Method Statement PEB
Method Statement PEB
The following points to be prepared and completed prior to starting the erection works.
1. Job Site to be cleaned, leveled and ready.
2. Determine the Storage Location
3. Maneuvering room for equipment
4. Utilities to be available
5. Ground slab to be concreted, cleared and leveled for moving scaffolding during
erection works.
B) Mobilization:
All the materials will be transported in Trailers and unloaded by forklift or crane as suitable.
Each truck or trailer will be accompanied with detailed packing lists of its contents. The
inspection forms will be reviewed and acknowledge
Notes:
The above items “A” to “D” are guidelines for Typical Pre- Engineered Building
Erection Works as applicable depending on the Job Complexity
• Sheeting Works:
1. Wall: Sheeting to start at the most viewed direction so that the sheet overlaps are not
visible.
2. Check for correct starting dimension as per erection drawings.
3. Check panel vertical. Repeat the vertical check as each panel is erected.
4. Roof: Sheeting to start by placing the first roof sheet to the given dimension for the
overhang at the eave.
5. String Line to be used as a guide for keeping the tail line of the sheeting straight.
6. Start at eave and work up the roof towards the ridge from both sides of the building.
7. The ridge sheet to be placed last.
8. Ensure that the end lap mastic is placed correctly without gaps.
• Final Check:
After completing all trims and accessories, a final inspection of the building to be made:
1. All bracings in position and tightened.
2. All bolts in place and high strength bolts tightened to correct tension.
3. Check that roof is clear of debris and ferrous metals.
4. Check mis-drilled holes and ensure that the self-tapping screws is fixed back tightly in
place.
5. Touch-up any damaged paint.
6. Clean up the site.
7. Hand over the building.
3. Unloading of Materials:
Unloading of Materials will be done by Forklift or Crane with trained approved riggers
and the lifting gear used will be condition having color codes painted on them as per
Client’s requirement.
5. Segregation of Materials:
The Foreman, Supervisor will do segregation of materials after reading the required
erection drawings, so as to have easy access to the required material in sequence with
the erection required.
7. Scaffoldings:
The erection of scaffoldings will be done under competent supervision. All scaffolders
will wear the required PPE, such as gloves, safety shoes, helmet and safety harness
during their scaffolding activities. The top of the scaffolding will have a railing, toe plate
and ladder for access. Scaffolding tag will be fixed and signed by competent person
“Safe to Use” on completion.
13. Alignment:
Alignment will be done by the Supervisor to check elevations and the verticality of the
columns and related steel work.
22. Demobilization:
The existing site store and office will be shifted from site and the site will be cleared and
handed over to the Client. Loading will be carried out using Forklift or Crane as
necessary with full safety precautions.
METHOD STATEMENT – PEB ERECTION WORKS 5