Method Statement PEB

The document provides a method statement for pre-engineered building erection works. It outlines preparations needed like site cleaning and utility availability. Equipment for lifting and erecting frames like cranes and forklifts will be mobilized. Detailed safety procedures are described for each step of unloading materials, erecting columns, beams and roof/wall cladding. Proper bracing and alignment checks are specified to ensure structural integrity during construction.

Uploaded by

osmanhmdy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
168 views5 pages

Method Statement PEB

The document provides a method statement for pre-engineered building erection works. It outlines preparations needed like site cleaning and utility availability. Equipment for lifting and erecting frames like cranes and forklifts will be mobilized. Detailed safety procedures are described for each step of unloading materials, erecting columns, beams and roof/wall cladding. Proper bracing and alignment checks are specified to ensure structural integrity during construction.

Uploaded by

osmanhmdy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

METHOD STATEMENT – PEB ERECTION WORKS

Pre-Engineered Building Erection Page 1 of 5

A) Job Site Preparation:

The following points to be prepared and completed prior to starting the erection works.
1. Job Site to be cleaned, leveled and ready.
2. Determine the Storage Location
3. Maneuvering room for equipment
4. Utilities to be available
5. Ground slab to be concreted, cleared and leveled for moving scaffolding during
erection works.

B) Mobilization:

The following facilities to be made available to the project site area.


1. Porta-Cabin as site offices
2. Generator
3. Erection Tools
4. Forklifts and Cranes

C) List of Erection Equipment & Tools:

C1. Lifting Equipment ( Ropes and Lines )


1. Mobile Telescopic Crane
2. 3 ton Forklift
3. Steel guy lines or temporary bracings
4. Manila ropes for hand lines
5. “Come-along”, “Tirfors” or Turnbuckles

C2. Electrical Equipment


1. Generator
2. Extension Leads and pigtails
3. Heavy Duty Drills
4. Heavy Duty Screw Gun with Hex sockets
5. Electric Nibbler and Electric Shear
6. Angle Grinder
7. Concrete Drill

METHOD STATEMENT – PEB ERECTION WORKS 1


METHOD STATEMENT – PEB ERECTION WORKS
Pre-Engineered Building Erection Page 2 of 5

C3. Hand Tools


1. Socket Wrench %” or 1” drive with assistant socket
2. Open ended wrenches, assorted imperial sizes
3. Spud Wrenches, 15/16” opening up to 1-1/8”
4. Crescent Wrench – 12”
5. Pipe Wrench
6. Screw Drivers – Standard and Philips
7. Aviation Snip – Left & Right
8. Pop rivet puller
9. Vice Grips
10. 4 lbs. Sledge hammer
11. Hacksaw Frame and Blades
12. Wood Saw
13. Spirit Level and plumb-bob
14. Chalk Line
15. Steel Measuring tapes 6M and 30M
16. Utility knife
17. Staple Applicators
18. Cold Chisel
19. Hard Hats
20. Safety Belts with bolt bags
21. Broom
22. Masonry drill bits 12mm
23. Extension Ladders
24. Step Ladders
25. Hilti Gun, cartridges and nails

D) Material Delivery, Unloading and Material Layout

All the materials will be transported in Trailers and unloaded by forklift or crane as suitable.
Each truck or trailer will be accompanied with detailed packing lists of its contents. The
inspection forms will be reviewed and acknowledge

Notes:
The above items “A” to “D” are guidelines for Typical Pre- Engineered Building
Erection Works as applicable depending on the Job Complexity

METHOD STATEMENT – PEB ERECTION WORKS 2


METHOD STATEMENT – PEB ERECTION WORKS
Pre-Engineered Building Erection Page 3 of 5

• Brief Erection Procedures:


1. Erection work will be carried out starting with the braced bay. Temporary bracing (guy
steel wires) used.
2. Frame columns to be installed and anchor bolts to be tightened to prevent columns from
rocking.
3. Sidewall girts between columns and permanent bracings to be installed.
4. Rafter pieces will be assembled on the ground and will be lift by one or two cranes
according to rafter span.
5. After completing the first bay, make plumb, alignment and squaring, same procedure to
continue erecting columns and rafters, with fixing minimum quarter of purlins before
releasing rigs from rafters.
6. After erecting all columns and rafters, girts, sag rods and bracings be completed, the
building to be checked in plumbness prior to start of sheeting works.

• Sheeting Works:
1. Wall: Sheeting to start at the most viewed direction so that the sheet overlaps are not
visible.
2. Check for correct starting dimension as per erection drawings.
3. Check panel vertical. Repeat the vertical check as each panel is erected.
4. Roof: Sheeting to start by placing the first roof sheet to the given dimension for the
overhang at the eave.
5. String Line to be used as a guide for keeping the tail line of the sheeting straight.
6. Start at eave and work up the roof towards the ridge from both sides of the building.
7. The ridge sheet to be placed last.
8. Ensure that the end lap mastic is placed correctly without gaps.

• Trims and Accessories:


1. Trims and Accessories will be installed according to erection drawings and
manufacturer’s instructions.

• Final Check:
After completing all trims and accessories, a final inspection of the building to be made:
1. All bracings in position and tightened.
2. All bolts in place and high strength bolts tightened to correct tension.
3. Check that roof is clear of debris and ferrous metals.
4. Check mis-drilled holes and ensure that the self-tapping screws is fixed back tightly in
place.
5. Touch-up any damaged paint.
6. Clean up the site.
7. Hand over the building.

METHOD STATEMENT – PEB ERECTION WORKS 3


METHOD STATEMENT – PEB ERECTION WORKS
Pre-Engineered Building Erection Page 4 of 5
DETAILED DESCRIPTION OF EACH INDIVIDUAL ACTIVITY OF ERECTION WITH
PROPER WORK PROCEDURE AND NECESSARY PRECAUTIONS TO BE FOLLOWED
ARE LISTED BELOW:

1. Signing of Work Permits:


The work will start only after the required work permits are obtained from Permit Issuing
Authority.

2. Chipping of Concrete Pedestal for Fixing Shims ( Bearing Plates ):


Chipping will be done at top of the concrete pedestal by using chipping hammer.
Bearing Plates will be fixed to the required level by the use grout under shim plate
around. The worker will wear safety goggles during this activity.
This Activity to be done if necessary.

3. Unloading of Materials:
Unloading of Materials will be done by Forklift or Crane with trained approved riggers
and the lifting gear used will be condition having color codes painted on them as per
Client’s requirement.

4. Opening of Wooden Boxes / Crates:


Wooden boxes, Crates or Packages will be opened in a safe manner using the correct
tools and experienced people wearing all PPE.

5. Segregation of Materials:
The Foreman, Supervisor will do segregation of materials after reading the required
erection drawings, so as to have easy access to the required material in sequence with
the erection required.

6. Inspection of Anchor Bolts:


The Anchor Bolts will be checked by the Supervisor so as to confirm that it is as per the
drawing and the work can be proceeded.

7. Scaffoldings:
The erection of scaffoldings will be done under competent supervision. All scaffolders
will wear the required PPE, such as gloves, safety shoes, helmet and safety harness
during their scaffolding activities. The top of the scaffolding will have a railing, toe plate
and ladder for access. Scaffolding tag will be fixed and signed by competent person
“Safe to Use” on completion.

8. Shifting and Erecting of Required Columns to Site:


Shifting of columns will be done to work site by Forklift so that the assembly can be done
for erection of frames.

9. Shifting and Erecting of Required Rafters to Site:


Rafters will be shifted to site for assembly and will be assembled in such a place that it
can be easily lifted and there is access for the crane. Two cranes will do erection of the
rafters if the length is more than 25 meters. Signaling will be given to the crane operator
by one qualified Rigger at the time of erection. Warning tape will be tied around the work
site so as to barricade the erection area so that no unwanted people trespass the
erection area. After erection of the rafters it is required to tie the rafters with guy wires to
the ground for stability so that the crane can be released.

10. Shifting and Erecting of Required Beams to Site:


Interconnecting beams (if available) will be fixed from the column to column or rafter to
rafter so as to make a cubical in order that it can stand by itself without support.
METHOD STATEMENT – PEB ERECTION WORKS 4
METHOD STATEMENT – PEB ERECTION WORKS
Pre-Engineered Building Erection Page 5 of 5
11. Erecting of Purlins:
Two erectors will do the erection of purlins. Crane will keep a bundle of purlins on the
rafter so that one purlin at a time can be taken for fixing. All people working on heights
will be wearing life harness for their safety.

12. Erection of Horizontal Bracings:


Horizontal Bracings will be done in a similar way as purlin erection.

13. Alignment:
Alignment will be done by the Supervisor to check elevations and the verticality of the
columns and related steel work.

14. Erection of Girts:


Erection of Girts will be done by using telescopic Forklift or Crane as per height and bolt
tightening will be done by using man-lift, basket or scaffolding to have complete safety
for the erectors.

15. Erection of Vertical Bracings:


Erection of vertical bracings will be done in a similar way of girt erection.

16. Fixing of Roof Cladding:


A particular quantity of sheets will be lifted and kept on top of the purlins. Fixing of
sheets will be done one at a time and the remaining sheets will be firmly tied to the
purlins or the structure by rope so it would not fly if there is sudden wind. Each person
will wear safety harness and it will be tied to a steel cable fixed to the steel rigid frame
along ridge of the building.

17. Fixing of Wall Cladding:


Side Wall and End Wall Cladding will be installed using certified scaffolding or movable
type. Scaffolding floor level will be 750mm from the eave line or the wall splice joints.
Each person will wear the required PPE for their safety.

18. Fixing of Trims and Flashings:


Trims and Flashings will also be fixed using pop riveting guns and as per the erection
drawings.

19. Fixing of Gutters:


Fixing of Gutters and other finishing materials will be fixed with full safety to the working
people.

20. Inspection & Final Check:


Punch List or Check Advice will be submitted to the Client at the stages required to
satisfy the Client’s requirements as to complete the job in the very best manner and
quality. After completing all trims and accessories, a final inspection of the building will
be made as described before.

21. Final Acceptance and House Keeping:


Upon completion of all works and fully inspected we will obtain Final Acceptance. The
work site will be cleared of all the non-required and excess materials and as per Client’s
and Safety Department’s requirements.

22. Demobilization:
The existing site store and office will be shifted from site and the site will be cleared and
handed over to the Client. Loading will be carried out using Forklift or Crane as
necessary with full safety precautions.
METHOD STATEMENT – PEB ERECTION WORKS 5