Job Hazards Analysis - REVISED Temfacil

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 3

Doc.

Code : FM-ESH-01-37

JOB HAZARDS ANALYSIS


Rev. No. : 1
Eff. Date : 20 Apr 2015
Page : 1 of 3

PROJECT NAME/LOCATION OF WORK PH LNG IMPORT TERMINAL PROJECT ILIJAN BATANGAS

To be filed up by Operations Supervisor/Head To be filed up by ESH Head/ Officer

Date Prepared: 07-17-23 JHA No.: SCIC-ESH-JHA-16


Date to be Completed: 07-17-23 Issued Date: 07-17-23
Permit Required: Isolation Required:
Type JHA: ( ) For Renewal ( X ) New Job/ New Work ( ) YES ( ) NO ( ) YES ( ) NO
( )Others: ____________________________ If Yes, indicate the Permits If Yes, indicate the Isolation
Requirements below: Requirements below:

WORK /JOB INSTALLATION/DISMANTLING OF AG&P /SCIC


DESCRIPTION: TEMFACIL

LIST OF MANPOWER / WORKERS AND CONDITIONS


Group Team Members Note: We have been instructed on this JHA/ Safe Work Procedure and understand that failure to
Undertaking the Work: comply with the instructions may lead to administrative and disciplinary action.
Full Name Position Signature Full Name Position Signature

WORK SEQUENCE / CONTROLS/RECOMMENDED


HAZARDS
JOB STEPS SAFE WORK PROCEDURE
Using the first two columns as a guide, decide
Take the job down into steps. Each of the
Identify the hazards associated with each step. Examine each what actions are necessary to eliminate or
steps should accomplish the major task and
hazard to find possibilities that could lead to an incident. minimize the hazards that could lead to an
be logical.
incident.

>Continuous advising them about


the COVID-19 protocol.
Not following on COVID-19 protocol. >Giving disciplinary action for not
COVID-19 Management
following on the guidelines about
Not Wearing of facemask COVID-19.
Dealing with infected COVID-19 personnel.

Preparation of Permit to Work >Supervisor responsible for


(PTW) from client Permit to work requirement not being followed the activity shall ensure that
(AG&P/Linseed) or incomplete attachment (MS, JHA, TSTI & all PPEs are available and
SDS) properly used.
>Ensure the availability of
Unavailability of the permit and JHA complete attachments of all
documents.
>Ensure that permit to work
available and approved by
authorized signatory before the
commencement of the activity
Provide appropriate
information and training all
employees before they start
the work on the site.

Lack of safety awareness / Knowledge & Make a suitable Plan for the
inexperience work and or job task
including personnel
accountable for
pre job preparation.
Doc. Code : FM-ESH-01-37

JOB HAZARDS ANALYSIS


Rev. No. : 1
Eff. Date : 20 Apr 2015
Page : 2 of 3
Unauthorized personnel
should not allow to work on
the working area.
Unauthorized Work
Obtain the required permits from
the permit issuer.
Clear the working area for
access to avoid slip. Trip
fall
Tripping hazard Barricading the area and
proper signboards should
be displayed

Only qualified crane operator


with NC II and rigger must
carry out the lifting activity.
Swing Load Critical lifting plan must be
(Strike against personnel and property) formulated before lifting.
Insulation for high tension
wires must be installed.
Tag line fitted to equipment.
Lifting of temporary
facilities container van.

Installation of barricade and


signage around the activity
area.
Equipment swinging
Advised lifting supervisor if
wind reaches 20 kph above
the lifting activity must stop to
avoid accident.

Wear appropriate PPE; eye


spectacles, gloves, hard hat,
Hit by concrete debris safety boots and body
protection while doing
specified activities.
Concreting of floor slab.

Observe body stretching,


Ergonomics Observe workers physical and
medical condition.

Installation/dismantling Fall from heights


of walls and roof. Provisions of scaffolding
platform and safe access
ladder. Observe proper
anchoring.

Installation of fall protection


system must be in place
Doc. Code : FM-ESH-01-37

JOB HAZARDS ANALYSIS


Rev. No. : 1
Eff. Date : 20 Apr 2015
Page : 3 of 3

before activity. Fall arrest


system should be worn by
workers during activities at
elevated area.

Wear appropriate PPE; eye


spectacles, gloves, hard hat,
safety boots and body
protection (full body harness)
while doing specified activities.

Observe proper handling,


never lift a heavy object above
shoulder level. Observe Buddy
Improper handling and Lifting procedure
system when in lifting.

Periodic inspection of electric


cables for cuts and damage.
Contact with live open electrical parts Ensure any cables on ground
are not positioned in or near
water.
Electrical conduiting,
wiring, receptacle and
lighting installation. Only qualified personnel
utilizing appropriate electrical
safety-related work practices
Short circuiting of electrical wires
and PPE shall perform work on
electrical systems and
equipment.

Remove all unwanted


material from the work area.
Housekeeping Slip, Trip and falls
Maintain proper material stacking
and cleaning at work site all time.

Prepared by: Noted by: Approved by:

Jay Joco Roel Montañano ______________________ ________________

ESH Head/OIC Project In-Charge HSE (Linseed) Representive Linseed O&M Team