxygen corrosion in the boiler and steam & condensate pipework.
The principle of a deaerator is to mix the make-up water with the condensate return and live steam direct
from the boiler in a tank. Flash steam may also be directed back to the tank. The effect is to mechanically
“scrub” the oxygen from the feed water and also to preheat it before it is pumped into the boiler.
In the system as set out above, it is no longer valid to measure the temperature of the feed water just before
it enters the boiler as the inlet temperature for the “steam meter” calculation. This water has already been
preheated by steam from the boiler and therefore this additional energy should not be taken into the software
calculation.
The solution is to treat the boiler and deaerator as one system. The energy into the system is supplied by the
burner and the inlet temperature is the “weighted average” of the condensate return temperature and
makeup water temperature. The outlet steam temperature is measured by a temperature sensor in exactly
the same way as in a system without a deaerator.
First the percentage “Make up“ in the “Feed water” must be calculated.
100 x V2
%Mu =
(V2 + V1)
Assuming a steam boiler with a volume of condensate return of 40 GPM and make up water of 8 GPM;
100 x 8
Make up % = = 16.7%
(8 + 40)
In order to calculate the second part to establish the “Weighted Average Temperature”, the following
equation is used.
Steam boiler with condensate return temperature of 176°F and a make up water temperature of 41°F. From
the above example the make up percentage is 16.7%
To implement the above control, the above calculations have been imbedded in the MM to obtain the
“Weighted Average Temperature” (Tave).
Heat Flow Metering is the measurement of the amount of heat being transferred to the water by a hot water
boiler. If the stack losses and the standing losses of the boiler at any moment are known then the remaining
energy is transferred to the water.
Radiation losses are specific to the boiler, 1% radiation losses are typical for a packaged boiler operating at
Maximum Continuous Rating (MCR). The loss is constant regardless of boiler output.
At 50% firing rate the radiation loss is equal to 2% of the energy input.
The total heat input at any given time is given by the Heat Flow Metering so the instantaneous heat input to
the water we can be calculated, and by integrating these values we can get a totalised value for hot water
flow.
Efficiency
Useful Heat into Water = Total Heat ×
100
Useful heat MBTU/Hr
Volume Flow in lbs/hr =
SP Ht BTU/lb/°F × (Flow Temp – Return Temp)
Calculation Example
A boiler firing at 75% firing rate has a heat input of 20,472,840 BTU/Hr (6MW). The temperature of the flow
(MM temperature detector) is 185°F and the temperature of the return water (T1 temperature sensor) is
167°F. The combustion efficiency is 82% (given by the Mk8 MM). Radiation losses stand at 1% at Maximum
Continuous Rating.
1% × 100
Efficiency % = 100% − �18% + �
75%
= 80.67%
Efficiency 80.67
Useful Heat into Water = Total Heat × = 20,472,840 ×
100 100
= 16,514,440 BTU/hr
16,515,440
Volume Flow in lbs/hr =
1 × (185 − 167)
= 917,524.4 lbs/hr
917,524.4
= = 15,120.7 cu ft Hr
60.68
From the above we can see that by enabling Heat Flow Metering expansion function and adding a return
temperature detector to the Mk8 MM, the following information can be obtained:
Spare Temperature Sensor features allows an addition temperature sensor to be used for monitoring either
the exhaust temperature or the coil / tubes temperature on a boiler. This feature also allows the setup of a
temperature threshold for that sensor where the burner shuts down if this threshold is reached.
To use the Spare Temperature Sensor feature, the Heat Flow Metering expansion feature must be unlocked.
The table below shows the expansion features relevant to the spare temperature senor feature.
The use of the spare temperature sensor is governed by expansion option 120.
If steam flow metring is not used then expansion option 120 can be set to 12 – spare temperature senor
only. If a spare temperature sensor is required with steam flow metring, please see the table below for the
possibility and the sensor number used for this function.
A standard Autoflame temperature sensor can be used as a spare sensor, please refer to the Autoflame
Sensors Manual.
Figure 16.7.A: Spare Temperature Sensor configured to measure coil temperature on a vertical coil-tube
steam generator
Figure 16.7.B: Spare Temperature Sensor configured to measure exhaust (stack) temperature on a vertical
coil-tube steam generator
Expansion option 131 allows a spare temperature shutdown threshold to be set. The burner will shutdown
and an alarm will be triggered when this threshold temperature is reached. This alarm can only be reset
when the spare temperature sensor reading drops below this threshold.
16.8 Faults
The table below show the faults which are directly related to the heat flow function.
17.1 Overview
17.1.1 Introduction
The fuel-air mixture determines the combustion performance; poor mixing of the fuel and air reduces the
burner’s combustion performance, and in turn, decrease the combustion efficiency. High fuel-rich
combustion results in incomplete combustion, leaving unburnt fuel in the combustion gas. Unburnt fuel
causes soot build-up and releases harmful CO emissions to the atmosphere. Incomplete combustion wastes
fuel so additional fuel is required to meet the load demand, causing higher fuel cost.
On the contrast, high amount of excess air in the combustion process wastes the heat generated by the
combustion process to heat the excess air and also accelerates the combustion gas travel through the boiler.
This in turns require more fuel to meet the demand and wastes fuel and increase costs. The fully metered
system is used in applications where it is not possible to measure the exhaust gases in the stack, or if the
firing rate is critical to system and controlled remotely.
In ideal stoichiometric combustion, all the fuel is mixed with the exact amount of air for it to be converted fully
to CO2, H2O (N2), releasing heat from the reaction. In the practical world where ideal and laboratory
conditions do not always exist, it is necessary to add more air than that required in stoichiometric combustion
to ensure complete combustion. The equivalence ratio of the combustion is:
(𝑛𝑛𝑎𝑎 /𝑛𝑛)𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠ℎ𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖
𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 𝜙𝜙 =
(𝑛𝑛𝑎𝑎 /𝑛𝑛𝑓𝑓 )𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑒𝑒𝑛𝑛𝑛𝑛
The excess air is the extra amount of air supplied over the amount of air required for complete combustion,
and can be determined from the equivalence ratio:
1 − 𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟
𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸 𝑎𝑎𝑎𝑎𝑎𝑎 =
𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟
1 − 𝜙𝜙
𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸 𝑎𝑎𝑎𝑎𝑎𝑎 𝜀𝜀 = × 100%
𝜙𝜙
21%
𝑂𝑂2 =
1
1+� �
𝜀𝜀
Higher excess air levels will give higher O2 values in the exhaust gases. The optimum excess air will depend
on the fuel type, the combustion chamber design and the burner turndown. High performance burners will
operate 3% O2 (dry) when firing on natural gas, which is equivalent to 15% excess air going into the burner,
whilst producing 0ppm of CO. The stoichiometric data in the lookup tables of the software is gives the excess
air based on the fuel and air flow rates, and the calorific value of the fuel.
The table below shows the Expansion Options used for configuring Direct Modbus.
17.3.1 Philosophy
The fully metered system will add a layer on top of the standard commission map, with the aim of
maintaining the fuel-air ratio for each firing rate. The system can either directly measure mass flow or use
corrected volume flows to maintain this ratio.
The Mk8 MM continuously measures the fuel and air flows to compensate for any variations from stored
values, in an effort to maintain the commissioned burner efficiency. To compensate for changes the MM will
trim the air damper position to try to maintain the commissioned excess air. In addition, the MM will move the
fuel valve, to try to achieve the firing rate required to maintain the commissioned heat input.
The fully metered combustion control works with the commissioned fuel valve and air damper positions,
storing the mass or volume flow of the fuel and air at each point. The flow data is recorded using two 4-20mA
inputs, which can be the data from a mass flow meter or calculated from volume flow meter. When using a
volume flow meter, the fuel density is used to calculate and display a mass flow using either default values or
temperature and Autoflame pressure sensors.
If variations occur from the commissioned fuel or air flow, the MM will trim servomotors up to an option
limited percentage of their commissioned positions at that time. Unlike other systems, the Autoflame fully
metered operation is based on the commissioned fuel-air curve, so combustion deviations are compensated
for faster than those systems without a base firing curve. Should any faults occur with the meters, the control
can be optioned to revert to the default fuel-air curve to allow the burner to continue to run.
As the fuel valve moves to reach the commissioning firing rate, based on the measured mass flow rate, the
air damper will also adjust to achieve the commissioned excess air, due to proportional change required in
air flow.
When measuring the mass flow, the control process will aim to maintain the same fuel-air ratio as the
commissioned fuel flow and air flow ratio. The burner’s firing rate can be controlled by the Autoflame internal
PID, external modulation, hand mode, DTI firing rate or Modbus firing rate. Without fully metered combustion
control, the MM would map the fuel valve angle through the fuel flow curve, whereas with this control, the
fully metered system firing rate is proportional to the mass flow. The firing rate is then determined by:
The maximum mass fuel flow rate is the fuel flow rate recorded at the high fire position during
commissioning. From this, once the burner commission is complete, the fuel flow curve is mapped out
automatically based on the formula above. This means that if the flow meters fail, the MM can revert back to
the default behaviour and use the pre-stored fuel flow curve. Also, if after commission the high fire position
was moved in single point change, the MM will update the fuel flow curve automatically.
The air servomotor will trim to maintain the commissioned fuel-air ratio. The fuel servomotor will trim to
maintain the commissioned firing rate. Both of these control function operate independently if fully metered
combustion control is enabled.
When using mass flow meters, the fuel and air rates are displayed on the MM, these are based on the 4-
20mA input signals from the mass flow meters. The control process will aim to maintain the same fuel-air
ratio as those set during the commissioning process.
If the fully metered system is set with a fuel mass flow meter, then the fuel temperature and pressure
sensors are not required for the fully metered control; however, the pressure sensor can still be used for VPS
and high/low pressure limits. If an air mass flow meter is used, then again, the air temperature and pressure
sensors are not required; however, the air pressure sensor can still be used for air pressure checking during
burner start-up e.g. purge air pressure proving.
The calorific value of the fuel is used to calculate the excess air, so this must be entered accurately.
When using volume flow meters for the fuel and mass flow rate information, corrections need to be applied to
derive the mass flow rate. The MM calculates the mass flows using the fuel density and calorific value; these
must be set accurately for the fuel being metered. If a differential pressure sensor is being used the system
can be optioned to perform square root extraction on the input, thus saving an external converter.
Based on the ideal gas flow, assuming that the humidity and the specific gas constant do not vary, the mass
flow rate is related to the volume flow rate by the following equation:
𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃
𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀 𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 ∝ × 𝑉𝑉𝑉𝑉𝑉𝑉𝑉𝑉𝑉𝑉𝑉𝑉 𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟
𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎
𝑃𝑃
𝑚𝑚̇ ∝ 𝑉𝑉̇
𝑇𝑇
This formula is used internally calculated in the MM to provide a mass flow rate, this is calculated individually
for both gas and air in the MM using the following assumptions:
Variable Action
Ambient air pressure Average ambient pressure, set in expansion option 153
Differential air pressure Air pressure correction not used (assumed 20mbar)
Air temperature Air temperature correction not used (assumed 20OC)
Gas pressure Gas pressure correction not used (assumed 100mbar)
Gas temperature Gas temperature correction not used (assumed 5OC)
If additional Autoflame temperature and pressure sensors are used on either or both the gas and air, then
the calculated mass flow rate displayed will be more accurate. In the event of a sensor failure, the
temperature/pressure value of the failed sensor that was stored at commissioning of value is used to
calculate the displayed mass flow rate allowing the system to continue to run. If the gas and air pressure
sensors are used also used for the VPS, gas pressure limits or air sensors limits, then the burner will lockout
in the event of a sensor failure.
17.4 Set-Up
17.4.1 Configuration
At minimum the MM will require 4-20mA signals from the air and gas flow meters. If using mass flow meters,
then temperature and pressure sensors for the fuel and air must be disabled for fully metered (they can still
be used for flame safeguard). Volume flow metering requires the fuel air and temperature and pressure
values to derive the mass flow rates. When using volume flow metering, enabling temperature and pressure
sensors will make the displayed mass flow calculation more accurate. Temperature and pressure sensors
should be installed near the volume flow meters.
The table below shows the MM terminals used for fully metered combustion control.
When wiring the gas and air pressure sensors, the screen is connected through the casing of the lead and
through the sensor; therefore the flying lead should be connected to the MM without a screen. The screen
should be carried through until the connection to the MM; the screen should not be connected to the S
terminal.
The table below shows the options/expansions options to be set for fully metered combustion control.
Option Description Setting
57 Fuel flow metering 1
61 Fuel 1 calorific value Must be set accurately
62 Fuel 2 calorific value Must be set accurately
63 Fuel 3 calorific value Must be set accurately
64 Fuel 4 calorific value Must be set accurately
Expansion Option Description Setting
140 Fully metered function 1
141 Fuel flow meter type As required
142 Fuel flow meter scaling As required
143 Air flow meter type As required
144 Air flow meter scaling As required
145 Fuel temperature sensor enable Optional
146 Air temperature sensor enable Optional
147 Fuel pressure sensor enable Optional
148 Air pressure sensor enable Optional
149 Maximum fuel channel compensation As required
150 Maximum air channel compensation As required
151 Action on air adjustment failure As required
152 Action on flow meter failure As required
153 Default ambient air pressure As required
154 Fuel 1 density Required for volume flow meter
155 Fuel 2 density Required for volume flow meter
156 Fuel 3 density Required for volume flow meter
157 Fuel 4 density Required for volume flow meter
The current firing rate can be fed back to an external system via a 4-20mA output signal on terminals 16, 17
and 18.
17.4.2 Limitations
When using a volume flow meter, the mass flow rate is calculated using the volume flow rate and either
default pressure and temperature values, or the measured pressure and temperature values.
The MM’s fully metered combustion control is capable of controlling the most common hydrocarbon fuels
including methane, ethanol, ethane, butane, pentane, acetylene and 1-proponal.
For FGR, oxy fuels, hydrogen and special fuels, please contact Autoflame prior to use;
The fully metered combustion control will not work on oil combustion curves.
If fully metered combustion control is used, then neither an external 4-20mA sensor for auxiliary water level
control nor external fuel flow metering using 4-20mA input can be used. When using the fully metered
system, the fuel flow metering is automatically calculated from the flow rate.
The gas/air pressure sensor recommission feature is not available when using volume flow meters, if these
pressure sensors need to be recommissioned; a full recommission of the burner is required. This is due to
the pressures needing to be stored at the same time as the required volume flow.
Economiser or deaerator options for steam/heat flow metering cannot be used if the temperature sensors or
make-up flow meter inputs are being used for volume flow metering. The IO module can be used instead for
deaerator.
During running the system can adjust the channel 2 air servomotor from the commissioned closed and open
positions to bring the combustion to the commissioned fuel-air ratio, as the fuel servomotor moves. However,
the rest of the channels can only be moved from the low fire and high position, and not outside of this range.
This means that if the fuel servomotor is at the commissioned high fire position, it cannot move further. The
firing rate is limited to less than 100% and if it is critical to the system operation, then the actual firing rate
should be monitored.
The calorific value must be entered corrected to the 1013mbar and 15OC, see options 61 to 64.
17.4.3 Commissioning
Important Note:
Prior to commissioning, the fuel and air servomotors must be calibrated to ensure that the position of the
valves and damper correspond to the potentiometer feedback signal as displayed on the MM. When the
valve is fully closed, the MM should display zero degrees. If it does not, please adjust the servomotor
potentiometer.
The commissioning procedure as described must be strictly adhered to. Anybody commissioning an MM
must be trained in operating combustion equipment safely. The Autoflame products must only be installed,
set up, commissioned and adjusted by an Autoflame certified technical engineer.
The fundamental idea of the system is to set a fuel valve position and then set a corresponding air damper
position. Care must be taken when adjusting the fuel and air positions so as not to create any unstable or
hazardous combustion conditions, e.g. moving the fuel valve to the open position without increasing the air
damper position. Improper use may result in property damage, serious physical injury or death.
The equivalence ratio and excess air provided on the MM are calculated displays based on setup and inputs
from external sources. The exhaust gases should be monitored using a combustion analyser at all times
during commissioning and for any changes to the combustion curve.
For the installation and pre-commissioning checks, please refer to sections 3.2 and 3.3.
The same commissioning procedure for the fully metered combustion control system as the standard
system’s servomotors and VSDs. The difference is that the commissioning engineer can see on the screen
the excess air going into the combustion process and can set the servomotors and VSDs accordingly.
The screen above shows the HIGH position for the servomotors and VSDs being set.
Pressing on the fully metered tab in the commission screen can show the following, based on how the
system has been set:
• Equivalence ratio 𝜙𝜙
• Fuel flow rate (mass, volume)
• Fuel temperature
• Fuel pressure
• Excess air 𝜀𝜀
• Air flow rate (mass, volume)
• Air temperature
• Air pressure
The table will populate mass flow rates of the fuel and air, and the excess air, for each commissioned point.
The commissioned points can be changed/added/removed in single point change as normal, please see
section 3.7 for more information. Note, if the sensors or the flow meters have a fault, then single point
change feature is disabled.
The home screen will display the current excess air going into the combustion process.
Pressing on the servomotors will show the fuel-air screens with the following information available:
17.5 Faults
The table below show the faults which are directly related to the fully metered combustion control function.
18 OPERATION
The home screen shown in Figure 18.1.i displays the current boiler setup. It provides operation information
for each component of the burner/boiler in real time. Pressing on components will display further information
e.g. pressing on the servomotor image will show the servomotor position history. This boiler room setup can
be configured to display what is actually on site, please see section 18.19.5 Boiler Room Configuration.
Servomotor Variable
speed drive
Flame scanner Oil pressure
sensor
Air pressure Gas pressure
sensor/ boiler sensor
steam
pressure
detector
#
External level Steam header
sensor for
water level
IBS EGA
Information Information
Kiln
18.1.2 Faults
Press in the Home screen to view the faults, which are categorised into lockouts, errors, alarms,
warning and first out alarms, and are access by pressing on the corresponding tabs.
18.2.1 Status
Press on the boiler load detector or the boiler image in the Home screen (Figure 18.1.i) to display the Status
screen, which gives the following information:
• Burner rating
• Current fuel selected and type
• Burner starts and run hours
• Current firing rate
• Control method – internal PID control, external modulation or DTI/remote firing rate
• Actual temperature/pressure reading from load detector
• Current setpoint – required, reduced, DTI or external
• Stat status – running interlock T53/ internal stat
• Burner switch on/off offset
• Reduced setpoint
• Indication if MM is firing to meet required or reduced setpoint (red = active, grey = inactive)
• Arrows for adjusting setpoint
Press the arrows to change the required or reduced setpoints. If these arrows are not
displayed, then either the user setpoint change has been disabled (option 15), the DTI is controlling the
setpoint (option 16), external setpoint is enabled (parameter 72), or OTC is enabled (option 80).
Note: Use parameters 29 and 30 to adjust the load detector reading if required.
Press in the Status screen in Figure 18.2.1.i to show the Status History. The setpoint, actual
temperature/pressure and firing rate are displayed graphically.
This data is logged for 24 hours on the MM. Use the buttons to change the timescale of the data
displayed and press and drag on the axis to zoom in/out of the graph.
This information is logged for 2 years on the DTI when connected with the MM.
Note: Power cycling the MM or changing fuel will reset the 24-hour history data log on the MM.
Press and hold for 3 seconds in the Status screen in Figure 18.2.1.i to disable the burner. Press
and hold this same button to enable the burner.
Press and hold for 3 seconds in the Status screen in Figure 18.2.2.i to put the MM in low flame
hold. Press and hold this button again to return to normal modulation.
Alternatively, the Mk8 MM can also be put in low flame hold via an input on terminal 95.
If low flame hold or hand mode is selected on the MM screen, this will override an input made on terminal 94
or 95.
Note: If using intelligent boiler sequencing, then putting the MM into low flame hold will remove the MM from
the sequence loop. It will resume sequencing once low flame hold is deselected and after the next scan time
elapses.
Note: If low flame hold and hand mode are both selected, then hand mode takes priority.