1996 AACE - F6 - Contingency Drawdown Using Risk Analysis
1996 AACE - F6 - Contingency Drawdown Using Risk Analysis
F6a
INTRODUCTION
Risk analysiscan be usedby owner companiesto accomplishmultiple objectives. First, management(or client) can establish
guidelinesfor contingency.Theseguidelinesshouldbe usedduring the pmject’sexecutionto drawdown the contingencyand not just
to developthe initial estimate.Second,managementcanestablishoverrun/underrundollar limits wherea project’sauthorizationmust
he reviewed.Third, risk analysiiadvisesmanagementon the appropriatestepsrequiredto reducethe risk andcorrespondiigoverrun
dollar limit if the projectis marginallyeconomical.Finally,managementcanestablishperformancemeasuresfor projectmanagement
groups in companies wherethereare multiple projectsbaseduponthe numberof projectsbeingcompletedoutsidethe approvalrange.
ESTABLISHINGCONTINGENCY
Severaltextbooksare availabledescribingthe technicalaspectsof Monte Carlo simulationand its usefor project risk analysis.
simply stated,the simulationmodelhasuseda randomnumbergeneratorto build the project 1,000or more timesin the computer,
StOtingthe resultsafter eachiteration through the model. The mathematicalmodel is built as a mirror of the estimatewith each
componentbeinginput asa probabilitydistributioninsteadof a discretenumber. Also, the computermodelthen presentsstatistical
re~tionshipsdevelopedfrom the population of resultsfrom eachiteration. The result is a probabilitydistribution (seefigure 1)
representingthe expenditureestimatesor forecastsbasedupon the inputs. The client canestablishexpectationsfor a project team
by eXpre=ingthem in termsof this probabilitydistribution.
l$’ expresSingan acceptablelevel of risk, the client hasprovidedthe project teamwith the informationneededto developthe
con%3encyestimateusingthecumulativeprobabilitydistribution. Someclientmanagements haveprovidedinstructionsto their project
F.6.I
teamsOn how much risk to take at various phasesof their projects. One exampleis a project team with instructionshrom their
managementto selecta 70% probabilityof underrunningduring the conceptualphaseof a project. Contingencyis cakukiteb aSthe
amountrequiredto bring the baseestimateup to the 70%probabilityof underrunninglevel. Folkwing prelimiWy engine+Xing, their
instructionsfrom managementare to then lowerthe probabilityof underrunningto 50%or the meanandto usethis guidelinetiOu@
project completion. “Ihe resulting estimateis called the SO/50estimatemeaningthere is an equal chanceof undemnning Or
overrunningthe project. This SO/XIguidelineis usedby severalcompaniesin the oil industry.
1992AACETRANSACTIONS
When the client doesnot provide guidelines,the presentationof a cumulativeprobabilitydistribution will provide someinsight
into the client’srisk quotient evenif a specificrule is not provided. Supposethe client insiststhat an 8% contingencyis all it will allow,
while the cumulativeprobabilitydistribution suggeststhat with an 8% contingencythere is a 75% chanceof overrunningthe project;
the project team then knowsthat the project must be tightly managedor an additionalcontingencyneedsto be hiddenwithin the
estimateas allowances.This information is usefulin determininga methodfor drawingdown the contingency.
Early ln the project the project team meetsto determinehow the risk analysiimodel’sinput rangeschangeas work progresses
from estimatedamountsto committedamountsto actualexpenditures.With a predefinedprocedurecommunicatedto the client and
all memberson the team,contingencybecomesa calculatedamount. The client is lesslikely to committhe contingencyestimateto
scopechangesearly in the project and not havethis reservefor unforeseenwhen neededduring the project’sexecution.
ovERRIJN/uNDERRuNLIMITs
E&mate overrun and underrun limits can also be establishedwith client guidelinesfor use of the cumulative probability
distribution. The estimate’scontidencefactor canbe established;manyclientsestablishan 80% confidencebctor guidelineby using
the 10% and 90% probability of underrunuing points on the distribution. The table below is an exampleof one management’s
expectationson estimateaccuracyrangesexpressedas percentages of the estimate. Note the narrowingof the accuracyrangeas the
F.6.3
Projectprogresses.Resultsfrom Monte Carlo risk analysisshould follow similar ranges;thus this table is an effectiveyardstickto
memre the effectiveness
of the process.
Estimate Confidence
EMmateTvue Accuracy Factor Many projectmanagersasktheir staff to adjustthe input
rangesto Monte Carlo risk modelsto fw&e at a preconceived
ConceptualINmate &SQ-8Q% 80% contingencyamount. This is difbcult whenthe resultsTom the
PreliminaryEstimate 930% 88% risk analysiiare threenumbers,the upper limit, lowerlimit, and
BudgetEstimate f15% 80% forecast amounts,which are presentedto managementfor
Control Estimate 910% 88% projectapprovaland at regularproject reviews
IDefinitiveESmate &5% 80%
fZxecution- Drawdown &5-10% 80%
IF.64
1992AACE TRANSACTIONS
Risk analy& is much strongerwhen the entire project team is involved in creatingthe rangesfor each of the components.
Estimatesare modelsderivedby.multiplyingquantityunits timespricesand summingthe results. The inputs to a Monte Carlo risk
analysisare probabilitydistributionsfor eachcomponentof the estimate. Sincethe mathematicsaround multiplying two probability
distributionsis not easy,asimulation techniquelike Monte Carlomodelingmustbe used. Whenthe inputsto the modelaredeveloped
asa teameffort, the individual membersof the teamcanexpresstheir subjectiveconcernsin a mannerthat will allowcommunication
of those concernsto the client in proportion to their impactsto the project. It also allowsfor inputs by all disciplineswith special
weightingto their areasof expertise(Purchasingwith inputs to equipmentand materialcosts,Constructionwith inputs to workhour
inputs, Labor Relationswith inputs to ratesper workhour,etc). Estimatedatabaseswith historicalunit factorsare excellentsources
for probability distributionsfor thosebctors.
Most estimatorsbuild estimatesusingunit ratesthat are the nwst Eke&,whichis usuallythe modein statisticalterms. Ihe mode
is the data point in a populationthat is repeatedthemosttimes. The natureof constructionis that mostprobabilitydistributioninputs
are skewedto the right; thus, the mode will be below the mean (average). Estimateprice and quantity inputs are examplesof
one-hwnpedfi~~ distiutions skewedto the right. Very few estimatorshaveaccessto detailedhistoricaldatabasesproviding
empiricalprobabiity distributions;thus, the inputsusedin practiceare subjective.Commercialsoftwarepackageswith Monte Carlo
featuresallowfor different distributionswith the mostfrequentlyusedbeinga triangular,normal,step,andskewed(beta)distribution.
AllChOl-iIlg
Sensitivity Analysis
By analy&g the inputs and resultsof a rlsk analysisa client cangain an understandingof how risky the projectis perceivedby
the project team. Analysisof the inputswill identifysensitiveareaswhereriskscanbe managedin the project. ClassicexamplesinvOlve
items like describingthe scopedefinition,purchasingmajorequipmentcomponents, or completingthe next phaseof engineering;each
Of thesewould lower the riskswhen completed. Other areasmay not be so obvious,like currencyconversions,union vs non-union
craft usage,skidvsstick built construction,transportation risks, engineeringor craft availability,technologychanges,environmentalrule
Changes, etc. As the project teamworkstogetherto developinputsto the risk analysllmodel,theseareasbecomebetter dehnedand
the tinal Monte Carlo risk analysii modelcan be run severaltimesto isolatethe effectsof unusualcomponentsto the model. These
areasOf concerncan then be discussedwith the client, and a plan can be developedto managethe associatedrisks
CONCLUSIONS
The prObabiity distribution resultingfrom Monte Carlo risk analysiscan be usedto establishthe overrun and underrun dollar
Utnitsfor a project. This quantifiesthe risks,allowingthe projectteam to statethe rangehasan 80% contldencelevel.
F.65
Whenprojectshavemarginaleconomics,risk analysisallowsthe projectteamto work with the clieat to lower the high end of the
mnge $ identitjhgandthen managingthe high-riskportionsof the project. Fiially, managementcanestablishperformancemeasures
for projectmanagementgroupsin companieswherethere are multiple projectsbasedupoa the numberof projectsking completed
outsidethe approvalrange.
Freund,LE. 1971.M&Iuem~tiesA
Bu&stiss. EnglewoodCliffs,NJzPrentice-Hall.
PAosteUer,
F, W.E.KRourke,and G.B. Thomas.1970.Jl%r&MQ wMnBts&sti~ &@&ia~~. Reading,IIIIIB:Addison-Wesley.
RandalB. Lorance,PE
Arc0 f%%ia5ka,
Inc.
PQ Box 7099
hadeM, CA,91103
F.6.6