Beam
Beam
Beam
We Know, Fb=MC/I
= 16.90 ft
Here,
Design load of test pile = 397.72 MT
Test Load of test pile= 795.43 MT
Capacity of single beam found = 607.09 MT
So, Number of Main Beams required = (795.43/607.09)
= 1.31 Nos.
So, using two (2) Nos Main beam (1200 m* 550 mm) is considered safe for conducting
above-mentioned test.
We Know, Fb=MC/I
= 17.88 ft
Here,
h2
Section Modulus Sx = 1559.083 in3
Sy = 221.602 in3 b2
S= 1780.684 in3
Length of Gider 39.36 ft C2
12.00 m
M= 58762.588 kip-in
4896.882 kip-ft
W= 34.306 kip/ft
= 1338.67 kip
= 607.09 MT
Number of I Beam = 1.317771
For Cross Beam
M= 7665.643 kip-in
638.804 kip-ft
W= 3.996 kip/ft
= 153.86 kip
= 69.78 MT
Number of I Beam = 13.18506