NEC3 (2005) - Searchable
NEC3 (2005) - Searchable
NEC3 (2005) - Searchable
construction
contract
June 2 0 0 5
\
•
,.
•
ut'
' •
..
1 ; J I '"
.+'
..
�
..
'
•
+l
•
Engineering a n d Construction Contract
design responsibility
An NEC document
June 2005
OGG advises public sector procurers that the form of contract used has to be selected
This edition of the NEC (NEC3) complies fully with the AEC principles. OGG recommends
the use of NEC3 by public sector construction procurers on their construction projects.
The NEC offers a u n i q u e and extensive range of products and services to support
NEC3 D I G I T AL T R A I NI N G
EC3 digital, the latest development from the NEC Training offers a suite of short courses at a
NEC, is a new service that provides you with a l l variety of venues across the UK and worldwide.
» View and print contracts the use of N E C . Our consultants are skilled
» Complete digital contract data and forms practitioners who are closely involved with the
extranets. EVENTS
NEC roadshows, seminars, workshops and
NEC word.de
USERS' GROUP
The NEC Users' Group is an essential support BOOKS
serv ice for all users of the N E C . It provides contact A comprehensive range of books and g u e s wrtten
w t h a n e t w o rk of users and dudes a free by NEC practitioners to support the contacts are
helpline seni ce, newsletters and a range of events available including users guides an contract
ntrc+
I ' 1 C A L .
J
characteristics:
• Its use stimulates good management of the relationship between the two
parties to the contract and, hence, of the work included in the contract
NEC3 Engineering and Construction Contract is one of the NEC family and is
consistent with all other NEC3 documents. Also available are the Engineering
D, E and F. I
Consultative edition 1 9 9 1
Second edition 1 9 9 5
J
Cover photo, Golden Jubilee Bridge, courtesy of City of Westminster a
t
9 8 7 6 5 4 3 2 '
I
British Library Cataloguing in Publication Data for this publication is available
t
%
All rights, including translation, reserved, The owner of this document may
reproduce the Contract Data for the purpose of obtaining tenders, awarding I
and administering contracts. Except as permitted by the Copyright, Designs
the prior written permission of the NEC Director, NEC, Thomas Telford Ltd, ,
1 Heron Quay, London E14 4JD.
Printed and bound in Great Britain by Bell & Bain Limited, Glasgow, UK I
f
i
'
CONTENTS
Acknowledgements iv
Schedule of Options 1
3 Time 9
5 Payment 13
6 Compensation events 15
7 Title 20
9 Termination 24
F Management contract 40
Option W2 45
X3 Multiple currencies 49
X5 Sectional Completion 49
X7 Delay damages 50
X12 Partnering 50
X16 Retention 53
Schedule of Cost 56
Components
Components
Contract Data 61
Index 74
ACKNOWLEDGEMENTS
The NEC first edition was produced by the Institution of Civil Engineers
The original NEC was designed and drafted by Dr Martin Barnes then of
Coopers and Lybrand with the assistance of Professor J. G. Perry then of the
The second edition of the NEC documents for engineering and construction
contracts was produced by the Institution of Civil Engineers through its NEC
Panel.
The third edition of the NEC Engineering and Construction Contract was
produced by the Institution of Civil Engineers through its NEC Panel. The
Flow Charts were produced by John S. Gillespie with assistance from Tom
Nicholson.
FInstCES, FAPM
NEC Consultant:
Secretariat:
The Institution of Civil Engineers acknowledges the help in preparing the third
J. C. Broome, BEng
C. F look, Esq.
D. Weeks, FRI CS
S. Zarka, FRICS
SCHEDULE OF OPTIONS
The strategy for choosing the form of contract starts with a decision between
Option W1 Dispute resolution procedure (used unless the United Kingdom Housing
Option W2 Dispute resolution procedure (used in the United Kingdom when the Housing
to use any of them. Any combination other than those stated may be used.
Option X1 Price adjustment for inflation (used only with Options A, B, C and D)
Option X15 Limitation of the Contractor's liability for his design to reasonable skill and
care
required.
CORE CLAUSES
1 General
Actions 10
10.1 The Employer, the Contractor, the Project Manager and the Supervisor shall
act as stated in this contract and in a spirit of mutual trust and co-operation.
terms 11.1 In these conditions of contract, terms identified in the Contract Data are in
11.2 (1) The Accepted Programme is the programme identified in the Contract
Data or is the latest programme accepted by the Project Manager. The latest
Programmes.
• done all the work which the Works Information states he is to do by the
• corrected notified Defects which would have prevented the Employer from
If the work which the Contractor is to do by the Completion Date is not stated
0
in the Works Information, Completion is when the Contractor has done all the •
c
work necessary for the Employer to use the works and for Others to do their • Q
£
work. O 0
0
E
(3) The Completion Date is the completion date unless later changed in 0
0
( 4) The Contract Date is the date when this contract came into existence.
( 5 ) A Defect is
• a part of the works which is not in accordance with the Works Information
or
with the applicable law or the Contractor's design which the Project
( 6) The Defects Certificate is either a list of Defects that the Supervisor has
notified before the defects date which the Contractor has not corrected or, if
(7) Equipment is items provided by the Contractor and used by him to Provide
the Works and which the Works Information does not require him to include in
the works.
(8) The Fee is the sum of the amounts calculated by applying the subcon
tracted fee percentage to the Defined Cost of subcontracted work and the
(9) A Key Date is the date by which work is to meet the Condition stated. The
Key Date is the key date stated in the Contract Data and the Condition is the
condition stated in the Contract Data unless later changed in accordance with
this contract.
(10) Others are people or organisations who are not the Employer, the Project
( 12) Plant and Materials are items intended to be included in the works.
(13) To Provide the Works means to do the work necessary to complete the
works in accordance with this contract and all incidental work, services and
(14) The Risk Register is a register of the risks which are listed in the
Contract Data and the risks which the Project Manager or the Contractor has
description of the actions which are to be taken to avoid or reduce the risk.
(15) The Site is the area within the boundaries of the site and the volumes
above and below it which are affected by work included in this contract.
"'
$ (16) Site Information is information w hich
::,
c c
• describes the Site and its surroundings and
ro u
• is in the documents which the Contract Data states it is i n .
E e
0
_
U • construct or install part of the works,
o • s uppl y Pl ant and Materials which the person or organisation has wholly
c c
g e or partly designed specifically for the works.
g 6
5 ( 1 8 ) The Working Areas are those parts of the working areas which are
0
,
•
c
Q
un l ess later changed in accordance with this contract.
c
O 0
0
( 19) Works Information is information which either
£
0 • specifies and describes the works or
0
and is either
12.1 In this contract, except where the context shows otherwise, words in the
singular also mean in the plural and the other way round and words in the
12.3 No change to this contract, unless provided for by the conditions of contract,
has effect unless it has been agreed, confirmed in writing and signed by the
Parties.
Communications 13
13.2 A communication has effect when it is received at the last address notified by
13.3 If this contract requires the Project Manager, the Supervisor or the Contractor
him by the Contractor for acceptance. If his reply is not acceptance. the
Project Manager states his reasons and the Contractor resubmits the commu
nication within the period for reply taking account of these reasons. A reason
13.5 The Project Manager may extend the period for reply to a communication if the
Project Manager and the Contractor agree to the extension before the reply is
<J)
due. The Project Manager notifies the Contractor of the extension which has Cl>
U
been agreed. :,
c c
13.6 The Project Manager issues his certificates to the Employer and the Contrac « c
E c
tor. The Supervisor issues his certificates to the Project Manager and the 0
Contractor. :g
0
other communications.
a compensation event.
the Supervisor 14.1 The Project Manager's or the Supervisor's acceptance of a communication
U
from the Contractor or of his work does not change the Contractor's responsi
1=
bility to Provide the Works or his liability for his design. %.
' £
o Q
0
14.2 The Project Manager and the Supervisor, after notifying the Contractor, may
£
delegate any of their actions and may cancel any delegation. A reference to 0
0
an action of the Project Manager or the Supervisor in this contract includes an
14.3 The Project Manager may give an instruction to the Contractor which changes
14.4 The Employer may replace the Project Manager or the Supervisor after he has
Areas 15.1 The Contractor may submit a proposal for adding an area to the Working
Areas to the Project Manager for acceptance. A reason for not accepting is
that the proposed area is either not necessary for Providing the Works or used
Early warning 16
16.1 The Contractor and the Project Manager give an early warning by notifying the
• delay Completion,
r
l • delay meeting a Key Date or
I
k.
neC 3 sgneenng ana construction contract
The Contractor may give an early waring by notifying the Project Manager of
any other matter which could increase his total cost. The Project Manager
enters early warning matters in the Risk Register. Early warning of a matter
for which a compensation event has previously been notified is not required.
16.2 Either the Project Manager or the Contractor may instruct the other to attend a
risk reduction meeting. Each may instruct other people to attend if the other
agrees.
• making and considering proposals for how the effect of the registered
• seeking solutions that will bring advantage to all those who will be
affected,
• deciding on the actions which will be taken and who, in accordance with
• deciding which risks have now been avoided or have passed and can be
16.4 The Project Manager revises the Risk Register to record the decisions made at
each risk reduction meeting and issues the revised Risk Register to the
Manager instructs the change at the same time as he issues the revised Risk
Register.
Ambiguities and 17
inconsistencies 17.1 The Project Manager or the Contractor notifies the other as soon as either
which are part of this contract. The Project Manager gives an instruction
requirements 18.1 The Contractor notifies the Project Manager as soon as he considers that the
Information appropriately.
£ Prevention 19
Q
'1l C 19.1 If an event occurs which
5 g
0
• stops the Contractor completing the works or
E
o • stops the Contractor completing the works by the date shown on the
0
A ccepted P rogramme,
and which
have such a small chance of occurring that it would have been unreason
20.1 The Contractor Provides the Works in accordance with the Works Information.
21.1 The Contractor designs the parts of the works which the Works Information
states he is to design.
21.2 The Contractor submits the particulars of his design as the Works Information
requires to the Project Manager for acceptance. A reason for not accepting
the Contractor's design is that it does not comply with either the Works
The Contractor does not proceed with the relevant work until the Project
21.3 The Contractor may submit his design for acceptance in parts if the design of
design 22.1 The Employer may use and copy the Contractor's design for any purpose
otherwise stated in the Works Information and for other purposes as stated in
the Works Information.
Design of Equipment 23
23.1 £
The Contractor submits particulars of the design of an item of Equipment to
the Project Manager for acceptance if the Project Manager instructs him to, A
e?
c
reason for not accepting is that the design of the item will not allow the Con c c
g e
tractor to Provide the Works in accordance with £ 6
0 .
oz
• the Works Information, c
z
c
People 24
- c
5
24.1 The Contractor either employs each key person named to do the job stated in 8 =
E
the Contract Data or employs a replacement person who has been accepted
0
c
by the Project Manager. The Contractor submits the name, relevant qualifica
Manager for acceptance. A reason for not accepting the person is that his
relevant qualifications and experience are not as good as those of the person
who is to be replaced.
24.2 The Project Manager may, having stated his reasons, instruct the Contractor
to remove an employee. The Contractor then arranges that, after one day, the
employee has no further connection with the work included in this contract.
and Others 25.1 The Contractor co-operates with Others in obtaining and providing information
which they need in connection with the works. He co-operates with Others and
shares the Working Areas with them as stated in the Works Information.
25.2 The Employer and the Contractor provide services and other things as stated
in the Works Information. Any cost incurred by the Employer as a result of the
25.3 If the Project Manager decides that the work does not meet the Condition
stated for a Key Date by the date stated and. as a result, the Employer incurs
on the same project. the additional cost which the Employer has paid or will
incur is paid by the Contractor. The Project Manager assesses the additional
cost within four weeks of the date when the Condition for the Key Date is met.
The Employer's right to recover the additional cost is his only right in t hese
circumstances.
Subcontracting 26
26.1 If the Contractor subcontracts work , he is res ponsible for Pro viding the Works
Project Manager for acceptance. A reason for not accepting the Subcontractor
is that hi s a ppointment wi ll not a llow the Contractor to Provide the Works. The
l _
, CO
• 0
• they w ill not a llow the Contractor to Provide t he Works or
? c
? 5
) . • th ey do not inc lude a statement th at the pa rties to the subcontract shall
Other responsibilities 27
• 0
5 £ 27.2 The Contractor provides access to work b ein g done a nd to Plant and Materials
) 0
0 bein g stored for this contr act for
£
0
• the Project Manager,
" • the Supervisor and
27.3 The Contractor o beys an instruction wh ich is in a ccordance with this contract
3 Time
Key Dates 30.1 The Contractor does not start work on the Site until the first access date and
30.2 The Project Manager decides the date of Completion. The Project Manager
30.3 The Contractor does the work so that the Condition stated for each Key Date
The programme 31
31.1 If a programme is not identified in the Contract Data, the Contractor submits
a first programme to the Project Manager for acceptance within the period
31.2 The Contractor shows on each programme which he submits for acceptance
• the starting date, access dates, Key Dates and Completion Date,
Works Information, 0
• the dates when the Contractor plans to meet each Condition stated for
r 0
the Key Dates and to complete other work needed to allow the Employer 0
t
? o
and Others to do their work,
¢
'0 �
• provisions for
c c
g e
I Q 5
• float,
.
O 0
o
• access to a part of the Site if later than its access date. £
0
l • acceptances, 0
and
r • information from Others,
!
t
c c
i • for each operation, a statement of how the Contractor plans to do the
� -
U
work identifying the principal Equipment and other resources which he
S 5
plans to use and C
31.3 Within two weeks of the Contractor submitting a programme to him for
acceptance, the Project Manager either accepts the programme or notifies the
Contractor of his reasons for not accepting it. A reason for not accepting a
programme is that
• the actual progress achieved on each operation and its effect upon the
warning matters,
• how the Contractor plans to deal with any delays and to correct notified
Defects and
Accepted Programme.
acceptance
• within the period for reply after the Project Manager has instructed him
to,
• at no longer interval than the interval stated in the Contract Data from
<fl
the Site 33.1 The Employer allows access to and use of each part of the Site to the Contrac
% tor which is necessary for the work included in this contract. Access and use
::,
z c« is allowed on or before the later of its access date and the date for access
O c3 shown on the Accepted Programme.
-
- c
0
to start work 34.1 The Project Manager may instruct the Contractor to stop or not to start any
<fl
work and may later instruct him that he may re-start or start it.
-$
- J
E 6 Take over 35
J .-
0
35.1 The Employer need not take over the works before the Completion Date if it is
? c
2?6 stated in the Contract Data that he is not willing to do so. Otherwise the
D.
'a Employer takes over the works not later than two weeks after Completion.
0
35.2 The Employer may use any part of the works before Completion has been
<fl
certified. If he does so, he takes over the part of the works when he begins to
"
-
c
<J)
use it except if the use is
n £
5 Q • for a reason stated in the Works Information or
0
any part of the works and its extent within one week of the date.
Acceleration 36
36.1 The Project Manager may instruct the Contractor to submit a quotation for an
revised programme showing the earlier Completion Date and the changed Key
Dates. The Contractor submits details of his assessment with each quotation.
36.2 The Contractor submits a quotation or gives his reasons for not doing so
40.1 The subclauses in this clause only apply to tests and inspections required by
40.2 The Contractor and the Employer provide materials, facilities and samples for
40.3 The Contractor and the Supervisor each notifies the other of each of his
tests and inspections before it starts and afterwards notifies the other of its
results. The Contractor notifies the Supervisor in time for a test or inspection
to be arranged and done before doing work which would obstruct the test or
inspection. The Supervisor may watch any test done by the Contractor.
40.4 If a test or inspection shows that any work has a Defect. the Contractor
40.5 The Supervisor does his tests and inspections without causing unnecessary
40.6 The Project Manager assesses the cost incurred by the Employer in repeating
a test or inspection after a Defect is found. The Contractor pays the amount "'
(l)
? a
assessed.
cs
o
C o
Q ¢
Testing and inspection 41
8 5
before delivery 4 1. 1 The Contractor does not bring to the Working Areas those Plant and Materials
"' b.
which the Works Information states are to be tested or inspected before 0
delivery unti I the Supervisor has notified the Contractor that they have passed
•
c
Q
£
Searching for and 42
O 0
Until the defects date, the Supervisor may instruct the Contractor to search for € a
notifying Defects 42.1
E
a Defect. He gives his reason for the search with his instruction. Searching 0
0
may include
• providing facilities, materials and samples for tests and inspections done
• doing tests and inspections which the Works Information does not
require.
42.2 Until the defects date, the Supervisor notifies the Contractor of each Defect as
soon as he finds it and the Contractor notifies the Supervisor of each Defect
Correcting Defects 43
43.1 The Contractor corrects a Defect whether or not the Supervisor notifies him of
it.
43.2 The Contractor corrects a notified Defect before the end of the defect
Defects notified before Completion and when the Defect is notified for other
Defects.
""
43.3 The Supervisor issues the Defects Certificate at the later of the defects date
and the end of the last defect correction period. The Employer's rights in
respect of a Defect which the Supervisor has not found or notified are not
43.4 The Project Manager arranges for the Employer to allow the Contractor access
to and use of a part of the works which he has taken over if they are needed
for correcting a Defect. In this case the defect correction period begins when
Accepting Defects 44
44.1 The Contractor and the Project Manager may each propose to the other that
the Works Information should be changed so that a Defect does not have to
be corrected.
44.2 If the Contractor and the Project Manager are prepared to consider the
Completion Date or both to the Project Manager for acceptance. If the Project
Uncorrected Defects 45
<I)
0) 45.1 If the Contractor is given access in order to correct a notified Defect but he
0
::,
has not corrected it within its defect correction period, the Project Manager
z co
6 assesses the cost to the Employer of having the Defect corrected by other
- c people and the Contractor pays this amount. The Works Information is treated
0
0 before the defects date, the Project Manager assesses the cost to the Contrac
$ tor of correcting the Defect and the Contractor pays this amount. The Works
g %
Information is treated as having been changed to accept the Defect.
o
2 ¢
2
D .
" a
0
<I)
i
-
c
_
0
5 0
0
£
0
0
5 Payment
'
' Assessing the amount due 50
I
f 50.1 The Project Manager assesses the amount due at each assessment date. The
I procedures of the Parties and is not later than the assessment interval after
• at the end of each assessment interval until four weeks after the Supervisor
i 50.3 If no programme is identified in the Contract Data, one quarter of the Price
"'
$
%
l
for Work Done to Date is retained in assessments of the amount due until c c
I «
c
the Contractor has submitted a first programme to the Project Manager for
l E c
I acceptance showing the information which this contract requires. 0
�
50.4 In assessing the amount due, the Project Manager considers any application 0
for payment the Contractor has submitted on or before the assessment date.
The Project Manager gives the Contractor details of how the amount due has "'
e $
been assessed.
c £
50.5 The Project Manager corrects any wrongly assessed amount due in a later c c
g e
payment certificate.
85
z
C
Payment 51
51.1 The Project Manager certifies a payment within one week of each assessment
�
date. The first payment is the amount due. Other payments are the change in �
c
the amount due since the last payment certificate. A payment is made by the 4
£
Contractor to the Employer if the change reduces the amount due. Other O C
c
payments are made by the Employer to the Contractor. Payments are in the
£
currency of this contract unless otherwise stated in this contract. £
51.2 Each certified payment is made within three weeks of the assessment date or,
if a different period is stated in the Contract Data, within the period stated. If
Manager does not issue a certificate which he should issue, interest is paid
on the late payment. Interest is assessed from the date by which the late
payment should have been made until the date when the late payment is
made, and is included in the first assessment after the late payment is made.
or
interest on the correcting amount is paid. Interest is assessed from the date
when the incorrect amount was certified until the date when the correcting
correcting amount.
annually.
'
sneC3 sngineenng an constructon contact
Defined Cost 52
52.1 All the Contractor's costs which are not included in the Defined Cost are
treated as included in the Fee. Defined Cost includes only amounts calculated
using rates and percentages stated in the Contract Data and other amounts
0
0
a
::,
co
u
c
0
:g_
0
•
•
c
0
c
8
E
i core causes n1 € C 3
•
l
!
6 Compensation events
Compensation events 60
l
t 60.1 The following are compensation events.
design which is made either at his request or to comply with other Works
( 2 ) The Employer does not allow access to and use of a part of the Site by the
later of its access date and the date shown on the Accepted Programme.
(3) The Employer does not provide something which he is to provide by the
(4) The Project Manager gives an instruction to stop or not to start any work
• carry out work on the Site that is not stated in the Works Information.
c
previously communicated to the Contractor. c
a quotation for acceleration or for not correcting a Defect) for a reason not "
•
c
stated in this contract. + @
d £
¢ C
(10) The Supervisor instructs the Contractor to search for a Defect and no € £
£
Defect is found unless the search is needed only because the Contractor gave c
c
insufficient notice of doing work obstructing a required test or inspection.
have such a small chance of occurring that it would have been unreason
Only the difference between the physical conditions encountered and those
for which it would have been reasonable to have allowed is taken into account
• before the Completion Date for the whole of the works and
the value of which, by comparison with the weather data, is shown to occur on
15
www.neccontract.com • copyright nec 2005
>jeC3 engineenng and construction contract
Only the difference between the weather measurement and the weather which
the weather data show to occur on average less frequently than once in ten
( 15) The Project Manager certifies take over of a part of the works before
( 1 6 ) The Employer does not provide materials, facilities and samples for tests
( 18) A breach of contract by the Employer which is not one of the other
( 1 9 ) An event which
• stops the Contractor completing the works by the date shown on the
Accepted Programme,
and which
60.2 In judging the physical conditions for the purpose of assessing a compensa
<f)
!
.
2
6
o
c
•
•
the Site Information,
6
D. • information obtainable from a visual inspection of the Site and
U
60.3 If there is an ambiguity or inconsistency within the Site Information (including
"
-
c
a,
the information referred to in it), the Contractor is assumed to have taken into
E
Notifying compensation 61
8
events 6 1. 1 For compensation events which arise from the Project Manager or the Supervi
notifies the Contractor of the compensation event at the time of giving the
submit quotations, unless the event arises from a fault of the Contractor or
quotations have already been submitted. The Contractor puts the instruction
61.2 The Project Manager may instruct the Contractor to submit quotations for a
61.3 The Contractor notifies the Project Manager of an event which has happened
• the Project Manager has not notified the event to the Contractor.
If the Contractor does not notify a compensation event within eight weeks
the Completion Date or a Key Date unless the Project Manager should have
61.4 If the Project Manager decides that an event notified by the Contractor
he notifies the Contractor of his decision that the Prices, the Completion Date
If the Project Manager does not notify his decision to the Contractor within
either
the Contractor may notify the Project Manager to this effect. A failure by the
61.5 If the Project Manager decides that the Contractor did not give an early <I)
0
warning of the event which an experienced contractor could have given, he u
::,
notifies this decision to the Contractor when he instructs him to submit c c
quotations.
«
E e
0
6 1. 6 If the Project Manager decides that the effects of a compensation event are
%
too u n c e rt a i n to be forecast reasonably, he states assumptions about the 0
the event is based on these assumptions. If any of them is later found to have
Quotations for 62
compensation events 62.1 After discussing with the Contractor different ways of dealing with the com
pensation event which are practicable, the Project Manager may instruct the
<I)
Contractor to submit alternative quotations. The Contractor submits the
t •
c
required quotations to the Project Manager and may submit quotations for
t
other methods of dealing with the compensation event which he considers
~
O
£
0
0 C.
' practicable.
E
0
c
62.2 Quotations for compensation events comprise proposed changes to the Prices
and any delay to the Completion Date and Key Dates assessed by the
I
#
Contractor. The Contractor submits deta ils of his assessment with each
tion event , the Contractor includes the alterations to the Accepted Prog ramme
t in his quotation.
f
62.3 The Contractor submits quotations within three wee ks of being instructed to
do so by the Project Manager. The Project Manager replies within two weeks of
t
t the submission. His reply is
• an acceptance of a quotation ,
only after e x plaining his reasons for doing so to the Contractor. The Contractor
submits the revised quotation within three wee ks of being instructed to do so.
-
as neC 3 engineering and construction contract
I
if the Project Manager and the Contractor agree to the extension before the
submission or reply is due. The Project Manager notifies the extension that
62.6 If the Project Manager does not reply to a quotation within the time allowed,
the Contractor may notify the Project Manager to this effect. If the Contractor
submitted more than one quotation for the compensation event, he states in
Manager does not reply to the notification within two weeks. and unless the
Project Manager.
Assessing compensation 63
events 63.1 The changes to the Prices are assessed as the effect of the compensation
event upon
=>
• the resulting Fee.
• c
% The date when the Project Manager instructed or should have instructed the
E c
0 Contractor to submit quotations divides the work already done from the work
=
0
not yet done.
63.2 If the effect of a compensation event is to reduce the total Defined Cost, the
U
Ql
Prices are not reduced except as stated in this contract.
g
! % 63.3 A delay to the Completion Date is assessed as the length of time that, due to
.
z 0 the compensation event, planned Completion is later than planned Completion
3 ¢
as shown on the Accepted Programme. A delay to a Key Date is assessed as
9 the length of time that, due to the compensation event, the planned date
0
0
when the Condition stated for a Key Date will be met is later than the date
-
c
0
63.4 The rights of the Employer and the Contractor to changes to the Prices, the
7 £
Completion Date and the Key Dates are their only rights in respect of a
Q
0 compensation event.
£
0
0
63.5 If the Project Manager has notified the Contractor of his decision that the
for cost and time for matters which have a significant chance of occurring and
63.7 Assessments are based upon the assumptions that the Contractor reacts
competently and promptly to the compensation event, that any Defined Cost
and time due to the event are reasonably incurred and that the Accepted
the Completion Date and the Key Dates were for the interpretation most
favourable to the Party which did not provide the Works Information.
63.9 If a change to the Works Information makes the description of the Condition
for a Key Date incorrect, the Project Manager corrects the description. This
correction is taken into account in assessing the compensation event for the
• if the Contractor has not submitted a quotation and details of his assess
I • if the Project Manager decides that the Contractor has not assessed the
• if, when the Contractor submits quotations for a compensation event. the
Project Manager has not accepted the Contractor's latest programme for
64.2 The Project Manager assesses a compensation event using his own assess
64.3 The Project Manager notifies the Contractor of his assessment of a compen
0
sation event and gives him details of it within the period allowed for the
%
Contractor's submission of his quotation for the same event. This period
starts when the need for the Project Manager's assessment becomes
c c
%
apparent. E c
0
64.4 If the Project Manager does not assess a compensation event within the time :g
0
allowed, the Contractor may notify the Project Manager to this effect. If the
Contractor submitted more than one quotation for the compensation event,
0
<lJ
he states in his notification which quotation he proposes is to be accepted. If
? o
the Project Manager does not reply within two weeks of this notification the
cd
s £
notification is treated as acceptance of the Contractor's quotation by the c €
9 c
Project Manager.
85
I %
0
I Implementing 65
O 0
• the Project Manager notifies the Contractor of his own assessment or u Cl.
E
• a Contractor's quotation is treated as having been accepted by the
0
C
Project Manager.
t
£
(
c
7 Title
Plant and Materials 70.1 Whatever title the Contractor has to Plant and Materials which is outside the
Working Areas passes to the Employer if the Supervisor has marked it as for
this contract.
70.2 Whatever title the Contractor has to Plant and Materials passes to the
Employer if it has been brought within the Working Areas. The title to Plant
and Materials passes back to the Contractor if it is removed from the Working
Marking Equipment, 71
Plant and Materials 7 1. 1 The Supervisor marks Equipment, Plant and Materials which are outside the
• the Contractor has prepared them for marking as the Works Information
requires.
$
:,
Removing Equipment 72
c
c 72.1 The Contractor removes Equipment from the Site when it is no longer needed
c
unless the Project Manager allows it to be left in the works.
0
8
0
Objects and materials 73
within the Site 73.1 The Contractor has no title to an object of value or of historical or other
0
q interest within the Site. The Contractor notifies the Project Manager when such
?
an object is found and the Project Manager instructs the Contractor how to
0
¢ £ deal with it. The Contractor does not move the object without instructions.
c o
9 c
4 6
.
73.2 The Contractor has title to materials from excavation and demolition only as
<I) a. stated in the Works Information.
0
2
� Q)
•
O 0
0
t
co co
�
c
-
(L
Employer's risks 80
• use or occupation of the Site by the works or for the purpose of the
�
• Loss of or wear or damage to the parts of the works taken over by the 0
Employer, except loss, wear or damage occurring before the issue of the
U
D efects Certificate which is due to <l)
c oo
• a D efect which existed at take over, c5
£
c co
• an event occurring before take over which was not itself an Employer's
Q e
risk or 85
• the activities of the Contractor on the Site after take over.
<Jl E.
0
• L oss of or wear or damage to the works and any Eq uipment , Plant and
O 0
• A dditional Employer's risks stated in the Contract D ata. 0
E
0
0
The Contractor's risks 81
8 1. 1 Fro m the starting date until the D efects Certificate has been issued, the risks
which are not carried by the Employer are carried by the Contractor.
�
Repairs 82 "
d c
� •
ro
82.1 U ntil the D efects Certificate has been issued and unless otherwise instructed 55
by the Project Manager, the Contractor promptly replaces loss of and repairs
"
damage to the works, Plant and Materials.
$
l
i Indemnity 83
I
and costs due to an event which is at his risk.
I
83.2 The liability of each Party to indemni fy the other is reduced if events at the
costs. The reduction is in proportion to the extent that events wh i ch were at the
I
other Party's risk contributed, taking into account each Party's responsibi l ities
I
1
l
Insurance cover 84
I
The Contractor provides the insurances stated in the Insurance Table except l
84.1
any insurance which the Employer is to provide as stated in the Contract Data. '
84.2 The insurances are in the joint names of the Parties and provide cover for
events which are at the Contractor's risk from the starting date until the
INSURANCE TABLE
Loss of or damage to the works, Plant The replacement cost, including the
Employer
c c property (except the works, Plant and Data for any one event with cross
s Materials and Equipment) and liability so that the insurance
E ce
0 liability for bodily injury to or death of applies to the Parties separately
z
a. a person (not an employee of the
0
Contractor) caused by activity in
Liability for death of or bodily injury to The greater of the amount required i
C
Q
•
0
e
employees of the Contractor arising by the applicable law and the
out of and in the course of their amount stated in the Contract Data l
8.5
a employment in connection with this for any one event
0
contract l
l
,,,
I
•
c Insurance policies 85
• Q
£
I
85.1 Before the starting date and on each renewal of the insurance policy until the t
~
€
Q
0
defects date, the Contractor submits to the Project Manager for acceptance
!
l
E
0 certificates which state that the insurance required by this contract is in force. I
u
The certificates are signed by the Contractor's insurer or insurance broker. A
!
reason for not accepting the certificates is that they do not comply with this l
!
contract.
l
t,
85.2 Insurance policies include a waiver by the insurers of their subrogation rights j
c c
�
+ -
(C against directors and other employees of every insured except where there s
i
S 5 l
c
fr aud.
85.3 The Parties comply with the terms and conditions of the insurance policies.
85.4 Any amount not recovered from an insurer is borne by the Employer for events
w hich are at his risk and by the Contractor for events w hich are at his risk.
If the Contractor 86
does not insure 86.1 The Employer may insure a risk which this contract requires the Contractor to
insure if the Contractor does not submit a required certificate. The cost of this
87 .1 The Project Manager submits policies and certificates for insurances provided
by the Employer to the Contractor for acceptance before the starting date and
the Employer does not change the responsibility of the Employer to provide
87.3 The Contractor may insure a risk which this contract requires the Employer to
insure if the Employer does not submit a required policy or certificate. The
"'
%
2
c c
6
E c
0
I
0
0
-"'
c
- Q)
£
O 0
0
9 Termination
I
Termination 90
90.1 If either Party wishes to terminate the Contractor's obligation to Provide the
Works he notifies the Project Manager and the other Party giving details of his
90.2 The Contractor may terminate only for a reason identified in the Termination
Table. The Employer may terminate for any reason. The procedures followed and
the amounts due on termination are in accordance with the Termination Table.
TERMINATION TABLE
than R1--R21
<J)
R
0
The Contractor R1-R10, R16 or P1 and P4 A1, A2 and A4
R19
<J)
«
s
c c
g c
9 5 90.3 The procedures for termination are implemented immediately after the Project
.
o Manager has issued a termination certificate,
0
90.4 Within thirteen weeks of termination, the Project Manager certifies a final
9 1. 1 Either Party may terminate if the other Party has done one of the following or
its equivalent.
or reconstruct) ( R 7 ) ,
assets ( R9) or
91.2 The Employer may terminate if the Project Manager has notified that the
Contractor has defaulted in one of the following ways and not put the default
91.3 The Employer may terminate if the Project Manager has notified that the
Contractor has defaulted in one of the following ways and not stopped
91.4 The Contractor may terminate if the Employer has not paid an amount certified
by the Project Manager within thirteen weeks of the date of the certificate
(R16).
91.5 Either Party may terminate if the Parties have been released under the law
91.6 If the Project Manager has instructed the Contractor to stop or not to start any
substantial work or all work and an instruction allowing the work to re-start or
• the Employer may terminate if the instruction was due to a default by the
Contractor ( R 1 8 ) .
• either Party may terminate if the instruction was due to any other reason
lf
(R2O). a
e
0
91.7 The Employer may terminate if an event occurs which S
c €
g e
• stops the Contractor completing the works or Q 7
0.
• stops the Contractor completing the works by the date shown on the
z
c
Accepted Programme and is forecast to delay Completion by more than
13 weeks,
�
"
and which c
@
Procedures on termination 92
92.1 On termination, the Employer may complete the works and may use any Plant
92.2 The procedure on termination also includes one or more of the following as
P2 The Employer may instruct the Contractor to leave the Site, remove any
Equipment. Plant and Materials from the Site and assign the benefit of
to the Employer.
P3 The Employer may use any Equipment to which the Contractor has title to
from Site when the Project Manager notifies him that the Employer no
Payment on termination 93
• to which the Employer has title and of which the Contractor has to
accept delivery,
93.2 The amount due on termination also includes one or more of the following as
• for Options A, B, C and D, any excess of the total of the Prices at the
"'
0
2
c
@
' 0
0
terms 11.2 (20) The Activity Schedule is the activity schedule unless later changed in
(22) Defined Cost is the cost of the components in the Shorter Schedule of
( 2 7 ) The Price for Work Done to Date is the total of the Prices for
A completed activity is one which is without Defects which would either delay
(30) The Prices are the lump sum prices for each of the activities on the
The programme 31 0
31.4 The Contractor provides information which shows how each activity on the e8
Activity Schedule relates to the operations on each programme which he co £
c
submits for acceptance.
0 c::
Acceleration 36 #?
r
0
36.3 When the Project Manager accepts a quotation for an acceleration, he
changes the Prices, the Completion Date and the Key Dates accordingly and
i 54.1 Information in the Activity Schedule is not Works Information or Site Information.
E
! 8
54.2 If the Contractor changes a planned method of working at his discretion so
that the activities on the Activity Schedule do not relate to the operations on
I £
54.3 A reason for not accepting a revision of the Activity Schedule is that (
c
or
J Assessing compensation 63
events 63.10 If the effect of a compensation event is to reduce the total Defined Cost and
I
' the event is
' 63.12 Assessments for changed Prices for compensation events are in the form of
I
!
63.14 If the Project Manager and the Contractor agree, rates and lump sums may be
Implementing 65
compensation events 65.4 The changes to the Prices, the Completion Date and the Key Dates are
Payment on termination 93
28
co £
d
c o
0 C:
g 5
0 .--
a
0
2
c
- Q)
€
~ a
Q
£
0
C
terms 11.2 (21) The Bill of Quantities is the bill of quantities as changed in accordance
(22) Defined Cost is the cost of the components in the Shorter Schedule of
• the quantity of the work which the Contractor has completed for each
(31) The Prices are the lump sums and the amounts obtained by multiplying
the rates by the quantities for the items in the Bili of Quantities.
Acceleration 36
changes the Prices, the Completion Date and the Key Dates accordingly and
I
accepts the revised programme. 0
e8
I The Bill of Quantities 55
c
d
55 .1 Information in the Bill of Quantities is not Works Information or Site Information. c o
g c
g2 7
I. .
Compensation events 60 ,,, E.
0
i 60.4 A difference between the final total quantity of work done and the quantity
i!l
• the difference does not result from a change to the Works Information, c
• the difference causes the Defined Cost per unit of quantity to change • £
O 0
and
" C.
• the rate in the Bili of Quantities for the item multiplied by the final total E
I 0
c
quantity of work done is more than 0.5% of the total of the Prices at the
f
L Contract Date.
If the Defined Cost per unit of quantity is reduced, the affected rate is
i
reduced.
60.5 A difference between the final total quantity of work done and the quantity for
t an item stated in the Bili of Quantities which delays Completion or the meet
I
ing of the Condition stated for a Key Date is a compensation event.
60.6 The Project Manager corrects mistakes in the Bili of Quantities which are
I
departures from the rules for item descriptions and for division of the work
1
neC 3 cngneenng and construction contract
Assessing compensation 63
events 63.10 If the effect of a compensation event is to reduce the total Defined Cost and
the event is
63.13 Assessments for changed Prices for compensation events are in the form of
• For the whole or a part of a compensation event for work not yet done
and for which there is an item in the Bill of Quantities, the changes are
• a changed rate,
• a changed quantity or
• For the whole or a part of a compensation event for work not yet done
and for which there is no item in the Bill of Quantities, the change is a
new priced item which, unless the Project Manager and the Contractor
ment.
• For the whole or a part of a compensation event for work already done,
I
the change is a new lump sum item.
If the Project Manager and the Contractor agree, rates and lump sums may be
I
used to assess a compensation event instead of Defined Cost. !
u Implementing 65
compensation events 65.4 The changes to the Prices, the Completion Date and the Key Dates are
e8
¢ _
a
0
£
� <l)
£
O 0
0
1 l
terms 11.2 (20) The Activity Schedule is the activity schedule unless later changed in
l accordance with this contract.
( 2 3 ) Defined Cost is
• retention,
and
work
0
and the cost of •
c
4. Q
9 g
• correcting Defects caused by the Contractor not complying with a
° z
constraint on how he is to Provide the Works stated in the Works
8
Information,
I
• Plant and Materials not used to Provide the Works (after allowing for
Information,
t
c c
• resources
availability
not used to Provide the Works ( after allowing for reasonable
tribunal.
{ (29) The Price for Work Done to Date is the total Defined Cost which the
;'· Project Manager forecasts will have been paid by the Contractor before the
h (30 ) The Prices are the lump sum prices for each of the activities on the
the
i· Providing Works ��.3 The contractor advises the Project Manager on the practical implications of
r_·----
[
20.4 The Contractor prepares forecasts of the total Defined Cost for the whole of
the works in consultation with the Project Manager and submits them to
the Project Manager. Forecasts are prepared at the intervals stated in the
Contract Data from the starting date until Completion of the whole of the
Subcontracting 26
26.4 The Contractor submits the proposed contract data for each subcontract for
A reason for not accepting the proposed contract data is that its use will not
The programme 31
31.4 The Contractor provides information which shows how each activity on the
Acceleration 36
changes the Prices, the Completion Date and the Key Dates accordingly and
40.7 When the Project Manager assesses the cost incurred by the Employer in
made to him in the same currency. Such payments are converted to the
2 currency of this contract in order to calculate the Fee and any Contractor's
_
c
9
share using the exchange rates.
O 0
0
Defined Cost 52
E
0 52.2 The Contractor keeps these records
0
Subcontractors and
52.3 The Contractor allows the Project Manager to inspect at any time within
53.1 The Project Manager assesses the Contractor's share of the difference
between the total of the Prices and the Price for Work Done to Date. The differ
ence is divided into increments falling within each of the share ranges. The
limits of a share range are the Price for Work Done to Date divided by the
the sum of the products of the increment within each share range and the
53.2 If the Price for Work Done to Date is less than the total of the Prices, the
Contractor is paid his share of the saving. If the Price for Work Done to Date is
greater than the total of the Prices, the Contractor pays his share of the
excess.
share at Completion of the whole of the works using his forecasts of the final
Price for Work Done to Date and the final total of the Prices. This share is
included in the amount due following Completion of the whole of the works.
53.4 The Project Manager makes a final assessment of the Contractor's share
using the final Price for Work Done to Date and the final total of the Prices.
54.1 Information in the Activity Schedule is not Works Information or Site Information.
that the activities on the Activity Schedule do not relate to the operations on
54.3 A reason for not accepting a revision of the Activity Schedule is that
• any changed Prices are not reasonably distributed between the activities
or
Assessing compensation 63
events 63.11 If the effect of a compensation event is to reduce the total Defined Cost and
the event is
85
(
63.12 Assessments for changed Prices for compensation events are in the form of 0
0
changes to the Activity Schedule.
63.15 If the Project Manager and the Contractor agree, the Contractor assesses a
0 0
of Cost Components. a
E
0
0
Implementing 65
compensation events 65.4 The changes to the Prices, the Completion Date and the Key Dates are
Payment on termination 93
93.4 If there is a termination, the Project Manager assesses the Contractor's share
after he has certified termination. His assessment uses, as the Price for Work
Done to Date, the total of the Defined Cost which the Contractor has paid and
which he is committed to pay for work done before termination. The assess
• the lump sum price for each activity which has been completed and
• a proportion of the lump sum price for each incomplete activity which is
l.
the proportion of the work in the activity which has been completed.
f 93.6 The Project Manager's assessment of the Contractor's share is added to the
!
t
!
:
1
l
r
www.neccontract.com c copyright nec 2005 33
>neC 3 engineenng an construction contract
terms 11.2 (21) The Bill of Quantities is the bill of quantities as changed in accordance
• retention,
and
work
(25) Dis allowed Cost is cost which the Project Manager decides
Information or
,,,
and the cost of
z
0
n £ • correctin g Defects after Completion ,
5 0
5 0 • correcting Defects caused by the Contractor not compl ying with a con
£
straint on ho w he is to Provide the Works stated in the Works Information,
8
• Plant and Materials not used to Provide the Works (a fter a llowing for
reasonable wastage) unle ss resul ting from a change to the Works Infor
mation ,
a vailability and u tilisation) or not taken away f rom the Working Areas
tribunal.
t
(29) The Price for Work Done to Date is the total De fined Cost which th e
Project Manager for ecasts w ill have been paid by the Contractor before the xt
ne
f
( 3 1 ) The Prices are the lump sums and the amount s obtaine d by multiplyin g
• the quantity of the work which the Contractor has com pleted for eac h
• a propo rtion of each l ump sum which is the p roportion of the wor k
20.3 The Contractor advises the Project Manager on the practical implications of
20.4 The Contractor prepares forecasts of the total Defined Cost for the whole of
the works in consultation with the Project Manager and submits them to the
Contract Data from the starting date until Completion of the whole of the
Subcontracting 26
26.4 The Contractor submits the proposed contract data for each subcontract for
A reason for not accepting the proposed contract data is that its use will not
Acceleration 36
changes the Prices, the Completion Date and the Key Dates accordingly and
40.7 When the Project Manager assesses the cost incurred by the Employer in
does not include the Contractor's cost of carrying out the repeat test or
inspection.
"'
I
e8
c _2
50.6 Payments of Defined Cost made by the Contractor in a currency other than the
85
currency of this contract are included in the amount due as payments to be "' o'.
0
made to him in the same currency. Such payments are converted to the
currency of this contract in order to calculate the Fee and any Contractor's
%.
Defined Cost 52 O
•
0
0
Subcontractors and
52.3 The Contractor allows the Project Manager to inspect at any time within
53.5 The Project Manager assesses the Contractor's share of the difference
between the Total of the Prices and the Price for Work Done to Date. The
difference is divided into increments falling within each of the share ranges.
The limits of a share range are the Price for Work Done to Date divided by the
the sum of the products of the increment within each share range and the
53.6 If the Price for Work Done to Date is less than the Total of the Prices, the
Contractor is paid his share of the saving. If the Price for Work Done to Date is
greater than the Total of the Prices, the Contractor pays his share of the
excess.
I
,
,
• www.neccontract.com
w copyright nec 2005 35
l
>neC 3 engineering and construction contract
share at Completion of the whole of the works using his forecasts of the final
Price for Work Done to Date and the final Total of the Prices. This share is
included in the amount due following Completion of the whole of the works.
53.8 The Project Manager makes a final assessment of the Contractor's share
using the final Price for Work Done to Date and the final Total of the Prices.
55.1 Information in the Bill of Quantities is not Works Information or Site Informa
tion.
Compensation events 60
60.4 A difference between the final total quantity of work done and the quantity
• the difference does not result from a change to the Works Information,
• the difference causes the Defined Cost per unit of quantity to change
and
• the rate in the Bill of Quantities for the item multiplied by the final total
quantity of work done is more than 0.5% of the total of the Prices at the
Contract Date.
If the Defined Cost per unit of quantity is reduced, the affected rate is
reduced.
60.5 A difference between the final total quantity of work done and the quantity for
an item stated in the Bill of Quantities which delays Completion or the meet
60.6 The Project Manager corrects mistakes in the Bill of Quantities which are
departures from the rules for item descriptions and for division of the work
<J) inconsistency between the Bill of Quantities and another document, the
•
c Contractor is assumed to have taken the Bill of Quantities as correct.
� "
£
O 0
0 Assessing compensation 63
£
events 63.11 If the effect of a compensation event is ta reduce the total Defined Cost and
8
the event is
63.13 Assessments for changed Prices for compensation events are in the form of
• For the whole or a part of a compensation event for work not yet done
and for which there is an item in the Bill of Quantities, the changes are
• achanged rate,
• achanged quantity or
• For the whole or a part of a compensation event for work not yet done and
for which there is no item in the Bill of Quantities, the change is a new
priced item which, unless the Project Manager and the Contractor agree
• For the whole or a part of a compensation event for work already done,
If the Project Manager and the Contractor agree, rates and lump sums may be
63.15 If the Project Manager and the Contractor agree, the Contractor assesses a
Project Manager may make his own assessments using the Shorter Schedule
of Cost Components.
Implementing 65
compensation events 65.4 The changes to the Prices, the Completion Date and the Key Dates are
Payment on termination 93
93.5 If there is a termination, the Project Manager assesses the Contractor's share
after he has certified termination. His assessment uses, as the Price for Work
Done to Date, the total of the Defined Cost which the Contractor has paid and
93.6 The Project Manager's assessment of the Contractor's share is added to the
I
t
I
l
! _
"'
e8
I
d
c c
g c
I £ 5
l 5
0
1
4
'
2
~., (
£
~
u Q
0.
'
l
i
l
I
l
l
I
;
1- neccontract.com
www.
c copyright nec 2005 37
I
!
i
neC 3 engneenng and construction contract
• retention,
and
work
Information or
• Plant and Materials not used to Pro vide the Works (after allowing for
mation,
• resources not used to Provide the Works (after allowing for reasonable
availabi lity and ut ilisation) or not taken awa y from the Workin g Areas
tribunal.
( 2 9) The Price for Work Done to Date is the total Defined Cost which the
Project Manager forecasts will have been paid by the Contractor before the
20.3 The Contractor advises the Project Manager on the practical implications of
20.4 The Contractor prepares forecasts of the total Defined Cost for the whole of
the works in consultation with the Project Manager and submits them to the
Contract Data from the starting date until Completion of the whole of the
Subcontracting 26
26.4 The Contractor submits the proposed contract data for each subcontract for
A reason for not accepting the proposed contract data is that its use will not
Acceleration 36
changes the Completion Date, the Key Dates and the forecast of the total
Defined Cost of the whole of the works accordingly and accepts the revised
programme.
0
o
=
repeating a test or inspection after a Defect is found, the Project Manager
I z
does not include the Contractor's cost of carrying out the repeat test or
I
in spection.
l
Assessing the amount due 50
50.7 Payments of De fined Cost made by the Contractor in a currency other than the
made to h m i in the same cu rrency. Such pa yments are con verted to the
currency of this contract in order to calculate the Fee using the exchange
rates.
f
<fl
Defined Cost 52 .,
52.2 The Contractor kee ps these records
?
I I
'O .!!!
l c c
• accounts of pa yments o f De fined Cost,
@ c
• proof that the payments ha ve been made , g 5
0 •
• other ecords
r as stated in the Works Information.
I
,, 0
i
52.3 The Contractor allows the Project Manager to inspect at an y i
t me within
~.
-
c
!
f
6 Q
a
E
l Assessing compensation 63
8
events 63.15 If the Project Manager and the Contractor a gree, the Contractor assesses a
t compensa tion event using the Shorter Schedule of Cost Components . The
t Project Manager may make his own assessments using the Shorter Schedule
•·
of Cost Components .
Implementing 65
compensation events 65.3 The chan ges to the forecast amount of the Prices , the Completion Date and
event.
I,
I
,.
t
neC 3 engineering and construction contract
• retention,
• payments to Others,
) "'
Q)
• the supply of equipment, supplies and services included in the charge
. u
) ::,
¢
for overhead cost within the Working Areas in this contract
z;
and
%
( • follow an acceptance or procurement procedure stated in the Works
? 6
Information or
J
:
c
• give an early warning which this contract required him to give or
? c
3 5
• is a payment to a Subcontractor for
' %
0
• work which the Contract Data states that the Contractor will do himself
or
€ (29 ) The Price for Work Done to Date is the total Defined Cost which the
) 0
0 Project Manager forecasts will have been paid by the Contractor before the
E
0 next assessment date plus the Fee.
0
20.2 The Contractor manages the Contractor's design, the provision of Site services
c
-
d
0
and the construction and installation of the works. The Contractor subcon
tracts the Contractor's design, the provision of Site services and the
construction and installation of the works except work which the Contract
20.3 The Contractor advises the Project Manager on the practical implications of
20.4 The Contractor prepares forecasts of the total Defined Cost for the whole of
the works in consultation with the Project Manager and submits them to the
Contract Data from the starting date until Completion of the whole of the
event, the Project Manager and the Contractor agree the change to the price
for the work and any change to the Completion Date and Key Dates. If they
Subcontracting 26
26.4 The Contractor submits the proposed contract data for each subcontract for
A reason for not accepting the proposed contract data is that its use will not
Acceleration 36
changes the Completion Date, the Key Dates and the forecast of the total
Defined Cost of the whole of the works accordingly and accepts the revised
programme.
50.7 Payments of Defined Cost made by the Contractor in a currency other than the
made to him in the same currency. Such payments are converted to the
currency of this contract in order to calculate the Fee using the exchange «
rates.
Defined Cost 52
Subcontractors and
52.3 The Contractor allows the Project Manager to inspect at any time within
E
compensation events 65.3 The changes to the forecast amount of the Prices, the Completion Date and
0
0
the Key Dates are included in the notification implementing a compensation
event.
i
DISPUTE RESOLUTION
Option W1
Dispute resolution procedure (used unless the United Kingdom Housing Grants, Construction and Regeneration Act
1996 applies).
Dispute resolution W1
W1.1 A dispute arising under or in connection with this contract is referred to and
The Adjudicator W1.2 ( 1 ) The Parties appoint the Adjudicator under the NEC Adjudicator's Contract
(2) The Adjudicator acts impartially and decides the dispute as an indepen
resigns or is unable to act, the Parties choose a new adjudicator jointly. If the
Parties have not chosen an adjudicator, either Party may ask the Adjudicator
adjudicator within four days of the request. The chosen adjudicator becomes
the Adjudicator.
his predecessor but not decided at the time when the predecessor resigned or
(5) The Adjudicator, his employees and agents are not liable to the Parties
for any action or failure to take action in an adjudication unless the action or
8 The adjudication W1.3 (1) Disputes are notified and referred to the Adjudicator in accordance with
E the Adjudication Table.
C
0
ADJUDICATION TABLE
Adjudicator?
The Project Manager The Contractor Between two and four weeks
e
accepted the notification itself being
Any other matter Either Party Between two and four weeks
Project Manager if the Contractor and the Project Manager agree to the exten
sion before the notice or referral is due. The Project Manager notifies the
extension that has been agreed to the Contractor. If a disputed matter is not
•
C
notified and referred within the times set out in this contract, neither Party may c c
� �
subsequently refer it to the Adjudicator or the tribunal. (t
c c
(3) The Party referring the dispute to the Adjudicator includes with his referral
8
referral. This period may be extended if the Adjudicator and the Parties agree.
and if the subcontract allows, the Contractor may refer the subcontract dis
pute to the Adjudicator at the same time as the main contract referral. The
Adjudicator then decides the disputes together and references to the Parties
for the purposes of the dispute are interpreted as including the Subcontractor.
uonoe Kue aster pue Moor pue 40epnlpy au J0 uoysypap Aue 10p\$u03al 0)
10e0/pn/p¥ au) uou q aep au Jo syaa no] uuM ua3 s uoneoyp)ou s1u
0
0
ssoun peunqun au o andsyp e 1aja )0u Keu Ke Y Jeunqun au o andsip
:::, "
)oe/)u00 su} uM eouepioooe "
2
up roe/pn[p¥ au} 0) pa1Jo1 uaq s/y seu 1y ssojun peunqu au) 01 )001000 U
sIu) u)IM uooauuoo u 1o 10pun a)ndsip Aue a]04 )0u sop Ae Y () t'IM 1eunq au) Kq MaAaH
;
'
' soup au) uuIM Jou)o au poupou seu e euyou Jy Bupuq pue peuy st
[nun pue ssojun saned ·au) uo Buipuq st uorsroop soepnfpy ·uL (OT)
'uoyspop stu Jo sope eu) peupou seu roeopnfpy au [pun pue ssoun (6)
pue au) 0 sHaaM 1n0] uu)IM suosea» siu pue uoysyap sIu Jo J08euey 200f04a
au pue saned au saynou pue andsip au) soproop 40epn[py au1 (8)
'andsip
Io 08euey 100[04 au) Jo0 uopoeu Jo uop)oe Aue 0s1A0 pue MO[al •
Option W2
Dispute resolution procedure (used in the United Kingdom when the Housing Grants, Construction and Regeneration
Dispute resolution W2
and decided by the Adjudicator. A Party may refer a dispute to the Adjudicator
at any time.
(2) In this Option, time periods stated in days exclude Christmas Day, Good
The Adjudicator W2.2 ( 1 ) The Parties appoint the Adjudicator under the NEC Adjudicator's Contract
(3) If the Adjudicator is not identified in the Contract Data or if the Adjudicator
his predecessor but not decided at the time when his predecessor resigned or
( 5 ) The Adjudicator, his employees and agents are not liable to the Parties for
the Adjudicator when it is issued. Within three days of the receipt of the notice
If the Adjudicator does not so notify within three days of the issue of the
provided within fourteen days of the referral. This period may be extended if
contract, the Contractor may, with the consent of the Subcontractor, refer the
subcontract dispute to the Adjudicator at the same time as the main contract
referral. The Adjudicator then decides the disputes together and references to
the Parties for the purposes of the dispute are interpreted as including the
Subcontractor.
Supervisor related to the dispute and alter a quotation which has been
• take the initiative in ascertaining the facts and the law related to the
dispute,
(5) If a Party does not comply with any instruction within the time stated by
the Adjudicator, the Adjudicator may continue the adjudication and make his
delay caused to the Contractor, he makes his assessment n the same way as
i
(8) The Adjudicator decides the dispute and notifies the Parties and the
3
� <JI
Project Manager of his decision and his reasons within twenty-eight days of
3 6
the dispute being referred to him. This period may be extended by up to four
0
teen days with the consent of the referring Party or by any other period agreed
3s by the P arties.
" a
0
( 9) Unless and until the Adjudicator has notified the Parties of his decision,
the Parties, the Project Manager and the Supervisor proceed as if the matter
<JI
disputed was not disputed.
z
0
£ (10) I f the Adjudicator does not make his decision and notify it to the Parties
5 Q
j 0 within the time provided by this contract, the Parties and the Adjudicator may
£ agree to extend the period for making his decision. If they do not agree to an
8 extension, either Party may act as if the Adjudicator has resigned.
between the P arties and not as an arbitral award. The Adjudicator's decision
is final and binding if neither Party has notified the other within the times
( 1 2 ) The Adjudicator may, within fourteen days of giving his decision to the
Review by the tribunal W2.4 (1) A Party does not refer any dispute under or in connection with this
contract to the tribunal unless it has first been decided by the Adjudicator in
(2) If, after the Adjudicator notifies his decision a Party is dissatisfied, that
Party may notify the other Party of the matter which he disputes and state
the tribunal unless this notification is given within four weeks of the notifica
to reconsider any decision of the Adjudicator and to review and revise any
( 4) If the tribunal is arbitration, the arbitration procedure, the place where the
arbitration is to be held and the method of choosing the arbitrator are those
e
o
o ]
4
"
e?
0
d !
c c
9
g z
.
;
C
"
•
-
'
a
S
0 '
€
£
£
Option Xi: Price adjustment for inflation (used only with Options A, B, C and D)
Defined terms X1
Xl.1 ( a ) The Base Date Index ( B ) is the latest available index before the base date.
(b) The Latest Index (L) is the latest available index before the date of
(c) The Price Adjustment Factor is the total of the products of each of the
proportions stated in the Contract Data multiplied by (L - B)/B for the index
linked to it.
Price Adjustment Factor X1.2 If an index is changed after it has been used in calculating a Price Adjustment
a The Price Adjustment Factor calculated at the Completion Date for the whole
-
- c
0 of the works is used for calculating price adjustment after this date.
3 Compensation events Xl.3 The Defined Cost for compensation events is assessed using the
• Defined Cost at base date levels for amounts calculated from rates
Price adjustment Options Xl.4 Each amount due includes an amount for price adjustment which is the sum
A and B of
2
c
, Q) • the change in the Price for Work Done to Date since the last assessment
n £
5 g of the amount due multiplied by the Price Adjustment Factor for the date
0
and
Price adjustment Options Xl.5 Each time the amount due is assessed, an amount for price adjustment is
• the change in the Price for Work Done to Date since the last assessment
of the amount due multiplied by (PAF/(1 +PAF)) where PAF is the Price
X2.1 A change in the law of the country in which the Site is located is a compensa
tion event if it occurs after the Contract Date. The Project Manager may notify
the Contractor of a compensation event for a change in the law and instruct
change in the law is to reduce the total Defined Cost, the Prices are reduced.
.
(1) (1)
o z
0 c
Multiple currencies X3 13
X3.1 The Contractor is paid in currencies other than the currency of this contract for
the items or activities listed in the Contract Data. The exchange rates are
$
X3.2 Payments to the Contractor in currencies other than the currency of this 2
c «
contract do not exceed the maximum amounts stated in the Contract Data. « c
Any excess is paid in the currency of this contract. E c
. 0
%
0
j
Option X4: Parent company guarantee
Parent company X4
guarantee X4.1 If a parent company owns the Contractor, the Contractor gives to the Employer
form set out in the Works Information. If the guarantee was not given by the -
c
Contract Date, it is given to the Employer within four weeks of the Contract • £
O 0
Date. o
E
I 8
I
t
,
%
Sectional Completion XS
X5.1 In these conditions of contract, unless stated as the whole of the works, each
l reference and clause relevant to
I
• the works,
• Completion and
• Completion Date
applies, as the case may be, to either the whole of the works or any section of
the works.
X6.1 The Contractor is paid a bonus calculated at the rate stated in the Contract
• Completion and
Delay damages X7
X7.1 The Contractor pays delay damages at the rate stated in the Contract Data
from the Completion Date for each day until the earlier of
• Completion and
X7 .2 If the Completion Date is changed to a later date after delay damages have
been paid, the Employer repays the overpayment of damages with interest.
Interest is assessed from the date of payment to the date of repayment and
X7 .3 If the Employer takes over a part of the works before Completion, the delay
damages are reduced from the date on which the part is taken over. The
Project Manager assesses the benefit to the Employer of taking over the part
of the works as a proportion of the benefit to the Employer of taking over the
whole of the works not previously taken over. The delay damages are reduced
in this proportion.
£
� <I)
~ c
Q
E
0
C
Option X12: Partnering
terms X12.1 ( 1 ) The Partners are those named in the Schedule of Partners. The Client is a
Partner.
Option.
(3) The Core Group comprises the Partners listed in the Schedule of Core
Group Members.
work together and is either in the documents which the Contract Data states
Actions X12.2 ( 1) Each Partner works with the other Partners to achieve the Client's objective
stated in the Contract Data and the objectives of every other Partner stated in
other Partners.
( 3) The Core Group acts and takes decisions on behalf of the Partners on
( 4) The Partners select the members of the Core Group. The Core Group
decides how they will work and decides the dates when each member joins
and leaves the Core Group. The Client's representative leads the Core Group
( 5) The Core Group keeps the Schedule of Core Group Members and the
•
o z
(6) This Option does not create a legal partnership between Partners who are
0 c
not one of the Parties in this contract. 0
Working together X12.3 ( 1 ) The Partners work together as stated in the Partnering Information and in
8
( 2 ) A Partner may ask another Partner to provide information which he needs • _ ::,
to carry out the work in his Own Contract and the other Partner provides it. [ [
.
·.. ·.-, .
. - E c:
(3) Each Partner gives an early warning to the other Partners when he ] £
becomes aware of any matter that could affect the achievement of another '
( 4) The Partners use common information systems as set out in the Partner
ing Information.
(6) The Core Group may give an instruction to the Partners to change the
-"'
c
( 7) The Core Group prepares and maintains a timetable showing the proposed
~ g
£
timing of the contributions of the Partners. The Core Group issues a copy of 0 0
0
the timetable to the Partners each time it is revised. The Contractor changes
E
his programme if it is necessary to do so in order to comply with the revised 8
timetable. Each such change is a compensation event which may lead to
reduced Prices.
(8) A Partner gives advice, information and opinion to the Core Group and to
other Partners when asked to do so by the Core Group. This advice, informa
tion and opinion relates to work that another Partner is to carry out under its
Own Contract and is given fully, openly and objectively. The Partners show
contingency and risk allowances in information about costs, prices and timing
(9) A Partner notifies the Core Group before subcontracting any work.
Incentives X12.4 (1) A Partner is paid the amount stated in the Schedule of Partners if the
Payment of the amount is due when the target has been improved upon or
achieved and is made as part of the amount due in the Partner's Own
Contract.
( 2 ) The Client may add a Key Performance Indicator and associated payment
to the Schedule of Partners but may not delete or reduce a payment stated in
l
t
!
;
Option X13: Performance bond
X13.1 The Contractor gives the Employer a performance bond, provided by a bank or
insurer which the Project Manager has accepted, for the amount stated in the
Contract Data and in the form set out in the Works Information. A reason for
not accepting the bank or insurer is that its commercial position is not strong
enough to carry the bond. If the bond was not given by the Contract Date, it is
X14.1 The Employer makes an advanced payment to the Contractor of the amount
3$
X14.2 The advanced payment is made either within four weeks of the Contract Date
c •
cd
·
cu o
or, if an advanced payment bond is required, within four weeks of the later of
E c
0 • the Contract Date and
• the date when the Employer receives the advanced payment bond.
~
0
The advanced payment bond is issued by a bank or insurer which the Project
Manager has accepted. A reason for not accepting the proposed bank or
insurer is that its commercial position is not strong enough to carry the bond.
The bond is for the amount of the advanced payment which the Contractor
has not repaid and is in the form set out in the Works Information. Delay in
X14.3 The advanced payment is repaid to the Employer by the Contractor in instal
each amount due assessed after the period stated in the Contract Data has
£
%, passed until the advanced payment has been repaid.
£
·8
8
X15.1 The Contractor is not liable for Defects in the works due to his design so far
as he proves that he used reasonable skill and care to ensure that his design
X15.2 If the Contractor corrects a Defect for which he is not liable under this contract
it is a compensation event.
Retention X16
X16.1 After the Price for Work Done to Date has reached the retention free amount,
• the date on which the Employer takes over the whole of the works
the amount retained is the retention percentage applied to the excess of the
Price for Work Done to Date above the retention free amount.
• in the next assessment after the Employer has taken over the whole of <J)
<J)
8
2
c «
« a
] Option X17: Low performance damages
E c
0
%
0
damages X17.1 If a Defect included in the Defects Certificate shows low performance with
pays the amount of low performance damages stated in the Contract Data.
%.
-
c
Q
£
Limitation of ability
li X18 ~ Q
0
E
X18.1 The Contractor's liability to the Employer for the Employer's indirect or conse
8
q uential oss is
l mited to the amount stated in the Contract Data.
li
X18.2 For any one event, the li ability of the Contractor to the Employer for loss of or
Contract Data.
f X18.3 The Contractor's liability to the Employer for Defects due to his design which
are not listed on the Defects Certificate is limited to the amount stated in the
Contract Data.
X18.4 The Contractor's total li ability to the Employer for all matters arisin g under or
the amount s tated in the Contract Data and applies in c ontract, tort or delict
and otherwise to the extent allowed under the law of the contract.
The excluded matters are amounts payable by the Contractor as stated in this
contract for
Option X2O: Key Performance Indicators (not used with Option X12)
the incentive schedule unless later changed in accordance with this contract.
X20.2 From the starting date until the Defects Certificate has been issued, the
Contractor reports to the Project Manager his performance against each of the
the Contract Data and include the forecast fi nal measurement against each
indicator.
Indicator will not achieve the target stated in the Incentive Schedule, he
X 20.4 T he Contractor is paid the amount stated in the Incentive Schedule if the
Payment of the amount is due when the target has been improved upon or
achieve d.
X 2 0.5 The Employer may add a Key Performance Indicator and associated payment
to the Incentive Schedule but may not delete or reduce a payment stated in
!1
c
~
0
£
0
0 0.
'
'
OPTION Y
Option Y(UK)2: The Housing Grants, Construction and Regeneration Act 1996
Definitions Y(UK)2
Y2.1 ( 1) The Act is The Housing Grants, Construction and Regeneration Act 1996.
Dates for payment Y2.2 The date on which a payment becomes due is seven days after the assess
ment date.
The final date for payment is fourteen days or a different period for payment if
stated in the Contract Data after the date on which payment becomes due.
The Project Manager's certific ate is the notice of payment from the Employer &
U
to the Contractor pecifying
s the amount of the payment made or pro posed to 2
cz d
be made and stating how the amount was calculated.
«
E c
0
Notice of Intentio n to Y2.3 If either Party intends to withhold payment of an amount due under this
%
withho d l payment contract, he notifies the other Party not later than seven days (the prescribed 0
period) before the final date for payment by stating the amount proposed to
be withheld and the reason for withholding payment. If there is more than one
A Party does not withhold payment of an amount due under this contract
l contract.
Suspension of Y2.4 If the Contractor exercises his right under the Act to suspend performance, it
- Q)
£
O 0
! " 11
5
I Option Y(UK)3: The Cont,acts (Rights of Third Parties) Act 1999
this contract under the Contracts (Rights of Third Parties) Act 1999 only if
the term and the person or organisation are stated in the Contract Data.
Additional conditions of Z1
I
contract Z1.1 The additional conditions of contract stated in the Contract Data are part of
this contract.
t
is used. In this schedule the Contractor means the Contractor and not his
• people who are directly employed by the Contractor and whose normal
place of working is within the Working Areas and
• pecple who are directly employed by the Contractor and whose normal
place of working is not within the Working Areas but who are working in
11 Wages, salaries and amounts paid by the Contractor for people paid according
to the time worked while they are within the Working Areas.
(a) travel
(c) relocation
( f) travel insurance
( n) a vehicle
14 The following components of the cost of people who are not directly employed
by the Contractor but are paid for by him according to the time worked while
Equipment 2 The following components of the cost of Equipment which is used within the
• the Contractor,
at the hire or rental rate multiplied by the time for which the Equipment is
required.
22 Payments for Equipment which is not listed in the Contract Data but is
or
at open market rates, multiplied by the time for which the Equipment is
required.
23 Payments for Equipment purchased for work included in this contract listed
• the change in value over the period for which the Equipment is required
and
• the time-related on cost charge stated in the Contract Data for the
The change in value is the difference between the purchase price and either
the sale price or the o pen market sale price at the end of he period
t fo r w hich
24 Payments for special Equipment li sted in the Contract D ata. T hese amoun ts
Equipment is required.
0
I
f the Project Manager agrees, an additional item of special Equipment may
compensation event.
28 Unless included in the hire rates, the cost of operatives is included in the cost
of people.
Plant and Materials 3 The following components of the cost of lant and Materials.
P
31 Payments for
I Charges 4 The following components of the cost of charges paid by the Contractor.
I
t 41 Payments for provision and use in the Working Areas of
I
• water,
i
4 • gas and
!
• electricity.
l
neC 3 engineering an construction contract
43 Payments for
( d) royalties
44 A charge for overhead costs incurred within the Working Areas calculated by
U
9 applying the percentage for Working Areas overheads stated in the Contract
- <fl
2 Data to the total of people items 11, 12, 13 and 14. The charge includes
) ¢
0 provision and use of equipm ent, supplies and services, but excludes accom
modation, for
(a) catering
<fl
(b ) medical facilities and first aid
8
::, ( c) recreation
z «
(d) sanitation
5 %
(e) security
-
- c
0
(f) copying
:g_
0
(g) telephone, telex, fax, radio and CCTV
.,
U
(i) computing
g
(j) hand tools not powered by compressed air.
3 6
:
0
2 c Manufacture and 5 The following components of the cost of manufacture and fabrication of Plant
? 6
fabrication and Materials which are
#
0
• wholly or partly designed specifically for the works and
51 The total of the hours w orked by employees multiplied by the hourly rates
Data.
Design 6 The following components of the cost of design of the works and Equipment
61 The total of the hours worked by employees multiplied by the hourly rates
63 The cost of travel to and from the Working Areas for the categories of design
insure and
l
; SHORTER SCHEDULE OF COST COMPONENTS
l
I
this schedule the Contractor means the Contractor and not his Subcontrac
• people who are directly employed by the Contractor and whose normal
by him according to the time worked while they are within the Working
Areas.
l "'
c
U
I 11 Amounts paid by the Contractor including those for meeting the requirements z
c «
of the law and for pension provision.
c
E e
0
Equipment 2 The following components of the cost of Equipment which is used within the
:g
Working Areas (including the cost of accommodation but excluding Equipment 0
for listed Equipment stated in the Contract Data to the rates in the published
o £
c
c
g e
list and by multiplying the resulting rate by the time for which the Equipment
8E
is required.
z
C
l 22 Amounts for Equipment listed in the Contract Data which is not in the
j
published list stated in the Contract Data. These amounts are the rates
t stated in the Contract Data multiplied by the time for which the Equipment is
required.
I
23 The time required is expressed in hours, days, weeks or months consistently
f
with the list of items of Equipment in the Contract Data or with the published
l 24
f
Unless the item is in the published list and the rate includes the cost compo-
I
26 Unless included in the rate in the published list, the cost of operatives is
27 Amounts for Equipment which is neither in the published list stated in the
open market rates, multiplied by the time for which the Equipment is required.
www.neccontract.com 59
€ copyright nec 2005
»neC 3 ngneenng an construction contract
Plant and Materials 3 The following components of the cost of Plant and Materials.
31 Payments for
32 Cost is credited with payments received for disposal of Plant and Materials
Charges 4 The following components of the cost of charges paid by the Contractor.
• payments for the provision and use in the Working Areas of water, gas
(l) "'
(l) and electricity,
• • payments for buying or leasing land, compensation for loss of crops or
o
o c
u buildings, royalties, inspection certificates, charges for access to the
Working Areas, facilities for visits to the Working Areas by Others and
• payments for equipment, supplies and services for offices, drawing office,
(l)
¢ _
? u 44 Consumables and equipment provided by the Contractor for the Project Man
"' a.
0
Manufacture and 5 The following components of the cost of manufacture and fabrication of Plant
Design 6 The following components of the cost of design of the works and Equipment
61 The total of the hours worked by employees multiplied by the hourly rates
63 The cost of travel to and from the Working Areas for the categories of design
• costs against which this contract required the Contractor to insure and
' I
I CONTRACT DATA
contracts
1 General • The conditions of contract are the core clauses and the clauses for main
• The works a re
U
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8
• The Employer is
c c
% c
Name . . . . . . . . . . . . . . . . • . . • . . . . . . . . . • . . . . . . • . . • . . • . . . . . . • . . . . . .
E c
0
Address . . . . . . . . . . . . . . . . . . . . • . . • . . . . . . , . . . . . . . . . . . . . . . . . . . . . . •
�
0
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . " .
a
0
• The Supervisor is
I
Name . . . . . . . . . . . • . . . . . . . . • . . . . . . • . . . . . . • . . • . . • . . . • • . . . • • • • . • •
-"'
c
Address . . . . . . . . . . . . • . . • . . • . . • . . . . . . . . . • . . . . . . . . . . . . • . . . . . . . . .
• c
O 0
0
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . £
8
• The Adjudicator is
Name . . . . . . . . . . . . . . . • . . • . . • . . • . . . . . . • . . . . . . • . . • . . • • . . . . • . • . • •
Address . . . • . . . . . . • . . . . . . . • . . . • . . . . . . . . . • . . • • . . . . . . . . • . . • . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . " .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . " ' .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . .
.neccontract.com
www
copyright nec 2005 61
i
>neC 3 engineering and construction contract
• The tribunal is . . . . . . . . . . . . . . . . . . . . . • . . • . . . . . . • . . • . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ' .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . " .
0
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . " .
<D <D
, G
o z
0 c
3 Time • The starting date is . . . . . . . . . . . . . . . . . • . . . . . . . . . . . . . . . . . . . . . . . . . . . .
u
• The access dates are
1 .
2 . . .
3 .. . .
<Ii
.. . . . . . .. . . .. . . . . .. . . . . . . . . .. . . . . . . . .. . . . . . . . . . . . . . . . . . . weeks.
c_
e8
'O.!!1 4 Testing and Defects
c o • The defects date is . . . . . weeks after Completion of the whole of the works.
g c
Q2 5
• The defect correction period is weeks except that
5
o • The defect correction period for is . . . . . . . . . . . . weeks
2
% Q 5 Payment • The currency of this contract is the .
£
~ Q
0
• The assessment interval is weeks (not more than five).
£
Celsius
. . . . . " ' .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ' ' - .
l
• The weather measurements are supplied by .
i
I
• The weather data are the records of past weather measurements for each
l
l
! calendar month which were recorded at .
I . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
"
8
:,
c c
I Where no recorded data are available · co o
E c
l 0
• Assumed values for the ten year return weather data for each weather
I
. . . . . . . . . . . . . . . . . . " .
U
. . . . . . . . . . . . . . . . . . . . . . . . . . " . s 8
I
cs £
d
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . c o
!
g c
g 5
' . . . . . . . . . . . . . . . . . . . . . " . d .
"' 15.
0
8 Risks and insurance • The minimum limit of indemnity for insurance in respect of loss of or
damage to property (except the works, Plant and Materials and Equipment)
and liability for bodily injury to or death of a person (not an employee of the _
2
Contractor) caused by activity in connection with this contract for any one - Q)
I event is O 0
€ 0
£
. " ' ' ' .
8
I
• The minimum limit of indemnity for insurance in respect of death of or
bodily injury to employees of the Contractor arising out of and in the course
of their employment in connection with this contract for any one event is
I
Optional statements If the tribunal is arbitration
I
' ' ' ' .
+
pwww.neccontract.com copyright nec 2005 63
l
»neC 3 engineering and construction contract
If the Employer has decided the completion date tor the whole of the works
If the Employer is not willing to take over the works before the Completion
Date
• The Employer is not willing to take over the works before the Completion
Date.
key date
1 . " •'• .
0 2
3l
::, 3 . . . . . . . . . . . • . . . . . . . . . . . . .
«
·mo
E c If the period in which payments are made is not three weeks and Y(UK)2 is
0
not used
8
0
• The period within which payments are made is .
"'
e8
c_ If Y(UK)2 is used and the final date for payment is not 14 days after the date
a
0 If there are additional compensation events
2 1 .
� (I)
£
0 0 2 . . . . . . . . . . . . . • . . • . . . . . . . . . . . . . . . . . . . . . • . . . . . . . . . . . . . . . . . . . . .
0 a.
E
3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . • . . . . . . . . . . . . . . .
8
1 .
2 .
3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . • . . . • . . • . . • . . • . . . • . .
• The insurance against loss of or damage to the works, Plant and Materials
is to include cover for Plant and Materials provided by the Employer for an
amount of
. . . . . . . . . . . . . . . . . . . . . . . . . .
Table
1. Insurance against. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . •
Cover/indemnity is . . . . . . • . • • . . • . . . . . • . . • . . . . . . . . . . • . . . . . . . . . . . . .
2. Insurance against. . . . . . . . . . • . . • . . • . . . . . . . . . • . . • . . . • . . • . . . . . . . .
Cover /indemnity is . . . . . . . • . . . . . . . . . . . . . . . . . . . . . . . . . . . . • . . . . . . . . .
3. Insurance against. . . . • . . . • . . • . . . . . . . . . • . . • . . . . . . • . . . . . . . • . . . • .
Cover/indemnity is . . . . . . . . • . . . . . . . . . . . . . . . • . . • . . . • . . • • . . • . . • . . . .
U)
1. Insurance against. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . • . . • . . • . . • • . . .
$
Cover/indemnity is . . . . . • . . • . . • . . • . . . • . . • . . . . . . . . . . . . . . . • . . . . . . . .
c c
v
The deductibles are . . . . . • . . . . . . . . . . . • . . . . . • . . . . . . • . . . . . . . . . • . . • . .
E e
0
2. Insurance against . . . . . . • . . • . . • . . . . . • . . . . . . • . . • . . . . . . • . . . . . . • . .
a
0
Cover /indemnity is . . . . . . . . . • . . . . . . • . . • . . • . . . • . . • . . • . . . • . . • . . • . . .
U)
0
The deductibles are . . . . . . . . . • . . . . . • . . • . . • . . . • . . • . . . . . . • . . . . . • . . . .
e a
3. Insurance against . . . . . . . . . . . . . . . . . . . . . . . • . . . • . . . . • . . . • . . • . . . • .
cs
£
c o
g c
Cover/indemnity is . . . . . • . . . . . • . . . . . . . . • . . . . . • . . • • . . • . . . • . . • . . • . . Q 6
0 .
en
1. Insurance against. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . • . •
c
%, g
s
Cover/indemnity is . . . . . . . . . . . . . . . . . . . . . • . . • . . . . . . . . . . . . . • . . . . . . .
Q
o
2. Insurance against . . . . • . . • . . • . . • . . . . . • . . . . . . • . . • • . • . . . . . . • . . • . . E
0
0
Cover/indemnity is . . . . . . . . . . . . . . . . . . . . . . . • . . • . . • . . . • . . • . . • . . • . . .
3. Insurance against. . . . . . . . . . . . . . • . . • . . . • . . • . . . • . . • . . • . . . • . . . . • .
Cover/indemnity is . . . . . . • . . . . . . • . . . . • • . . . . . . . . . . . . . . . . . . . . . . . . . .
If Option B or D Is used
amended as follows . . . . . . . . . . . . . . . • . . . . . . • . . • . . • . . . • . . • . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
,
.
'
If Option C or D Is used
less than % . . . . . . . . . . . . . . . . . . . . . . . . . . . %
from %to % . . . . • . . • . . • . . . . . . . . . . . . . . . • %
from %to . . . . • . . . . % ,. . • . . • • . . . . . • . . . . . . . . . . . . . %
greater than %
· · · · · · · · · · · · · · · · · · · · · · · · · · · % .
If Option C, D, E or F Is used
• The Contractor prepares forecasts of Defined Cost for the works at intervals
on (date).
If Option X1 is used
<I)
• The proportions used to calculate the Price Adjustment Factor are
$
0 linked to the index for . . . . . . . . . . . . . . . . . . . . . . . . . . . . • . • .
z •
«
5 0 .
-
- c
0
0. . . . . . . . . . •
5 0. . . . . . . • • • •
<I)
0. . . . . . • . . . .
$
2 6 0 .
0
? c 0...........non-adjustable
? 5
) .
' %
0
1.00
) 0
) a. If Option X3 Is used
E
• The Employer will pay for the items or activities listed below in the currencies
8
stated
in the currency
on . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . • . . • . . • . . • . . . . . . . (date).
If Option X5 is used
I
• The completion date for each section of the works is
2 . . . . . . . . . . . . . . . . . . . . . . . . . . .
3 . . . . . . . . . . . . . . .
4 . . . . . . . . . . . . . . . . . . . . . . . . . . .
1
I . . . . . . . . . . . . . . . . . . . . . . . . .
2 . . . . . . . . . " ' .
I
3
i 4 . . . . . . . . . . . . . . . . . . ' .
"'
c
!!l
I Remainder of the works . . . . . . . . . . . . . . . . . . . . . . . . . • . . . . . . . . . • . . . . . •
c @
%
l If Options XS and X7 are used together E c
I C
+
• Delay damages for each section of the works are E
C
'
j
section description amount per day
l
•
(l;
f 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
e
l 2 . . . . . . . . . . . . . . . . . . . . . . . . . .
d
i c c
g e
j 3 . . . . . . . . . . . . . . . . . . . . . . . . . £ a
. . . . . . . . . . . . . . . . . . . . . . . . . .
0 .
<\
(/) c
' 4 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . c
I
'
'
Remainder of the works . . . . . • . . . . . . . . . • . . . . . . . . . . . . . . • . • . . . . . • . • .
t u
t
l
%
If Option X6 is used (but not If Option XS is also used) £
t
O C
c
• The bonus for the whole of the works is per day.
£
I
£
If Option X7 is used (but not if Option XS Is also used)
• Delay damages for Completion of the whole of the works are per day.
l
I
• The Client is
Name . . . . . . . . . • . . . . . . . . . . . • . . • . . . . . . . . . . . . . • . • • • • • • · · · · · · • · · ·
Address . . . • . . • . . . . . • . . . . . • . . . . . . • . . . . . . • . . • . . . • . . . . . . . . . . . . . •
I
. ' .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . ' .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ' .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . " .
. . . . . . . . . . . . . . . . . " . . " .
-
- c
0
• The retention free amount is . . . . . . . . . . • . . . . . • . . • . . • . . . . . . . . . • . . . . . .
a
0
• The retention percentage is . . . . . . • . . . . . . . . . . . . . . . • . . • . . . . . . . . . . . %.
for . . . . . . . . . . . . . . . . . . . . . . . • . . . . . . . . . • . . . . . . . . .
for . . . . • . . . . . • . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
for . . . . • . . . . . • . . • . . . . . . . . • . . . . . . • . . • . . . . . . . . . .
£
0
£
g for . . . . . . . • . . • . . • . . • . . • . . • . . • . . • . . . • . . • . . • . . • .
a
£
If Option X18 is used
8
• The Contractor's liability to the Employer for indirect or consequential loss is
limited to .
• For any one event, the Contractor's liability to the Employer for loss of or
• The Contractor's liability for Defects due to his design which are not listed
• The Contractor's total liability to the Employer for all matters arising
is limited to .
I
f Option X2O is used (but not if Option X12 Is also used)
at intervals of months.
• term • person or
organisation
If Option Z Is used
V
d
[
c «
·
ro c;
E e
c
i
c
V
d
e
c0
-0l':
c c
g c
85
"' 1:
c
V
�
c
• £
O C
<.> C
£
£
i
Part two -- Data provided by the Contractor
contracts
Name . . . . . . . . . . . . • . . • . . . . . • . . . . . . . . • - . • • • • • • • • • • • • • • · • • • • • • • •
Address . . . . . . . . . . . . . . . . • . . • . . • . . • . . • . . . . . . . . . . . . . . . . . . • . . . • . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
( 1) Name . . . . . . . . . . . . . . . . . . . . . • . . • . • • . . . . . • . . • . . . . . . . . . . . . . . . . •
g
u Job . . . . . . . . . . . . . . . . . . . . • . . • . . . . . . . . • . . • . . . . . . . . • . . • . . • . . . • . . . •
2
z «
ij c3 Responsibilities . . . . . . . . . . . . . . . . . . . . . . • . . . . • . . . . . . . . . . . . • . . . • . . . .
- c
6
z
0 Qualifications . . . • . . . . . . • . . • . • • . . • . . . . • . . • . . • • . . • . . . . . • . . . • . . . . .
Experience . . . . . . • . . • . . . . . . . . • . . • . . . . . . . . • • . . . . • . . . • . . • . . • • . . • • .
3
q
g
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
z o (2) Name . . . . . . • . . . . . . . . . . . . • . . . . . • . . . . . . . . . . . . . . . . . . . . . • . . . . . .
3 g
.9
Job . . . . . . . . . . . . • . • . . . . . • . . • . . . . . . . . • . . • . • • . . . . . . . . . • . . • . . . . . . .
» a
0
Responsibilities . . . . • . . • . . • . . • . . • . . • . . • . . . . . . . . . . . . . . . . . • . . . • . . . •
l!l
c
Qualifications . . . . . • . • • . . . . . . . . • . . • . . . . . . . . • . . • . . • . . . . . . . . . . . . . . .
J "'
£
5 g
3 0 Experience . . . . . . . • . . • . . . . . . . . . . . . . . . . . . . . • . • . . • . . • . . . • . . . . . . . • .
£
0
0
Optional statements If the Contractor is to provide Works Information for his design
If the Contractor is to decide the completion date for the whole of the works
If Option A or C Is used
!
• The activity schedule is . . . . · . . . . . . . . . . . • . . . . . . . . . . . . . . . . . • . . . . .
!
'
!
If Option B or D Is used
If Option A, B, C or D is used
I
If Option F is used
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ' . "'
c c
I
·ro
u
I . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
E e
0
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
E
0
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
VJ
If Option A or B is used e%
"0 �
C
O
Data for the Shorter • The percentage for people overheads is . . . . . • . . . . . . . . . . . . . . . . . . . . . . %.
g e
g 6
Schedule of Cost
Components
• The published list of Equipment is the last edition of the list published by
;
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
O 0
• The rates for other Equipment are
a
E
Equipment
size or capacity rate
8
. . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
t
l
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
• The hourly rates for Defined Cost of desi gn out side the Working Areas are
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . ' . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . ' . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
suauodu10o 1s0o
ore seary BupyoM au) apysno u8sap 0 1s0 p9uog 10) sae nou uL • Jo sanpouos uoq 1o] ee(
opysno uopeoqe] pue amnoejnueu Jo 1s0 pauyog Jo] sae ApnOu auL •
1ad
10d
c
5 c
1ad e c
( C
1ad U
ue u 'oenu0o su) uo I0M Jo] poseuomnd uoudynb J0 $uy pas] au] • so 40 a1npauos 0) ee
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
uuoI] pue o) ssu odxo Buyyoen sou sooojduro uBysop jo sou03a00 au] •
I
• The categories of design employees whose travelling expenses to and
from the Working Areas are included as a cost of design of the works and
l
. . . . . . . . . . . . . . . . . . . . . . . . ' ' ' .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
I If Option C, D or E is used
I
Data for the Shorter • The percentage for people overheads is %.
Schedule of Cost
• The published list of Equipment is the last edition of the list published by
I Components
% (state plus or m i n u s ) .
t "'
0
2
C c
c
J . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
' . . . . . . . . .
E c
t 0
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . R
1 0
¢
l
. . . . . . . . ' . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
I
i
�
j
t
0
1
%
-
c
0
£
Q
0
I
} www.neccontract.com e copyright nec 2005 73
l
.
r
-
»> n€C 3 Engineering and Construction Contract
Index by clause numbers (Option clauses indicated by their letters, main clause heads by bold numbers).
Terms in italics are identified in Contract Data, and defined terms have capital initial letters.
acceptance adjudication
contract data for subcontract C26.4, D26.4, E26.4, Adjudication Table W1.3( 1)
F26.4 Adjudicator
036.3
administration order 9 1.1
quot ations 44.2, 60.1(9), 62.3, 65.1, A36.3, advanced payment 93.1, X14.1-3
reasons for w ithholding 13.4, 13.8, 15.1, 2 1. 2 , advanced payment bond X14.2
X13.1
agreement, Parties/Party 12.4
replacement Contractor's employee 24.1 ambiguities 17, 60.3, 63.8, B60.6, D60.6
and Activity Schedule A54.2, A54.3, C54.2, C54.3 correction of assessment 50.5, 51.3, X1.2
C 5 2 . 3 , D 1 1 . 2 ( 25) , D 52.2-3, E 1 1 . 2 ( 2 5 ) , E52 . 2, amount due 50, 51.1, 51.3, 90.4, 93.1, 050.6,
E52.3, F11.2(26), F52.2, F52.3 C5 3.3, C53.4, D 50.6, D53.7, D53.8, E50 .7,
Activity Schedule A11.2(20,30), A31.4, A54.1-3, A63.10, A63 . 1 2 , A65.4, 863.10-13, €52.2,
Contractor's share C53.1, C53.3-4, C93.4, €93.6, address to w hich sent 13.2
D 1 1. 2 ( 2 9 ) , £ 1 1. 2 ( 2 9 ) , F 1 1 . 2 ( 2 9 ) , X 7 . 2 , Y 2. 2 l a n g u a g e for 13.1
60.1(6)
bankruptcy 91 . 1 compensation
payment 50.5, 51.1-3, 90.4, 91.4 Key Dates affected by 60.1(4), 61.3, 62.2, A65.4,
change(s) in forecast Prices, Completion Date and 860.6, 863.10, 865.4, C65.4, D60.4, D60.6,
change(s) of Prices, Completion Date and Key Dates 863.10, C63.15, D63.15, E63.15
d ue to compensation events A65.4, B65.4, quotations 61.4, 61.5, 62, 64.1, 64.3-4, 65.1,
C65.4, D65.4 A 1 1 . 2 ( 2 2 ) , 8 1 1 . 2 ( 2 2 ) 0 1 1. 2 ( 2 5 ) ,
and acceptance of submission 13.4, 13.8, 14.1 section of the works X5.1
I
>neC 3 cngneenng and construction contract
Completion (continued)
Contract Date 1 1 . 2 ( 4 ) , 860.4, 060.4, X2.1, X4.1,
and take over of works 35.1-2, 35.3, 6 0 . 1 ( 1 5 ) , X13.1, X14.2
X16.1, X16.2 A ccepted Programme 6 0 . 1 ( 1 9 )
whole of works 32.2, 50.1, 60.1( 13), 92.1, 93.2, compensation events 6 0 . 1 ( 1 2 ) ( 1 9 )
C20.4, C53.3, D20.4, D53.7, E20.4, F20.4, prevention 19.1
X1.2, X16.1 termination 91.7
work necessary 1 1 . 2 ( 2 ) ( 1 3 ) Contractor
62.2, 63.3, A65.4, 865.4, C65.4, D65.4, accounts and records C 1 1 . 2 ( 2 5 ) , C52.2- 3 ,
E65.3, F65.3 0 1 1. 2 ( 2 5 ) , 052.2-3, £ 1 1. 2 ( 2 5 ) , £52.2,
definition 11.2(3)
£52.3, F 1 1 . 2 ( 2 6 ) , F52.2, F52.3
f Defect(s)
i accepted 44.2 actions 10.1
notification of com p ensa ti on events 61.3
Activity Schedule A31.4, A54.2, C31.4, 054.2
P rice Adjustment Fa ctor calculation X1.2 adding to working areas 15.1
in programme (first/revised) 31.2, 36.1, A36.3, adjudication W 1. 3 ( 1 - 2 ) ( 4 ) , W 2 . 3 ( 3 ) ( 7 )
8 36.3 , C36.3, D36.3 advanced payment X14.1, X14.3
rights to change 63.4
advice to Project Manager C20.3, D20.3, E20.3,
section of the works X5.1 F20.3
and take over of works 35.1-2, 60.1(15)
and ambiguities/inconsistencies 1 7 . 1
and weather measurement 6 0 . 1 ( 1 3 )
amount due to e
b p aid to 50.2, 50.4, 5 1. 1
work to b e done by 1 1. 2 ( 2 ) , 30.1
assessment of compensation events 62.2, 64.1,
C ondition 11.2(9), 25.3, 30.3, 3 1. 2 , 63.3, 63.9,
863.13, C63.15, D63.13, D63.15, E63.15
860.5, D60.5
Bill of Quantities 8 1 1. 2 ( 2 8 ) , 863.13, 063.13
conditions, i dentified and defined rms 1 1 . 2 ( 9 )
te
certificates ssued to 13.6
i
notified of delegate for Project Manager /Supervisor Contracts (Rights of Third Parties) Act ( 1 9 9 9 ) Y(UK)3
Plant and Materials 2 7 . 2 , 41.1, 80.1, 92.2, 93.1 additional costs 25.3
quotations 36.1, 36.2, 44.2, 62.1-5, 64.1 indemnity against 83.1, 83.2
responsibilities 14.1, 20--7, C20.3, C20.4, C26.4, currency of this contract 51.1, C50.6, 050.6, E50.7,
F26.4
F20.3 decision(s)
termination 80.1, 90.2, 90.4-5, 91.2, 91.4, and compensation events 60.1(8), 61.1, 61.4-6
tests and inspections 40.2, 40.3, 40 .5, 40.6, 41.1, Project Manager 30.2, 50.1, 60.1(8), 61.1-2,
title to objects and materials within Site 73.1, 73.2 E11.2(25), F11.2(26)
title to Plant and Materials 70.1, 70.2 risk reduction meeting 16.4
www.neccontrac
t.com c copyright nec 2005 77
neC 3 cngneerng and construction contract
and compensation events 6 1 . 4 , 63.1-2, 63.7, Completion of works on termination 93.1, 93.2
of Equipment 23 93.1-2
of works C20.3, D20.3, E20.3, F20.3 tests and inspections 40.2, 40.6, 6 0 . 1 ( 1 6 ) , C40.7,
direct fee percentage 1 1 . 2 ( 8 ) , 93.2 title to Equipment, Plant and Materials 93.1
l
1
!
o --nec3
'
i
2
loss, dama g e or w ear 80.1 indemnity 83
!
marking of 7 0 . 1, 71 information
$
'
and programme 31.2 in Activity Schedule A54.1, C54.1
see a/so P lant and M aterials see a/so Site Information; Works Information
exchange rates C50.6, D50.6, E50.7, F50.7, X3.1 Contractor's cost C40.7, D40.7
for tests/inspections 40.2, 42.1, 60.1(16) 61.5-6, 62.1, 62.3-4, 64.1, X2.1
I see a/so services to remove Contractor's employee 24.2
t
# failure to pay in time, actions to be taken 91.4 on resolution of ambiguities and inconsistencies
f fault of Employer or his design 80.1 to stop/not start work 34, 60.1(4), 91.6
calculation(s) 11.2(8), 63.1, 93.2, C50.6, D50.6, that change Works I nformation 14.3, 18.1, 44.2,
'
E 50.7, F 50.7 60.1(1), 63.8-9
fee percentage see direct fee percentage certificates 85.1, 86.1, 8 7.1 - 3
forecasts 61.6, 63.1, 65.2, 93.2, C20.4 , C53 .3, by Employer 84.1, 85.4, 86.1, 87
interest
73.1 interpretation
legal 12
r identified terms 11
implementing compensation events 32.1, 65, A65.4, acceleration 3 6 . 1 , A36. 3 , C36.3, D36.3
t
»>neC 3 sngneenng and construction contact
D 1 1 . 2 ( 2 3 ) , E l l . 2 ( 2 3 ) , Fl l. 2 ( 2 3 ) 65.1
materials Parties/Party
Partnering X12
NEC contract 26.3, C26.4, D26.4, E26.4, F26.4 defined terms X12.1
de -" n e C 3
Contractor 40.6, 45.2, 51.1, 86.1, 050.6, 052.2, and retention X16.1
Housing Grants, Construction and Regeneration Act A63.12, C11.2 ( 30), C54.3, C 63.12
and marking of Equipment, Plant and M aterials and compensation events 61.4, 62.2, 63.1-2,
on termination 93.1, 93.2, A93.3, C 93.4 , C93.6 , Contractor's share C53.1 - C53.4, D53.5
..
[ performance bo nd X13, X13.1
Employer's risk 80.1
1
see so low performance
a/ E11.2(25 ) , F1 1 .2 ( 26)
perf ormance suspension Y2.4 accelerated 36.1 , A36.3, B36.3, C36.3, D36.3,
Plant and Materials 11.2(12)(17) acceleration 36.1, A36.3, 836.3, C 36.3 , D36.3 ,
loss of o r damage to 80.1, 82.1, 84.1 13.4, 14.1, 15.1, 21.2, 31.3, 85.1
not used to Pro vide the Works C11.2(25), acceptance of contract data for subcontract C26 .4,
removal of 92.2
acceptance of otation
qu 4 4.2, 60.1(9), 62.3, 65.1,
64, A63.10, B63.10, B63.13, C63.15, reply to communication 13.3-5, 60.1(6), 62. 3 ,
assessment of Contractor's share C53.1, C53.3-4, request to remove resources from Working Areas
Contractor's employees 24.1, 24.2 proposed instruction or changed decision 61.2, 62.3
F65.3 060.4-7
inspection of Contractor's accounts and records see also bill of quantities; Bill of Quantities
instruction(s) 14.3, 17.1, 18.1, 24.2, 2 7 .3, 34.1, for acceleration 36.1-2, 60.1(9), A36.3, B36.3,
62.3-4, 82.1, 87.1, 91.6, C26.4, D 2 6.4 , acceptance of 36.1, 44.2, 6 0 . 1 ( 9 ) , 62.3, 65.1,
insurance 85.1, 87.1 for compensation events 61.4, 61.5, 62, 64.1,
moving of Equipment, Plant and M aterials 70.2, 72.1 for proposed instruction/changed-decision 61.2
programme 11.2(1), 31.1, 31.3, 32.2, 50.3 D11.2 ( 25,31 ) , D60.4, D63.13
repairs 82 Site
replacement( s) access to 31.2, 60.1(2)
time allowed 13.3-5, 31.3, 32.2, 3 6 . 2 , 6 0. 1 ( 6 ) , removal of Equipment, Plant and Materials 72.1,
62.5-6 92.2
Contractor 14.1, 20-7, C20.3, C20.4, 026.4, S ite nformation 11.2(16), 60.2
I
020.3-4, 026.4, E20.3-4, E26.4, F20.2-4, and Activity S chedule A54.1 , A54.2 , C54.1
. Employer's 83.2, 87.2 starting date 31.2, 32.2, 50.1, 81.1, 84.2, 87.1,
retention 50.3, 93.1, X16 C20 .4, D20 .4, E 20 .4, F20.4
revised Activity Schedule A54.2, A54.3, C54.2, instruction(s) given not to 3 4 . 1 , 6 0 . 1 ( 4 ) , 91.6
revised programme 32.1-2, 36.1, 64.2, A36.3, strikes, risks due to 80.1
.·_ Rights of Third Parties (Contracts) Act Y(UK)3 subcontracted fee percentage 1 1 . 2 ( 8 )
] definition 1 1. 2 ( 1 4 ) Subcontractor
l
r www.neccontract.com
t copyright nec 2005 83
I
i
l
>neC3 engineering and construction contract
--
forecasts of total Defined Cost C20.4, D20.4, reply to communications 13.3, 13.5, 31.3, 32.2,
non-acceptance of 13.8, 1 5 . 1 , 21.2, 23.1, 26.2, time risk allowances 31.2, 63.6
quotations 36.1, 3 6 . 2 , 44.2, 61.4, 62.1, 62.3-6, Equipment, Plant and Materials 92.1, 92.2
data 26.2, 26.3, 026.4, D26.4, E26.4, F26.4 Plant and Materials 70
Supervisor D93.5
certificates issued by 13.6, 43.3, 50.1 identified and defined terms D11.2(33)
marking of Equipment, Plant and Materials 70.1, identified and defined terms 1 1 . 2 ( 2 7 )
suppliers 1 1 . 2 ( 1 0 ) ( 1 7 ) decisions 5 1. 3
take over of works 35, 43.4, 6 0 . 1 ( 1 5 ) , 80.1, X6.1, reviews W1.4(1-6), W2.4(1-5)
taxes 52.1
amount due on 90.2, 90.4, 93.1, 93.2, A93.3 undecided disputes, Adjudicator W1.2(4), W2.2(4)
certification of 90.1, 90.3, 90.5, C93.4, D93.5 United Kingdom Housing Grants, Construction and
payment on 93.1, 93.2, A93.3, C93.4, 093.5 usurped power, risks due to 80.1
third party rights, contracts Act Y3.1 wastage of Plant and Materials C 1 1 . 2 ( 2 5 ) ,
( addition 15
and Bil l of Quantities B55.1, D55.1
works definition 1 1 . 2 ( 1 9 )
+
Completion of whole 11.2(13), 32.2, 50.1,
t Equipment 1 1 . 2 ( 7 )
60.1(13), 9 2.1, 93 .2, C 20 .4, C53 .3, D 2 0.4 , h ealth a nd safety 27.4
D5 3. 7, E20.4, F20.4,X1.2, X16.1
instructions that change 14.3, 18.1, 44.2, 6 0 . 1 ( 1 ) ,
'
t
,
t
!
!
i
l
t
3
i
l