West Grove For Fire Only Bayabas Residential Estimate
West Grove For Fire Only Bayabas Residential Estimate
West Grove For Fire Only Bayabas Residential Estimate
A. General Requirements
a.1 Permits and Licenses 1.00 lot ₱ 50,000.00 ₱ 50,000.00
a.2 Excavation and Backfilling 1.00 lot ₱ 100,000.00 ₱ 100,000.00
a.3 Material Testing and Soil Boring 1.00 lot ₱ 120,000.00 ₱ 120,000.00
a.4 Safety Facilities 1.00 lot ₱ ‐
a.5 Equipment Rentals
a.9.1 Scaffoldings and H. Frames 1.00 lot ₱ 150,000.00 ₱ 150,000.00
a.9.2 Forms Rental 1.00 lot ₱ 150,000.00 ₱ 150,000.00
₱ 570,000.00
B. Footings
₱ 241,770.67
C. Columns
GROUND FLOOR
C1 Concrete Column 0.25m L x 0.40m 44.80 40 pcs
cement 564 bags ₱ 220.00 ₱ 124,185.60
sand 20.70 cu.m ₱ 750.00 ₱ 15,523.20
gravel 41.40 cu.m ₱ 1,200.00 ₱ 49,674.24
16mm dia Reinforcement Bar 400.00 pcs ₱ 392.00 ₱ 156,800.00
10mm dia Reinforcement Bar 260.00 pcs ₱ 156.00 ₱ 40,560.00
G.I Tie Wire 89.60 kls ₱ 90.00 ₱ 8,064.00
₱ 394,807.04
D. Concrete Beams 1200
Concrete Beam 0.25m L x 0.35m 144.00
cement 1663 bags ₱ 220.00 ₱ 365,904.00
sand 66.53 cu.m ₱ 750.00 ₱ 49,896.00
gravel 133.06 cu.m ₱ 1,200.00 ₱ 159,667.20
16mm dia Reinforcement Bar 1600 pcs ₱ 392.00 ₱ 627,200.00
10mm dia Reinforcement Bar 1280 pcs ₱ 156.00 ₱ 199,680.00
G.I Tie Wire 432 kls ₱ 90.00 ₱ 38,880.00
₱ 1,441,227.20
E. Concrete Slab
Ground Floor Slab 170 1134 sqm
cement 1786 bags ₱ 220.00₱ 392,931.00
sand 78.59 cu.m ₱ 750.00₱ 58,939.65
gravel 157.17 cu.m ₱ 1,200.00₱ 188,606.88
12mm dia Reinforcement Bar 120.00 pcs ₱ 221.00₱ 26,520.00
10mm dia Reinforcement Bar 120.00 pcs ₱ 156.00₱ 18,720.00
G.I Tie Wire 340.20 kls ₱ 90.00₱ 30,618.00
₱ 716,335.53
F. Septic Tank 1 set ₱ 65,000.00 ₱ 65,000.00
₱ 65,000.00
G. CHB Walls 4.00 150 ₱ 600.00
Ground Floor 278.30
5" chb 11950 pcs ₱ 14.00 ₱ 167,300.00
Cement 180 bags ₱ 225.00 ₱ 40,465.69
Sand 119.50 m3 ₱ 750.00 ₱ 89,625.00
10mm dia Reinforcement Bar 175 pcs ₱ 156.00 ₱ 27,300.00
Plastering 956 sqm
Cement 574 bags ₱ 220.00 ₱ 126,192.00
Sand 23.90 m3 ₱ 750.00 ₱ 17,925.00
consumables 1.00 lot ₱ 15,000.00 ₱ 15,000.00
₱ 483,807.69
H. Electrical Works
lighting, power line, panel board, circuit, 1 lot ₱ 249,480.00 ₱ 249,480.00
lighting fixtures and outlet 1 lot ₱ 174,636.00 ₱ 174,636.00
₱ 424,116.00
I. Plumbing Works
Fixtures
urinal 3 set ₱ 3,500.00 ₱ 10,500.00
Water Closet 5 set ₱ 7,500.00 ₱ 37,500.00
Lavatory Set set ₱ 3,000.00 ₱ ‐
Kitchen Sink 2 pcs ₱ 5,500.00 ₱ 11,000.00
GooseNeck Faucet 2 pcs ₱ 1,200.00 ₱ 2,400.00
Floor Drain 10 pcs ₱ 250.00 ₱ 2,500.00
Pipelines
1/2 uPVC pipe 3m 50 pcs ₱ 97.50 ₱ 4,875.00
Pipe, PVC 4"øx3m 50 pc ₱ 751.40 ₱ 37,570.00
Pipe, PVC 3"øx3m 50 pc ₱ 574.60 ₱ 28,730.00
Meter, Water, EVJET, (with calibration Certificate) 1 set ₱ 2,500.00 ₱ 2,500.00
₱ 137,575.00
J. Door and Windows
double door sliding door 1800x2100 6 set ₱ 11,000.00 ₱ 66,000.00
Flush door type 10 set ₱ 3,500.00 ₱ 35,000.00
pvc or alum door for t&b 10 set ₱ 2,800.00 ₱ 28,000.00
door accessories 26 set ₱ 3,000.00 ₱ 78,000.00
Aluminim frame window 50 sqm ₱ 4,500.00 ₱ 225,000.00
₱ 432,000.00
L. Tiling Works
60x60 floor tiles 3024 pc ₱ 180.00 ₱ 544,320.00
30x30 floor tiles ( bathroom) 43 pc ₱ 55.00 ₱ 2,376.00
30x60 wall tiles ( batherooms) 100 pc ₱ 90.00 ₱ 9,000.00
30x60 wall tiles kitchen wall accent ( counter top) 31 pc ₱ 90.00 ₱ 2,772.00
granite 7 lm ₱ 2,000.00 ₱ 13,200.00
Exterior Wall tiles 30x60 82 pcs ₱ 90.00 ₱ 7,410.00
Adhesive 188 bags ₱ 500.00 ₱ 94,154.40
Cement 151 bags ₱ 220.00 ₱ 33,142.35
₱ 706,374.75
M. Painting Works
WALL AND CEILING skimcoat 282 bags ₱ 450.00 ₱ 126,858.60
Flat Latex Paint 137 gal ₱ 660.00 ₱ 90,210.56
Semi Gloss Latex Paint 127 gal ₱ 660.00 ₱ 84,128.00
Door Flat wall Enamel 2 gal ₱ 660.00 ₱ 1,170.58
Gloss Enamel 2 gal ₱ 660.00 ₱ 1,140.48
Railings Epoxy Primer 4 gal ₱ 660.00 ₱ 2,640.00
Consumables 1 lot ₱ 15,000.00 ₱ 15,000.00
₱ 321,148.22
Total Material Cost ₱ 5,934,162.09
Labor Cost ₱ 2,076,956.73
SUPERVISON
Overhead Cost/ Contigency
Total Materials and labor Cost ₱ 8,011,118.82
SIX MILLION FORTY SEVEN THOUSAND TWO AND TWENTY FOUR CENTAVOS
Prepared by: