A Comprehensive Assessment of Markets For Frequency and Voltage Control Ancillary Services
A Comprehensive Assessment of Markets For Frequency and Voltage Control Ancillary Services
A Comprehensive Assessment of Markets For Frequency and Voltage Control Ancillary Services
D octor o f Philosophy
2008
Yann Rebours
uest
ProQuest 13841598
ProQuest LLC.
789 East Eisenhower Parkway
P.O. Box 1346
Ann Arbor, Ml 4 8 1 0 6 - 1346
CONTENTS
C ontents 3
L ist of tables 9
L ist of figures 11
A bstract 17
D eclaration 19
Copyright 21
A bbreviations an d acronym s 25
Symbols 33
C hapter 1 In troduction 43
1.2 Stakeholders 46
1.3 Marketplaces 49
1.3.1 Basic features of a marketplace 49
1.3.2 Generation markets 51
3
4 CONTENTS
1.7 Summary 81
2.1 Introduction 83
References 251
Publications 287
The au th o r 289
Appendices 291
A .l BasicsofStatisti.es 291
A. 1.1 Univariate data 291
A. 1.2 Bivariate data 294
8 CONTENTS
Index 315
Table 1.2: Possible generation variation as a function of unit type. Based on UCTE (2004b)78
Table 2.4: Vocabulary used to name frequency control reserves in various systems 102
Table 2.5: Frequency deviation for which the entire primary frequency reseive is deployed
as a function of the droop and the primary frequency control reserve 104
Table 2.9: Technical comparison of voltage control parameters in various systems 113
Table 2.10: Recommendations for secondary reseive in some systems within the UCTE 121
Table 3.1: Daily management of frequency control reserves provided by EDF Producer 153
Table 4.2: Procurement methods chosen across various systems as of October 2006 196
Table 4.3: Structures of payment chosen across various systems as of October 2006 201
Table 4.7: Parameters of the demand in the considered examples of market coordination212
Table 4.8: Parameters of the offers in the considered examples of market coordination 212
Table 4.9: Result of the clearing processes in the examples of market coordination 212
Table 4.10: Settiement rules chosen across various systems as of October 2006 216
Table 4.11: Frequencies of market clearing across various systems as of October 2006 217
Table 4.12: Frequencies of reviews of the needs across various systems as of October 2006218
Table 4.13: Price caps across various systems as of October 2006 222
■
LIST OF FIGURES
Figure 1.1: Distinction between ancillary and system sendees. Based on Eurelectric (2000)44
Figure 1.5: Dynamic and quasi-steady-state frequency deviations. Based on UCTE (2004b)57
Figure 1.9: Configuration of the zone 0 with the loss of a generating unit 64
Figure 1.12: Temporal representation of the three instantaneous powers (inductive dipole) 67
Figure 1.13: Representation of the powers in the complex plane (inductive dipole) 68
11
12 LIST OF FIGURES
Figure 1.16: Typical P-Q diagram from the stator side. Based on Testud (1991) 73
Figure 1.18: Reactive power consumption of a 400 kV / 2 000 MVA line as a function of
the phase current 76
Figure 2.2: The three functional frequency controls considering a generating unit 95
Figure 2.3: Frequency and French regulation signal on 31 March 2005 [Tesseron (2008)] 96
Figure 2.4: The three functional voltage controls considering a generating unit 99
Figure 2.5: Representation of responses of an AS provider for two different inputs 115
Figure 2.7: Proposed standardised definition of quality of afrequency or voltage control AS117
Figure 2.8: Representation of the actual response of the group versus its estimate 117
Figure 2.11: Probability density o f the necessary frequency control power 124
Figure 2.12: Empirical and normal cumulative distribution functions of the activated tertiary
control power in 2006 in France 126
Figure 2.17: Frequency control reserve indicators in 2004-5 across systems surveyed 135
Figure 2.18: Direct control by the reserve receiving TSO [UCTE (2005)] 139
Figure 2.19: Control through the reseive connecting TSO [UCTE (2005)] 139
Figure 3.1: Representation of two over-sized elements because of voltage control 145
Figure 3.2: Schematic dispatches to understand de-optimisation and opportunity costs 148
Figure 3.3: Overview of the optimisation process at EDF Producer [based on Ernu (2007)] 151
Figure 3.4: The two datasets considered to calculate the de-optimisation cost 155
Figure 3.7: Frequency distributions of the gap between A POGEE dispatch and APOGEE
demand for all the studied time steps between 1 and 48 164
Figure 3.8: Evolution of the relative de-optimisation cost from 01/01/2005 to 30/08/2007166
Figure 3.9: Frequency distribution of the relative de-optimisation cost for all the studied
days 167
Figure 3.10: Frequency distribution of the variation of de-optimisation cost over two days
for all the studied days 168
Figure 3.11: Autocorrelation function of the de-optimisation cost up to 1-year period 169
Figure 3.12: Partial autocorrelation function of the de-optimisation cost up to 1-year periodl70
Figure 3.13: Partial autocorrelation function of the de-optimisation cost around a 3-month
period 170
Figure 3.14: Partial autocorrelation function of the de-optimisation cost around a 1-month
period 170
Figure 3.15: Partial autocorrelation function of the de-optimisation cost around a 1-week
period 171
14 LIST OF FIGURES
Figure 3.21: Normalized de-optimisation cost as a function of the mean normalized primary
reserve demand for all the studied days (r - 0.38) 175
Figure 3.23: Normalized de-optimisation cost as a function of the minimum reserve share
provided by thermal units for all the studied days (rXT= 0.44) 176
Figure 3.24: Relative de-optimisation cost as a function of the new demand for reserve for
24/05/2007 178
Figure 3.25: Simplified relative de-optimisation cost as a function of the new demand for
reserve for 24/05/2007 179
Figure 3.26: Percentage of time when marginal costs of energy are higher than marginal
costs of reserves as a function of the time step for all the studied days 180
Figure 3.27: Percentage of time when marginal costs of primary reserve are higher than
marginal costs of secondary reserve as a function of the time step for all the studied
days 180
Figure 3.28: Percentage of time when marginal costs of reserves are null as a function of the
time of the day for all the studied time steps 181
LIST OF FIGURES 15
Figure 3.29: Frequency distribution of the relative de-optimisation cost due to time control
with f = 49.99 Hz for all the studied days from 01 /01 /2005 183
Figure 3.30: Frequency distribution of the relative de-optimisation cost due totime control
f — 50.01 Hz for all the studied days from 01/01/2005 183
Figure 4.2: NYISO’s demand curve for secondary frequency control. Data based on
NYISO (2008) 193
Figure 4.3: Same utilisation payments for two different utilisations 199
Figure 4.4: Representation of the generic frequency control ancillary sendee trapezium used
in Australia. Based on NEMMCO (2001) 201
Figure 4.5: Reactive power capability curve in Great Britain [National Grid (2008c)] 202
Figure 4.6: Illustration of a gaming possibility with a real-time reactive power market 217
Figure 4.8: Effect of an offer cap (a) and a purchase cap (b) 221
Figure 4.9: Four intensities of an incentive scheme [Keller and Franken (2006)] 232
Figure 4.10: Ancillary sendees cost indicators across systems s u n n e d in 2004-5 235
Figure A.2.4: Entity relation modelling of the main tables of OTESS 302
Figure A.2.5: Modification and import of datasets with OTESS (operations 2 and 6 in
section A.2.2) 308
Figure A.2.6: Management of data in the database (operation 7 in section A.2.2) 308
16 LIST OF FIGURES
Figure A.2.7: Creation of new data in the database (operation 7 in section A.2.2) 309
Figure A.2.8: Basic calculation on the data (operation 7 in section A.2.2) 309
Figure A.2.9: Display of a graph with OTESS (operation 7 in section A.2.2) 310
Figure A.2.10: Analysis of data with OTESS (operation 7 in section A.2.2) 310
ABSTRACT
All users o f an electrical pow er system expect that the frequency and voltages
are maintained within acceptable boundaries at all times. Some participants,
mainly generating units, provide the necessary frequency and voltage control
sendees, called ancillary services. Since these participants are entitled to receive
a payment for the sendees provided, markets for ancillary sendees have been
developed along with the liberalisation o f electricity markets. However, current
arrangements vary widely from a power system to another.
17
DECLARATION
No portion of the work referred to in this thesis has been submitted in support of an
application for another degree or qualification of this or any other university or other
institute of learning. ■
19
20 DECLARATION
COPYRIGHT
The author of the thesis (including any appendices and/or schedules to this thesis) owns
any copyright in it (die “Copyright”) and s/he has given The University of Manchester the
right to use such Copyright for any administrative, promotional, educational and/or
teaching purposes.
Copies of tliis thesis, either in full or in extracts, may be made only in accordance
with the regulations of die John Rylands University Library of Manchester. Details of these
regulations may be obtained from the Librarian. This page must form part of any such
copies made.
The ownership of any patents, designs, trade marks and any and all other intellectual
property rights except for the Copyright (the “Intellectual Property Rights”) and any
reproductions of copyright works, for example graphs and tables (“Reproductions”), which
may be described in this thesis, may not be owned by the author and may be owned by
third parties. Such Intellectual Property Rights and Reproductions cannot and must not be
made available for use without the prior written permission of the owner(s) of the relevant
Intellectual Property Rights and/or Reproductions.
21
22 COPYRIGHT
ACKNOWLEDGEMENT
First, I would like to sincerely thank Pr Daniel Kirschen, who was really an amazing
supervisor during these three years. He took the time to discuss and read, had great ideas,
made numerous useful comments, showed an open-mindedness and was not bothered by
my French accent.
I would also like to thank the people at Electricite de France (EDF) that make this
PhD happens, and in particular the persons that got closely involved with this work:
Etienne Monnot, Bruno Prestat, Sebastien Rossignol and Marc Trotignon. Moreover, I
address particular thanks to Duane Robinson who helped me to find this thesis. Lastly, I
would like to thank EDF for its funding over the three years. However, the Hews expressed
in this work are not necessarily those of EDF.
This thesis, though meaning some lonely hard time, matured in an environment
both nice and studious. I thus would like to address many thanks to all the fellows from the
University of Manchester that helped me enjoy this thesis, and in particular: Chandra for his
knowledge of the Curry Mile; Jerry for his pertinent philosophical thoughts; Miguel for his
daily quotes from The Simpsons; Ricardo for his enthusiasm to visit the U.K.; Sky for the
badminton games; and Vera for the walks in the Peak District. Many thanks also to all my
colleagues from EDF, and especially the colourful R12 group, who constantly showed
support, suggested ideas and had good cheer. I would like to thank in particular: Sebastien,
my first Jedi master; Etienne, who made me run and was constantly of good counsel; Bruno
and Mehana, for their support over these three years; Marc, who spent hours reading and
discussing the ideas laid in this thesis and others; Stefan, who has always good ideas,
especially at Miami Beach or in a squash court; Frederic, who has unfailingly interesting
discussions that pop, from Into the Wild to the amount of wind blowing in Corsica; Jean-
23
24 ACKNOWLEDGEMENT
Pierre, with whom we tried to solve the world’s problems (we are still working on it); and
Jerome for his explanations about APO G EE clearer than those about squash.
As it is not possible to find all the information in books, papers or on the Internet, a
part of the information given in this thesis come from discussions with various people, in
particular: Richard Benejean and Jean-Michel Tesseron for historical procedures on
frequency control; Jean-Louis Bousquet for transmission lines; Alain Chollois for contracts
between landlords and wind producers; Renaud Crinon and Jean-Paul Echivard for the
regulation of a nuclear power plant; Arnaud Fauchille for time control; Christian Launay
and Romuald Texier-Pauton for ED F’s operational process to dispatch generating units;
Virginie Pignon for various subjects in economics; Alain Tanguy for high-voltage
transformers; Luc Tran for the behaviour of French hydro units; and Francois Bouffard and
Julian Barquin for their numerous useful comments on the final draft of this thesis. The
surveys of the various systems have been possible only with the kind participations of
Jurgen Apfelbeck, Christer Back, Noel Janssens, Ton Kokkelink, Thomas Meister, Luis
Rouco, Ilya Usov and Raymond Vice.
Lastly, I would like to express my thanks to my family and my friends who provide
me constant support over these three years and who even got the curiosity to read some of
this work. I wish that you keep drying your hair every morning thinking about frequency
and voltage controls.
AS Ancillary Sendee
AU Australia
BDEW Btmdesverband der Energie- und Wassemnrtschaft e. V (Federal association for the
energy and water management) (Germany)
BE Belgium
CAL California
25
26 ABBREVIATIONS AND ACRONYMS
Cl Cost Indicator
Cigre Cornell International des Grands RJseaux Electriques (International Council on Large
Electric Systems)
CNSE Comision Nacional del Sistema Electrico (National Commission of the Electrical
System) (Spain)
C 02 Carbon dioxide
DC Direct Current
DE Germany
DG Distributed Generation
DGEMP Direction Generale de I'Energie et des Matieres Premieres (General Direction of Energy
and Raw Materials) (France)
DIDEM E Direction de la DEmande et des Marches Energetiques (Direction of the Demand and
Energy Markets) (France)
DO Distribution Owner
DP Dynamic Programming
ES Spain
FQ First Quartile
FR France
GB Great Britain
or Gigabyte
I Intentional
or Integral
INSTN Imtitut National des Sciences et Techniques Nucleaires (National Institute of Nuclear
Science and Techniques) (France)
LP Linear Programming
MB Megabyte
MO Market Operator
NI Non Intentional
NL The Netherlands
No rec. N o recommendation
NZ New Zealand
OTC Over-The-Counter
OTESS OiiTilpour PEtiide des Scrviccs Systbm (Tool for the study of ancillary services)
P Proportional
PI Proportional Integral
RI Reserve Indicator
SE Sweden
SO System Operator
SS System Service
T Total
TO Transmission Owner
TQ Third Quartile
VCG Vickrey-Clarke-Groves
C capacitance (in F)
Statin h-optimisaim, relative de-optimisation cost due to frequency control of the day D (no
unit)
33
34 SYMBOLS
^without „Jt™ dispatch cost while not providing reserves during the day D (in €)
x %oj wi/hi mm* dispatch cost with the demand for reserves equals to X % of the initial
C I^S cost indicator for a given ancillary service for zone ^ (no unit)
deviation between the empirical F*(x) and the modelled F(x) series, used in
the Kolmogorov test
f'K the nominal frequency of the power system set in the controller of generating
unit i (in Hz)
SYMBOLS 35
H hour
i current (in A)
k electrical node
' m u w vp titm estimate of the internal consumption of the zone ^ (in MW)
Pmaxtenmmhtion estimate of the maximal internal consumption of the zone ^ (in MW)
electrical active power consumed and produced before the perturbation (in W)
P'demand demand for power generation for the time step i (in MW)
P'dispatch power generation dispatched during the time step i (in MW)
PG
!O active power set-point of the generating unit i without any frequency control (in
WO
P.C
tnfercotmecltou active power exported by the zone ^ to the power system (in W)
p~inttmmtrtion0 scheduled active power exported by the zone \ to the power system (in W)
P5
intercomiecliontn measured value of the total power exchanged by the zone with other zones,
where a positive value represents exports (in W)
maxgeneration estimate of the peak generation for the zone y; for the day (in MW)
Pz
Penallyp penalty due to the power mismatch for the time step i (in €)
Penalty^ penalty due to the primary frequency control reserve mismatch for the time
step i (in €)
Penalty^ penalty due to the secondary frequency control reserve mismatch for the time
step i (in €)
j2 maximum of the instantaneous reactive power or simply the reactive power (in
var)
Q.pqd reactive power flowing through the point of delivery (in var)
R resistance (in Q)
^P"'demand demand for primary frequency control reserve for the time step i (in MW)
Ppddjspal(h primary frequency control reserve dispatched during the time step i (in MW)
dispanhth frequency control reserve dispatched on thermal units during the time
Psc'demand demand for secondary frequency control reserve for the time step i (in MW)
Psc'dispatch secondary frequency control reserve dispatched during the time step i (in MW)
PsJdispatchth secondary frequency control reserve dispatched on thermal units during the
R IP reserve indicator for the primary frequency control reserve of the zone y (in %)
R /y reserve indicator for the secondary frequency control reserve of the zone ^ (in
%)
Shajf base apparent power for a given per-unit representation (in VA)
t time (in s)
Vk root mean square voltage from the ground to theelectrical node k (in V)
window the width of the extrapolation (an odd integer larger or equal to three)
Z impedance (in Q)
(no unit)
APG change in the active power set-point of the generating unit i for any frequency
deviation (in W)
deviation (in W)
(in WO
APfotemnmrfiian change in the power transfer between the zone and the other interconnected
power systems (in WO
constraint)
X'R weighted marginal cost of reserves for the time step i (in (€/MW0/h)
42 SYMBOLS
Xp marginal cost of primary frequency control reserves for the time step i (in
(€/MW)/h)
Xk marginal cost of secondary frequency control reserves for the time step i (in
(€/MW)/h)
A frequency characteristic o f the power system for a given frequency deviation (in
W /Hz)
t delay (in s)
A have access to a system that meets a certain standard of quality. In particular, this
user expects that the frequency and voltage will stay close to their nominal values because
most electrical appliances are designed for a particular frequency and a given voltage.
Failure to meet these frequency and voltage standards would lead to losses for the users that
may range from a burnt bulb to the loss of production in an expensive process (e.g., in an
automobile factory). Efficient frequency and voltage controls are thus essential to maintain
a high welfare for all power system users.
The frequency and voltage control services are called system services (SS) because they
are delivered by the power system to all the users. Some users of the system, such as
generators, contribute to these system sendees by acting on the frequency of the system or
the voltage at the point where they are connected to the system. Because these sendees
A Comprehensive Assessment of Marketsfor Frequency and Voltage Control A n d lla y Services, Yaiin Reborns, 2008 43
44 CHAPTER 1 INTRODUCTION
provided by users are ancillary to the production or consumption of energy, they are called
ancillary services (AS). This distinction between system and ancillary services is depicted in
Figure 1.1.
Power system
System services
Ancillary services (e.g., frequency and
voltage controls)
Some users
The other users
>.g., generators)
Figure 1.1: D istin ctio n b etw een ancillary and system services. B a sed on Eurelectric (2000)
Ancillary services have been provided by users of the power system since its early
days, more than one hundred years ago. However, it is only since the recent liberalization of
the electricity sector that ancillary services have been treated as a commodity by themselves.
Indeed, the reform of the electricity sector has led to a separation between network and
generation activities (see section 1.2). Markets for ancillary services resulting from this
separation have been developed independently across countries, depending on the previous
historical procedures or market architecture. Markets for ancillary services are thus currently
very different across systems. In addition, while ancillary services are commodities that
differ in many ways from the electrical energy product, efforts in the liberalization process
were concentrated on the main product, i.e. electrical energy and its transmission.
Therefore, the theoretical framework is much less advanced for ancillary services than it is
for energy and transmission markets. Lastly, the structure of power systems is currently
evolving fast, driven by high energy prices, aging infrastructures, increasing environmental
constraints, an intensified competition and the appearance of new technologies. For
example, new generation technologies are developed, interconnections between countries
are used closer to their limit and consumers are getting more active. Hence, markets for
ancillary services have to be adapted to this evolving structure.
In summary, markets for ancillary services are disparate across countries; they lack
from a consistent theoretical framework; and they have to be constantly adapted to the
changing structure of power systems. It is thus essential to assess current markets for
ancillary services to avoid inappropriate architectures that would lead to inefficiencies and
thus a reduced global welfare. However, stakeholders do not have a general and systematic
1.1 INCREASING WELFARE OF POWER SYSTEM USERS 45
tool that would help them assess the current markets for ancillary sendees and thus improve
current practices. Therefore, tills thesis proposes to fill this gap by providing the tools to
perform a comprehensive assessment of markets for ancillary services along three aspects:
the technical definition of ancillary sendees, the cost of provision and the market design.
This thesis is organised in five chapters. Chapter 1 presents the basic layout, the
stakeholders and the marketplaces of a power system. The basic concepts underlying
frequency and voltage controls are then introduced. Even if this thesis is focused on the
ancillary sendees provided by conventional large generating units, most o f the concepts are
applicable to any provider of ancillary sendees as well. The explanations are intended to be
suitable for all readers irrespective of their technical background. In particular, the concept
of reactive power is explained. Nevertheless, readers familiar with frequency control will
notice that the new concepts of average and instantaneous frequency characteristics are
defined. Lastly, technologies providing ancillary sendees are presented.
46 CHAPTER 1 INTRODUCTION
Chapter 2 focuses on the delivery of ancillary services. First, the needs of users in
terms of system services are examined. To meet these needs, ancillary services have to be
provided by some users of the system. Therefore, the specification of the quality o f ancillary
services is discussed. Lastly, the optimal quantity and location of the ancillary services are
debated. In particular, Chapter 2 shows that the amount of ancillary services currently
provided does not correspond to the actual needs of users in terms of system services.
Chapter 3 describes the main costs incurred by the provision of ancillary services by
a producer. A practical methodology to evaluate the cost of frequency control due to the
day-ahead capacity reservation is then proposed and successfully applied to Electricite de
France (EDF) Producer’s portfolio. In particular, this study gives interesting insights on the
parameters affecting the cost of frequency control. Lastly, the cost of the time control (i.e.,
the cost to maintain the frequency average at 50 Hz) is assessed for France.
1.2 S ta k eh o ld er s
Broadly speaking, the elements of a power system are physically divided into three main
categories: generating units, the network and loads. The network, which provides the
electrical link between loads and generating units, is actually divided into two main parts
(see Figure 1.2). The transmission network is meshed and operated at high voltages (e.g., 63 kV
to 400 kV in France), while the distribution network is usually operated in a radial fashion and
at lower voltages (e.g., 400 V to 20 kV in France). Networks are mainly constituted of lines,
1.2 STAKEHOLDERS 47
transformers1 and various controllers. Conventional large generation (e.g., coal, nuclear, large
hydro, gas or fuel) are connected to the transmission network, while smaller generation
(e.g., wind, small hydro, combined heat-power plant or photovoltaic) tend to be connected
to the distribution network, which led to the term of distributed generation (DG) to designate
this kind of generating units. Lastiy, consumers withdraw energy from the system, either at the
transmission level (large consumers) or at the distribution level (small consumers).
The various elements of a power system are owned by different parties. Prior to
liberalisation, most of them were owned by vertically-integrated companies, which owned at
the same time generation, transmission, distribution and retail. Currently, the ownership of
these activities tends to be separated. Large generating units are owned by generation
companies, which most of the time finds then roots in the historical vertically-integrated
companies. The transmission network is owned by a few entities (Transmission Owners, TO,
or transmission companies), whereas distribution networks are usually owned by many entities
(Distribution Owners, DO, or distribution companies), such as the city councils in France. Lastly,
end users are obviously owned by a large number of stakeholders. Therefore, end users are
usually gathered in consumer associations to get a more powerful representation. In addition,
they deal with retailers (or suppliers), which buy large volumes of energy from generation
companies and is in relation with the intermediate stakeholders, such as distribution and
transmission operators. In certain cases, retailers can also buy the electricity produced by
the end users who own generating assets. Note that retailers generally do not own
significant physical assets, except intelligent meters in some cases.
1 A transform er allows to converts energy from a given voltage to another level with the help o f two
windings around a magnetic circuit. T he first w inding brings pow er into the magnetic circuit, while the second
winding withdraws pow er from it. A difference in the num ber o f turns for each winding leads to a voltage
change, bu t w ith a similar pow er transm itted. N ote that Figure 1.2 did n o t explicitly display any transform ers.
48 CHAPTER 1 INTRODUCTION
The competitive sectors of the electricity industry, i.e. generation and retail, need
marketplaces to trade products (see next section). The Market Operators (MO) are in charge
of these marketplaces. In addition, other participants may provide additional services in the
marketplace, such as the brokers, who help bring buyers and sellers together.
Frequency and voltage controls involve all the stakeholders described above.
Indeed, generation companies, system operators and end users modify the frequency and
voltages through their actions, as explained in Chapters 1 and 2. In addition, the market
operators, the regulator and the legislator design the rules used to manage frequency and
voltage controls, as shown in Chapters 2 and 4.
1.3 MARKETPLACES 49
Transmission
network
Large
consumer
—v Centralized
generation
Small ^
consumer
Distribution
network Distributed
generation
In order to facilitate exchanges of products between stakeholders and to send signals to all
the participants, markets have been developed along with the liberalization. Section 1.3.1
presents the basic features of a marketplace, while sections 1.3.2 to 1.3.5 introduce the main
marketplaces that one is likely to find in the electrical industry.
The goal of a marketplace is to bring a buyer and a seller together, so they can exchange a
given good at an agreed price. If the delivery of the good is instantaneous (e.g., when one
buys some Camembert cheese at a favourite daily shop), or if the good cannot be resold by
the buyer before the delivery (e.g., when one buys a Norman wardrobe to be delivered to
the buyer die next day), the market is called a spot market. Otherwise, the quality of die good
has to be described, as well as the date of delivery and the price to be paid at delivery. Such
a market where commodities are traded for delivery in the future is named futures (or
sometimes forward) market. In practice, there are several futures markets, which deal with a
particular product (e.g., 1-year or 6-month delivery). Obviously, the products of the 1-year
futures market can be traded 6 month later in the 6-month futures market. Futures markets
50 CHAPTER 1 INTRODUCTION
are useful to participants to hedge against risk associated with the volatility of the spot
prices.
To trade these products (spot or future), the marketplace can be organised in two
ways. A centralised market is cleared by a unique entity that collects the offers to sell (supply
curve) and the bids to buy (demand curve). A unique price 7t* is seen by both buyers and
sellers, and a quantity q* is traded. This price and this quantity correspond to the point
where supply and demand match (see Figure 1.3). Note that it can be easily proven that the
price 71* is equal to the marginal cost of the producer2 providing the last offer (considering a
perfecdy competitive market3). On the other hand, in a decentralised market, sellers and buyers
can enter directly into contracts to buy and sell (sometimes without knowing each other’s
identity). The transaction is thus bilateral. In such a market, there is no "official price”, but
there may be mechanisms that allow all the participants to be informed of either the price
of the last trade or a weighted average of recent transactions.
The participants can also decide not to meet in a public marketplace, but to agree
on a bilateral contract outside any organised structure. This kind of transaction, which Is very
popular in the electricity industry to manage long-term contracts, is called over-the-counter
(OTC)4. Such transactions are usually facilitated by brokers. If the bilateral contract is firm,
it is called a fonvard contract. On the other hand, if the delivery is optional, it is called an
option. Several types of options are possible: European (a unique date of delivery), American
(which can be exercised once before a given date), swing (which can be exercised several
2 T he marginal cost is the cost to provide an additional good in the delivery (one M W h in the case o f
an energy market).
3 A perfect competitive m arket is a m arket w here no participant uses its dom inant position to distort
the signals sent by the market to participants.
4 O n die down side, O T C contracts cannot guarantee the pro d u ct provision, whereas the m arket
operator has the provision liability in an organised market.
1.3 MARKETPLACES 51
times, but there is a limit in terms of energy), Asian (which is a variant of European: the
average price of the good is taken instead of the spot price) or Bermuda (which can be
exercised at some given dates). Kluge (2006) describes in depth methods to price options in
electricity markets.
Both organised and OTC markets lead to an equilibrium, i.e. a set of operations by
stakeholders that equals supply and demand. This equilibrium can be either Pareto efficient,
i.e. it is impossible to increase the benefit of a party without decreasing the benefit of the
others, or qualified as a Nash equilibrium, i.e. in which no participant has interest to change
its position. Note that a Pareto equilibrium takes into account potential cooperative
behaviours by stakeholders, whereas a Nash equilibrium is obtained only with the help of
unilateral decisions. Therefore, a Nash equilibrium is often not Pareto efficient.
price
Demand
Tf
Supply
quantity
Figure 1.3: Market equilibrium
companies need to find buyers for their products over a long period to reduce risks. In
particular, sufficient revenues are essential for generation companies to invest and thus to
maintain sufficient capacity in the long-run5. Therefore, long-term markets are essential in
generation markets. In practice, the generation companies secure their investment with
long-term OTC bilateral contracts or vertical integration. However, futures markets in
electricity are deemed to provide unreliable signals. In fact, the price of futures tends to be
constant whatever is the delivery date (e.g., 1-year, 2-year or 3-year delivery) [e.g.,
Powernext (2008)], whereas the price of electricity is likely to increase in the future.
Therefore, long-term generation markets are still an issue in electricity markets.
Once the generating units have been built and most of the power traded in an OTC
manner, generation companies and the buyers of their products enter in the short-term
futures markets (i.e., one-month or shorter) to balance their positions. Finally, the market
closest to real-time is the spot market. This spot market can be organised either with a
centralised (pool) or a decentralised (exchange) unit commitment, as discussed in
section 4.6.1. If the delivery delay of the spot market is too long (e.g., more than
15 minutes), an additional market is necessary to balance the positions of the participants.
This additional market is called the balancing mechanism (or balancing market). This kind of
market is more restrictive than the day-ahead market6 in order to avoid the exercise of
market power by some participants (e.g., prices cannot be changed easily) and is usually
operated by the system operator.
Markets for ancillary services, which are described in depth in Chapter 4, are part of
the generation markets. In particular, markets for ancillary services and for energy are tightly
linked, since a generation company can make the choice to allocate one MW of production
capacity as an ancillary service or as energy.
For further information on generation markets, see for example Wilson (2002),
Kirschen and Strbac (2004a), Baldick et al. (2005) or Joskow (2006). D G EM P/D ID EM E
(2003) provides reference prices for generating plants, as well as their building time.
5 Building sufficient generating capacity in the long-term is p art o f the pow er system adequacy issue
described in section 2.2.1.
Since the transmission network has a cost, participants have to pay for the right to
use it. To charge users, Transmission System Operators rely on two methods. First, they
can charge the users with an ex-ante price, i.e. the users know in advance the price that they
are going to pay for their transmission use. A typical example of an ex-ante price is the
postage stamp, for which the users pay a transmission fee that does not depend on die
location of the energy generation or consumption. This tariff is designed to recover the cost
of transmission expansion and operation, but the signals sent to participants may be too
weak to foster an optimal use of the transmission network (e.g., to encourage the
construction of new generation plants in a congested area). On the other hand, an ex-post
price is possible. Such a price is calculated after (and not prior) the actual use of the
network. To allow hedging, some ex-post price estimates are given to the participants. E x
post prices are often used for competitive procurements of the available transmission
capacity. However, the actual implementation of such competitive procurements is still
under debate. A popular approach in USA is to link transmission and generation markets by
defining energy prices at each node of the system. Such prices are called Locational
Marginal Prices (LMP) and are precisely computed ex-post. The differences between the
LMPs then provide an income to the owner of the line between the two nodes. Such nodal
energy markets are completed with financial instruments that allow a party to hedge against
price differences between two nodes of the network (the Financial Transmission Rights, or
FTR). Quintana and Bautista (2006) give a short and comprehensible introduction to this
topic.
7 H ow ever, the actual construction o f the lines may be done by entities under com petition (the
Transm ission Owners).
54 CHAPTER 1 INTRODUCTION
In the same manner as generation markets, transmission markets involve both short
and long terms. Therefore, the network charges should allow the transmission owners to
raise enough money to develop the network, in addition to give short-term signals to
optimally use the available transmission capacity and to charge the users fairly. But because
generation and transmission investments are linked it may be difficult to reflect the optimal
allocation between generation companies and transmission owners.
For further reading, Kirschen and Strbac (2004a) provide a good introduction to the
issues and solutions of transmission markets. Pignon (2003) analyses the transmission tariffs
in Europe, while Rious (2007) discusses the coordination between generation and
transmission investments in a deregulated environment.
The idea of a retail market is to allow all end-users to freely choose their supplier of
electricity. Retail markets are deemed to improve services and prices offered to the end
users. However, competition in retail markets is currently quite limited [e.g., see CRE (2008)
for France]. In addition, retail markets are not complete. Indeed, end users sign only long
term OTC contracts with their supplier because of the technical limitations. It is thus not
possible for a user to swap from one supplier to another in real-time, as it would be the case
in a prefect decentralised market.
The markets described previously are directly linked to the generation, transmission and
consumption of electricity. However, these markets rely on other commodities. First, they
are sensitive to the various fuel markets (e.g., coal, gas or nuclear). Second, they are also
impacted by the environment markets that price the pollution, such as the nitrogen oxides
(NOx) and the carbon dioxide (CO^, or guarantee the renewable provenance of electricity
(the so-called green certificates in Europe). Lastly, the cost of generating units may be
impacted by the prices of other commodities, in particular raw materials such as steel or
copper.
1.4 FUNDAMENTALS OF FREQUENCY CONTROL 55
/ =
P © (1.1)
2 2%
As shown in Figure 1.4, the electrical power provided by a generating unit comes
from the alternator. The mechanical rotation of the rotor creates a rotating magnetic field,
which is then converted into an alternative current in the stator. The rotor is driven by the
prime mover, which can use different types of fluids such as steam, water or wind. The
mechanical power PMprovided to the prime mover creates a torque Tm on the shaft (the
mechanical torque). On the other hand, the electrical power Pf delivered by the generator
creates an opposite torque Tt on the rotor (the electrical torque). If these two torques equal
each other, the rotor’s speed will not change. However, if the mechanical torque is larger
than the electrical torque, the rotor will accelerate. Conversely, if Tm is lower than T,, the
alternator will slow down. This relation can be easily modelled mathematically with the so-
called swing equation given in (1.2), where J is the total moment of inertia of the rotor
masses (in kg.m2), cl? the rotor acceleration (in rad.s"2) and Pt the power lost in the
process (in W) [Grainger and Stevenson (1994)].
8 A synchronous zone is an area interconnected through alternative current. In transient state, the
frequency actually varies slightly from one part o f the network to another, especially in a large interconnected
netw ork. A n illustration with the N o rth A merican network is given by Z h o n g et at (2005), while K undur
(1994) describes the theoretical fundamentals.
9 A pow er system is like a tandem , on which all the cyclists have to pedal at the same speed to
transm it power.
56 CHAPTER 1 INTRODUCTION
Electrical power
Mains
Mechanical power
(steam, water, wind...)
1—\pm )
r*
y
Rotor
-V Prime mover
\i
Stator Te
L ?
Lost power Alternator = rotor + stator
d~co
Jo>.— r = P * - P - P < (1.2)
at
Equation (1.2) is very important for dynamic studies since it shows the behaviour of
a particular unit in response to mechanical or electrical power changes. From the generating
unit’s perspective, Pr is imposed by the network, as it is equal to the difference between the
consumption and generation of active power at the terminals of the generator10. If the
electrical power drawn by the power system decreases (i.e., if P, decreases), the electrical
machine will start accelerating. In addition, all the generating units across the system will
also accelerate, according to the same reasoning11. Therefore, the mechanical power injected
into the machines has to be reduced to slow down the rotors. Conversely, if the electrical
power drawn by the system increases (i.e., if Pe increases), the generating units will slow
down and the mechanical power will have to be increased to maintain the same speed.
In conclusion, the active power injected in or withdrawn from the power system
affects the frequency of the system. By adapting the mechanical power provided to
generating units, the rotor speed (and thus the electrical frequency) can be controlled.
Similarly, the frequency can also be controlled by adapting the consumption of electricity by
the loads.
,0 Obviously, the active pow er provided by the generator is n o t included in this difference.
11 This reasoning is true if the netw ork capacity is sufficient. Otherw ise, pow er oscillations can
appear, i.e. som e generating units can accelerate while others are slowing down.
1.4 FUNDAMENTALS OF FREQUENCY CONTROL 57
frequency
target
frequency quasi-steady-state
frequency deviation dynamic frequency
deviation
time
To make explicit this relation between load and frequency, let us consider a stable
power system state, in which the same amount of active power P0 is consumed and
produced at the nominal frequency f r A quasi-steady-sate frequency deviation A f from the
nominal frequency f (i.e., usually 50 Hz or 60 Hz) will lead to a consumption change
U P „ ,p,„„ according to the Equation (1.4).
At = / „ - / , (1-3)
12 A pow er system never reaches a steady state because various param eters are always fluctuating. F o r
example, the frequency usually comes back to its target value after a perturbation w ith the help o f various
controls (see C hapter 2).
58 CHAPTER 1 INTRODUCTION
where /jlf is the quasi-steady-state electrical frequency of the power system (in Hz); and D,
positive and expressed in % /H z, is called self-regulation of the load. It depends on the structure
of the power system, in particular on the number and the types of loads on-line. The term
“self-regulation” is used because this effect tends to be naturally opposed to frequency
variations. However, it is usually not sufficient to compensate imbalances without a large
quasi-steady-state frequency deviation since the value of this parameter is usually between 1
or 2 % /H z [UCTE (2004b)].
performed by a simple feedback loop (see Figure 1.6) with an adjustable parameter 1/ sGi
where s'G is called the droop of the generating unit i (in per-unit and positive). The relation
between the power set-point of the generating unit, the droop and the frequency deviation
is given in (1.5) [UCTE (2004b)]. Therefore, the lower the droop, the stronger is the
generating unit’s response. This Equation can be compared to (1.4) concerning the self
regulation of load.
AJ fw f - fJ n‘
J m
=
AP' P c -P L
1 Git 1 Gn (L5)
p i= -—LT xPLxAf:
In X JG
where APG is the change in the power set-point of the generating unit i for any measured
frequency deviation t f m
’ (e.g., dynamic or quasi-steady state), P G
‘ tt the generating unit’s
nominal output power, PG0 the power set-point without any frequency control and f ’n the
nominal frequency of the power system registered in the generating unit’s controller. Note
that die negative sign can be sometimes omitted to define the droop sG, which thus leads to
Nr.
A Pgeneration = 2 > 4
£=1
f Ng
v -nk
<;,xaa//,A
(1.6)
'^-J J„ v A
\k=i G J
AP.generation AT
V^=i sc J
The droop is individual to each generator and is generally set at around similar
values in order to avoid the non-linearities that can appear if generating units reach their
maximal outputs for different frequency deviations13. In practice, droops range between 4
and 20 % (see section 2.3.4.2), which lead to very different responses.
Change in
power set- Measured
point AP g Speed frequency fn
T ransducer
controller
Electrical Mechanical
power set- + power Pm
Process
Speed co,
point P g o - Prime mover
controller + Alternator * Electrical
power Pe
13 The non-linearities can be spotted easily w ith the concept o f instantaneous frequency characteristic
developed in section 1.4.6.
60 CHAPTER 1 INTRODUCTION
AP + AP.consumption APgeneration = 0
<=> AP - APgeneration - APconsumption (1.7)
( T}k \
Gn
<=> AP
E
\k=\ sg y
x ^ j — D x P Qx A f
Jn
AP
(t8)
o x ii+ 7 - Z %
Jn k^l SG
The number N G and the droops sG of the generating units providing speed control
actually vary over time, as well as the self-regulation D. However, for a given imbalance AP
(i.e., for a few tens of minutes), these parameters can be assumed to be constant. In
addition, the nominal powers PG and the nominal frequency^, are also constant, so the
In addition to the automatic actions of the generating units (i.e., speed control) and loads
(i.e., self-regulation), the entity responsible for the power system (i.e., the system operator)
can take several additional actions to restore frequency:
Therefore, in the same manner as for (1.9), but considering any actions that can be
taken as a function of frequency, a simple linear relation can be assumed between the power
imbalance AP (a positive value indicates an excess in consumption) and the quasi-steady
state frequency deviation Af.
(1.10)
A/
where A(A/"), positive and expressed in MW/Hz, is the frequency characteristic of the power
systemfor the quasi-steady statefrequency deviation A/r[UCTE (2004b)].
The definition of the frequency characteristic described above does not show the
regulating capacity actually available for a frequency different from /). To fill this gap, it is
proposed to introduce the concept of instantaneous frequency characteristic X, defined for an
elementary quasi-steady-state variation of the frequency d f as in (1.11). The partial
derivation is used since the active power consumed or generated in the system can vary
along with other parameters such as voltage. The frequency characteristic for a given
perturbation A, which represents the average of the instantaneous frequency characteristic,
can then be easily calculated through an appropriate integration, as shown in (1.12).
canmmptwa^fqss ) generation^\-fqrs)
(1.12)
14 N etw ork assets are considered here as consum ers o f active pow er (e.g., see section 1.5.4 for the
consum ption o f a line).
62 CHAPTER 1 INTRODUCTION
Figure 1.7 shows the interest of this new definition. First, the instantaneous
frequency characteristic A. of the regulating devices can be easily calculated. Therefore, the
frequency characteristic A(A^) can be conveniendy deduced for any frequency deviation.
Second, the contributions of the different regulating devices are clear in the top graph (e.g.,
the participation of a particular generator becomes recognisable), whereas it is much more
difficult to identify them in the bottom graph. Last, non-linear behaviours of the system are
spotted easily (e.g., in this case, the system does not react anymore to frequency changes
beyond a certain point).
” ^ disconnection of loads
0 A f (Hz)
Figure 1.7: E xam ple o f in stantaneous and average frequency characteristics o f a pow er system
other zones
consumpUOi
interconnection
/generation
zone z
In the case of a quasi-steady-state frequency deviation Af, the generation and the
consumption of the zone is affected, because of the Equation (1.10), as expressed in (1.13).
In other words, a frequency change leads to a deviation from the scheduled power transfer
between the zone ^ and its neighbouring zones.
Then, let us suppose that die zone 0 loses generating unit 1 that produces (see
Figure 1.9).
64 CHAPTER 1 INTRODUCTION
other zones
consumptioi
■' © ©
© ©.
generation interconnection
zone 0
Following this loss, the frequency of the whole power system starts to decrease (see
section 1.4.1). Therefore, each zone starts to increase its exchange according to
Equation (1.13). For all the zones except zone 0, the change in generation AP*„eratio„ is only
O n the other hand, zone 0 has the following exchange deviation because both P^ and
The algebraic sum of all the exchanges at the various interconnections is zero because all
the exchanges are considered twice: once positive and once negative, which leads to:
= 0 (1.16)
Therefore:
This section introduces the main principles and definitions that are necessary to understand
voltage control. In particular, the concept of reactive power is explained in section 1.5.1.
u(t)
— H h-------
m
F igure 1.10; A dipole (receipting convention)
U) “ 27tX / (1.18)
15 A passive dipole is an electrical elem ent w ith two nodes and w ithout any internal energy source.
16 T h e current quantifies the debit o f electrons and the voltage the electrical pressure that is exerted
on the electrons.
17 A lag o f 30° is equivalent to 7 1 /6 radians. As the current lags the voltage in this case, the dipole is
said to be inductive.
66 CHAPTER 1 INTRODUCTION
P(t)
i(t)
u(t)
t(s)
F igure 1.11: T em poral representation o f voltage, current and in stan tan eou s pow er (inductive dipole)
Figure 1.11 shows that the absorbed powerp(t) is sometimes negative (i.e., when u(t)
and i(t) have opposite signs), which means that the dipole provides power during this time.
Since the dipole does not have any internal source of energy, it has to sometimes withdraw
more energy from the source before giving it back later on. This storage/release can be
mathematically isolated in two components as follows [Bastard (1998)]:
S p jt), called instantaneous reactive power, is null on average and represents the alternation
between the storage and release of energy by the dipole;
S pr(t% called instantaneous active power, is always positive and represents the power actually
used by the dipole.
Equations from (1.22) to (1.26) give the mathematical expressions for p jt) and p r(t), where P
is die average of the instantaneous active power (or simply the active power) and Q the
maximum of die instantaneous reactive power (or simply the reactive power). Note that cos (p
is usually called power factor and noted pf. Figure 1.12 shows the temporal representation
of the three instantaneous powers for the same dipole as considered in Figure 1.11.
P = UI cos cp
P(t)
pr(t)
px(t)
Us)
F igure 1.12: T em p oral representation o f the three in stan tan eou s pow ers (inductive dipole)
Temporal representations are not very easy to handle because the sine and cosine
functions lead to complex calculations when added or multiplied. A practical manner to
handle sinusoidal values is to transform them into the complex plane, where the sinusoidal
values can be seen as vectors that are rotating in this plane. Equation (1.27) shows the
transformation used in this example, while Equation (1.28) gives the result of this
transformation for the three instantaneous powers, where P, O and S are complex values. S
is called the apparent power because it is related to the instantaneous power, i.e. the physical
power used by the dipole. Equation (1.29) expresses the link between instantaneous powers
and their complex representations. Equation (1.30) shows the simple link between the three
powers. Lastly, Figure 1.13 shows the representation of the three powers in the complex
plane. The projection of these vectors on the real axis gives the instantaneous physical
values, because of Equation (1.29). Note that the power vectors are rotating in a clock-wise
68 CHAPTER 1 INTRODUCTION
manner at twice the angular frequency CO18, whereas the voltage and the current rotate
\(B~)
A e f t +; B e W ; X = Asm(B)\-^X = A e 2 = ^ [s in (B )- jc o s ( j3 )] (1.27)
p = p e i(-2w/-71)
jf-2u>/— 1
2) a - 28)
S = P + £ = S e l(?
A ( / ) = P + Re(p)
'pA =M g) (1-29)
p(t) = P + Re(S)
S 2 = P2 + Q 2 (1.30)
lm f
P(t) Re
F igure 1.13: R epresentation o f the pow ers in the co m p lex plan e (inductive d ip ole)
18 T he alternating com ponent o f active pow er that can be seen in a tw o-phase system creates
vibrations in a rotating machine. H ow ever, in an equilibrated three-phase system, the sum o f the three pow er
vectors leads to a constant power, as the three alternating com ponents are cancelled.
1.5 FUNDAMENTALS OF VOLTAGE CONTROL 69
19 T h e reactance X is die imaginary p art o f the impedance Z, H ere, X is equal to _Loj, w here L is the
physical characteristic o f the elem ent and is called the inductance (see section 1.5.4).
20 A single dipole is equivalent to a three-phase electrical elem ent by considering drat the diree
phases are equilibrated and that the single dipole represents one phase. T herefore, the three-phase pow er is
equal to drree times the single-phase power.
21 See section 1.5.1 for a short explanation on the phasor representation o f electrical values. See for
example G rainger and Stevenson (1994) for tire link between voltage and current.
70 CHAPTER 1 INTRODUCTION
F igure 1.15: P hasor representation a sso cia ted w ith F igure 1.14
where:
V =
vt+v2
(1.32)
A V = V j- V 2
(1.33)
Therefore, supposing that J /, is constant (e.g., with the help o f a controlling device such as
a generating unit), any change in the consumption of the reactive power by the end terminal
will result in a voltage drop. Therefore, by controlling the consumption of reactive power
Q_2i the voltage 1V2 can be maintained at this terminal. In other words, by maintaining
voltage and current in phase (and thus limiting the reactive power consumed by the line),
voltage drops/rises can be limited in the transmission network. This direct link between
voltage and reactive power is less strong for distribution networks because the ratio X /R is
lower (see section 1.5.4), so the term RP2 is not negligible anymore, and both active and
reactive power consumption have to be controlled to maintain voltage.
As shown in Figure 1.4, the mechanical power Pm of a generating unit is converted into
electrical power Pt through the alternator. The rotor of an alternator is equivalent to a large
rotating magnet. This rotating magnetic field then induces an alternative voltage (the internal
voltage) in die windings of the stator. The latter are connected to the system through the
mains, and provide the stator voltage. The internal voltage is proportional to the amplitude of
die magnetic flux. Therefore, the voltage at the stator of the transformer is controlled by
adjusting the magnetic field of the rotor, which is itself regulated by the field current
flowing in the windings of the rotor (the exciter current) [Grainger and Stevenson (1994)].
In practice, the Automatic Voltage Regulator (AVR) controls the exciter current to
maintain the stator voltage at the given value. The exact configuration and tuning of such
system varies from one technology to another and relies on die local condition of the
machine. In addition, the AVR can include a Power System Stabilizer (PSS). A PSS takes
into account die speed or the active power of die machine to act on the exciter current.
Kundur (1994) provides much detail on the configurations and tuning of AVR and PSS.
To understand the link between the stator voltage and the reactive power
produced/absorbed by the generating units, Figure 1.14 and Figure 1.15 can be used.
Figure 1.14 is an equivalent of a stator, where X and R represent the impedance of the
stator; V , the internal voltage; V2 the stator voltage; I the stator current (i.e. the current
flowing out of the terminals of the generator). Note that the internal voltage L) is physically
created along the whole stator windings. Therefore, die proposed model is only an
equivalent, in which die internal voltage source and die impedance are separated (a
Thevenin model). The stator voltage V2 always lags the internal voltage V, in generator
mode. However, the stator voltage can either lag or lead the stator current I. If the
generator is over-excited, the stator current I lags the stator voltage V 2 and the generator
delivers reactive power (as represented In Figure 1.15). In this case, die system consumes
72 CHAPTER 1 INTRODUCTION
reactive power in this case because Q 2 positive24. On the other hand, if the generator is
under-excited, the stator current leads the stator voltage, the generator absorbs reactive
power and the system provides reactive power (Q2 < 0) [Grainger and Stevenson (1994)].
Most of the time, a generating unit controls the voltage (and thus the reactive power
produced or consumed by the generator) at its stator. However, the system operator may
ask the operator of the generating unit to express its reactive power capability at the Point
of Delivery (POD) instead of the stator. The POD is the point owned by the generator that
is the electrically closest to the network (see Figure 3.1). As rule-of-thumb, at the nominal
apparent power Sn of the generating unit, the reactive power absorbed by the auxiliaries26,
the step-up transformer27, and the transmission line up to the POD is usually around 15%
of T,,28. Therefore, the reactive power Qp0D supplied by the generator to the network can be
estimated using Equation (1.34).
a P0 D * Q 2- 0,15xJ„
20 T he auxiliaries are all the elem ents that a pow er plant needs to run, such as pum ps, controllers o r
light.
27 T he nom inal stator voltage is generally lower (e.g., 20 kV) than th e nom inal voltage at the P O D
(e.g., 400 kV). T he producer thus needs to step-up the voltage through a transform er.
28 T he m ajor com ponent o f the 15 % is due to the im pedance o f the step-up transform er, w hich is
around 13 % (see note 74 p. 145).
1.5 FUNDAMENTALS OF VOLTAGE CONTROL 73
Limit imposed by
Limit imposed / ■'Ah ■opportunity cost: ■A copper losses
by the rotor / y m y be incurred
edge/
temperatui^ ©
Working zone
Limit imposed
by iron losses
0 Q (M) Q
Reactive consumption Reactive production
Figure 1.16: T yp ica l P -Q diagram from the stator side. B a sed on T estu d (1991)
29 Coo is called the smceptance o f the capacitance and is often denoted B, N o te that the reactance o f the
capacitance is equal to 1 /C o .
74 CHAPTER 1 INTRODUCTION
R jLa)
Li -2
■AAAr
2 _L 2 _L
jCco jCco ~ j~
T ab le 1.1: Characteristics o f a 50-H z transm ission lin e im p ed an ce for o n e ph ase. B a sed on Kundur
(1994) and E D F internal docu m en ts
U nderground
Voltage Aerial line
cable
(kV) R L Leo C Cw C Cw
Leo/R
(Jfi/km ) ( m il/ k m ) (a /k m ) (nF /k m ) (fiS /k m ) (n F /k m ) (n S /k m )
45 0.22 1.14 0.36 1.7 10.3 3.25 - -
I ,* W
(1.35)
V,xV2= V
1.5 FUNDAMENTALS OF VOLTAGE CONTROL 75
So the consumption of the line in active P and reactive Q powers is as follows, where R IZ
are the Joule losses; —B V 2 the reactive power provided by the capacitance; and X I 2 the
reactive power consumed by the inductance30 [Johannet (1997)]:
P = BJ2
(1-36)
q =x f - brx
Pj =P2+ RI~
(1.37)
IQ} =J22 + X X - B V ^
^= 3xJ
= 3 x TVx I
r t1-38)
= V 3xK to. f e x 3 x J _ lm.
= V x 400 000 x 3 x / .....
The reactive power consumption as a function of the current has been calculated
using (1.36) and Table 1.1, and is shown in Figure 1.18 for three 400 kV / 2 000 MVA lines
of different lengths, for which the base parameters32 are given in (1.39). Four remarks can
be drawn. First, a line can produce reactive power, which leads to a voltage difference
between the two terminals of the line (see section 1.5.2). In particular, the voltage rise at no
load is called the Ferranti effect. Second, it is clear that a long line requires more reactive
30 W hen the line is heavily loaded, die term —B V 2 becomes negligible in com parison to X I 2, which
leads to the simplified m odel o f section 1.5.2.
31 T he N - l criterion states that the loss o f an elem ent (e.g., a line) should n o t jeopardize the security
o f the system.
32 T he absolute value is found by multiplying the base value by the per-unit value.
76 CHAPTER 1 INTRODUCTION
support than a short line. Third, for any line length, the reactive power consumption is
always null for a given power, called the characteristic power, which corresponds to a
current It given by (1.40), where Zt is called the characteristic line impedance. Lastly, it is
important to note that an underground cable produces much more reactive than an aerial
line because of its high susceptance B (see Table 1.1). This high reactive power leads to
strong voltage rises that limit the length of underground cables.
0 .2 5 -
0 .2 0 - 2 0 0 km
0 . 15 -
1 5 0 km
0 .0 5 -
5 0 km
0.00-
- 0 .0 5 -
I (p.u.)
F igure 1.18: R eactive pow er co n su m p tio n o f a 400 kV / 2 000 M VA line as a fu n ction o f the p h ase
current
Vim = 400kV
.5^ = 2 000 MVA
V, 2
z #„ = - f ^ = 80Q (U9)
^ base
^ , = ^ l = 5000A
base
V
1 = (1.40)
z = (1.41)
transmitted P, (see section 1.5.1). This larger current causes more reactive power O to be
consumed in the line (see Figure 1.18). Therefore, the reactive power sent by one side of
the line is not fully transmitted to die other side. This phenomenon also appears for active
power, but to a lesser extent because the resistance is much lower than the reactance (see
Table 1.1). Therefore, it is not possible to transmit reactive power over long distances.
Contrary to frequency control, a voltage change in a particular area of a power system will
usually not be seen by the whole interconnected area because the impedance is getting very
high when the bus considered is far from the voltage drop. The mitigation of voltage drops
is however more complex than for frequency drops. Indeed, a voltage drop may be created
by a fault, such as a short circuit between a line and a tree. Injecting more reactive power is
useless in this case, as it would lead to very high current. Therefore, the fault needs to be
isolated first. Fault isolation is one of the areas that the power system protection discipline
covers. See for example Anderson (1999) for more details on the adopted strategies.
If the voltage is still low when all the faults have been cleared (i.e., considering a
quasi-steady state), more reactive power has to be injected as close as possible to the voltage
drop. This compensation is mainly done by using the capability of generating units, as
described in section 1.5.3. Other techniques can also be deployed and are described in the
following section. As there are hundreds of buses in the transmission network (and
thousands considering the distribution network), the voltage is actually controlled at key
points, which leads the other bus voltages to follow. The control of key points is described
in section 2.3.3.3.
This section provides an overview of the current technologies that can be used to control
frequency and voltage. For further details, Flirst and Kirby (1998) provide a comprehensive
comparison between most of the technologies mentioned in this section.
78 CHAPTER 1 INTRODUCTION
Thermal units, which are based on a temperature difference between a hot and a cold
source that makes a fluid flowing (usually steam, but also hot gas, for example in the
case of a gas turbine or a diesel generator). This family uses energy resources such as
coal, fuel, gas, nuclear or the Earth’s heat in the case of geothermal energy;
S Non-thermal units, which are based on the natural flow o f a fluid, such as wind or
water, or other technologies, such as photovoltaic electricity generation. This family is
getting more important, since they usually produce little greenhouse gas (e.g., C 0 2) over
their lifetime.
Generating units are technically limited in terms of frequency and voltage controls.
These limits are due in particular to the boiler output flow, to the lag induced by controllers,
to the thermal gradient that is bearable by the unit, to the inertia of the process, or to
environmental constraints (e.g., the maximum water level variation for a hydro unit).
Table 1.2 gives an idea of the possibilities of some typical generating units, where the
possible generation variation is expressed in percentage of the nominal output power of the
unit per minute. The difference between hydro and thermal units essentially comes from the
inertia and the thermal constraints of the boiler of the thermal units. The differences across
thermal generating units are due to the various complexities in changing the flow of
combustible in the process [Wood and Wollenberg (1996)].
T able 1.2: P ossib le gen eration variation as a fu n ction o f u n it type. B ased o n U C T E (2004b)
33 Coal is constituted betw een 75 and 91.5 % o f carbon, whereas lignite has betw een 50 and 60 % o f
carbon [Hoinkis and Lindner (2007)].
1.6 TECHNOLOGIES USED TO PROVIDE ANCILLARY SERVICES 79
To control the temperature of the boiler, most of the thermal generating units rely
on the variation of the energy flow. However, in the case of nuclear power plant, nuclear
material cannot be removed or added in operation. Therefore, nuclear generating units use
two principles, which have an impact on the possible variation of active power [Gautier
(1990)]:
V Change the boron concentration in the reactor core. This technique has a large time
constant (tens of minutes to change output by a few tens of percent);
V Use the control rods to regulate the neutron flow. Control rods can be either “black” or
“grey”. The former can only shut down the reactor, whereas the latter ones can tune
more precisely the reaction. The technology of “grey” control rods was developed
during the eighties. Therefore, only nuclear plants built after this period and that have
installed this system may modulate their active power relatively quickly. Power plants
with the regulating control rod can vary their power up to 5 % /min.
Second, because lines and transformers have a relative high inductance, they draw
large amounts of reactive power. In addition, the resistance of theses elements induces
active power losses (see section 1.5.4). Therefore, the impedance of the network can be
modified by taking transmission lines in or out of sendee. This method creates over
voltages, increases the chances of incident during the manoeuvre and is limited in
amplitude. In conclusion, the basic transmission and distribution assets are useful but have
a limited manoeuvrability by comparison with the generating units.
BO CHAPTER 1 INTRODUCTION
First, passive elements such as capacitances and inductances can be added to change
the reactive power consumption/production at different points of the network. They can
be switched on or off either manually or remotely. They are cheap and very helpful, but
create transients, can introduce resonance problems and their reactive power compensation
depends on the voltage.
Some power electronics can be added to these passive elements to increase their
capabilities. These devices belong to the large family of the Flexible Alternating Current
Transmission Systems (FACTS). Their cost is obviously higher than for passive elements, but
they allow a continuous regulation similar to generating units. Some FACTS are dedicated
to voltage control, such as Static var Compensators (SYCs), while others are intended for
flow control but can perform voltage control as well, such as Unified Power Flow
Controllers (UPFCs) [Hingorani and Gyugyi (2000)].
High-inertia rotating machines can be used as well. They can provide both high
quality reactive power control (they are said to work as synchronous compensator.s) and a short
term active power control through their inertia (they are said to work as energy storage devices).
They are usually expensive because o f their moving parts, and their capabilities in terms of
frequency control are limited. Therefore, the improvement in the storage of electricity may
help the development of new devices purpose-built to provide ancillary services.
1.6.4 Loads
The power system end-users are large consumers of ancillary services because their
consumption of active and reactive powers varies a lot over time. They can thus have a big
role to play to improve the control of frequency and voltages. However, their availability is
often not predictable, their rating is typically small (which increases management costs), and
their participation is most o f the time not continuous. However, the development of low-
cost information systems in parallel with high energy prices (because of more
environmental constraints and less available energy resources) may foster a more active
participation of loads in the future.
1.7 SUMMARY 81
- Vincent: You know what they call a Quarter Pounder with Cheese in Paris?
- Jules: They don't call it a Quarter Pounder with Cheese?
- Nah, man, they got the metric system. [...] Thy call it a "Royale with Cheese".
Pulp Fiction movie (1994)
2.1 Introduction
Chapter 1 has shown that users expect a certain standard for the frequency and voltages. In
addition, users can provide ancillary sendees to help maintain this standard. Therefore,
Chapter 2 assesses the delivery of ancillary sendees. First, section 2.2 makes explicit the
needs of users in terms of system sendees. Section 2.3 then introduces the various
specifications that define the different qualities of ancillary services that users can provide.
From the needs of the users and die available qualities of ancillary sendees, the quantity of
each AS quality can then be determined, as presented in section 2.4. Lastiy, section 2.5
discusses die issues related to the delivery location of ancillary sendees.
A Comprehensive Assessment of Marketsfor Frequency and Voltage ControlA nailmy Sendees, Yann Rebours, 2008 83
84 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
The needs of users can be expressed as appropriate reliability, power quality and power
system utilisation. System services, by controlling reactive and active power balances, help
to meet these three objectives. This section reviews these objectives and shows that they
may be contradictory. Therefore, a trade-off has to be found and the best objective function
depends on the system considered.
2.2.1 Reliability
The reliability of a power system is the probability that the system will be able to serve
consumers. Adequacy and security underlie the concept of reliability. An adequate system is a
system with sufficient facilities (e.g., transmission lines and generation) to satisfy the
consumers, while considering static conditions. A secure system is able to respond to
contingencies, i.e. considering dynamic conditions [Billinton and Allan (1996)]. Therefore,
day after day, the adequacy and the security of a power system constitute its reliability.
Obviously, system services are essential to maintain the security of the system (see
sections 1.4 and 1.5). But they also affect the adequacy decisions. First, enough capabilities
to provide reactive and active powers have to be built in the long-term in order to respond
to contingencies in the short-term (see section 4.3.1). Second, AS capabilities and
transmission capacity are linked (e.g., reactive support can increase transmission capacity
and transmission capacity can increase frequency control capabilities), so they have to be
coordinated. Therefore, system sendees deeply influence the reliability of power systems
from both security and adequacy aspects.
Even if reliability (and therefore security) is a quality and not a good, reliability can
be considered as a public good in economic language [Abbott (2001), Boucher et al. (2006)].
Indeed, the characteristics of a public good are (a) the impossibility (or high difficulty) to
exclude a consumer and (b) the inexistence of competition in the consumption: what one
consumes does not deprive another one [Varian (1999)]. Reliability fits this definition,
because separating the reliability of two users is very difficult, especially with more and
more interconnected systems, and because any user can enjoy the reliability of the power
system without depriving the others. Note that system services are not a perfect public
good since over-consumption by a participant may hamper the welfare of the others, in the
2.2 NEEDS OF USERS FOR SYSTEM SERVICES 85
same manner as the over-consumption of a freeway reduce the welfare of drivers because
they are travelling more slowly.
Unfortunately, users of a same power system have very different points of view on
what the reliability of die electric system, i.e. the level of public service, should be. To
consider a well-known example, a semi-conductor factory and a residential consumer do
not give the same value34 to a reliable source of electricity. In addition, reliability is at least
100 times more valuable to consumers than it is to generators [Kirschen (2002)]. The value
of security35 is even more complex to calculate than the value of reliability because the value
of security varies in real-time whereas reliability is defined over a given period. For example,
a residential consumer would value short-term security much more while watching the final
of the world cup on TV than while sleeping. Easdy, this problem increases with the size of
the synchronous network. For example, all the users of the synchronous continental
European network have to agree on consistent reliability criteria. Consequentiy, an
independent party has to define the appropriate level of security for the power system36.
This independent party may be eitiier the system operator or the regulator on behalf of the
consumers. Two approaches can be adopted to define the necessary level of security.
On the one hand, deterministic security criteria can be adopted, such as the famous N -l
criterion. According to tiiis criterion, the power system has to be able to continue operating
without a major component (e.g., a transmission line or a large generator). This criterion is
therefore binary (die system is declared as secure or not) [Kirschen (2002)] and relatively
easy to calculate. A flaw of this system is to considerer only a predefined set of
contingencies, and to ignore completely events with a low probability of occurrence.
Another flaw is to consider that all die events are statistically independent, whereas the
recent North American37 and European38 experiences show diat the increasing complexity
34 T he customer damage function gives the cost o f an outage for a given customer. F rom the custom er
damage functions, the Value O f L ost Load (VOLL), which is determ ined through surveys, expresses the value
that the average consum er places on being deprived o f one kW h w ithout w arning [Eariuki and Allan (1996),
Joskow and Tirole (2004)],
35 Practically, T he Expected Energy N o t Served (EENS) may be used to measure the security o f a
pow er system [Kirschen and Jayaweera (2007)]. N ote that the E E N S does n o t take into account the value o f
energy.
36 In any case, a pow er system is never totally secure [Kirschen (2002)]. H owever, it can have a
certain level o f security. This level o f security has then an im pact on the reliability o f the system,
37 T he N o rth -E ast o f the USA and the South-East o f Canada had a blackout on the 14* o f A ugust
2003 that affected around 50 millions people [U.S.-Canada Pow er System O utage T ask Force (2004)].
86 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
of the system multiplies dependencies [Kirschen and Strbac (2004b)]. In addition, for a
given operating point, the risk of outage (and so the value of security) relies heavily on the
weather conditions [Kirschen and Jayaweera (2007)]. Therefore, deterministic criteria of
security do not reflect the real level of security of the system, but are very practical in the
day-to-day operation of the system.
38 T he w hole Italy (around 60 millions people) was plunged in the dark on th e 28th Septem ber
2003 [UCTE (2004a)] and 15 millions E uropean households were disconnected during the incident o f the 4th
N ovem ber 2006 that originated in G erm any [UCTE (2007)].
2.2 NEEDS OF USERS FOR SYSTEM SERVICES 87
directly related to the security of the system. Hence, quality and security can be separated
only for a small set of quality parameters.
In conclusion, frequency and voltage controls impact the quality of power supply.
Therefore, the quality has to be included in the objective function for system sendees.
39 In particular, in interconnected systems, policies regarding the necessary system services m ust be
decided in coordination w ith the other systems, because the security o f the w hole interconnected pow er
system is at stake.
88 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
accurately is difficult and translating this definition into the specification of a quantity and
quality of system services is even more difficult, as will be shown in sections 2,3 and 2.4.
Third, system services, especially frequency control, are shared by all the areas of an
interconnected power system (see section 1.4). Therefore, all system operators within an
interconnected system should have coherent policies, which may be difficult if users have
contractory objectives. Last, the ideal objective function is difficult to implement.
A first objective function that can be adopted is the cost-effectiveness (also called
the rational-buyer) approach, which tries to minimise the procurement cost for an ex-ante SS
specification. Obviously, diis simple policy does not guarantee that a Pareto-efficient SS
specification is attained (see section 1.3.1). However, it is very easy to implement because
the procurement cost is usually better known than the value of system services.
On the other hand, the cost-benefit approach tries to maximize the global welfare, i.e.
the sum of the individual profits and surpluses. This situation is always Pareto-efficient in
theory [Kirschen and Strbac (2004a)]. However, determining the surpluses or the profits of
the participants depending on the system services can be quite complex, because users give
different values to security and these values are hard to define, as shown previously. In
addition, it often implies a probabilistic computation, which is computationally demanding
(e.g., the Monte-Carlo method) [Bhattacharya and Zhong (2001)].
In other words, the cost-effectiveness objective function only takes into account the
cost of system services, while the cost-benefit approach takes into account both the cost
and the value of system services. The latter objective function is the most desirable, but it is
also the least practical. Therefore, the optimisation problem is often solved by subdividing
the system into subsystems (e.g., transmission, energy, frequency control...), then by
optimising the necessary system services separately with a cost-benefit objective function,
and lastly by refining the needs to take into account the dependencies.
The first task required to fulfil the expectations of users in terms of system services is to
define the ancillary services that are able to meet the needs. As the definitions of AS differ
widely from the classical energy product by many ways, this section investigates how to
separate AS in different products according to various specifications (namely: optimal,
2.3 SPECIFICATION OF TH E QUALITY OF ANCILLARY SERVICES 89
elemental')', functional, actual and standardised) and therefore to be able to specify the
quality of ancillary services needed.
140 M ore generally, w hen getting closer to the real-time, the products are getting m ore and m ore
differenciated (e.g., base/peak, dien h o u r by hour, then 15 m in ...).
older wind farms cannot withstand voltage sags as severe as those that more recent ones
can withstand, because of the new rules that have been imposed.
Specifications
General Precise
Increase the number of providers for a given
+++ 4”
specification
Foster innovation +++ ++
Reduce transaction costs ++ +
Recognize the capabilities of providers + +++
Help understand the behaviour of providers + +++
The SO should specify the ancillary services needed for both the long and short
term. Regarding the long term, each power system has to define at the time of connection of
new users (i.e., as part o f the connecting conditions) the compulsory quality needed. A good
principle is to avoid scarcity for ancillary services to guarantee the adequacy of the system,
but without making the connection o f new participants unreasonably expensive (see
section 4.3.1). A good practice is probably to implement a basic requirement for every unit
and to allow the grouping of a few devices to provide the final required quality. In case of
compulsory provision, these connecting requirements should be remunerated in order to
have a transparent energy price and to avoid distortion of competition between two
producers that were connected at different times under different rules. Lastly, it may be
useful for developers to benefit from standard connecting requirements across several
systems, because this will reduce the cost of procuring standard devices (e.g. a standard
alternator for a given power). Note that since frequency is shared by all the participants,
frequency control ancillary services are more likely to benefit from standardised connection
rules than voltage control ancillary services.
In the short term, the SO has to define the global specification for the system (see
section 2.2.4). To fulfil this need, it can either require a standardised quality for each
provider, or the quality can be part of the provider’s offer. The choice will impact the
market design (see section 4.4.1). In practice, most systems define a standard quality that
any provider has to meet if it wants to provide the service considered (see section 2.3.4).
Such a practice limits the number of participants but eases the settlement. Some devices
could be grouped in order to achieve the requirement together (but without necessarily
2.3 SPECIFICATION OF TH E QUALITY OF ANCILLARY SERVICES 91
fulfilling the requirements alone). In other words, several devices could be considered as
one AS provider.
To maintain the frequency and voltages within their defined ranges and therefore to
keep the balances of active and reactive powers, devices with one or more of the four
following capabilities can be used:
>4 Devices that are able to control the active power and therefore mainly help control the
global frequency:
■ Up active power balancing, devices that increase the active power injection or decrease
the active power absorption;
■ Down active power balancing, devices that decrease the active power injection or
increase the active power absorption.
Y Devices that are able to control the reactive power and therefore mainly help control
local voltages:
■ Up reactive power balancing, devices that increase the reactive power injection or
decrease the reactive power absorption;
■ Down reactive power balancing, devices that decrease the reactive power injection or
increase the reactive power absorption.
Such devices basically consist of two main components. First, the available resource
(e.g., the headroom of a generator) and the different actuators (e.g., the exciter of a
generator) form the active part of the device that we will call capability of control. This
capability can be discrete (e.g., a capacitor bank) or continuous (e.g., a synchronous
condenser), which leads to different impacts on the stability of the system. Most of the
time, discrete capabilities of control are cheaper and simpler, but usually stress more the
system during switching (see section 1.6).
92 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
Controller
Main controller
device A ,
Controller
Controller Controller device B J Controller
device A , Controller device C , device C
device B J
(a) (b)
potentially provide ancillary sendees. The following sections improve these elementary
specifications.
2 . 3 . 3 . 1 F r e q u e n c y co n tr o l
Figure 2.2 provides a schematic representation of the three functional frequency controls
provided by a generating unit. Primaryfrequency control is a local automatic control that adjusts
the active power generation of the generating units and the consumption of controllable
loads to restore quickly the balance between load and generation and counteract frequency
variations. In particular, it is designed to stabilize the frequency following large generation
or load outages. It is thus indispensable for the stability of the power system. All the
generators that are located in a synchronous zone and are fitted with a speed governor
perform this control automatically (see section 1.4.4). The demand side also participates in
this control through the self-regulating effect of frequency-sensitive loads, such as induction
motors (see section 1.4.3), or the action of frequency-sensitive relays which disconnect
some loads at given frequency thresholds42. However, this demand-side contribution is not
always taken into account in the calculation o f the primary frequency control
response [UCTE (2004b)]. The provision of this primary control is subject to some
constraints. Some generating units that increase their output in response to a frequency
42 F o r small frequency thresholds, loads usually participate on a voluntary basis, as for example in
Australia JN EM M CO (2004)1- H owever, for large frequency excursions, the system operator has to perform
com pulsory load-shedding through a defined protection scheme [e.g., U C T E (2004b)]. Lastly, we can also
imagine systems in w hich additional loads are connected as a function o f frequency.
94 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
drop cannot sustain this response for an indefinite period of time. Their contribution must
therefore be replaced before it mns out.
Secondary frequency control is a centralised automatic control that adjusts the active
power production of the generating units to restore the frequency and the interchanges with
other systems to their target values following an imbalance [Jaleeli et al (1992)]. In other
words, while primary control limits and stops frequency excursions, secondary control
brings the frequency back to its target value. Only the generating units that are located in
the area where the imbalance originated should participate in this control, as it is the
responsibility of each area to maintain its load and generation in balance (see section 1.4.7).
Note that loads usually do not participate in secondary frequency control. Contrary to
primary frequency control, secondary frequency control is not indispensable. This control is
thus not implemented in some power systems where the frequency is regulated using only
automatic primary and manual tertiary control. However, secondary frequency control is
used in all large interconnected systems because manual control does not remove overloads
on the tie lines quickly enough. For example, Figure 2.3 shows the action of the French
secondary frequency control on a day. The regulation signal is comprised between —1 and 1,
and the deployed secondary frequency control power depends on the reserved capacity.
However, with the development of quartz- or GPS43-based devices, synchronous clocks are
now getting rare, though still used by some household appliances such as washing
machines [Bosch (2006)],
A certain amount of active power, usually called frequency control reserve^ is kept
available to perform these controls. The positive frequency control reserve designates the
active power reserve used to compensate for a drop in frequency (it is thus provided by
devices with up active power balancing capabilities, as described in section 2.3.2). On the
other hand, the deployment of negative frequency control reserve helps decrease the
frequency.
Primary control
(automatic)
= APL Governor
GO produced Interconnected
Generator
network
tertiary control
Secondary
Tertiary control controller
s e c o n d a r y control
(managed by TSO &
interconnection 0
generating unit)
Secondary control
(managed directly by TSO)
F igure 2.2: T h e three functional frequency controls con sid erin g a gen eratin g unit
43 GPS stands for Global Positioning System. This system is based on a netw ork o f satellites that
send inform ation to ground devices, such as the universal time or the position o f the device.
96 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
1200 iaoo
T*npt
Figure 2.3: Frequency and French regulation sign al on 31 M arch 2005 [T esseron (2008)]
2 .3 .3 .2 S p in n in g r e s e r v e
The term “spinning reserve” is very popular to designate some frequency control reserves.
In particular, many authors use this term without defining it because they assume that its
meaning is obvious and unambiguous. However, a partial survey of the literature produces
very different definitions:
Therefore, a definition which fits all systems would be helpful. First, it seems
essential to remove the idea of time, as each system has its particularities. Second, there is a
system operator in any system. Third, the term spinning reserve is used in the optimization
literature as a capacity that can be re-dispatched (scheduling objective), which can be
different from the operational capacity (stability objective). Fourth, it seems interesting to
get detached from the terms such as “generator” or “demand-side”, to reduce ambiguities.
The following definition is therefore proposed in this thesis: the spinning reserve is the unused
capacity which can be activated on decision of the system operator and which is provided by devices which are
synchronised to the network and able to affect the activepower.
^ If a generator decides not to provide reserve, its spare synchronized capacity is not
spinning reserve, as it cannot be activated by the system operator. However, in many
systems, generators have to offer all their spare synchronized capacity in the balancing
mechanism (see section 1.3.2). Therefore, in this case, the system operator has the
possibility to call upon all the synchronized capacity;
S A consumer can provide spinning reserve, if it agrees to be disconnected or to reduce
its load upon request from the SO. For example, pump loads are good candidates for
die provision of spinning reserve from the demand side.
2 . 3 . 3 . 3 V o l t a g e c o n tr o l
Figure 2.4 provides a schematic representation of the three functional voltage controls
provided by a generating unit. Primary voltage control is a local automatic control that
maintains the voltage at a given bus (at the stator terminals in the case of a generating unit)
at its set point. Automatic Voltage Regulators (AVRs) fulfil this task for generating units.
Other controllable devices, such as static voltage compensators, can also participate in this
primary control (see section 1.6).
Secondary voltage control is a centralised automatic control that coordinates the actions
of local regulators in order to manage the injection of reactive power within a regional
voltage zone. This uncommon technology is used in France and Italy [Paul et al (1990),
Corsi et al. (1995) and Vu et al (1996)].
Terliay voltage control refers to the manual optimisation of the reactive power flows
across the power system. This is performed by either modifying the set-point of pilot
voltages in case of a secondary control, or by directly modifying the voltage set-point of the
unit. Tertiary voltage control also includes the startup of additional units and the operation
of other means such as capacitor banks.
2.3 SPECIFICATION OF TH E QUALITY OF ANCILLARY SERVICES 99
Interconnected
p ro duced network
Voltage
representative
Q s e c o n d a r y + tertiary controls S econ d ary of the zone
controller
pilot w a n te d
s e c o n d a r y control setpoint
Secondary control
(managed by TSO) tertiary control
F igure 2.4: T h e three fu n ction al voltage controls con sid erin g a generating unit
Note that similar surveys have been performed by Eurelectric (2000), Cali et al
(2001), Arnott et al (2003) or Raineri et al (2006). However, the present sui'vey differs from
44 U C T E is the U nion for the C o-ordination o f Transm ission o f Electricity, which is the association
o f the T SO s operating w ithin the synchronous system o f mainland E urope. T he U C T E establishes the
security and reliability standards fo r this interconnected system.
these in terms o f the systems studied and the framework used to compare the features of
the ancillary services. In addition, the reader should keep in mind that specifications change
over time. Therefore, such a survey should be updated regularly to remain relevant.
2 .3 .4 .1 V o ca b u la ry
The profusion of terms used for ancillary services may lead to some misunderstandings and
confusion when one tries to compare services from different power systems or
jurisdictions. Table 2.4 classifies the services considered in the survey with the help of the
functional framework developed in section 2.3.3. The names are shown in the original
languages to avoid misinterpretation. In this table, for each type of control, the reserves are
ordered from the fastest (left) to the slowest (right). Reserves within a given column are
thus similar. Within a system, terms are classified from the most general (up) to the most
specific (down). A dashed line means that positive and negative reserves have different
names. For instance, in Great Britain, the terms “primary response” and “secondary
response” are used for the positive primary frequency control reserve and “high frequency
response” for the negative one. In some cases (e.g., Australia), the name of a service is used
as the corresponding reserve does not have a name.
A number of observations can be drawn from this Table. First, it is clear that care
must be taken when comparing services defined in different systems. For example, the
terms “secondary response” (GB), “secondary control reserve” (UCTE) and “secondary
2.3 SPECIFICATION OF THE QUALITY OF ANCILLARY SERVICES 101
reserve” (PJM) describe three completely different sendees. Even the term “reserve” may
lead to some misunderstandings. For example, in Australia, “reserve” designates
investments in generation capacity and not the frequency control reserves as defined in this
thesis. “Spinning reserve” is another example of an ill-defined term, as explained in
section 2.3.3.2.
Primary Secondary
frequency control frequency control Tertiary frequency control reserves
reserves reserves
Reserve
Frequency response Operating reserve
> 30 min
PJM Regulation Primary reserve Secondary reserve
Synchronised Quick start
reserve47 reserve
Frckvcnsstyrd
SE Normaldriftsrescrv and (does not exist) Seven different types of reserves
Stomingsreserv
47 In 2006, PJM changed the denom ination “spinning reserve” to “ synchronized reserve” .
48 G erm any recently rem oved Studenreserve and N otreserve from tertiary frequency control
reserves.
2.3 SPECIFICATION OF TH E QUALITY OF ANCILLARY SERVICES 103
2 . 3 . 4 . 2 P rim a r y f r e q u e n c y co n tr o l
Policy makers tend to specify various parameters that have a significant effect on primary
frequency control. The most important technical parameters for frequency-related ancillary
services are the deployment times. The maximum amount of time that can elapse between
the request from the TSO and the beginning of the response by the sendee provider will be
called the deployment start. Full availability is the maximum time that can elapse between the
moment when the provider receives the request and the moment at which it delivers its full
response. Lastly, deployment end is the maximum amount of time during which the service
must be provided starting from the time of the request.
The accuracy of the measurements is another important issue because it affects the
efficiency of the control and die payments to the providers. For example, if the
instrumentation at a generating unit overestimates the frequency, its response to frequency
deviations will be inadequate and the generating unit may be paid more than what it
deserves. However, it is generally in the interest of producers to measure accurately so they
can argue more persuasively with the TSO in case of a dispute.
The frequency deviation for which the entire primay frequency reserve has to be deployed is also
an important parameter. Indeed, using this information, the value of the droop and
Equation (1.5) of p. 58, one can calculate the maximal share of the nominal power output
that a generating unit must keep in reserve to provide the required primary frequency
control power. For example, Table 2.5 shows the frequency deviation for which the entire
primary frequency reserve is deployed as a function of the droop and the primary frequency
control reserve.
The frequency characteristic represents the total action of the primary frequency control
provided by generators and the self-regulating effect of the load (see section 1.4.6). In
104 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
North America, the terms of “Beta” or “frequency governing characteristic” are preferred
to designate this parameter [Ingleson and Ellis (2005)].
The insensitivity of a primary controller is the frequency band within which the
controller does not change its output. Two insensitivities should be distinguished: the non-
intentional insensitivity, which is intrinsic to the controller, and the intentional insensitivity,
which is added on purpose. In Europe, the non-intentional insensitivity is sometimes simply
called insensitivity while the intentional insensitivity is called dead band. The sum of these
two insensitivities gives the total insensitivity. If two generators have different total
insensitivities, it means that the one with the smallest insensitivity will participate to the
primary frequency control before and probably more frequently than the other one.
T ab le 2.5: F requency deviation for w h ich the entire primary frequency reserve is d ep loyed as a
fu n ction o f th e droop and the primary frequency control reserve
D roop s'G
__________________________ 4% 5.7 %
Reserve relative___ 2 %_____40 mHz 57 mHz____
to 7 % 140 mHz 200 mHz
Table 2.6 summarizes the primary frequency control parameters in nine different
systems'19. Since units providing primary frequency control must respond immediately to a
change in frequency, the “deployment start” does not appears in this Table.
Deployment times are the same all across the systems within the UCTE because it is
important to have a homogeneous response in the synchronous zone. On the other hand,
NERC does not make any recommendations on the value of this parameter. A faster
primary frequency control is used in Great Britain because the size of this system makes it
more susceptible to frequency variations.
49 T he following abbreviations are used: N o rec.: no recom m endation; Pri., Sec. or Hi.: primary,
secondary o r high frequency response; I: intentional; N I: non intentional; T: total.
2.3 SPECIFICATION OF TH E QUALITY OF ANCILLARY SERVICES 105
estimated from requirements in the tendering process for primary frequency control
sendee [National Grid (2008b)].
Within the UCTE, the fu ll deployment of the primmyfrequency reserve must occur before a
deviation of ± 200 mHz; has happened. Hence, TSOs with a tight requirement for the droop
(i.e., a small droop, such as in France) would need to reserve a large headroom for their
generating units if they want to provide their primary frequency control continuously until
+ 200 mHz. However, in practice, units with a small droop attain their maximum before the
limit of ± 200 mHz, so they do better than what the UCTE recommends. In Belgium and
Germany, no general condition is applied to the droop as this parameter is agreed between
the generators and the TSO during the procurement process (see Chapter 4). Lastly, the full
deployment of the British primary frequency reserve happens for larger deviations than in
the UCTE because the British power system has a smaller inertia.
Policies on controller insensitivity are similar in all systems, except in Great Britain,
where the requirement is less strict. NERC has recently changed its policy and no longer
recommends any insensitivity. Before, a total insensitivity of 36 mHz (30 mHz if a 50/60
coefficient is applied to account for the difference in nominal frequency) was
required [NERC (2004)], which is three times the UCTE’s requirement (10 mHz).
However, the UCTE’s requirement applies only to the controller [UCTE (2004b)], while
NERC former recommendation was for the “governor” [NERC (2004)]. This last term is
not formally defined, but is commonly understood to include both the primary frequency
controller and the actuators (e.g., jacks and valve). Therefore, in this table, the insensitivity
of the controller only and the insensitivity of the whole generator unit are not distinguished.
Finally, the accuracy ofthefrequency measurement is not addressed explicitly in most systems.
Table 2.6: Technical comparison of primary frequency control parameters in various system s 106
'
R eferences and energy (2008a), National
(2005), NERC (2006) TcnncT (2006) BDEW (2007b) department (2003), (2005), TcnncT (2006) department
department (1998) Grid (2008b)
l R TE (2004) (2002)
o
o
VI
•'d y
tn
VI
VI
ft. oo
T'S
2 ^ 2
VI VI VI
lft 1/1 V5
Pri.: > 30 s
Sec.: > 30 min
o
c
c
c
c
6
c
Al
c
Al
Vs
tn
m
in
Al
Al
Al
Al
m
in
U1
At
Deployment end
E
C
■E
■g
Mi.: as long as
required
o0
It
N
T
©
O
U
01
U
No rec, 20,570 MW/Hz
-T
N
~ 4,200 MW/Hz
N
characteristic ~ 600 MW/Hz
oOO
1 yearly peak = 2,000 MW/Hz
requirem ent demand/Hz
§
?
c
N
O
No rec.
-H
frequency No rec. No rec. No rec. No rec.
+ 5 mHZ ± 10 mHz ± 10 mHz
m easurem ent desirable
T: ± 10 mHz T: ± 10 mHz
T: ± 36 mHz in 2004;
-fl
NI: No rec. I: should be NI: No rec. I: should be NI: ± 10 mHz NI: No rec.
NT. No rec.
^ si
insensitivity
2 2 o
H ci «
+1
g& M g °^
+i ? +i V
I: No rec.
0 h-I
S o o +!
2iT)
^
1©
©
©
O
+l
to
iS
m
bi
2
0
2
u
-H
1
o
R
+i
©
©
o©
NI
01
CO to
>4 <
+1
N
± 200 mHz
fN
%
A
&
P. M E
S« £hL X
© ©O
1 E S
ai-> *j
h
© L©O
of:
1c
X
+l
©
©
O
O
iS
N
j®
ir>
2.3 SPECIFICATION OF TH E QUALITY OF ANCILLARY SERVICES 107
2 . 3 . 4 . 3 S e c o n d a r y f r e q u e n c y con trol
Secondary frequency control can actually be organized in three ways: centralised, pluralistic
and hierarchical [UCTE (2004b)]. In a centralised organisation, the control is performed by a
single controller for the whole control area. In a pluralistic organisation, the system is split into
independent zones, each of which having its own controller and regulating capacity. In a
hierarchical organisation, the organisation is similar to the pluralistic approach but a main
controller coordinates the action of all the other controllers.
The Area Control Error (ACE) of a zone g, which charaterises die imbalance of the
where is the measured value of the total power exchanged by the zone with
other zones (a positive value represents exports). Note that E>leminmthll w is slightly different
from the actual exchanges E>ttK0Himlhii because of measurement errors. f z is the measured
network frequency by the zone, is the target frequency, which can differ from the nominal
frequency when controlling the synchronous time (see section 2.3.3.1). The additional term
Jl!B introduces a very small correction factor. This factor compensates the difference
between the integration of the instantaneous power exchanged and the demand’s energy
measurements [NERC (2006)]. K z is the IC-factor of the control area (in M W /Hz and
positive) and Bz the frequency bias setting (in W/0.1 Hz and negative). K < and Bz are an
when Pmttramuedion
\ m
—ITiiikrwmKCtiou 0 is equal
1
to —AM/p
\J m
—Jf,)
I /
(in
\
other words,5 the imbalance of
tire area is only due to the action of the primary frequency control). Note that a positive
Furthermore, when the term f z —f t is negative, the primary frequency control power
108 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
increases and Ace versa. Lastly, when siC E UCfE is negative, the secondary frequency
control power increases and Ace versa. It is clear that conflicts appear only when K z is
inferior to A z .
When the target frequency f of the power system is different from the nominal
frequency fn, a part of the primary frequency control reserve is undermined. In fact, primary
frequency controllers are based on the nominal frequency (see section 1.4.4). Therefore, this
use of primary frequency control has to be compensated. For example, requirements for
primary frequency control reserves in France are changed as follows50 [RTE (2004)]:
A Iff — 49.99 Hz51, the reserves are increasedhy 150 MW;
A If ft — 50.00 Hz, no change;
A If j t — 50.01 Hz, the reserves are decreased by 150 MW.
Because of data management problems, the frequency and the power flows through
interconnections are measured with discrete time steps. Therefore, the time steps of
frequency and power exchanges measurements, as well as the cycle time of the controller,
should be considered carefully. Shorter cycle times produce a more efficient secondary
control, but also imply higher data management costs.
50 T he policy to change the requirem ent for primary frequency control reserves as a function o f the
target frequency is not adopted in all systems, which creates security breaches.
51 In G reat Britain, time control is perform ed by changing the nom inal frequency by ±0.05 H z or
±0.10 H z [National G rid (2008a)]. In N o rth America, the target frequency is changed by ±0.02 H z [NERC
(2006)].
2.3 SPECIFICATION OF TH E QUALITY OF ANCILLARY SERVICES 109
The speed of the effective frequency correction by the secondary control depends
on the error si2e. Nevertheless, the frequency normally should begin to come back to its
target value (neglecting the frequency oscillations) no later than the full deployment of the
primary frequency reserve. Indeed, at that time, the balance between consumption and
production should have been re-established using the primary frequency control and the
secondary frequency control should have started its action.
Table 2.852 shows the parameters adopted for secondary frequency control in eight
different systems. Great Britain is not included in this table because secondary frequency
control is not used in that country.
Deployment times in European countries are generally smaller than what the UCTE
recommends, probably to provide some additional margin or to remain consistent with
former local policies. For its part, NERC does not provide any specific recommendation.
However, it imposes some performance criteria through its Disturbance Control Standard
(DCS) and its Control Performance Standard (CPS) [NERC (2006)]. To give an example of
US practice, within PJM, the secondary frequency control power should be deployed within
five minutes and for at least one hour (i.e., the duration of the regulation market) [PJM
(2007)]. Lastly, UPS does not impose a deployment time but sets a minimum gradient that
must be respected.
Unlike the UCTE, NERC does not make any particular recommendations regarding
the design of the secondaryfrequency controller\ Where this data is available, the proportional term
is very small, while the integral term is about 100 s. Contrary to the frequency characteristic
requirements given in Table 2.6, the K-factor (fC~ or —10Bz) cannot be estimated because
it represents the actual frequency response of the system, which is not publicly available
data. This parameter can be variable in real-time in North America, whereas it is constant in
Europe. As guidelines for the K-factor, UCTE asks for a 10 % overestimation of the
frequency characteristic while NERC recommends the exact value.
52 T he following abbreviations and symbols are used: N o rec.: n o recom m endation; e: accuracy; T:
cycle time; P, I o r PI: proportional, integral and proportional-integral controller.
Table 2.8: Technical comparison of secondary frequency control parameters in various system s 110
NERC U PS UCTE DE FR ES NL BE
Spanish industry
and energy
'
R eferences UCTE (2004b), TcnncT BDEW (2007a), department TcnncT (2003), Belgium economic
NERC (2006) (2006) BDEW (2007c) RTE (2004) (2006a) DTe (2005) department (2002)
Immediate or
om
VI
No rec. <30s
■§
oHI
Deployment start <30s No rec.
C
< 10 s
CHAPTER 2
£ 5 min
< 15 min
VI
As soon as possible
c
a
‘S
VI
VI
U“)
E
No rcc. < 300-500 s
lO
Full availability < 5 min since < 10 min
® &
^ VI
(gradients imposed)
w
15 May 2008
6
-o
Al
m
As long as
Al
m
At
U“i
No rec. As long as required
C
Deployment end As long as required As long as required
C u
5 *o
required j
1
U
u
is«
*3
Tj
Cl
L)
Control organisation No rcc. No rec. Pluralistic Hierarchical Pluralistic
C
Centralised
O
Frequency
N
N
1.0<e< 1.5 mHz s: Unknown
N
vJ h
p 'a
t S
- >
VI L
VI H
v ,H
ii
Vf II
1 »
2 "
ij 'S
VI H
£ «
VI H
^ VI
o VI
T: No rec.
u-> w
m easurem ent T=2s
E xch an ges
VI
0)
e-
VI
fO
e: Unknown s < 0.5%
to £
£ -
mH
VI H
in in
“ VI
II
IT) T-
^ VI
^ 11
— VI
c w
lO "St
T = 4s T: Variable
VC c/3
4
m easurem ent
VI £—
VI
vo
m
M-
S3
Controller type No rec. I or PI depending on the additional PI
regulation zone heuristics
DELIVERY OF ANCILLARY SERVICES
o
o
Integral term No rec. 40-120s 50-200 s Unknown 115-180 s 100 s 100-160 s 50-200 s
It
V
O
Unknown
^3
900 MW/Hz
VO
O
Contrary to the primary frequency control, the parameters of the primary voltage control
cannot be compared between systems, and most of the time, even between units. In fact,
the parameters of the voltage controller must take into account the configuration of the
surrounding network. However, the requirements in terms of reactive power capabilities can be
compared, as they measure the ability of the unit to control voltage and because one Mvar
from a hydro unit is generally equivalent to one Mvar from a thermal unit. To allow a
benchmarking between systems, the reactive power requirement given at the terminals Q 2 is
converted to the Point O f Delivery (POD) 0 POD(see section 1.5.3).
Sometimes, reactive power requirements may be given for the dimensioning voltage
Udim instead of the nominal voltage of the network Un. The dimensioning voltage is the
actual average voltage at which the generating unit is connected, which may vary from U„.
The possible reactive power/voltage pairs are given by the U /Q diagram of the unit. To
convert from the reactive power requirement at Uflm/ to the one at U/n a typical U /Q
diagram should be used on a case by case basis. In this survey, we assume that U/limand L/„
are equal.
Concerning deployment times, the primary voltage control is immediate and must
operate continuously, as it maintains the voltage at its nominal value and insures stability.
From an accounting perspective, cycle times and accuracy are less important for the
voltage control than for the frequency control, because the utilization cost of reactive
power is generally considered to be too low to require a precise metering [Da Silva et al.
(2001)]. However, for the stability of the system, the measurement accuracy and the
parameters of the voltage controller should be considered carefully.
Most of the TSOs make recommendations regarding the effectiveness of the control\ and
in particular the stability margins [Spanish industry and energy department (2000), Belgium
economic department (2002), French economic and industry department (2003) and
BDEW (2007a)]. However, these requirements were not considered in this survey because it
focuses on features of ancillary sendee controls.
112 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
Table 2.9i3 shows the reactive power requirements in eight different systems. While
these requirements are often specified using a complete P /Q diagram, this table can only
show the maximum requirements for Pn.
NERC and the UCTE do not give any recommendation on reactive power
requirements because it is a local problem. UPS requirements are negociated case by case.
Spanish requirements are quite low in comparison to the other systems in the Table.
Therefore, connecting conditions are less stringent on this point in Spain than in the other
systems. However, reactive power connecting conditions do not imply that one system uses
more or less reactive power than another one since TSOs can contract for additional
reactive capabilities or use some of their own reactive power sources (see Chapter 4).
53 T he following abbreviations and symbols are used: N o rec.: n o recom m endation; pf: pow er factor;
Pn: nom inal power; P O D : P o in t O f Delivery; Udim: dim ensioning voltage; Un: nom inal voltage.
Furtherm ore, note that the expressions lagging and leading refer to the stator voltage and the stator current
(see section 1.5.3).
2.3 SPECIFICATION OF TH E QUALITY OF ANCILLARY SERVICES 113
PQ
O
W 0, jOP
pa SN
s Q
9 cO
u
« P, « «
o P
o <a
"Q Q
o ,C
o. *2
o ”3
. a
o* &* 3 * o, E s &, a
’o Ph
is a o8 I"3 .9
M l
o a .3
i*\ ^ «o Q n n
ou "=?O So
'j
8P LT5 Q _
a
~ Q P ° uT3
£ O -o s " g
o Q
ao II 9 v.
w ® ,0
■«a * UJ
&
w
H
u
P
3
C\
c4 C/D
a
<u p
3«
H
u
PCi
a
£
*
3
art •8a B4a ^
& 5r ^
rt «u ^
u 4- .
a a a o
o S '3 9 bJD
'5 h a u
& §
9 •§ TJ
3 uM d
■a ’a 55
3 *■ a-
S .3S
pci <i a w &a a
114 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
step function)54. For example, as shown in Figure 2.5, the two deployment times fd h t
and t biirphjmcnl are totally different, whereas it is the same AS provider that is considered in
both cases. Consequently, if two policy makers take different typical input signals, the
capability of a provider cannot be translated directly to the other policy maker. Therefore, a
standardised description may help the providers communicate their capabilities.
Second, actual specifications for ancillary services are with good reason focused on
the quasi-steady state (e.g., frequency characteristic or full deployment for a given frequency
deviation)53. Therefore, the dynamics of the providers are ignored .Providers that react fast are
more useful to the system56 and have to respond more often, which increase their provision
cost (see Chapter 3). Hence, these providers should be entitled to receive a premium for a
provision of AS with an improved quality (see Chapter 4). In addition, the SO is eager to
know the actual dynamics of the AS providers to better understand the reactions of the
system. In particular, after collecting the data on dynamics from all the AS providers, the
SO can run simulations to check whether its security criteria are fulfilled or not.
Lastly, the current frameworks define their requirements for each type ofproviders (e.g.,
conventional power plants, distributed generation, purposely-built devices or loads). In
order to foster innovation, it would be useful for the policy maker to benefit from a
framework that describes any provider.
54 F o r manual ancillary services such as tertiary reserves, the inp u t signal is m anaged by the provider
itself (e.g., it can activite its fast units very close to the end o f the deployem ent time).
55 T h e short response (< 30 s) o f a frequency control provider is linked to stability, whereas the
longer-term response (beyond 30 s) is linked to the active pow er actually provided by the prime
m over [Proctor (2001)].
56 Dynamics that are too fast can also lead to an unstable system.
2.3 SPECIFICATION OF TH E QUALITY OF ANCILLARY SERVICES 115
input
o u tp u t o u tp u t t
t'-deployment
a t tdeployment
b t
(a) (b)
F igure 2.5: R epresentation o f resp on ses o f an AS provider for tw o different inputs
Still, these innovative methods do not take into account all the specificities of an AS
provider such as deadbands or delays. Therefore, an original specification of frequency and
voltage control ancillary sendees is proposed here and illustrated in Figure 2.7. Primary,
secondary and tertiary controls are only differentiated by the input signal, which is either
computed locally, either sent by the SO or set by the device operator. Lastly, note that
capacitor banks and generators do not provide the same reactive power capability because
the actual reactive power supplied by a capacitor varies with the square of the voltage at its
terminals [Fourment et al. (1995)]. This variation can be taken into account in this
framework by using the tenninals voltage as input.
In all the cases, the device responds to the input signal57 with its own dynamics,
characterised by five parameters. First, the equipments have a delay of response, generally
associated with the transmission of data. This delay can also be very useful for providers
57 AS providers may also respond to several input signals. F o r instance, the active pow er
consum ption o f a load usually depends on b oth voltage and frequency o f the electricity supply [K undur
(1994)].
116 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
that need a certain time before being able to react, such as disconnected gas turbines.
Second, all equipments have a certain insensitivity, which is given by the deadband. In
addition, this insensitivity can be used by all-or-nothing providers, such as loads fitted with
a low-frequency relay. Third, the response of the device to the input signal is approximated by a
first order system (see Figure 2.8). Obviously, a generating unit is not a first order system,
but in most of cases, the approximation is sufficient to check whether the security may be
guaranteed. This feature is important because slow and fast controllers have different values
for the SO. If the provider agrees (and is able) to give a more precise description of its
device (e.g. a second order system), this better description would be easily implemented in
the model. Fourth, the process is limited by its maximum and minimum outputs (i.e., the
negative and positive reserves) and by the maximum slope. The fifth and last parameter is the
maximum duration of the control. This maximum duration may be expressed in terms of
energy, which can be very useful for hydro units, storage devices or loads.
It is worth noting that classical control schemes for generators, FACTS and loads
can fit this framework. In the particular case of generators, this structure may be used for
different levels o f active power production, since the dynamics of a unit are a function of its
output. However, it is not clear whether this structure is appropriate for future forms of
regulation such as adaptive commands, neural networks or fuzzy logic.
output
A .<5 -1
Input K
signal
1+r-s
Delay D eadband P ro c e s s Limiter Duration
Figure 2.7: P rop osed standardised definition o f quality o f a frequency or voltage control AS
input
output
actual
response
1+ T- s
estimated
response
delay
F igure 2.8: R epresentation o f the actual resp on se o f the group versus its estim ate
This standardised framework can be used to describe any AS provider. All the
stakeholders would thus speak a common language. The particularities of providers would
be recognized and the SO would have a better understanding of the system. In addition, to
help identify types of AS providers that are either abundant or scarce, or to create a
market38, AS providers can be grouped in categories as a function of specific profiles, as
shown in Figure 2.9. However, such profiles require an input signal, so it reduces the
universality of the specification.
58 Allowing product substitution betw een different qualities w ould be necessary in such a market.
118 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
input
output
actual
response
Calibre
Dynamic Quasi-steady-state
requirements requirements
2 .4 Q uantity o f A ncillary S e r v ic e s
The previous section has provided various frameworks to specifiy the quality of a given
ancillary service. None of the proposed frameworks stands out from the crowd. Therefore,
the chosen specification depends on the constraints of the power system considered. Using
these specifications, this section focuses on the quantity of system (and thus ancillay)
services needed to meet the expectations of users in terms of reliability, power quality and
utilisation. The optimal method is first presented (section 2.4.1), before reviewing and
discussing the practical methods used within the UCTE (sections 2.4.2 and 2.4.3). The
requirements in various systems are then given. Some original methods to define the
appropriate quantity of system services are introduced (section 2.4.4). Lastly, actual
requirements across systems are compared (section 2.4.5).
As shown in section 2.2.4, the optimum quantity of system services is the one that maximizes
the global welfare. However, this optimum is very difficult to reach because many
parameters have to be considered. In particular, the value and cost of system services are
2.4 QUANTITY OF ANCILLARY SERVICES 119
Lastly, when the timeframe considered gets longer, the problem of volumes of
system sendees moves from the security domain to the adequacy domain. The SO should
give the right signals to the investors in order to obtain enough AS capacities in the long term.
This issue remains open and is deeply linked to the investment in energy production
capacities (see section 4.3.1).
The primary frequency control reserve within the UCTE is based on the largest
power devia don to be handled, which is 3 000 MW, "assuming realistic characteristics
concerning system reliability and size of loads and generation units” [UCTE (2004b)]. This
reserve is linked to the frequency characteristic of the system and is thus shared by the
59 Section 2.2 shows the difficulty to express the value o f system sendees, while C hapter 3
dem onstrates that it is im possible to calculate precisely the cost to provide ancillary services.
120 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
whole interconnected network, as explained in section 1.4.7. The burden o f this reserve is
then shared across the whole interconnected power system according to the generation of
each system.
On the other hand, the secondary frequency control reserve is activated by a given
zone to balance its own production and consumption. Therefore, the reserve of a zone
varies in function of the size and portfolio considered. Within the UCTE, the calculation of
secondary reserves originates from an empirical formula [UCPTE (1991)]. This formula was
developed during the seventies from half-hourly measurements of production and
consumption. The means used at that time where relatively limited, such as hand-calculation
based on information given by phone by operators of generating units. The first formula
has then evolved over time. Table 2.10 gives an overview of the evolution of the secondary
reserve R(y , by considering a few systems within the UCTE and depending on the available
information. The current UCTE formula (i.e., since 2004) is a compromise based on all the
previous formulas. However, TSOs prefer to take margins to increase the security of the
system, especially during fast variations of the load. Lastly, note that the UCTE
recommends that the loss of the largest unit in the zone be compensated by both secondary
and fast (i.e., deployed in less than 15 min) tertiary frequency control reserves [UCTE
(2004b)].
2.4 QUANTITY OF ANCILLARY SERVICES 121
At
least System Formula References
since
1991 Germany 1 1 2 500 * * UCPTE
(1991)
2 Vv Pz
maxgttitralt'on
PL-grnrtu, = estimate of the peak generation for the
day (in MW)
/A —estimated power deviation in % related to
Pmax frnmiiion • Ttie average of I) was around 3.5 %, and die
maximal value 9 % during rapid load fluctuations (6-
9 h)
1991 France UCPTE
Rxr = 2.8 x p mimipt!on
(1991)
R ;r = 0.02 x during rapid load fluctuations
’P<v»snmptm ~ estimate of the internal consumption (in
MW)
1991 Italy Re UCPTE
sec = 0.0125 x Econsumption
(1991)
1998 Spain Rse
^c = 3X A// maxconsumption Spanish
industry
Ri = 6 XVP L mmumption dul'lng mPid lo£ld fluctuations and energy
department
P L — prim, = estimate of the maximal internal (1998)
consumption (in MW)
2004 UCTE UCTE
K = V10x + 22 50 0-150
(2004b)
2006 France R;, = min {5OO , ^ 1 0 x + 22 500 -15o) Texier-
Pauton
demand gradient (2007)
sec s
6
if the demand gradient is higher than 12 000 M W /h
Clearly, the UCTE formula is a compromise between previous methods, which were
developed during the seventies, when the portfolio and the measurement means were
different than what is available today. This section thus attempts to put into perspective the
current UCTE formula.
122 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
2 .4 .3 .1 Link b e t w e e n s e c o n d a r y a n d tertia ry c o n tr o ls
Tertiary and secondary frequency controls have the same objective: bringing back the
exchanges of the area to their targets values (or the frequency to its target in a case of an
area without any interconnection). A trade off is thus possible between secondary and fast
tertiary reserves. Consequently, the definitions of the necessary secondary and fast tertiary
frequency reserves have to be considered together. However, the current requirement of the
UCTE ignores this possible trade-off.
Figure 2.10 represents the compensation of an imbalance with the help o f both
secondary and tertiary frequency controls. Despite having the same objective (i.e.,
compensate the imbalance of the zone), the tertiary frequency control is less flexible than
the secondary frequency control. Indeed, tertiary frequency control offered by generating
units or consumers usually include delays and minimum durations of use. However, some
power systems can benefit more from flexible tertiary frequency control than other systems.
Hence, each power system should have its own requirements for secondary reserves as a
function of the available tertiary frequency control offers (which vary over time).
2.4 QUANTITY OF ANCILLARY SERVICES 123
Imbalance to
compensate
Controls (in MW)
Energy of tertiary control
Tertiary control
Energy of
secondary control
'I-A N.
", N Secondary control
2 . 4 .3 . 2 N o rm a lity
If the necessary secondary and tertiary frequency control powers can be determined to
compensate a given imbalance, one can plot die probability density of the necessary
frequency control powers60 for any imbalance. Figure 2.11 gives a stylised representation of
such a density. As it would be too expensive (and actually impossible) to have always
enough frequency control power, policy makers have to accept that not all positive or
negative imbalances will be covered. This is translated by two limits on the probability
density (a limit for the negative tail and another for the positive tail, as shown in
Figure 2.11).
The choice to cover 99 % of the cases is usual. For example, this criterion
correponds to the one chosen in France for the margin of the morning peak [RTE (2004)].
60 W hen the regulation signal is equal to —1 (see section 2.3.3.1), tire positive secondary frequency
control pow er is equal to twice the secondary? frequency control reserve.
124 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
Then, this criterion has to be distributed amongst positive and negative imbalances,
according to the priority given and eventually the related cost (e.g., 0.5 % each tail).
The requirements within the UCTE during the nineties (see Table 2.10) made the
assumption that the necessary secondary frequency control power follows a normal law.
Hence, the necessary secondary frequency control power to be covered during 99 % of the
cases can be easily deduced: it should be ±2.576 x cr, where cr is the standard deviation of
the normal law considered, as shown in Table 2.11 [Saporta (1990)].
Probability
Necessary
negative Necessary positive
Imbalances not control power control power to be Imbalances not
covered to be covered covered covered
Necessary frequency
control power
The normality hypothesis was made when the available techniques were limited.
However, because of the current computation capabilities, recent reserve requirement can
now be based on more complex density functions. To give an example, Figure 2.12 shows
the empirical cumulative distribution function of the activated French tertiary control
power in 200661, and the corresponding normal cumulative distribution function with an
61 The example is based on the tertiary frequency control because the data on the activated secondary
frequency control pow er was n o t available.
2.4 QUANTITY OF ANCILLARY SERVICES 125
average of -4.5 MW and a standard deviation of 893 MW. The activated tertiary control
power is defined as twice the energy of tertiary frequency control deployed over half an
hour (see Figure 2.10). In other words, it represents the average power needed to provide
the activated energy62. The data are from RTE (2007a). Note that the transmission losses
are included in these data, since RTE is treated as a consumer that uses active power to
cover the network losses.
To test whether the two cumulative distribution functions are equivalent, the
Kolmogorov test was performed. This test validates an empirical series F* (jQ by
<2-3>
In this case, jDKb, m, = 0.055 is obtained, whereas the threshold for the Kolmogorov
test is 0.0081 for 17 520 elements63 with a confidence of 80 % 64. Therefore, the series is far
from following a normal distribution. This difference is explained by the threshold that can
be seen around zero (see Figure 2.12). In other words, it is highly probable that the
activated tertiary frequency control power is null over a half-hour. In fact, participants have
incentives to reduce their imbalances, as the balancing mechanism charge users that are in
imblance.
consumption of the zone , whereas our study has considered all the data. However,
because of the link between secondary and tertiary frequency controls, secondary frequency
control power may also not follow a normal distribution. Nevertheless, the same calculation
62 T herefore, up and dow n balancing can com pensate each other over a h alf hour.
G3 T he series has 17 520 elements because there are 365 days x 48 half-hours/day.
1-073
64 0.0081 is obtained w ith the following formula: , [Saporta (1990)].
^ 17 520
126 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
should be performed to assess the foundation of the policy for the secondary frequency
control reserves.
2a
a>
>
JH
3
£3
o
F igure 2.12; E m pirical and norm al cum ulative distribution fu n ction s o f the activated tertiary control
pow er in 2006 in France
2 . 4 .3 . 3 S ta tio n n a r ity
Making assumptions on future imbalances relies on the hypothesis that the series
considered is stationnary, i.e. that its standard deviation and its average do not change over
time (see Appendix A. 1). However, since the portfolio of a system evolves in time,
especially with the increase in distributed generation, it is possible that the necessary
frequency control power not be stationnary. Therefore, the reserve requirements should be
updated frequently.
2 . 4 . 3 . 4 S y m m e tr y o f r e s e r v e s
As shown in Figure 2.11, the necessary frequency control power can be on average different
from zero. In other words, there may be an expected imbalance. This can happen when the
participants have an incentive to under- or over-estimate their production or consumption.
In practice, this happens when the balancing mechanism has assymmetric prices. Therefore,
symmetrical reserves do not guarantee that sufficient reserves are available to hedge against
imbalances. However, the secondary reserve is only dimensioned as a positive power within
2.4 QUANTITY OF ANCILLARY SERVICES 127
the UCTE. Therefore, the current recommendation does not guarantee enough negative
control power capacity.
2 . 4 .3 . 5 C o s t o f o u t a g e a n d c o s t o f p r o v isio n
The probability density function discussed above does not take into account the cost of
being short of system services (e.g., the cost of the outage resulting from by the lack of
reserves). Indeed, as shown in section 2.2, this cost varies over time, so the risk cover factor
(and the frequency control reserves) should also vary with time. For example, RTE’s
objective is to have a probability of using exceptional means (e.g., load disconnections)
inferior to 1 % at the morning peak and 4 % at the evening peak [RTE (2004)]. However,
the UCTE currently does not recommend such a differentiated requirement over time.
Voting may also be an alternative. In such a system, users would vote for say three
levels of system sendee A, B and C. When a level of system sendee is chosen, the cost is
128 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
split equitably amongst all the users. However, this system may lead to some difficulties. For
example, let suppose that A is preferred after the vote. However, it is possible that a
majority of users prefer B to A, a majority prefer C to B and that a majority prefer A to C!
And even if such cycles can be avoided, the result may not be efficient because a vote is
binary while the volume of system services is continuous. Lastly, voting does not necessarily
provide a good incentive for users to honestly reveal their true preferences. For example,
Varian (1999) illustrates these flaws using the case of a vote in the Congress of the United
States in 1956.
In the case of a continuous public good, Varian (1999) shows that a Pareto-efficient
amount of the good is obtained when the sum of the absolute rates ofsubstitution between the
private good and the public good for all consumers equals the marginal cost of providing an
extra unit of the public good. However, it is not clear what private good can be substituted
for security in a power system. For example, such a private good might be a generator close
to the load, a private line, load-shedding or a small network with a DC link. A system can
also be imagined in which a load or a distribution company gives instructions directly to an
AS supplier in order to follow the consumption of the load or the distribution
company [Tyagi and Srivastava (2006)]. Anyway, the marginal rate of substitution is unlikely
to be useable directly since it is hard to compute.
Instead o f the rates of substitution, a related idea could be used: the cost of insecurity65.
Indeed, the cost of insecurity is specific to every user of the power system. It can thus be
proven very easily that the optimal quantity of system services is obtained when the
marginal cost of insecurity equals in absolute the marginal cost of system services (see
Figure 2.13). This optimisation problem seems therefore to be straightforward. However,
even if the cost of system services as a function of the quantity can be calculated,
computing the cost of insecurity is much harder for three reasons. First, determining the
value that users put on electricity is not easy and this value varies with time. Second,
supposing that the value of electricity is known for all the users, determining the related
cost of insecurity for different quantities of system services requires huge amounts of
computation. Lastly, the cost of insecurity is represented here by a smooth curve. In
practice, it is very likely that this cost exhibits discontinuities. For example, if just one MW
65 T he security is a public good, while the damages o f insecurity lead to private losses for a user.
T herefore, the cost o f insecurity can be seen as a private good th at can be substituted for security.
2.4 QUANTITY OF ANCILLARY SERVICES 129
of reserve is missing, the TSO may have to disconnect a whole feeder, which usually
represents several MW. Despite these difficulties, this method is one of the main current
research axes. Amongst others, see for example the recent contributions by Papadogiannis
and Hatziargyriou (2004), Galiana et al (2005), Abiri-Jahromi et al (2007) or Ortega-
Vazquez and Kirschen (2007). However, note that these papers do not consider the impact
of system services on power quality and the utilisation of the power system (see section 2.2).
C ost
Total cost
Cost of
system services
Cost of insecurity
Another possible solution relies on a tax, called the Groves-CIarke tax, described by
Varian (1999). In this system, each user gives the value g of benefits it derives from the
public good. In addition, if the public good is provided, everybody will have to pay a certain
amount cn known in advance by all the users. The net value //,- can then be computed. This
value is negative if the user loses money by buying the public good and positive if it benefits
from the public good. Pivotal agents are the users that change the sign of the total net value,
i.e. E;/,. In others words, pivotal agents are essential to the decision to procure the public
good. The pivotal agents then pay the harm that they do to non-pivotal agents, i.e. the total
net value without the participation of the pivotal agent. This tax disappears from the
system: it is not given to a participant in order to avoid gaming. Tills scheme is really an
incentive on participants to reveal the true value of the product. However, it works only
when all the Pareto efficient allocations of the public good lead to the same amount of
public good (a situation called quasi-linear indifference). In addition, the Groves-CIarke tax
is not Pareto efficient since the tax disappears from the system. However, in the case of a
130 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
large number of participants, this tax may be rather small, because nobody would be pivotal.
This method helps determine the efficient amount of public good, but does not help with
the cost allocation66. Lasdy, note that the cost allocation scheme has an impact on the value
of the tax, but does not affect the decision of buying or not the public good.
Table 2.12 illustrates the Groves-CIarke tax mechanism for a public good that costs
100 €. It can be seen that the proposed cost allocation c-t is different from the value v{ given
by the participants. Therefore, this mechanism may be considered as unfair by some
participants. On the other hand, participants have incentives to reveal the true value of the
good. In fact, if they underestimate it, the good may not be bought at all and the
participants may thus loose the benefit from the public good. But if the participants
overestimate the value of the public good, they may be pivotal and pay a tax that will
undermine any potential extra benefits.
Let us imagine a practical example for a given SS67. First, the TSO determines the
SS cost for a given period of time (e.g., one hour of the day) as a function of the quantity,
and allocates it to, say, the four groups of system users A, B, C and D (see Figure 2.14). For
example, these groups of users could be the balancing entities68 in France.
68 A balancing entity acts on the balance betw een production and consum ption w ithin a specific
perim eter o f the market.
2.4 QUANTITY OF ANCILLARY SERVICES 131
C o st total cost
o f SS
Q u an tity of S S
F igure 2.14: A llocation o f SS costs b etw een four groups o f users
Then, each group of users reveals the value that it gives to the quantity of SS for the
given period of time (see Figure 2.15 - note that a discontinuous curve could also be
envisioned). To be able to let the value of SS be estimated by users, the TSO has to give
them some system information. For example, for a given quantity of SS, the probability of
level of quality of supply is estimated. All the values of SS are then added in order to obtain
the total value expressed by all the users to the SS. Unfortunately, this step is likely to be
very difficult to implement in practice because it may be very difficult for users to estimate
the value of system sendees. In addition, the TSO may not be able to give sufficient
information on the impact of a given quantity of system sendees.
Value
of SS
Q uantity of SS
Figure 2.15: V alue o f SS for a group o f user
With the cost and the value of the SS, the TSO can find the optimal quantity q* of
SS, which maximizes the difference between value and cost, i.e. the net benefit of SS (see
Figure 2.16).
132 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
€ i
V alue of S S
C ost of S S
Quantity
of SS
The last step consists in chatging the tax to the pivotal agents as explained with the
example of Table 2.12. The product of this tax can then be given to the regulator to help it
to finance market audits or other related activities.
The advantage o f the proposed method is that it switches the burden of calculating
the cost of insecurity from the SO to the users of the system. In addition, it gives an
incentive to the users to bid the real value of SS for them. On the other hand, the TSO has
to be able to provide precise information on the impact of a given level of SS, which is
likely to be very difficult to compute. Therefore, building the curve of the quantity of
system services versus their value (see Figure 2.15) is the thoughest point to solve to make
this method practical.
To compare volumes, system specificities and especially the size of the power
system need to be taken into account. Therefore, a specific indicator, called Reserve Indicator
2.4 QUANTITY OF ANCILLARY SERVICES 133
(RI), is proposed in this thesis. It is calculated by dividing die amount of reserve in the
system by the hourly average energy production or consumption (in MWh/h), depending
on the type of reserve. Hence, the SO of a system with a high RI procures more reserves
per unit of energy produced or consumed than one with a lower indicator. One advantage
of this indicator is that it can be calculated easily on the basis of parameters that are easy to
obtain. While the concept o f reserve indicator could also be applied to reactive power
sendees, not enough information is available on reactive power volumes to include a
reactive reserve indicator in this work. Usually, the amount of primary control reserve is
linked to the production. For example, the UCTE contribution coefficients for primary
control are based on the annual production of each system [UCTE (2004b)]. Therefore, the
reserve indicator used for the primary reserve R/C (in %) is obtained by dividing the
average primary frequency control reserve RV (in MW) by the hourly energy production
R
(2-4)
E genemttor)
In most systems, the secondary control reserve is linked to the estimated peak
consumption during a given period. Therefore, the reserve indicator used for the secondary
R IICCl = ^
(2.5)
V }
consumption
where Ry. (in MW) is the average secondary frequency control reserve and E^nji/mp/kii (in
Figure 2.17 shows the primary and secondary frequency control reserve indicators
calculated in 2004 or 2005, depending on data availability, for various systems69. For the
sake of clarity, primary and secondary RIs are not separated in this graph. However, in
69 Australia and N ew Zealand have been included in order to have a different view from n o n
interconnected systems. F o r data on electricity production and consum ption, see IE A (2005). F o r data on
reserves, see the websites o f TSO s and m arket operators o f the systems.
134 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
order to explain differences, primary and secondary frequency control RI will be discussed
separately.
Except in Australia, the primary reserve indicator is higher in small systems with no
interconnections or limited interconnection capacity such as Great Britain70, New Zealand
and Sweden. Indeed, the primary frequency control reserve is si2ed to counteract the loss of
the biggest unit, which is about the same in all the synchronous zones. Within the UCTE,
Spain has a higher primary frequency control RI because of its compulsory provision (see
section 4.4.2). The values of this indicator for Germany and France are similar. Finally,
systems outside the UCTE have a non-symmetrical primary frequency control reserve
(positive different from negative) and PJM’s R^- was not calculated because, contrary to the
secondary frequency control, there is no specific requirement for the volume of primary
frequency control reserve yet [NERC (2005)].
70 N ote that for G reat Britain, primary and secondary frequency responses have been added to obtain
the total primary frequency control reserve.
2.5 LOCATION OF ANCILLARY SERVICES 135
0) _ 5 .
3
XT : Primary negative frequency control reserve unknown
© T Primary frequency control reserve not formally specified
.MO-J
F igure 2.17: F requency control reserve indicators in 2004-5 across system s surveyed
2 .5 L ocation o f A ncillary S e r v ic e s
In addition to the quality and the quantity of ancillary sendees, the location of the ancillary
sendees has to be considered carefully.
71 T h e location issue is in this case relatively similar between active pow er AS and electrical energy-
only products.
136 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
control are likely to be distributed across the whole interconnected network to reduce
unplanned power transits following a large generation outage.
Second, in case of a grid separation, the separated parts of the network cannot stay
stable without any frequency control system service. Therefore, a uniform distribution of
frequency control services is desirable. In particular, distributed generation could be very
useful to provide such a uniform distribution of reserve.
On the other hand, reactive power ancillary services are local products (see
section 1.5), so the reactive sources have to be as electrically close as possible to the reactive
loads. Therefore, the location of providers of reactive control AS is very important. In
addition, like frequency control, voltage control AS impacts the transmission capacity.
Indeed, (a) reactive power AS need a minimal available transmission capacity to be helpful;
(b) flows of reactive power increase the active power losses; and (c) reactive power AS can
increase or decrease active power flows.
72 T hese values are only indicative. F o r com plete inform ation, refer to E D F (2004) for the
distribution netw ork and to R T E (2006) for the transm ission network. N o te that the actual average loss o f
supply is m uch lower than the com m itm ent. Indeed, the average loss o f supply was 60 m inutes for the
distribution netw ork in 2004 [E D F (2006)] and 1 m inute 42 for the transm ission netw ork in 2006 [RTE
(2007c)].
2.5 LOCATION OF ANCILLARY SERVICES 137
As the location of ancillary services is important, systems have to develop policies to benefit
from sufficient ancillary sendees at the appropriate places, as discussed in section 4.3.1.
Moreover, systems have to define technical procedures to allow some ancillary sendees to
be exchanged between participants. In fact, TSOs usually do not choose where the AS
providers are.
Within the UCTE, the requirement for primary frequency control reserve is split amongst
the various TSOs according to their electrical energy produced annually (see section 2.4.2).
UCTE (2005) proposes to allow exchanges of primary frequency control reserves between
TSOs. In this framework, the Reserve Receiving TSO (RRT) benefits from the contribution
of one or several units connected in the area of the Reserve Connecting TSO (RCT). Two
methods have been proposed:
V A n A S provider (in the area of the RCT) supplies primary frequency controlfor the RRT. In this
case, the RCT has to give its agreement;
V The RCT provides primary frequency control for the RRT. Therefore, the providers in the area
of the RCT see an increase of their provision of primary frequency control.
2 . 5 . 2 . 2 S e c o n d a r y f r e q u e n c y c o n tr o l
In North America, regulation (i.e., secondary frequency control) can be traded between
systems with the help of the following services [NERC (2006)]:
'C Overlap regulation service-, a control area incorporates some or all of another control area's
tie lines, frequency response and schedules into its own ACE equation (see
section 2.3.4.3);
V Supplemental regulation service, a control area takes into account all or a portion of the ACE
of other control areas in order to provide more regulating power for these areas.
The UCTE (2005) has also proposed changes to allow generating units to provide
secondary frequency control to another zone. Two architectures have been proposed,
which do not directly use the ACE:
V Direct control by the Reserve Receiving TSO (see Figure 2.18): the generating unit in the
reserve connecting area receives the regulation signal directly from the RRT. The
participation of the unit is added to the balance of the RRT and substracted from the
balance of the RCT;
V Control through the Reserve Connecting TSO (see Figure 2.19): the RCT receives the
regulation signal from the RRT. The RCT changes its ACE accordingly. Therefore, all
the generating units providing regulation in the area of the RCT participate in the
regulation effort. This service is thus somewhat similar to the North-American
supplemental regulation service.
Lastly, note that such arrangements will have consequences on the current operating
pratices. In fact, contrary to the current organisation, the exchanges at the interconnections
will not come back to their scheduled values after deployment of the secondary frequency
control power.
2.5 LOCATION OF ANCILLARY SERVICES 139
LFC: LFC:
G= AF+K Af G= AP+KAf
m e a s u r e m e n t v a lu e
LFC: LFC:
G=AP+K A f G= AP+K A f
© t.
*■ control signal
Because of the local, characteristics of voltage control, this ancillary service cannot be easily
traded over long distances (see section 1.5.4). Therefore, sufficient reactive power providers
must be located across the system (see section 4.3.1). In addition, the voltage control
management requires a strong cooperation at the connecting bus between two different
entities; for example, between two TSOs of two neighbouring areas, a TSO and a DSO, or
a TSO and a generating unit. Such cooperation has to be defined with the help of a specific
contract or regulation rules.
140 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
2 .6 C on clu sion
This chapter has explored the issues related to the delivery of ancillary services, namely: the
expression of the needs, the quality, the quantity and the location of ancillary services.
Current policies can be improved by taking into account more accurately the value given by
the users to system services and by refining some empirically-defined requirements. In
particular, the following assessment list is proposed for the delivery of ancillary services:
(b) a deadband; (c) dynamics of the process; (d) a limiter; and (e) a duration of
sendee. Contrary to current specifications, this standardised description does not
rely on the input signal, does take into account the dynamics and can be applied to
any type of provider. Lastly, the term “spinning reserve” is defined in a standardised
manner: the spinning reserve is the unused capacity which can be activated on
decision of the system operator and which is provided by devices that are
synchronized to the network and able to affect the active power;
■ Rationalisation of ancillary services', in practice, specifications of ancillary sendees differ
from one system to another. Therefore, efforts should be made to unify similar
ancillary services in order to foster short-term exchanges of sendees.
S Quantity of ancillary services:
■ Responsibility for requirements', because system sendees are public goods, only the
system operator can define the requirements for ancillary sendees. In addition, the
public good characteristic makes very difficult the design of new methods that
define the requirements for ancillary sendees;
■ Definition of requirementsfor ancillary services', the requirements should take into account
(a) the possible trade-off between products; (b) the potential non-normality, (c)
non-stationarity and (d) non-symetry of imbalances; (e) the time-dependent cost and
value of ancillary sendees. However, current practices are usually opaque. Therefore,
the system operator has to explain to all the participants how the requirements are
calculated;
* Elasticity of requirements-, the fixed demand for ancillary sendees currendy used is
inelastic and marred with large uncertainty. Therefore, the benefit of procuring
more or less 10 MW of reserve is not assessed;
■ Synopsis of requirements', an indicator has been developed to compare requirements for
ancillary sendees and thus gives incentives to participants to improve their practices.
S Location of ancillary sendees:
■ Importance of location', die location of reactive power providers is particularly
important. For frequency control, die actions of providers are global but still may be
hampered by a bad location (e.g., a congested area);
* Incentives in the long rum since AS providers cannot be moved easily, appropriate
incentives should be given to have access to sufficient AS capabilities at the
appropriate locations in the long run;
142 CHAPTER 2 DELIVERY OF ANCILLARY SERVICES
■ Exchanges in the short temr. technical mechanisms should exist to allow participants to
exchange AS in the short fun to help maximize the global welfare. In addition,
standards should be developed to allow neighbouring participants to communicate
(e.g., a TSO and a DSO). ■
CHAPTER 3
COST OF ANCILLARY SERVICES
A. smile costs less money than electricity hut gives as much light.
Henri Groues (1912 - 2007)
3.1 Introduction
T IS essential for a provider of ancillaiy sendees to understand the cost of its supply in
I order to take the appropriate decisions for its investments and its contracts.
Furthermore, policy makers also need to appreciate the structure of the costs of ancillaiy
sendees in order to design the most appropriate market. This chapter therefore reviews the
main components of the cost of ancillary sendees (section 3.2). A practical methodology
based on operational data is then proposed to estimate the cost incurred by a producer
when it must reserve capacity on a day-ahead basis to provide frequency control
(section 3.3). This methodology was successfully applied to EDF Producer’s generation
portfolio and gives interesting insights on the costs of frequency control ancillary sendees
(sections 3.4 and 3.5). In addition, the cost of time control is assessed for France
(section 3.6).
A. Comprehensive Assessment ofMarketsfor Frequeue)' and Voltage ControlAncillary Services, Yann Rebours, 2008 143
144 CHAPTER 3 COST OF ANCILLARY SERVICES
3 .2 Main C o st C om p on en ts o f A ncillary S e r v ic e s
The reflection on the cost of ancillary services started in the mid-nineties, in particular with
the work by Hirst and Kirby (1996)73. At EDF, internal studies started at the same time in
order to prepare the separation between activities of transmission (i.e., RTE) and generation
(i.e., EDF Producer) o f electricity (see section 1.2). After more than ten years of various
studies, the cost of ancillary services is now much better understood than it was before the
separation o f transmission and generation activities. This section reviews the main cost
components that frequency and voltage control ancillary services cause for an electricity
producer. The additional costs for the system operators are not considered.
73 In addition, various publications at that time were discussing the theoretical fram ew ork to
unbundle prices for energy and ancillary services, such as Baughman et aL (1997a), Baughm an et aL (1997b),
H ao and Papalexopoulos (1997), Z obian and Ilic (1997a), Z obian and Ihc (1997b).
3.2 MAIN COST COMPONENTS OF ANCILLARY SERVICES 145
Producer TSO
over-sized
To show tire complexity of determining the fixed costs due to ancillary services, let
us briefly discuss the additional cost of a step-up transformer used for voltage control. Step-
up transformers for large power plants are custom-built. The cost of this kind of
transformer relies on various parameters related to their design such as the labour needed to
design and build It, the materials used, its nominal power, its reactance74, its number of
poles73 and its capability to withstand lightning surges (the protection level).
In addition, the transportation cost can vary a lot from one site to another because
it is quite difficult to transport such a transformer. Typically, a site close to a large river or a
railroad has cheaper transportation costs than a power plant on an isolated site. Moreover,
if the oil tank or the magnetic circuit are reused, the cost may decrease drastically. Lastly,
74 F o r nuclear pow er plants, the reactance o f step-up transform ers ranges from 12 to 14 %. To
diminish this reactance, the winding length should be shortened. T o do so, a smaller winding radius can be
used, b u t the mechanical constraints are increased. Alternatively, a larger section may be used, bu t this m ethod
increases the space used, the w eight and the cost. A n optim um has thus to be found to satisfy the criteria o f
the generating company.
75 T hree single-phased transform ers are 15 % m ore expensive than a stand-alone three-phased
transform er.
146 CHAPTER 3 COST OF ANCILLARY SERVICES
the policies of the companies have also an important impact. Indeed, the generator may
favour different manufacturers to spread risks, while manufacturers may reduce prices to
increase their market shares.
Once the investment cost has been calculated, the actualised cost should be
determined in order to spread the investment cost over the lifetime of the transformer.
However, diis lifetime varies between 30 and 40 years for nuclear power plants, and some
step-up transformers for hydro units are still in use after 80 years of service16. In addition,
the investment cost is done in terms of apparent power (i.e., in MVA) and not in terms of
reactive power (i.e., in Mvar). Appropriate amortisation and separation between active and
reactive powers thus need to be performed. To do so, various techniques are possible. For
more details, see for example Eurelectric (1997), Da Silva et al. (2001), Alvarado et al (2003)
or Elizondo et al. (2006), who all try to give the estimated total investment cost due to
voltage control in various countries.
In conclusion, fixed costs are quite difficult to compute because costs are complex,
assets used to provide ancillary services have usually other purposes than the sole provision
of ancillary services and the lifetime to consider is not very clear. Therefore, it may be
useless to try to determine a very precise fixed cost, because calculations are likely to be
plagued by large uncertainties.
77 F o r example, an expensive unit may be called to provide only voltage control to support a given
area.
78 T he efficiency o f therm al units is related to the main steam pressure and the throttling o f the
turbine control valves. Bakken and Faanes (1997) show that the efficiency can decrease by 2 % w hen the
control valve is completely open, w hich can happen w hen a unit provides frequency control.
148 CHAPTER 3 COST OF ANCILLARY SERVICES
■ Deployment cost: it is the direct extra-cost to actually provide the requested service.
For example, more fuel may be used because the unit generates extra power or the
active power losses may increase [Cigre Task Force (2001), Gross et al (2002)];
■ Additional maintenance cost: wear-and-tear is increased, so elements of the unit are
aging faster than without providing any ancillary service. Note that this cost is
particularly high when a generating unit is used as a synchronous
compensator [Saluden (2006)].
Spot pn ce 2 Spot p n ce 2
Spot price 1 . ////
///s /s /s /s s s s s s s s s s /s ;
'S S S S /J S S S S
//////////A
V S /////S /S ,
P o w er P o w er P o w er
Figure 3.2: Schem atic d isp atch es to understand d e-op tim isation and opportunity costs
79 Windings o f step-up transform ers are w rapped in paper to avoid electrical contact betw een turns.
W hen die current increases, th e tem perature in the transform er increases as well. T his tem perature increase
extends die cellulose chains that are contained in the paper, w hich may possibly lead to a rupture. This rupture
may cause a short circuit betw een two adjacent turns. In addition, the cellulose rupture releases w ater, which
may react w ith the h o t oil.
3.3 M ETHODOLOGY AND HYPOTHESES TO ESTIMATE COST 149
In conclusion, variable costs are somewhat easier to identify and quantify than fixed
costs. The cost of capacity reservation is likely to be significant for frequency control, while
it is close to zero for voltage control, except for synchronous compensator operation. As
far as frequency control is concerned, the de-optimisation cost (i.e., the difference between
the costs of dispatch with reserves and without reserves) represents the main capacity
reservation cost. The direct utilisation cost due to voltage control is lower than the direct
utilisation cost due to frequency control. However, voltage control produces higher stress in
alternators and thus extra maintenance cost.
The previous section has presented the various components of the cost incurred by a
generating company because of ancillaiy sendees. Determining this cost is difficult because
(a) various time horizons have to be considered; (b) the cost has different origins; (c) the
allocation of the cost amongst the different products is hard, so double-accounting is
possible; (d) such a determination relies on simulations, because the system cannot be run
again without AS provision, so assumptions have to be made, which lead to uncertainties
and thus potential errors. Nevertheless, as discussed in this chapter, it is possible to estimate
the de-optimisation cost, which is one o f the most important components of the cost of
AS. This section introduces the optimisation process at EDF Producer (sections 3.3.1 and
3.3.2), describes the methodology adopted to estimate the de-optimisation cost for EDF
Producer (sections 3.3.3 and 3.3.6) and presents the main tools that have been used and the
related hypotheses (sections 3.3.4 and 3.3.5).
A generating company has to take decisions for various time horizons, such as [Ernu
(2007)]:
S Up to one week ahead: adequacy analysis, timing o f maintenance for thermal units,
definition of the generation cost, option contracting;
S Up to one day ahead, dispatch of the production, trade-off with available options (e.g.,
option contracts or spot market, as presented in section 1.3.1);
'd Several hours ahead bidding/offering in the balancing mechanism and re-dispatch.
When the time horizon increases, the number of constraints diminishes but the
uncertainty increases. Therefore, probabilistic approaches are adopted to deal with long
term issues: a large amount of computing power is used to run a large number of cases with
a relatively low number of constraints. O n the other hand, when the time horizon
decreases, the uncertainty decreases but there are many more constraints. Deterministic
methods are thus preferred: the computing power is used to take into account the
maximum number o f constraints, and the uncertainty is dealt with by taking margins (see
Figure 3.4 in section 3.3.3).
Figure 3.3 shows the tools used by ED F Producer to optimise and take decisions
over the different time horizons. ARRET, GLOBAL, LOCAL, OPHELIE and ARGOS
are the names of the various software chains. ORION, MNR, COMP AS and APO G EE
refer to the models used to optimise the decisions taken. Note that all the software chains
are operated by humans. Indeed, the solutions proposed by the models need to be
supervised and experts may decide to take different decisions by considering constraints not
handled by the models.
3.3 METHODOLOGY AND HYPOTHESES TO ESTIMATE COST 151
Feasible planning
Indicative generation
planning
Marginal costs
Market options to buy
Figure 3.3: O verview o f the optim isation process at E D F Producer [based on E m u (2007)]
^ APOGEE, which optimises the generation of the 110 thermal units and the 50 hydro
valleys8". APOGEE two days optimises the portfolio with a resolution of half-hourly
time steps over two days, i.e. 96 time steps81. As explained in section 3.3.1, decisions to
start up or shut down nuclear power plants must be made well in advance. Therefore,
once a nuclear unit is available, APOGEE usually commits it because the variable cost
of a nuclear power plant is very low but the shutdown costs are high. However,
APOGEE takes into account the maximum deep slow downs allowed per day and may
sometimes ask to shut down a nuclear power plant82;
81 A P O G E E can also be used to optimise the portfolio over 12 days (it is thus designated as
A P O G E E 12 days). T he algorithm is the same as A P O G E E 2 days, but the datasets are different. F o r the
sake o f simplicity, the term “A P O G E E ” is used in this thesis to designate A P O G E E 2 days.
82 W hen A P O G E E decides to shut dow n a nuclear pow er plant, it takes into account the tens o f
MW that the pow er plant consum es for its auxiliary systems. However, A P O G E E ignores the transmission
fees that will be incurred if all the nuclear units o f a given site do not produce any power, which is very rare.
152 CHAPTER 3 COST OF ANCILLARY SERVICES
^ CANYON, which optimises the 500 hydro units by taking into account much more
hydro constraints than A PO G EE does. This optimisation tries to meet the set points
provided by A POGEE for the valleys;
S COCKPIT, the Human-Machine Interface (HMT) that helps co-ordinate the various
modules of ARGOS. In particular, COCKPIT allows operators to change the dispatch
provided by the models.
Table 3.1 presents the management of frequency control reserves throughout the
short-term process adopted at ED F Producer.
This fee is quite high in France and across E urope because m o st o f the transm ission tariff is paid by
consum ers [French econom ic and industry departm ent (2005)].
3.3 METHODOLOGY AND HYPOTHESES TO ESTIMATE COST 153
85 Actually, producers cannot re-declare their production dispatch at any time. They can do it only at
specific times every hour.
154 CHAPTER 3 COST OF ANCILLARY SERVICES
To calculate this cost, APO G EE is used to run two simulations: one with the
reserve provision and a second one without any demand for frequency control reserves (see
Figure 3.4). Both of these dispatches are fictitious because the dispatch proposed by
APOGEE does not correspond to the ultimate dispatch. Indeed, CANYON and the
operators change the dispatch of APOGEE (see section 3.3.2). The cost difference between
the two dispatches gives the de-optimisation cost, as expressed in (3.1), where C T
f hmem> and
Without mmts are ^ie dispatch costs for the day D with and without providing reserves,
C di-optimisation
D = C with
D. m in t —C without
D resent (3' r»/
\
So far, such a study has never been conducted in the literature. Indeed, previous
publications were either not focused on the de-optimisation cost or were considering a
fictitious portfolio for a limited number of days and with a non-dedicated algorithm [e.g.,
3.3 METHODOLOGY AND HYPOTHESES TO ESTIMATE COST 155
H im and Kirby (1997), Proctor (2001), Wu el al. (2004), Galiana et ah (2005), Ortega-
Vazquez and Kirschen (2007)]. O n the other hand, the proposed method is practical
because the computation burden is manageable and because it acknowledges that doing
again the whole optimisation process without considering the reserve provision is practically
impossible, since too many parameters are likely to change. This method is also realistic,
because the constraints and the portfolio are actual data. Lastly, the optimisation algorithm
used is complete and adapted to the problem, as it has been specifically developed by EDF
over tens of years.
3 .3 .4 .1 In p u ts o f t h e m o d e l
All the input data considered in this study are those available to A PO G EE at around 13h00
on D—1 (see Table 3.1). The first run of our study has the operational data as input, without
any change. On die other hand, the second run uses as input the operational data with the
reserve demand set to zero. However, even if the demand is zero, units can still provide
reserves for this second run, because:
S Units that have been pre-scheduled with reserve prior to the APOGEE run are still
providing reserves;
S A PO G EE may estimate that it is cheaper to dispatch reserve than not to provide any.
156 CHAPTER 3 COST OF ANCILLARY SERVICES
3 .3 .4 .2 A v a ila b le d a t a s e t s
A POGEE uses text files as inputs and outputs. To give an idea of the quantity of data to
manipulate, a dataset for one day represents around 60 text files and 6 MB. Table 3.2 shows
the periods studied and the available data. A non-valid day is a dataset for which APO G EE
was not able to run, usually because of files lost during the process o f archiving the
operating data. In addition, the data from 01/01/2006 to 24/06/2006 were unfortunately
not available. The present study is therefore based on 879 valid days, which is a sufficient
large number to give significant results. In addition, note that each day represents 48 half-
hourly time steps, so 42 192 valid half-hours are included in this study.
N um ber N um ber o f
N um ber Percentage o f
From To o f valid non-valid
o f days non-valid days
days days
08/09/2004 31/12/2005 480 460 20 4.2 %
25/06/2006 30/08/2007 432 419 13 3.0 %
T otal 912 879 33 3.1 %
3 . 3 . 4 . 3 H y p o t h e s e s fo r m i s s i n g d a t a
As shown in Table 3.2, some datasets were not available. These missing data are simply
ignored when frequency distributions84 are calculated. However, it is important to complete
this missing data to capture any seasonal effects (see section 3.4.2).
These missing data cannot be arbitrary set to zero because this will unbalance the
series. Therefore, a moving average is used: the average of previous and next data is
calculated to obtain the missing data x exlrapg/a/fd, as expressed in (3.2), where x is the series
considered and window the width of the extrapolation (an odd integer larger or equal to
three). This approach is more accurate if the series has a strong autocorrelation. For the
special case of time steps, time step 1 is completed by averaging all the time steps 1 from
D—i and D+i, where i varies from 1 to the half of the window, and so forth for the 47
remaining time steps. The size of the window actually does not matter too much since the
number of non-valid data is low. However, this window was chosen as a function of the
seasonality of the series. Lastly, note that this extrapolating method does not differentiate
working and non-working days.
Sec A ppendix A .l for an explanation o f the basic statistics and m ethods used in this thesis.
3.3 M ETHODOLOGY AND HYPOTHESES TO ESTIMATE COST 157
x[k]+ £ * [£ ]
nvidrn—1 £=D+1
X (xmpo!atti \ = . , I
window —1
3 .3 .4 .4 O th er d a ta
The RTE’s r e s e r v e demand for EDF Producer, as well as EDF Producer’s programme d'appel
(see Table 3.1), have been retrieved as spreadsheets from 01/01/2005 to 31/08/2007.
The target frequency of die secondary frequency control for each day during this
period has also been provided (i.e., 49.99, 50.00 or 50.01 Hz, see section 2.3.4.3). These data
are useful to calculate the cost of time control (see section 3.6), since the target frequency
impacts the volume of frequency control reserve.
3 .3 .5 .1 APOGEE
As presented in section 3.3.2, APOGEE optimizes EDF Producer’s thermal units and
hydro valleys over two days (i.e., 96 half-hourly time steps). In an optimisation problem, the
primalproblem is to minimize the objective function / ( x px ,...x j subject to the j constraint
functions mj( x ,,x 2...xn) >where (x t, x ?...xtt) are the primal variables, for which the values are
The primal problem is often difficult to solve directly because the constraints create a
coupling between the primal variables, so the dualproblem, which leads to the same solution
if the objective function f ( x px 2...xH) is strongly convex85, is often used instead and is
defined as:
85 A strong])' convex two-dimension set is a set for which the segm ent betw een any pair o f its points is
contained in the set, boundaries excluded. A realjunction is strongly convex if the set o f points lying on or
above its graph forms a strongly convex set.
158 CHAPTER 3 COST OF ANCILLARY SERVICES
and where (Xr .X .) are called the Lagrange multipliers. They represent the worst penalty that
can be applied to the violations of constraints (the worst constraints imply that the solution
found is the best). Note that the dual problem is feasible only if it is separable (i.e., if the
primal objective function and the constraints are additive, or in other words, if the
minimum of the Lagrangian function can be found for a given set of Lagrange multipliers).
This method consisting in putting the constraints into the objective function is often called
dual optimisation technique or Lagrangian relaxation [e.g., Lasdon (1968), Wood and
WoUenberg (1996), Bertsimas and Tsitsiklis (1997) or Kirschen and Strbac (2004a)].
To find the solution of the dual problem, A PO G EE uses an algorithm based on the
price decomposition (see Figure 3.5) [Lemarechal (2004)]. The coordination algorithm
increases or decreases the prices for power and reserves as a function of the mismatch
between the target and the dispatch. These prices are the Lagrange multipliers. The sub
problems are then optimised individually, where each thermal sub-problem is solved using
Dynamic Programming (DP)86 and each hydro sub-problem is solved using Linear
Programming (LP)87. Each sub-problem maximizes the profits that would arise if the
Lagrange multipliers were prices that could be turned into income. Note that the generation
cost of hydro is equal to the value of water times the quantity of water released. In addition,
every group has a penalty to switch from reserve provision to no reserve provision (and
vice versa). This cost has no physical meaning, and is only a penalty to “encourage”
APOGEE to propose a “smooth” program, i.e. that avoids erratic switchings.
Following this first optimisation, the dual variables (i.e., the prices for power and
reserves) are obtained. A second optimisation is then performed to fine-tune the first
solution. The augmented Lagrangian method is used in this case [Cohen (1978)]. To
calculate the cost of the whole dispatch, APO G EE penalizes the gap between the target
86 A D P problem is m odelled as a set o f various states. T he optim isation algorithm then tries to
maximize the gain to switch from different states.
87 In a LP problem , th e objective function to solve is a set o f linear functions. In A P O G E E , the
simplex m ethod is used to solve this problem .
3.3 M ETHODOLOGY AND HYPOTHESES TO ESTIMATE COST 159
and the dispatch for power and reserves. Penalties are the same for all the first 48 time steps
of the day. They then decrease by 5 % per time step.
Concerning A PO G EE’s convergence performance, the same penalties and the same
number of iterations are applied to the two dispatches of a given day (i.e., with and without
reserves). However, note that these penalties and the number of iterations have actually
evolved over the period studied, as a function of computing power and operational policies.
multiplying for each time step the gap with its corresponding marginal cost (see
section 3.3.6).
Coordination algorithm
Prices for pow er and reserves for each time step Generation
planning
3 .3 .S .2 O T E S S
APOGEE uses text files as inputs and outputs (around 6 MB/dataset). In order to manage
such a large set of data (1 758 valid days and 10 GB o f data), a specific tool has been
developed in this study, named OTESS (OuTilpour PEtude des Services Systeme - Tool for the
study of ancillary services) and described in more details in Appendix A.2. The purpose of
this tool is to modify the APOGEE input datasets, store the A POGEE output data in a
relational database and then to study the data through a web-basedinterface (see
Figure 3.6). The main features of OTESS are the following:
S Extract the selected data from the A PO G EE output files and store them into a
relational database;
3.3 M ETHODOLOGY AND HYPOTHESES TO ESTIMATE COST 161
S Store any kind of additional data in its database, such as such as the target frequency,
the balancing mechanism prices or the final dispatch planning (the programme d’appel)-,
S Easily modify data with user-defined scripts;
V Allow complex querying on cross-related tables;
^ Display data with various graph types directly from queries(e.g., scatterplots or
frequency distributions). Most of the graphs of this chapter are extracted from OTESS;
S Perform basic data mining techniques;
S Export data under various formats (e.g., CSV or XML88);
S Share data between users since it is a server-based softwarewitha web-based human-
machine interface;
S Run on both Linux and Windows environment;
'S Based on free software;
^ Is strongly modular since it is object-oriented.
E DF’s dispatch
a lgo rith m (APOGEE)
Core o f OTESS
Database
otess
®?<.F J f l ||J ^ § & a U w d r e h u u s e O utputs R esource* Web-based
human-machine
Management of dataset^ ^ f ^ , script '1. Initial interface
3 . 3 . 5 . 3 N A G a d d - in for E x c e l
88 CSV stands for Comm a-Separated Values and XML for Extensible M ark-up Language
162 CHAPTER 3 COST OF ANCILLARY SERVICES
not been implemented in OTESS yet. Instead, the Microsoft® Office Excel® statistical
add-in from Numerical Algorithms Group (2007) has been used in this study after having
exported the data under CSV format.
In this study, the dispatch cost is directly extracted from APOGEE, and not from
COCKPIT. Therefore, some errors of tens of k€ may mar the results because A POGEE
does not exactly calculate die cost from the actual dispatch (see section 3.3.5.1).
the different marginal costs, P the power dispatched during the time step (in MW), Rsei. the
secondary reserves (in MW), Rpn the primary reserves (in MW) and D the day o f dispatch.
With:
These relations are worth some comments and some remarks from section 3.3.5.1
have to be highlighted. First, these costs and penalties are calculated for the day D because
uncertainty is too high for D + l to consider gaps for D + 1 as wrong. Second, tertiary reserve
is not included in (3.6) because it is currendy not optimised by A PO G EE two days
(whereas it could do so). Indeed, ED F Producers and RTE agreed that specific units (hydro
3.3 METHODOLOGY AND HYPOTHESES TO ESTIMATE COST 163
units and gas turbines) provide this reserve. Third, the penalty for reserves is zero when
APOGEE provides more reserves than its target. Lastly, the hydro cost may be negative if
reservoirs have higher levels of water at the end of the day than they had at the beginning.
In addition, the hydro cost does not represent the actual cost (which is close to zero for
hydro), but instead values the loss of water.
164 CHAPTER 3 COST OF ANCILLARY SERVICES
0 2t
0.18-
0 1&
0 14
Distribution
0.12
0 1
00 8
00&
0 04
0 02
(a) Power
0 2t
0.18t
0 16
0 14
Distribution
01
0 08
0 06
0 04
002
0 18
0 16
0 14
0 12
Distribution
0 1
0 08
006
0 04
0.02 J"
Figure 3.7: Frequency distributions o f the gap b etw een A P O G E E dispatch and A P O G E E dem and
for all the studied tim e steps b etw een 1 and 48
3.4 DAY-AHEAD DE-OPTIMISATION COST FOR A PRODUCER 165
While the previous section presents the methodology adopted in this study, as well as the
hypotheses made, this section gives the results obtained concerning the de-optimisation
cost. For obvious confidentiality reasons, only data that do not reveal EDF costs, while
providing essential results are given here. These results can be applied to some extent to
other systems. However, die best would be to apply the same methodology with the actual
portfolio and optimisation algorithm of each system.
the de-optimisation cost Cft_ by the dispatch cost with reserves as shown
in (3.8). The missing days have been extrapolated with a 7-day moving average (see
section 3.3.4.3). Extrapolated points have been marked by crosses in Figure 3.8.
de-optimisation
relathx de—optimisation
(3.8)
irith resen ys
166 CHAPTER 3 COST OF ANCILLARY SERVICES
0.08
0.07
2005 2006
0.06
.2 0.05
0.04
2007
% 0.03
0 .0 ’
Figure 3.8: E volu tion o f the relative d e-op tim isation c o st from 0 1 /0 1 /2 0 0 5 to 3 0 /0 8 /2 0 0 7
First, the de-optimisation cost tends to be relatively highfrom the beginning ofA pril (around day
90) to the end of October (around day 300), with the most expensive days in April 2005 and
August 2006. The high de-optimisation cost during summer can be explained by the
environmental constraints, which lead to less hydro power being available. Nevertheless,
2007 sees a low cost during the summer, which may be explained by both a better
modelling of the capabilities of hydro units and a better water availability. Second, the
relatively low cost during the whiter hides a high absolute de-optimisation cost. Indeed, the dispatches
are expensive during this period because the portfolio is constrained by the high demand
for energy. The parameters influencing the costs will be discussed in more details in
section 3.4.3.
Besides giving some hints on the parameters that may influence the de-optimisation
cost, Figure 3.8 gives two important results. First, the day-ahead de-optimisation cost is not
negligible, since it represents up to 7.8 % of the initial dispatch cost. In particular, Figure 3.9
shows the frequency distribution of the relative de-optimisation cost Cfela(i!Kde_optimjmtion. The
average of the relative de-optimisation cost calculated by APO G EE two days was equal to
2.2 % over the studied period. Therefore, this cost cannot be ignored, since it represents
hundreds of millions of Euros every year. In addition, note that this result is in line with
3.4 DAY-AHEAD DE-OPTIMISATION COST FOR A PRODUCER 167
Proctor (2001), who estimates the spinning reserve costs around 2 % of the total operating
expenditure in a 16-unit system.
Second, the day-ahead de-optimisation cost exhibits strong daily variations. To evaluate the
gives the relative variation of the de-optimisation cost for D in comparison to D -l. The
frequency distribution of this indicator is given in Figure 3.10. It is clear that the de
optimisation cost has a strong variation (greater than ±20 % in more than 54 % of the
days). The design of the market should therefore take this variation into account to help
participants seize the opportunities (see Chapter 4).
1
D dr- optimisation de—optimisation
A%C de—optimisation D-l (3.9)
C de—optimisation
0.15 t
0.14
0.13
0.12
0.11
>,0.09
| 0.08
£ 0.07
£ 0.06
0.05
0 04
0.03
0.02
0.01
- . 1 1 1 l l .l 1 1 1 «=w =
0.01 0.02 0.03 0 04 0.05 0.06 0 07 0.08
Relative deoptimisation cost
F ig u re 3.9: F re q u e n c y d is trib u tio n o f th e relative d e -o p tim isa tio n c o st for all th e stu d ie d d a y s8
89 T he term “probability” is used here instead o f “relative frequency” by misuse o f language (see
A ppendix A.1.1).
168 CHAPTER 3 COST OF ANCILLARY SERVICES
0.13r
0.12
0.11
0.1
0.09
>. 0 08
1 0.07
| 0.06
it 0.05
0.04
003
0.02
001
Figure 3.10: Frequency distribution o f the variation o f d e-op tim isation c o st over tw o days for all the
studied days
days. Figure 3.15 shows a clear weekly seasonality, while Figure 3.13 and Figure 3.14 analyse
in more details die two peaks around 30 and 90 days. The partial autocorrelation
coefficients are however not large enough for these two peaks to be really significant.
Lastly, there is no seasonality effect over longer periods, such as several months.
0.5
0.4
c 0 ,3
.9
go 0-2
oo
3 0.1
<
100
- 0 .2 J
w From 01/01/2005 to 31/12/2005 -v From 01/08/2006 to 31/07/2007
F igure 3.11: A utocorrelation function o f the d e-op tim isation c o st up to 1-year period
170 CHAPTER 3 COST OF ANCILLARY SERVICES
0.4
0.2 -
LL.
o<
CL
- 0.1 -
Period
-0.2 J
F igure 3.12: Partial autocorrelation fu n ction o f the d e-op tim isation c o st up to 1-year period
0.1
0.05
91 92 96
-0.05
- 0.1
Period
-0.15
Figure 3.13: Partial autocorrelation fu n ction o f the d e-op tim isation co st around a 3-m on th period
0.2
0.15
0.1
0.05
20 21 22 27 28 U 35
-0.05
- 0.1
Period
-0.15
Figure 3.14: Partial autocorrelation fu n ction o f the d e-op tim isation c o st around a 1-m onth period
3.4 DAY-AHEAD DE-OPTIMISATION COST FOR A PRODUCER 171
0.7 -|
0.4 -
u.
O
<
CL
0.2 -
Period
F igure 3.15: Partial autocorrelation fu n ction o f the d e-op tim isation c o st around a 1-w eek period
3 . 4 . 3 . 1 I m p a c t o f t h e m a r g in a l c o s t s
Figure 3.16 shows the normalized de-optimisation cost as a function of the weighted
marginal cost of reserves 4^ , as defined in (3.10) and where the notations are similar to the
ones used in section 3.3.6. Since is defined for each time step of the day, the data
plotted here is the average over the 48 time steps of a day. It is clear that the de
optimisation cost and the weighted marginal cost of reserves exhibit a strong linear relation,
confirmed by a correlation coefficient91 r of 0.94. Figure 3.17 shows the de-optimisation
cost as a function of the primary and secondary reserve marginal costs, and a similar linear
relation is found. Therefore, the expected de-optimisation cost clearly increases ivith the daily average
marginal costs of reserves,
Xn
Kfri
x R.Pn ■
dispatch
T A.1 x R ,
K*r a t dispatch
(3.10)
RpP 1dispatch + R ;^tspaicb
R 2.5
w
nx
1 1.5 2 2.5 3 3.5 4 4.5
E -0.5 Weighted marginal cost of reserves (average)
Figure 3.16: N orm a lized d e-op tim isation c o st as a fu n ction o f the average n orm alized w eig h ted
m argin al c o st o f reserves for all th e stu d ied days (rxy = 0.94)
.3 1.5
F igure 3.17: N orm a lized d e-o p tim isa tio n c o st as a fu n ction o f th e average norm alized m arginal co st
o f reserves for all the stu d ied days
3 .4 .3 .2 I m p a c t o f t h e d e m a n d for r e s e r v e s
Figure 3.18 shows the relation between the de-optimisation cost and the maximum primary
reserve demand over the day (i.e., max^R^/ rfj). The correlation between these two
variables is not very clear, but the period spanning from 01/08/2006 to 31/07/2007
exhibits a more interesting relation (see Figure 3.19). Indeed, when the maximum demand
increases, the de-optimisation cost becomes more spread with a trend for high expected
values, whereas the expected de-optimisation cost is quite low when the maximum primary
3.4 DAY-AHEAD DE-OPTIMISATION COST FOR A PRODUCER 173
reserve demand over the day is low. This relation is however not true for 2005, as shown in
Figure 3.20, which explains the poor correlation over the whole study period (i.e.,
Figure 3.18). The de-optimisation cost is dispersed for a given reserve amount since the portfolio
conditions may be very different for the same reserve demand. In addition, requiring high
volume of reserve increases the constraints on die dispatch, so the de-optimisation cost tends to
increasefor high reserve demands.
The daily average of primary reserve demand shows a similar relation as the
maximum demand for primary reserve, as shown in Figure 3.21. On the other hand, the
impact of secondaty reserve on the de-optimisation cost seems to be Io n since the correlation coefficient
is equal to -0.18 and since Figure 3.22 does not show any clear pattern. This is probably due
to the fact that the French generating units’ capabilities are twice as large for secondaty
reserves than they are for primary reserves (e.g., most of the French nuclear power plants
allocate around 2 % of their nominal power to primary reserve and 5 % to secondaty
reserve92). Therefore, dispatching primary reserve is more constraining than dispatching
secondaty res ewe for the French portfolio.
In conclusion, primary res ewe demand seems to have an impact on the de
optimisation cost, whereas the influence of secondary reserve has not been clearly
identified. Therefore, increasing the primary reserve provision capabilities may be a good
way to reduce the constraint due to primary resewe demand and thus to decrease the de
optimisation cost. In addition, an accurate generic de-optimisation cost function depending on the
de?nand for reserves cannot be built because the dispersion is high. This latter subject will be
investigated in more details in section 3.4.4.
92 Some nuclear pow er units, such as 900-MW plants, may be dispatched how ever w ith a 7-%
provision o f primary frequency control reserve.
174 CHAPTER 3 COST OF ANCILLARY SERVICES
4.5r-
4
3 .5 -
* X
X
X K X ' ....
» 1.5
“ * * v ’ . jj t f *** *
t) -0.5
-2.5 —
F igure 3.18: N orm a lized d e-op tim isation c o st as a fu n ction o f the m axim u m n orm alized primary
reserve d em an d for all the stu d ied days (r*y = 0.39)
o
2 0.51
Normali
F igure 3.19: N orm alized d e-op tim isation c o st as a fu n ction o f the m ax im um n orm alized primary
reserve dem and from 0 1 /0 8 /2 0 0 6 to 3 1 /0 7 /2 0 0 7 (rxy = 0.71)
x x
.... . . x . .
..
x x x n
'H 15 * -
? 15 *2 iS’.S 3 M r
-0.5 nali^i prir^ryTesjtn/e ^lepiandf(maiimum)
* -* H f— ~
x * ....
F igure 3.20: N orm a lized d e-o p tim isa tio n c o st as a fu n ction o f the m axim u m norm alized primary
reserve d em an d from 0 1 /0 1 /2 0 0 5 to 3 1 /1 2 /2 0 0 5 (% = 0.13)
3.4 DAY-AHEAD DE-OPTIMISATION COST FOR A PRODUCER 175
# m
a 1.5 % ■*
d (r»M n)
**
Figure 3.21: N o rm a lized d e-op tim isation c o st as a function o f the m ea n norm alized primary reserve
dem and for all the studied days (rX7 = 0.38)
u 2.5
» 1.5
£ 0.5
«2.5 3 3.5 4
.M -0.5 ^(m ean)
F igure 3.22: N o rm a lized d e-op tim isation cost as a function o f the m ea n norm alized secondary
reserve dem and for all the studied days (rxy = -0.18)
Figure 3.23 shows the relation between the de-optimisation cost and the minimum thermal
share for reserve rnin(share'/t/) over the day. The thermal reserve share sharetb for a time step
i is calculated as shown in (3.11). When the minimum thermal share is high, the de
optimisation cost tends to be high as well. In other words, when hydro cannot he used extensively
to provide reserves for some critical time steps, the de-optimisation cost tends to be high. As a corollary,
thermal participation to reserves tends to be expensive for some critical time steps. This link
between hydro participation and de-optimisation cost is explained in section 3.4.4.
R P” dispatch
J tb + Riff ‘dispafrb lb
share[, (3.11)
RP***dispateb + Rsec’dispatch
176 CHAPTER 3 COST OF ANCILLARY SERVICES
4 ---------
jrvqg (minimum)
Figure 3.23: N orm a lized d e-op tim isation co st as a fu n ction o f the m in im u m reserve share provided
by therm al units for all the stu d ied days (rxy = 0.44)
As shown in section 3.4.3.2, the de-optimisation cost is linked to the daily average reserve
demand, but the relation is not straightforward. Therefore, this section attempts to provide
an insight on this relation by analysing the evolution of the de-optimisation cost for a given
day as a function of the reserve demand. Thursday 24 May 2007 is considered here, because
this is a recent day with an average de-optimisation cost. Indeed, the relative de
optimisation cost for this day is around 1.9 %, whereas the average is 2.2 % for all the
studied days (see section 3.4.1). The initial demand for reserves has been multiplied by a
coefficient ranging from 0 % to 100 %, with a step of 1 %. As 100 % correspond to the
simulation with the initial demand and 0 % to the simulation without reserves, 98 additional
simulations have been launched for this study.
of the average reserve demand over the day. This de-optimisation cost is redefined as
shown in (3.12), where C ®lhX»/0^ A/mnr( ^ ) corresponds to the dispatch cost when the
demand for reserves is equal to X % of the initial demand, with X ranging from 0 to 100.
The average amount of reserves along the horizontal axis is obtained by summing the
demand for primary and secondary reserves over the 48 steps of the day, and then by
dividing this sum by 48. Below an average demand around 500 MW (i.e., one third o f the
total reserve demand), reserves do not cause any supplemental cost for APOGEE
according to our hypotheses (see section 3.3.3) and the model’s limits (see section 3.3.5.1).
3.4 DAY-AHEAD DE-OPTIMISATION COST FOR A PRODUCER 177
demandof reserves between 0 and 500 MW, In other words,the dispatch cost
x %nj inina ^ie same whatever is the provision of reserves below 500 MW.
However, beyond this point, the de-optimisation cost depends almost linearly on the demandfor reserves,
with a slope around 2.7x1 (T3 % /MW/day, i.e. C fT hx%nf hMajirJMf(X ) increases almost linearly
beyond 500 MW of reserve. Figure 3.25 shows the schematic cost curve superimposed on
the actual calculation.
,y \ C uith
D resort —C nitb
D X % of initial n s m v(PC)
\ )
rrla/iiv de—optimisation \ / y' •D \ ' )
uitb re.te/rr
(3.i3)
C relative
D de—optimisation fOl
\ ) = CD
rclaliif de-optimisation
(3141
V' >
93 R em em ber that the choice has been m ade in this stud}7to keep ail die initial operational constraints
to evaluate the de-optim isation cost (see section 3.3.4.1).
178 CHAPTER 3 COST OF ANCILLARY SERVICES
procedures thus do not acknowledge that it may be more efficient to set hydro units at
100 % for some expensive time steps, though at degraded efficiency. As a consequence of
these two operating procedures (i.e., pre-scheduled reserves and compulsory participation
when providing energy)94, providing reserves with hydro cause litde de-optimisation cost for
APOGEE, whereas there is an actual de-optimisation cost. It is important to note that the
second part of the curve of Figure 3.25 is likely to give an order of magnitude of the actual
constraints due to both hydro and thermal reserves. Therefore, the actual de-optimisation
cost could be extrapolated by using the second part of the curve for the whole reserve
demand. Furthermore, it is also important to quote that the “free hydro reserve” for the
model (but which has a cost in the real world) is only available during the day, i.e. when
hydro units are synchronised. At night, this is not true because French hydro units are not
synchronised except some units that are able to pump water or those that cannot store
water (run-of-water units). However, this type of units cannot provide reserves while
pumping.
This threshold effect that leads to a non-linearity may thus explain the poor direct relation
between the average reserve demand and the de-optimisation cost (see section 3.4.3.2). This relation is
also in line with the conclusions of section 3.4.3.3, i.e. the de-optimisation cost calculated by
APOGEE tends to increase when the hydro participation in reserve decreases.
is 1-6
S °-8
0>) 0.6
§ 0.4
* 0.2
100 200 300 400 500 600 700 800 900 1000 1100 1200 1300
Average amount of reserves (MW)
•v De-optimisation cost for the 24/05/2007 S' Smoothed de-optimisation cost
Figure 3.24: R elative d e-op tim isation c o st as a fu n ction o f the n ew d em an d for reserve for 2 4 /0 5 /2 0 0 7
9,1 T hese operational limitations will be rem oved in the short term , b u t will require a m ore complex
optim isation algorithm.
3.5 MARGINAL COSTS OF FREQUENCY CONTROL FOR A PRODUCER 179
1.8
Supplemental cost:
1.6 2.7x10-3 %/d ay/MW
100 200 300 400 500 600 700 800 900 1000 1100 1200 1300
Average amount of reserves (MW)
F igure 3.25: Sim plified relative d e-op tim isation cost as a function o f th e n ew dem and for reserve for
2 4 /0 5 /2 0 0 7
Section 3.4.3.1 has shown that the marginal costs impacts the final de-optimisation cost.
Indeed, the marginal costs of reserves reflect the constraints due to frequency control
provided by a producer. Therefore, this section proposes to study these marginal costs. For
confidentiality reasons, the absolute values are not given. Instead, comparisons between
marginal costs are preferred in order to identify the binding and non-binding constraints.
during critical time steps in order to allow a conversion of the cheaper energy into reserves. However, such
arrangements would be profitable only if the difference between the marginal costs of
reserves and energy is large enough. For confidentiality reasons, this data cannot be
published here.
To assess the influence of the type of frequency control, Figure 3.27 shows the
percentage of time when marginal costs for primary reserve are higher than marginal costs
for secondary reserve as a function of the time of the day for all the studied time steps. It is
clear that primary reserves are usually more binding than secondary reserves, which is in line with the
results of section 3.4.3.2. Indeed, this section shows that the de-optimisation cost is more
sensitive to the demand for primary reserve than the demand for secondary reserve.
100 ,
90 —
£ 70 \
! 60 |
O 50
E 40
§ 30
a>
a 20
10
Time step
F igure 3.26: P ercentage o f tim e w h en m arginal costs o f energy are h igh er th an m arginal costs o f
reserves as a fu n ction o f the tim e step for all the stu d ied days
£ 30
30
Time step
F igure 3.27: P ercentage o f tim e w h en m arginal costs o f primary reserve are h igh er th an m arginal
c o sts o f secondary reserve as a fu n ction o f the tim e step for all the stu d ied days
3.5 MARGINAL COSTS OF FREQUENCY CONTROL FOR A PRODUCER 181
20r
18
16
g 14
0
E 12
20 30
Time step
-v Null primary marginal cost v Null secondary marginal cost
Figure 3.28: P ercen tage o f tim e w h en m arginal costs o f reserves are null as a fu n ction o f th e tim e o f
the day for all the studied tim e steps
RTE modulates its demand for primary frequency reserves by ±150 MW because of the
time control. In fact, the time control modifies the system frequency, which leads to the
deployment of primary frequency control power (see section 2.3.4.3). As the demand for
reserves impacts die de-optimisation cost (see section 3.4.3.2), this section estimates the de
optimisation cost because of the modulation of the demand for reserves. Therefore, new
simulations were launched with the following changes in the initial datasets:
S Targetfrequency at 49,99 ITy. the initial primary reserve demand is decreased by 150 MW for
each time step of the day;
V Targetfrequency at 50.01 Hy: the initial primary reserve demand is increased by 150 MW for
each time step of the day.
Note that these values correspond to the modulation of the demand for the whole
of France. Therefore, by applying these values to EDF Producer’s portfolio, the de
optimisation for the whole France can be estimated. It is thus assumed that the French cost
structure is equivalent to the one of EDF Producer.
Figure 3.29 and Figure 3.30 give the frequency distribution of the relative de
optimisation cost due to frequency control for all the studied days from 01/01/200596. On
average, the time control cost (because of an increased reserve demand) 0.46 % of the initial
dispatch cost at 49.99 Hz, and saved (because of a decreased reserve demand) 0.57 % of the
initial dispatch cost at 50.01 Hz. The average cost obtained with the target frequency set to
50.01 FIz has to be taken with caution, since the number of days is not sufficient to provide
very significant results, and because the scattering of data is high (27 days at 50.01 Hz,
whereas there were 175 days at 49.99 Hz). The de-optimisation cost due to time control thus
represents tens of millions of euros over oneyear. One can thus wonder whether this cost is justified.
Lasdy, it is important to note that the de-optimisation cost due to time control is included
in the de-optimisation cost calculated in section 3.4, since the initial demand for reserves
takes into account the time control.
% T he time control study is perform ed from 0 1 /0 1 /2 0 0 5 because available data on target frequency
span from 0 1 /0 1 /2 0 0 5 to 3 1 /0 8 /2 0 0 7 (see section 3.3.4.4).
3.7 CONCLUSION 183
0.16,
0.14
0.12
0 . 1*
| 0.08
o
£ 0 06
0 04
0 02
Hi
02 04 0.6 0.8 1 1.2
Relative de-optimisation cost (in %)
Figure 3.29: Frequency distribution o f the relative de-op tim isation cost due to tim e control w ith
f, = 49.99 H z for all the studied days from 0 1 /0 1 /2 0 0 5
0.16,
0.14
0.12
>. 0.1
fg 0.08
.a
o r- rn r~ n
£ 0 06
0.04 _ jjfc
0 02
Figure 3.30: Frequency distribution o f the relative d e-op tim isation co st due to tim e control
f, = 50.01 H z for all the studied days from 0 1 /0 1 /2 0 0 5
3.7 C onclusion
This chapter has reviewed the main cost components of ancillary sendees and has proposed
a methodology to estimate the day-ahead de-optimisation cost due to frequency control
incurred by a producer. This methodology has been successfully applied to EDF Producer,
and has provided several interesting results. Therefore, this methodology could be applied
to other producers in order to perform a similar economic assessment. The main findings
of this chapter are listed below. Policy makers could use these findings to assess their
current policies.
S Estimating the full real cost of ancillary services is impossible for a producer.
184 CHAPTER 3 COST OF ANCILLARY SERVICES
■ Ancillary services exhibit both fixed and variable costs that have each several cost
components such as over-investment, capacity reservation or utilisation;
■ Different inter-dependent time horizons have to be considered, from tens of years ahead
to real-time. For example, the day-ahead de-optimisation cost is linked to the over
investment that has been done several years before;
■ It may be difficult to separate the cost due to ancillary servicesfrom the cost due to otherproducts
such as the provision of energy. A classical example is the separation of the cost of
reactive and active power provisions with an alternator;
■ The cost of ancillary services depends on the portfolio considered and it is affected by many
uncertainties, especially for utilisation costs.
V One main cost component of frequency control is the day-ahead de-optimisation cost due to
the reservation of the capacity to provide reserves. A. methodology has been proposed to
estimate this cost and a specific tool, named OTESS, has been developed to apply this
methodology to any producer;
V This methodology has been successfully applied to ED F Producers portfolio (i.e., around 150
thermal units and 50 hydro valleys) over 879 days with actual operational data and
ED F’s actual optimisation algorithm;
V The results obtained are very helpful to assess the frequency control provision in France. In
addition, they give some hints to improve the system regarding both the technical
aspects and the market design. In particular:
* The de-optimisation cost is not negligible, since it represents up to 7.8 % of the initial
dispatch cost. In addition, this result is an underestimate because of the modelling
limitations (numerous inflexible constraints for hydro units) and the methodology
(short-term approach and unchanged initial constraints). Therefore, an efficient
provision of frequency control reserve is essential to reduce this cost as much as
possible;
■ The de-optimisation cost exhibits strong variations (greater than ±20 % in more than 54 %
of the days). Consequently, the market design should take this variation into
account to help participants reap opportunities;
■ The seasonality of the de-optimisation cost is relatively poor; even if the auto-correlation of
the de-optimisation cost is quite good over one week. Therefore, it does not seem
possible from the timeframe considered to select a particular period and then to
generalise the result of this period over the whole timeframe. In particular, results
3.7 CONCLUSION 185
cannot be generalized from one year to another. Hence, future studies on the de-
optimisation costs have to consider a large number of days to be accurate. In
addition, these further results may help to identify potential seasonalities;
■ For EDF Producer, the de-optimisation cost is sensitive to three majorparameters'.
n The expected marginal costs, there is a strong link between the marginal costs of
reserves and the de-optimisation cost. Therefore, the marginal costs can be used
as a proxy to estimate the de-optimisation cost;
n The primaty reserve demand: primary reserve demand has an impact on the de
optimisation cost, whereas the influence of secondary reserve has not been
clearly identified. Therefore, increasing the primary reserve provision capabilities
may be a good way to reduce the constraint due to primary reserve demand and
thus to decrease the de-optimisation cost. Unfortunately, it is impossible to
build a generic de-optimisation cost function depending on the demand for
reserves because the dispersion is high;
n The quantity of reserves provided by hydro units, when hydro cannot be used
extensively to provide reserves for some critical time steps, the de-optimisation
cost tends to be high. As a corollary, thermal participation to reserves tends to
be expensive for some critical time steps. This trend is due to a somewhat
simplistic modelling of hydro units in the optimisation algorithm and should be
weaken in the future with more complex constraints taken into account.
■ The demandfor reserves can be the most binding constraint. Therefore, the demand for one
additional MW of reserve can cost more than the demand for one additional MW of
energy. It may thus be useful to develop storage or load control strategies for these
critical time steps in order to allow a conversion of the cheaper energy into reserves;
■ The reserves may not be binding at all (from the model’s perspective), so the security of
the system can be increased at very low cost by increasing the demand for reserves
during periods when the marginal costs of reserves are low. This result is in line
with the conclusion of Chapter 2 arguing the advantages of an elastic demand for
reserve.
■ The de-optimisation cost due to time control represents tens of millions of eurosperyear in France.
The value of such an expenditure needs to be proven. ■
186 CHAPTER 3 COST OF ANCILLARY SERVICES
CHAPTER 4
PROCUREMENT OF SYSTEM
SERVICES
It is often the solution directly set aside that mould have been the tight one.
Edouard Michelin (1859 - 1940)
4.1 Introduction
NCILLARY sendees and energy are most of the time provided by the same
A generating units, and the provision of AS generally reduce the amount of energy that
a generating unit can produce, and vice versa. Ancillary sendees can thus be viewed as an
externality of the energy market. To manage externalities, economists recommend using
property rights [Boucher et al. (2006)]. Property rights are the rights of an individual to own
property and keep the income earned from it. If these property rights are well defined, trade
between agents would result in an efficient allocation of the externality [Varian (1999)]. In
other words, the externality becomes a constraint or a trade-off opportunity. In addition,
Chapter 3 has shown that die cost of providing ancillary sendees is not negligible. These
two reasons motivate the creation of a market for ancillary sendees to procure system
services.
A Comprehensive ^Assessment of Marketsfor Freqtten/y and Voltage Control Ancillary Services, Yann Reboucs, 2008 187
188 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
As capacities for energy and AS are physically linked and since AS often involve the
production or consumption of energy, markets for energy and ancillary services present
numerous similarities, while trying to take into account AS specificities described in
Chapter 2. A lot of attention has thus been concentrated on defining pricing mechanisms to
coordinate ancillary services with the markets for electrical energy in a centralised unit
commitment structure. However, by focusing on centralised pricing and assuming that a
spot market combined with bilateral contracts is the best model, one misses some aspects
of the AS markets, which are not only crucial but also very different from what one finds in
energy markets. Difficult issues that have not received enough attention include for example
the procurement of AS in the long-term, a coordinated clearing of markets for energy and
reserves with a decentralised unit commitment, or an allocation of the cost of AS that gives
proper incentives.
This chapter identifies and discusses eight fundamental issues in the design of
markets for ancillary services, namely: (1) choosing the entity responsible for AS
procurement (section 4.2); (2) matching demand and supply (section 4.3); (3) choosing the
relevant procurement methods (section 4.4); (4) defining the structures of offers and
payments (section 4.5); (5) organizing the market clearing procedure (section 4.6); (6)
avoiding price caps (section 4.7); (7) providing efficient incentives (section 4.8) and (8)
assessing the procurement method (section 4.9). Addressing these eight issues is essential to
the development of electricity markets that are not only efficient but also durable. This
chapter does not pretend to propose a standard market design, since all market
architectures should be tailor-made and evolve over time in relation to the market
structure97. Instead, it discusses current issues and proposes solutions for most of the
features that a market has. In addition, it surveys actual practices in order to illustrate the
discussion. This survey complements previous works by, amongst others, Kirby and Hirst
(1996), Cali et al. (2001), Arnott et al. (2003), Zhong (2003), Eurelectric (2004) and Raineri et
ah (2006).
It is assumed in this chapter that the required quantity and location of each quality
of system services have been defined for the various time horizons. The discussion in this
chapter is focused on the issues related to the procurement of the required system services.
97 T he market architecture describes how the m arket works (e.g., defining the auction process), while
the m arket structure refers to w hat is traded and by w h o m (e.g., a lo t o f small companies).
4.2 NOM INATING TH E ENTITY RESPONSIBLE OF PROCUREMENT 189
Procurement is the act of ensuring the presence in the system of the necessary SS (provided
in part -with the help of some AS). As general rules, the procurement of system services
should [Cali et al. (2001)]: (a) permit participants to recover the investments with enough
return; (b) reduce the total cost to consumers of SS; (c) give an incentive to improve the
sendee level; (d) find a price between the value and the cost of the sendee; (e) have a price
setting mechanism with a reasonable transaction cost98. The present chapter will mainly
discuss the short-term procurement (say up to two or three years), even if most of the
concepts are also applicable to long-term procurement.
The definition and the deployment of system sendees is a responsibility that falls naturally on
the system operator, even if it does not always control directly some of these sendees, such
as the primary frequency control ancillary sendee (see section 2.3.3.1). On the other hand,
the Entity Responsible for Ancillary services Procurement (ERAP) can be either the system
operator or some users of the system.
A tempting solution is to put several users of the power system into competition for the
procurement of AS. For example, the load-serving entities (LSEs) of PJM must provide
frequency control sendees such as regulation and synchronised resen^e in pro rata of their
load share [PJM (2008)]. This approach creates some competition between AS buyers and
providers, which should result in lower prices. It also implicitly allocates the cost of ancillary
sendees amongst LSEs. However, this approach has three weaknesses. First, the LSEs
themselves are not users of AS and therefore do not know the true value of AS. Therefore,
this results in an inelastic demand, which may jeopardise the match between supply and
demand (see section 4.3). Second, the quantity, quality and location of system sendees are
set by an entity that has no incentive to reduce the demand, because it does not pay for
then procurement. Last, imposing such requirement on users can be a barrier to the entry
of new competitors if the level of AS required from each participant is too high.
98 This list is n o t exhaustive. F o r example, increase innovation may also be an objective o f the
procurem ent.
190 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
Another popular approach is to designate the system operator as the single buyer'9. This
solution solves the problems mentioned above but raises others issues, common to most of
regulated activities. First, the SO needs to recover somehow the costs incurred, which is an
issue by itself addressed in section 4.8.2. Second, the management rules of the SO have to
be transparent in order to ensure a fair treatment of all SS users, whatever their position in
the industry (e.g., incumbent or new entrant). Third, as discussed in section 4.8.5, the SO
should have enough incentives to optimise its procurement process. In particular, if the TO
and the SO are the same entity, this entity should have enough incentives to choose the best
procurement processes and not to select only the self-procurement (see section 4.4.1). In
conclusion, designating the system operator as the ERAP is probably the most desirable
solution if proper incentives are put in place by the regulator.
99 A single buyer can force th e providers to supply AS (i.e., the com pulsory procurem ent described in
section 4.4).
4.3 MATCHING SUPPLY AND DEMAND 191
100 M ost o f the time, the legislator defines the connecting conditions. H owever, it usually follows the
technical advice o f the system operator.
101 See section 4.9.3 for a short discussion on barriers to com petition.
192 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
possible, enough incentives should be given to AS providers to offer their capacity in the short
term to make enough AS available (e.g., compulsory minimum participation may be required
for a market with an intrinsic concentration problem).
In addition, an elastic A.S demand102 is essential (which is possible only when the
ERAP is the SO). Indeed, Figure 4.1 illustrates the problem that appears when the supply is
insufficient to meet the demand (e.g., when the system is stressed). This figure also shows
that some responsiveness, even a small amount, can be enough to match supply and
demand, especially when the system is constrained. In practice, demand for AS is usually
very inelastic because the criteria used to define the amount of SS usually ignore the cost
and the value of AS provision. However, all the system operators that buy AS have implicit
non-vertical demand curves because, at some point, they will not accept to pay for
additional AS103, even if their explicit demand is most of the time totally inelastic (as shown
in section 2.4). Anyway, some SOs have an explicit demand curve. For example, the New
York Independent System Operator (NYISO) has a demand curve for secondary frequency
control as shown in Figure 4.2 [NYISO (2008)]. In this case, if the supply is larger than the
ISO’s target, supply and demand will surely meet. However, this demand curve is very
simple and does not reflect the true value of system services. In addition, one could argue
that secondary frequency control reserve above its target is worth something (black-outs
happen also at night, when frequency control reserves tend to be cheaper, as shown in
section 3.5.2). Therefore, this curve could be refined.
supply
supply
demand demand
quantity o f AS quantity of AS
(a) m arket failure (b) market clearing is possible
102 A dem and is said to be elastic w hen it is sensitive to the price o f the comm odity. N o te th at there
w ould probably be a cross-elasticity (which represents the link betw een the prices o f two commodities)
betw een active pow er AS and load reduction, supposing that load reduction can be priced through dem and-
side offers. See K irschen and Strbac (2004a) for m ore details about elasticity.
103 T his limitation on dem and is tightly related to the price caps discussed in section 4.7.
4.4 CHOOSING TH E RELEVANT PROCUREMENT METHODS 193
Price
($/iviwm)
300
250
Q u an tity o f se c o n d a ry
fre q u e n c y co n tro l (MW)
target - 25 MW target
The entities responsible for AS procurement can use various methods to obtain ancillary
sendees, namely: (a) compulsory provision, (b) self-procurement, (c) bilateral contracts, (d)
tendering and (e) spot market. Various factors influence the choice of one of these methods
over the others. These factors include risk aversion, market concentration, mode of energy
and transmission rights trading, costs recovery method, centralised or decentralised AS
control (see section 2.3.2), and the type of providers (e.g., loads are likely to prefer bilateral
contracts).
The fourth and fifth procurement methods involve the development of a tendering
process or the creation of a spot market. Drawing a line between these two methods is not
always easy. Here, the term spot market is used to denote a market where standardised
products with a short delivery (i.e., one week or less) are exchanged (see section 1.3.1). A
tendering process involves less standardised products with a longer duration. Both methods
enhance transparency and foster competition. On the down side, they have high data
management costs and may facilitate the manipulation o f the market by some participants.
Furthermore, a pure spot market for AS is unlikely to be implemented because markets
respond too slowly. In other words, the ERAP will never be able to buy AS instantly.
104 Bilateral contracts can also be traded in an organised m arket, w here contracts are standardised and
called future contracts. N o te that a m arket trading short-delivery futures is close to the sp o t m arket (see
section 1.3.1).
i°5 N ote that w hen risk diminishes, investm ents are eased.
4.4 CHOOSING TH E RELEVANT PROCUREMENT METHODS 195
Therefore, an AS spot market is in reality a future market with products with short
deliveries and short durations. AS markets are thus incomplete106, like electrical energy-only
markets [Wilson (2002), Boucher et al (2006)].
Table 4.1 summarizes for each procurement method some of the perceived
advantages (+) and disadvantages (—). This grading is subjective and thus may change from
a market participant to another. Moreover, advantages and disadvantages will be affected by
the duration of the contracts. Table 4.1 shows that no method is superior to all the others.
Furthermore, the importance of each parameter varies across jurisdictions (e.g., a market
designer may give more importance to a procurement method that facilitates entrance of
new participants, whereas another designer may prioritise market transparency). In
particular, a market design relying on bilateral contracts associated with a spot market is not
necessarily the best solution. As various methods are complementary, market designers are
likely to choose a mix of methods, as shown in section 4.4.2.
T ab le 4.1: Param eters in flu en cin g the ch o ice o f A S-procurem ent m eth od
106 A complete m arket is a m arket in which ever}7 contingency can be negotiated. In other w ords, “there
is a forward m arket for ever}7 com m odity at ever}7 date”, as form ulated by Mas-Colell et ai (1995), p. 745.
196 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
T able 4.2: P rocurem ent m eth o d s c h o sen across various system s as o f O ctober 2006
107 See Table 2.3 in section 2.3.4 for basic inform ation on systems and the signification o f the
abbreviations. In addition to personal com m unications and the websites o f the m arket and system operators,
the following references were particularly used: AU: N EM M C O (2001), N EM M C O (2004); D E : E .O N
(2005), B D E W (2007a); ES: Spanish industry and energy departm ent (1998), Spanish industry and energy
departm ent (2000), O M E L (2005); FR: R T E (2004), French econom ic and industry departm ent (2005), R T E
(2007b); GB: N ational G rid (2008b), N ational G rid (2008c); N Z : Electricity Com m ission o f N ew Zealand
(2004), N Z IE R (2005), Electricity C om m ission o f N ew Zealand (2005); PJM: PJM (2005a), PJM (2005b), PJM
(2008); SE: SvK (2005).
4.5 D EFIN IN G TH E STRUCTURES OF OFFERS AND PAYMENTS 197
The structures of bids are related to the scoring and clearing processes, while the structures of
payments are related to the settlement process. A good price structure helps send correct
price signals to the participants. It also ensures that costs are recovered efficiently. As
guidelines, an efficient structure of payment should reflect as closely as possible the various
costs that a provider of sendees may incur, while avoiding double accounting [Cali et al
(2001)], and staying simple enough to be practical. Indeed, if the structure of remuneration
increases in complexity, recovery of cost would be a priori more efficient, but it would also
be more difficult to choose the best offer because the theory of multi-dimensional auctions
is complicated, even for two-part offers [Chao and Wilson (2002)]. As usual, the principal
issue is to find the most appropriate balance. For example, paying separately the meals in a
plane and the cost of the flight may be more efficient than paying an all-in-one flight ticket.
Indeed, budget travellers may prefer to buy a cheaper ticket and to bring their own
sandwich rather than to purchase a more expensive bundle ticket. On the other hand,
separating the costs of the crew, the fuel and the plane does not bring a lot of advantages to
consumers.
Ancillary sendees cannot be remunerated in the same manner as the classical electrical
energy product (i.e., MWh). For example, a generator that is part-loaded in order to provide
frequency control expects to get a payment for the sendee, even if it is not actually called
during the period considered. In the scientific literature, most of the discussions on
structures of offers and payment of AS are concentrated on three components, namely
capacity, utilisation and opportunity cost [e.g., Hao and Papalexopoulos (1997), Singh
(1999), Oren (2001), Chao and Wilson (2002), Chicco and Gross (2004) or Galiana et al.
(2005)]. The literature also proposes innovative components [e.g., Doherty et al. (2005)]. In
addition, some systems like Great Britain have adopted additional components, as shown in
section 4.5.2. This section discusses six identified structures for offers and payments that
are used in practice or have been proposed in the literature, namely: (a) a fixed allowance,
(b) an availability price, (c) an utilisation payment, (d) a payment for the opportunity cost,
(e) an utilisation frequency payment, and (f) a price for kinetic energy.
198 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
An utilisation payment remunerates the actual delivery of the service. To use economic
language, availability and utilisation payments can be considered as an option fee and a
strike price, respectively. More specifically, an AS with this payment scheme is equivalent to
a swing option because the SO can usually exercise it several times (see section 1.3.1).
However, ancillary services with availability payments are different from standard financial
options, because their goal is not to provide a financial hedge, but to fulfil preset standards
for a “security hedge” [Singh (1999)]. Secondary frequency control is a very good example
of AS with both availability (e.g., in €/M W /h) and utilisation payments (e.g., in €/MWh),
because the TSO can exert or not its option on the available capacity through the regulation
signal sent to the generating unit (see section 2.3.3.1). An utilisation payment should
consider the amplitude of delivery of the service. For example, an utilisation spike has often
a stronger impact on the provider than a continuous utilisation does. Figure 4.3 shows two
different utilisations, which are however usually entitled to the same utilisation payment
because both energy integrals are equal.
4.5 D EFININ G THE STRUCTURES OF OFFERS AND PAYMENTS 199
output
(a)
output
In addition to availability and utilisation payments, the payment of the opportunity cost
has been identified for a long time by the community as an important allowance [Hirst and
Kirby (1997)]. As presented in section 3.2.2, the opportunity cost represents the profit that
the provider would have made if it had sold other products (e.g., energy) instead of
supplying the service. Note that to compute the opportunity cost, the supply curves of units
have to be provided, which is not popular in markets with decentralised unit commitment.
In addition, it is usually assumed that the energy’ price would not change if the unit were
economically dispatched without providing any AS. This assumption is a good
approximation only when the liquidity of the market is sufficient.
A price for kinetic energy (e.g., in €/MWs) remunerates the quantity of kinetic energy’
made available to the system [Doherty et al. (2005)]. This innovative approach recognizes
that machines wdth high inertia (and thus with a high kinetic energy) reduce the rate of
change of frequency'"8 (but still cannot stabilize it durably). In fact, a power system must
have a maximum rate of change of frequency (in Hz/s) following a contingency, so the
participants reducing this rate of change of frequency should be remunerated. However,
108 H igh inertia is characterised by a large / and thus a large d~wm/dr in equation (1.2) o f section 1.4.1.
200 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
Fixed and availability remunerations are favoured for basic and enhanced voltage
controls. Except in Great Britain, New Zealand and Spain, the actual use of reactive power
through the voltage control is not remunerated, so the utilisation cost of reactive power
does not seems to be considered as significant. Voltage control is not remunerated at all in
Sweden, The active power used when generators work in synchronous compensator mode
is remunerated in Australia, France, PJM and Spain. Opportunity costs are not widely used,
probably because they are more difficult to compute and they may be included in availability
payments when a long period is considered (e.g., a week or more).
The structure of the offers is often identical to the structure of the payments, but
some differences can appear. First, a payment component may be indexed on another
market instead of being explicitly defined in the bidding process. For example, the
utilisation payment of an active power AS can be based on the energy-only spot market.
Second, the structure of an offer may be more complex than the structure of a payment.
For example, it can be desirable to have different offer prices for different conditions of
utilisation of an AS provider. However, the price of payment is unique for this provider. In
4.5 D EFIN IN G TH E STRUCTURES OF OFFERS AND PAYMENTS 201
practice, providers often provide an offer curve. For example, Australian generators can
offer up to ten frequency control AS price bands depending on the output of the given
generator (see Figure 4.4) [NEMMCO (2001)]. In Great Britain, an equivalent system is
used for reactive power AS, where up to six price bands are possible (see
Figure 4.5) [National Grid (2008c)].
Utilisation Opportunity
Fixed Availability Utilisation
frequency cost
Primary frequency AU, DE, FR,
GB GB GB, NZ -
control GB, NZ, SE
Secondary AU, DE, FR,
- DE, ES, FR - PJM
frequency control PJM, ES
Basic voltage FR, GB, NZ,
FR, GB, NZ GB, NZ - PJM
control PJM
Enhanced voltage AU, ES, FR,
FR, GB ES , GB - AU, DE
control GB
R esp o n se (MW)
R esponse max
(MW) x
Dispatched
output (MW)
Band 1 (MW) F jPrice ;band A ^App/MW/h]
Obligatory Reactive
Active Power
Obligatory Reactive
Power Service Power Service
(Grid Code) - 0.95p1 (Grid Code) - 0 85pf
Leading
Full Output
Rated MW
Figure 4.5: R eactive pow er capability curve in Great Britain [N ation al Grid (2008c)]
Beyond the number of parameters to consider in the price structure, another interesting
issue is the price sign (i.e., positive or negative price) and the price symmetry (i.e., down and up
sendees with same prices). For example, if a unit provides secondary frequency control,
shall it pay or be remunerated for reducing its output when the regulating signal requires it?
Indeed, the SO may argue that in such cases this unit saves money by not producing power
(so the unit should pay back), whereas the producer may argue that this reduction helps
maintain the system in a secure state (so the unit should be paid). In the case of reactive
power, the question is even harder, since both production and absorption can be paid or
charged, depending on the state of the network (i.e., whether the voltage is higher or lower
than desired). To achieve maximum flexibility in offers and hence enhance competition, it is
probably best to avoid placing any constraint on the sign of the price or requiring pricing
symmetry.
The market clearing process matches supply and demand by setting the prices and the
amounts traded. Self-scheduled AS providers are not considered here, since they do not
participate directly in the price discovery process resulting from the market clearing.
4.6 ORGANIZING THE MARKET CLEARING PROCEDURE 203
This section discusses the main features that a clearing procedure must have: (a) the
structure of the market can be either centralised or decentralised (section 4.6.1); (b) various types
of auctions are possible. Auctions define how the offers must be made (section 4.6.2); (c)
scoring, i.e. ranking offers in a way that encourages truthful bidding and an efficient choice
(section 4.6.3); (d) because the various AS are correlated with each other and with energy,
coordinating the various markets is necessary (section 4.6.4); (e) there are still differences of
opinion about the best settlement rule, in particular on the choice between discriminatory and
uniform prices across AS products, and between the zonal and nodal approaches
(section 4.6.5); lastly, (f) timing of the market events such as clearing, closure of demand and
offers, as well as duration of contracts have to be chosen carefully (section 4.6.6).
With a centralised unit commitment, the market (usually called "pool”) is cleared by a unique
entity. In pool energy-only markets, which are popular across the United States, participants
provide bids and offers. Then, the system operator directly commits and dispatches the
producers. Therefore, this approach favours links between AS and other products such as
energy. For example, the opportunity cost can be calculated easily. However, markets with a
centralised unit commitment are deemed to be opaque because the clearing process is quite
complex. In addition, bidders have to provide a lot of information and this system hardly
takes into account all the variables of the system.
On the other hand, a decentralised unit commitment may be adopted. In this system,
which is popular across Europe, participants propose bids and select offers directly in the
market. Therefore, a global co-optimisation is difficult since participants buy and sell
independently from each other. Instead, each participant does its own co-optimisation with
its assets. Therefore, the dispatching is a priori less efficient, but participants in the market
are able to take more parameters into account. Note that the decentralised arrangement
described here can use centralised markets (usually called “exchanges”) as described in
section 1.3.1.
To probe further, CER (2003) discusses in more details advantages and drawbacks
of pool and power-exchange markets.
204 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
By setting the rules for submitting and matching bids and offers, an auction helps determine
the value of a commodity that has an undetermined or variable price. More precisely, in the
case of ancillary services, the auctioneer wants to reveal the marginal cost of AS providers
for each cost component. In economics, various auctions are available, depending on the
problem considered. Section 4.6.2.1 discusses the general categories o f auctions, while
section 4.6.2.2 introduces the usual auctions and section 4.6.2.3 examines the most
appropriate arrangement for AS procurement.
4 .6 .2 .1 P rin cip a l c a t e g o r i e s o f a u c t io n s
Second, an auction can be single-sided or double-sided. In the former type, only one
buyer or one seller wants to acquire or sell the good. In the latter type of auction, several
buyers and sellers participate in the auction. As highlighted in section 4.2, the AS buyer(s)
for a given zone can be either unique (e.g., the SO) or several (e.g., users with AS
requirements). Therefore, single-sided and double-sided auctions are both possible for AS.
Even if solutions based on the unique buyer are popular, SOs may compete against each
other to buy AS across interconnected systems, as discussed in section 2.5. Therefore, the
procurement of ancillary services is likely to move towards a double-sided auction in the
long-term.
4.6 ORGANIZING THE MARKET CLEARING PROCEDURE 205
Third, single-unit and multiple-unit auctions are possible. Single-unit auctions deal
solely with identical goods (e.g., buying 1 000 iPods). This type of auctions is the simplest
and benefits from a lot of analysis [Varian (1999)]. On the other hand, differentiate goods
are traded in multiple-unit auctions (e.g., buying 100 second-hand cars). Unfortunately,
properties of single-unit auctions cannot be extended to multiple-unit auctions [Staropoli
and Jullien (2006)]. Therefore, multiple-unit auctions are much harder to deal with and no
hasty conclusion should be drawn when dealing with such auctions. AS auctions can be
either single- or multiple-unit, depending on the differentiation possible between AS
providers (see section 2,3).
Commenting on auction design, Klemperer (2002) states that “one size does not fit all”,
because an auction helps to answer to a specific need. For example, an auction that is used
to trade private-valued multiple-unit goods is not necessarily efficient for common-valued
single-unit goods. Iti practice, some types of auction are often used. The usual types of
auction presented in this section are English, Dutch, sealed-bid first-price and Vickrey.
From these usual auctions, different variants are possible.
In a Dutch auction, a price is given by the auctioneer and then the price is decreased
by steps until a buyer is interested. Dutch auctions have the advantage of being very fast109.
An AS auction based on a modified Dutch auction may be imagined as follows. The ERAP
would propose to buy a given quality of ancillary service from AS providers. The ERAP
would start with the highest price that it would be ready to pay for and then AS providers
would manifest their interest. As long there would be an AS provider interested, the price of
the contract would decrease by step. The last AS provider to accept would win the AS
contract. However, such a system may not be Pareto efficient because it is not guaranteed
that the latest accepted price be the lowest price that the AS provider was ready to accept.
In a sealed-bid auction (also called Yankee auction or sealed-bid first-price auction), all
the participants make a bid (or an offer) at the same time. The best bid takes the good and
pays as bid110. This type of auction is commonly used in tendering processes in the
construction in industry. Lastly, this auction is applicable to both multiple-unit and single
unit procurements, but it is often not Pareto efficient. In fact, “no buyer knows other
buyers’ valuations, so the highest valuation buyer may bid too low and lose to another
bidder” [Bergstrom (1999)]. A system for ancillary services is easily imagined in which the
ERAP would call to tender the AS providers. The AS providers would submit their offers,
then the ERAP would select the best ones.
109 T he D utch auction holds its nam e from the D u tch m arkets w here this auction is used to trade
cheese and flowers [Varian (1999)].
1!0 A variant o f this auction is possible with a uniform pricing, e.g., based o n the last accepted offer
o r die first rejected offer.
4.6 ORGANIZING THE MARKET CLEARING PROCEDURE 207
Bids Settlement
{a} {b} {a,b} Gets Pays
Bidder 1 12 € 6€ 20 € {a } 12-(30-25) = 7 €
Bidder 2 3€ 18 € 25 € {b} 18-(30-20) = 8 €
Bids Settlement
{a} {b} {a,b} Gets Pays
Bidder 1 1 000 € 6€ 20 € {a } 1 000-(l 018-25) = 7 €
Bidder 2 3€ 18 € 25 € {b} 18-(1 018-20) = -980 €
4 . 6 . 2 . 3 S e l e c t i n g t h e a p p r o p r ia te a u c tio n m e th o d
Table 4.6 summarizes some features of the described auction methods. English and Dutch
auctions are multiple-round auctions, while sealed-bid first-price and Vickrey are single
round auctions. All auctions are Pareto efficient under particular conditions, but only the
Vickrey auction gives incentives to buyers to reveal their true value for a good, even in an
111 N o te th at sellers are som etimes ready to pay to get rid o f their goods, especially w hen the goods
cannot be stored anymore (e.g., electricity o r perishable products).
112 F o r example, a V C G auction helps determine the price o f each product, whereas the cost
allocation is pre-determ ined in the Clarke-Groves tax system.
208 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
imperfectly competitive market [Chao and Wilson (2002)]. However, all auctions are
vulnerable to collusion or strategic behaviour [Varian (1999)]113.
The desirable features for an AS auction are highlighted in bold. In fact, AS auctions
are multiple-unit, as explained in section 4.6.2.1. In addition, it is desirable to have an
auction both Pareto- and revenue-efficient and that helps to reveal the true value of the
good. Lasdy, single-round auctions are easier to manage in real-time than multiple-round
auctions, so they should be preferred. It is clear from Table 4.6 that none of the proposed
auction methods fulfils all the requirements. In practice, sealed-bid auctions (first-price or
uniform-price) are very popular across systems to procure ancillary services, because they
are convenient for the procurement methods preferred by participants, i.e. tendering
processes and spot markets (see section 4.4). However, despite their interesting features, the
Vickrey and VCG auctions do not seem to be used because they are unpractical.
Nevertheless, Chao and Wilson (2002) propose a market design for spinning reserves based
on Vickrey and VCG auctions.
In conclusion, sealed-bid first-price auctions are probably the best trade-off so far.
However, stakeholders have to keep in mind that such auctions do not guarantee the Pareto
efficiency and do not reveal the true value of AS, so they are likely to send incorrect signals
to the market. The possibility of non-efficient prices is even higher because markets for
ancillary services usually involve an oligopoly and repetitive auctions. Participants have thus
time to understand the market and the gaming possibilities [Staropoli and Jullien (2006)].
S in g le / H elp to S in g le /
A uction S in g le /D o u b le Pareto R evenue
M ultiple- reveal true m ultiple-
m ethod sid e efficient efficien t
un it value round
English Both Both Yes Yes No Multiple
Dutch Both Both Y es114 Yes No Multiple
Sealed-bid
Both Both Y es114 Yes No Single
first-price
Vickrey Single Both Yes Yes Yes Single
VCG M ultiple Both Yes No Yes Single
113 T o probe further into auction theory, Varian (1999) gives a com prehensive introduction, while
K lem perer (1999), K lem perer (2002), and Pekec and R o th k o p f (2004) discuss auctions in m uch m ore details.
Lasdy, Staropoli and Jullien (2006) show the interest o f laboratory experim ents, w hich help m arket designers
to study and assess the perform ance o f m arket rules in an environm ent simpler than reality.
To score offers while trying to minimity its procurement cost, the ERAP must take into
account both the price and the probability of AS utilisation. This presents two difficulties.
First, the optimisation problem introduces AS prices (i.e., the dual variables) into the primal
problem, which makes the optimisation problem much harder to solve [O’Neill et al
(2006)]. Though, Lull et al (2006) have proposed recently an optimisation algorithm that
overcomes this difficulty by updating the Lagrangian multiplier in an iterative process, i.e. in
a similar way as die price decomposition117. Second, taking into account the probability of
AS utilisation may favour gaming. For example, some units may lower their utilisation
offers and increase their availability payments to increase their profits [Singh (1999)]. To
avoid such gaming, Chao and Wilson (2002) have proposed a new scoring method for
active power AS. The idea is to force providers to reveal their true energy marginal cost
through a Vickrey auction (see section 4.6.2.2). For the settlement, the opportunity cost of
die various energy offers constitute die availability payment, and energy is paid at the lowest
unused energy offer.
115 N o te that the scoring should also include a tie-breaking feature th at separates two bids with the
same score. D efining this rule is a relatively easy task if bids can be split.
116 As explained in section 2.2.3, the ERA P can either minimize the procurem ent cost (m ethod also
know n as the rational buyer approach) or maximize the global welfare. B oth objective functions are dependent
on the settlem ent m ethod chosen. Various settlem ent m ethods are described in section 4.6.5.
117 See section 3.3.5.1 for an introduction to the primal and dual problem s and to the price
decom position m ethod.
210 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
Since AS are an externality of other products such as energy and because several AS
products exist (see section 2.3), AS auctions have to be coordinated. In independent merit-order
auctions, each ancillary service auction is cleared independently. However, because an AS
provider can generally provide several AS products119, this approach may lead to infeasible
solutions. Therefore, sequential auctions (also called cascading clearing) have been defended in
the early designs of market for frequency control AS [Hirst and Kirby (1997), Singh (1999)].
With this method of coordination, AS are provided in a prioritised manner. Once an AS is
bought, the capacity of the successful provider of this service for the following AS auction
118 H owever, because o f their local effect, reactive pow er AS have stronger geographical constraints
than active pow er AS do. See section 1.5 for m ore details.
is reduced. However, this approach suffers from some flaws, in particular price reversals,
illustrated by die infamous failure of the Californian AS market at the end of the
1990s [Brien (1999), Oren (2001)]120. Since then, it has been recognised that simultaneous
auctions have to be in place for AS and energy-only markets [e.g., Yan and Stern (2002), Ma
et al (2003), Baldick et al (2005) or Galiana et al (2005)].
120 A price reversal is said to appear w hen an ancillary sendee o f lower quality is m ore expensive than
another o f higher quality. F urther in this section, the example o f Table 4.9 illustrates such a price reversal. As a
practical example, during the Californian crisis, the price o f non-spinning reserve was m ore expensive than the
price o f spinning reserve, whereas spinning reserve should be m ore expensive to provide than non-spinning
(see section 2.3.4.1 for the vocabulary o f reserves).
121 W e consider here a supply (or product) substitution, i.e. the supply for a lower quality AS can be
substituted by a higher quality AS. In die case o f a dem and substitution, the dem and for a lower quality AS
can be substituted by a higher quality AS [Oren (2001)].
122 See section 4.6.1 for a short discussion between pools and exchanges.
212 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
auctions are much less transparent than independent or sequential auctions, whereas
participants usually prefer transparent processes. Fourth, it could be argued that it would be
better to co-optimize the products over long periods of time to obtain better results.
Indeed, transmission and generation capacity investments have an impact of the cost of
ancillary services. However, such a long-term optimization is likely to be difficult to
implement in a liberalized environment.
T ab le 4.7: Param eters o f the d em an d in the consid ered exam p les o f m arket coordination
Product Volum e
AS 1 100 u
AS 2 100 u
Total 200 u
T able 4.8: Param eters o f the offers in the con sid ered exam p les o f m arket coordination
T ab le 4.9: R esu lt o f the clearing p rocesses in the exam p les o f m arket coordination
An administrative price is set by the regulator or the SO and can be either nodal or
zonal. This form of remuneration, also called regulated pricing, can take several forms: a
reimbursement (i.e., an ex-post payment that compensates the AS providers for the cost of
sendees), a value-based payment (i.e., a payment based on the estimated value of AS) or a
tariff (i.e., an administrative rule of payment) [Cali et al. (2001)]. In practice, since the value
of AS may be hard to calculate and tends to be high or very high (see section 2.2.1),
reimbursements and tariff payment are preferred in practice. An administrative price is
particularly justified when dominance of some participants is an issue. In general, however,
a regulated price is not desirable as it reflects very imperfectly the actual cost of providing
an ancillary sendee, particularly when this cost changes with time or circumstances, as it is
the case of frequency control ancillary services (see section 3.4.1).
With discriminatory auction prices, winners of the auction pay/receive different prices
for the same good. Discriminatory auction prices are suitable when the quality of the
ancillary services offered is highly differentiated, so the offers are not easily comparable.
However, a discriminatory auction price does not give providers an incentive to offer their
marginal cost, except when market concentration is low [Stoft (2002)]. In the particular pay-
as-bid discriminatory system, the supplier receives the price of its accepted offer. Variants of
tire pay-as-bid system are possible, as proposed by Bushnell and Oren (1994). However,
Staropoli and Jullien (2006) argue that discriminatory auctions generally perform poorly in
214 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
In a uniform price system, all the winners of the auction pay/receive the same price.
This form of pricing, defended for example by Chao and Wilson (2002) for frequency
control AS, is deemed to give suppliers a real incentive to offer their marginal cost. O n the
other hand, it is not adapted to differentiated products because all the offers have to be
comparable. Various settlement rules are possible in the case of a uniform price system and
are described below [Oren (2001), Shahidehpour et al. (2002)]. We consider here only the
settlement rules in case of a simultaneous auction because it has been shown in section 4.6.4
that sequential auctions do not guarantee efficiency, though being simpler than
simultaneous auctions.
Link between uniform prices of different AS of same nature (e.g., all frequency control
ancillary services):
■ Common price between AS of same nature: this approach, defended by Galiana et
al. (2005), is based on the fact that all the active power AS have an equal role in the
security. In addition, the philosophy of common pricing between AS can be
justified by the fact that some AS cost components may be common (e.g., an energy
payment);
" Separate prices between AS of same nature: the classical approach, in which each
AS has its own market clearing price.
Z Methods to calculate the market clearing price:
■ Marginal value pricing: the price is equal to the most expensive of all the accepted
AS offers of equal or lower quality;
■ Last accepted bid: the price is equal to the highest accepted bid for the AS
considered;
■ First rejected bid: the price is equal to the lowest rejected bid for the AS considered.
Note that Bernard et al. (1998) and Staropoli and Jullien (2006) report that the last
accepted offer auction performs slightly better in energy markets than the first
rejected offer mechanism does. However, this conclusion cannot be directly
extended to AS.
V Perimeter of the uniform pricing:
■ Zonal prices: they may be preferred for frequency control AS because the value of
frequency control AS is usually not geographically dependent (see section 1.4).
4.6 ORGANIZING THE MARKET CLEARING PROCEDURE 215
However, defining the zone remains a problem because congestions may prevent
the supply of the AS. In practice, the area of the TSO is often considered as the
price zone [O’Neill et al. (2006)];
■ Nodal prices: they may be favoured for voltage control sendees because their effect,
and so their value, Is local (see section 1.5). Some system operators, such as in
Texas, argue that nodal payment of AS gives an incentive for relieving congestion
similar to energy [Mickey (2006)], In addition, Galiana et al. (2005) argue that it
gives more signals to compute the marginal value of security in a nodal fashion than
in a zonal manner. On the other hand, nodal pricing is expensive to implement,
increase the complexity of bilateral contracts123 and may increase the market power
of some participants. More broadly, discussions on the relative advantages of nodal
and zonal pricing are still ongoing in many countries [Sioshansi and Pfaffenberger
(2006)].
Table 4.10 summarises the settlement rules chosen across various systems as of
October 2006 (see 107 p.195). PJM and Spain are the only systems where primary frequency
control is not remunerated, so these systems do not recognize the property rights of
generating units over their governor response. When this sendee is remunerated, a
discriminatory auction price is preferred because primary frequency control is a
differentiated product. Secondary frequency control services are remunerated in all the
systems that use it. Since secondary frequency control is managed directly by the TSO and
uses energy, it is obviously a service that providers deliver to the TSO and should therefore
be remunerated. For basic voltage control there is as yet no consensus on whether this
sendee should or should not be remunerated. Finally, discriminatory auction price is the
preferred option for enhanced voltage control where this sendee is defined.
123 Bilateral contracting is eased in energy-only market with the help o f “hub prices” that reflect the
average price in a given zone [O’Neill et al (2006)].
216 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
T able 4.10: Settlem ent rules ch o sen across various sy stem s as o f O ctober 2006
One of the most obvious parameters in the market timing is the frequency of market
clearing. The frequency of market clearing can vary from several years to a continuous
quotation. The more often the market is cleared, the closer the market should be to the
actual cost of supply and value of demand, the better are the signals given to the
participants, and the more efficient the market should be. However, the feasibility and
practicality of the market decreases when the frequency of clearing increases. It is not the
purpose here to describe in details all the associated engineering issues (e.g., computing
capacity, means of communication, data format, speed of transmission), but, as usual, a
trade-off has to be found between the operational requirements and the possible economic
benefits. In general, the lower the frequency of clearing is, the easier it is to use complex
scoring methods. In addition, a high frequency market clearing helps players understand the
behaviour of the market, and therefore to game it, as happened in California, where some
capacities were withheld in order to raise prices [Brien (1999)]. Therefore, a low frequency
market clearing has the advantage of reducing somewhat the influence o f dominant players.
4.6 ORGANIZING THE MARKET CLEARING PROCEDURE 217
Table 4.11 gives the frequencies of market clearing across various systems as of
October 2006 (see 107 p.195). In practice, the active power AS can benefit from high
frequency market clearing (e.g., every five minutes in Australia). However, even if real-time
reactive power markets have been proposed, for example by Zhong et al. (2004), none has
been implemented yet. In fact, the variable cost of reactive power is low [Hao and
Papalexopoulos (1997)], so benefits from a high frequency clearing are likely to be low as
well. In addition, reactive power is local, so gaming is increased, as illustrated by the simple
example of Figure 4.6. By increasing the reactive power absorption of generator B, the value
of reactive power production is increased as well. Therefore, load L is giving more money
to generator A, even if load L’s consumption has not changed. In conclusion, with a simple
collusion between generators A and B, it is easy for them to make money from L.
T ab le 4.11: F req u en cies o f m arket clearing across various system s as o f O ctober 2006
AU DE ES FR GB PJM NZ SE
Secondary
Every 5 Every six Ever)7two or
frequency minutes months
Ever)7day
three years - Ever)’ hour Ever)7year
control
B asic
Ever)7two or Every six
voltage - - - tliree years months
Every year No rec.
control
E n h an ced
Ever)7two Ever)7two or Every six
voltage years
No rec. Ever)7year
three years months
. -
control
Gets p a id Production of
€X+ Y reactive power
> Pays € Y
Pays € X JAbsorption of
reactive power
F igure 4.6: Illustration o f a g a m in g possib ility w ith a real-tim e reactive pow er m arket
A parameter related to the frequency of market clearing is the opening duration of the
market. For example, a day-ahead market has typically an opening duration of less than one
218 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
day. In addition, note that the instant of the gate closure is important as it has to be
coordinated with the other markets (see section 4.6.4).
The frequency of offer submissions (i.e., supply side) should not be confused with the
frequency of market clearing. Indeed, it represents how often an AS provider can modify its
offers. In order to reflect as closely as possible the actual conditions of the market, it may
be desirable in general to have a high frequency offer submission system. However, close to
the actual operation of the system, real-time offer submission may favour gaming and be
unpractical as well. Therefore, most of the systems have adopted a market where AS offers
are frozen on a day-ahead or longer basis before the actual operation o f the system. For
example, in PJM, secondary frequency control offers are partly frozen after 6 pm on the day
ahead (new offers and price changes are not possible), whereas the market is actually cleared
every hour of the operating day [PJM (2008)].
The frequency of reviews of the needs (i.e., demand side) in terms of ancillary services is
also an important parameter of the market timing. By reviewing on a frequent basis the
amount of ancillary services that it needs, an ERAP can ensure that it only purchases what it
really needs to meet its objective function (see Chapter 2). Table 4.12 gives the frequencies
of the reviews of the needs across various systems as of October 2006 (see 107 p. 195).
Practices are thus very different from a system to another.
T able 4.12: F req u en cies o f review s o f the n eed s across various system s as o f O ctober 2006
AU DE ES FR GB PJM NZ SE
Every month,
Primary or on the day,
Every 5 Every' half-
frequency Twice the year - Every' day if applicable - Every year
minutes hour
control (revision
contract)
Secondary
Every 5 Every six
frequency Every day Every' day - Twice a day Every year -
minutes months
control
B asic As soon as the
Every six Every' half-
voltage - - - generating unit Unknown -
months hour
control is connected
The date of settlement is a minor factor, but has also to be taken into account,
especially if complex calculations to estimate the AS utilisation are needed.
4.6 ORGANIZING THE MARKET CLEARING PROCEDURE 219
Lastly, the duration of contracts is also an important parameter in the market timing.
Note that the duration of the opening of the market and the duration of the contracts are
not necessarily linked, even if they are often the same in an energy-only spot market. As
soon as a long-term contract (e.g., several years) is in place, there is no more competition
until it comes up for renewal. This can be either a drawback or an advantage for the ERAP
if the contract is respectively worse or better than the other offers on the market. In
addition, the value of long-term contracts resides in the fact that the price is fixed over
time [Kirschen and Strbac (2004a)] and allows suppliers to include maintenance and semi
fixed costs [DePillis (2006)]. Short-term contracts (e.g., five minutes) increase competition
and opportunities, but also risks. It should be noted that even if the needs are constant, the
available resources can vary during the day, which can brings some opportunities to the
ERAP.
markets, while long-term contracts are preferred for larger volumes, with the help of
bilateral contracts124.
Long-term
supply curve
Demand curve 2
Quantity of AS
F igure 4.7: Supply curves for different due dates
Price caps appear to be good remedies against abuses o f market power. However, they
should be avoided in markets for ancillary services. Figure 4.8 illustrates the effects of an
offer cap (i.e., that specifies the maximum offer price that a supplier can propose) and a
purchase cap (i.e., that limits the buyer’s demand price). A unique cost component is
considered for each quantity of ancillary service (e.g., in €/MW), the demand curve is
assumed to be vertical (inelastic demand, e.g. for a volume R^.) and the supply to be
sufficient to meet demand and supply. In both cases, the price cap PC is the same for the
given period. Lastly, q* represents the amount of AS finally bought.
The graph on the left shows that with an offer cap the initial demand will be met but
will cause a revenue shortage for the AS providers and will discourage them from investing
in new capacity. On the other hand, a purchase cap avoids this revenue shortage, but leads to
a lower amount of AS {q* < R^). In a sense, a purchase cap is only a simplistic demand
curve. Unfortunately, the value of AS is not a linear function of the quantity of AS because
one supplemental MW of AS may be enough to avoid a load-shedding of several MW.
Therefore, an appropriate demand curve is much more desirable than price caps. In other
words, AS have a value, but dais value is difficult to determine because, as discussed in
section 2.2, the needs of users are hard to define.
PC PC
F igu re 4.8: E ffect o f an offer cap (a) and a purchase cap (b)
Despite their drawbacks, if one of the two proposed price caps is adopted, finding
the appropriate price is an issue. Theoretically, the value of AS has to be taken into account
at some point. In practice, Table 4.13 shows the price caps adopted across various systems
as of October 2006 (see 107 p.195). Australia has implemented a purchase cap at the VOLL
(i.e. AUD 10,000 in August 2001) for active power AS, whereas PJM has adopted offer caps
at 100 $/M W /h for its secondary frequency control AS market. Most of the European
countries have not adopted any price cap yet for these products. In addition, price caps are
constant over time, whereas it would be better to have a different value for each market
clearing [Singh (1999)].
222 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
AU DE ES FR GB PJM NZ SE
Since system services are public goods, free riding is a strong temptation for participants in
markets for AS. Therefore, participants should have enough incentives for behaving
properly (section 4.8.1). Besides competition, several tools are available to the market
designers to give incentives to participants. The typical solution is to introduce penalties and
rewards (section 4.8.5), assuming that sufficient A.S monitoring is in place (section 4.8.4). The
method chosen to allocate the costs of system services has also a deep impact on the behaviour of
the participants (section 4.8.2). Furthermore, an appropriate information system helps users
respond to incentives (section 4.8.3). Finally, it is important to remember that intangfble
incentives, such as the fear of blackouts, also influence participants because they can damage a
company’s image even if it was not directly responsible.
125 T he Value O f L ost Load (VOLL) is equal to A U D 10,000 in Australia (August 2001) [N EM M CO
(2001)].
4.8 PROVIDING APPROPRIATE INCENTIVES 223
addition, in the case of AS trading across systems and with the SO as ERAP, the SO should
not have a right of pre-emption over the cheap AS providers within its territory.
Second, the entities responsible for A S procurement should have a procurement cost in
accordance with the objective function of the SS needs. If the ERAPs are users of the
system (e.g., the PJM’s LSE described in section 4.2), this pressure will come up naturally
with the competition against other ERAPs, except in the case of the use of a dominant
position. If the ERAP is the SO, the regulator should intervene to control the cost with the
classical tool of regulated activities. For example, Weisman (2005) compares two types of
regulated price: proftt-share penalties and revenue-share penalties. Note that the profit-
share penalties seem to be more efficient than the latter one. However, these regulated
prices do not guarantee that AS expenses are optimal.
Third, the A S providers should not deviate from what they are contractually obliged
to deliver and they should declare any deviation from such obligations. Indeed, not
delivering the contracted AS when requested could jeopardize the security of the system. In
addition, they should have enough incentive to offer their services at their marginal long
term cost.
Lastly, it is desirable to give some incentives to all the users of the network to improve
their behaviour in order to reduce the need for system services.
126 Because o f the public good characteristic o f system services, n ote that the allocation o f SS costs is
som ew hat similar to the transm ission pricing problem .
224 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
4 . 8 . 2 . 1 A l l o c a t i o n o f t h e fi x e d c o s t s
To fairly allocate SS fixed costs127 a first solution is to share them in proportion to the use
of the system. Indeed, SS fixed costs, besides being sometimes difficult to quantify, are
usually difficult to separate between users. For example, the cost can be split amongst
different classes of users. Then, the cost for each class is divided amongst the users in the
class on the basis of their energy consumption/production only. Obviously, this cost
allocation can have different levels of complexity.
The easiest solution to implement is to include directly the SS fixed costs in the
transmission tariff, as recommended by a Cigre Task Force (2001). This approach seems to be
the fairest and most of the European systems have adopted it [ETSO tariffs task force
(2006)]. Consequently, the SS fixed costs are allocated in function of the various parameters
of the tariff (e.g., voltage level at the connection point, maximum power subscribed, or
quantity of energy injected/withdrawn).
Even if no user actually uses any SS, a quantity of SS is always reserved as a function of the
particular configuration of the system, such as the type o f users connected or the power
transits (see section 2.4). Important parameters in the assessment of the SS needs are the
reliability and the size of users connected. For example, Kirby and Hirst (2000) have shown
that industrial consumers account for 93 % of secondary frequency control. On the other
127 SS fixed costs are for example T O ’s capacitor banks, the inform ation system o r the staff necessary
to provide the system services (see section 3.2.1).
4.8 PROVIDING APPROPRIATE INCENTIVES 225
hand, large generating units increase the requirement for tertiary frequency reserve. In
addition, an unreliable large generator increases risks more than a small reliable one. Lastly,
loads are the principal consumers of reactive power.
The tariff proposed in section 4.8.2.1 may be inefficient to allocate the SS potential
utilisation cost, because such a tariff does not give any incentive to the entities that increase
the SS potential utilisation cost to reduce it. Therefore, it would be interesting to distinguish
between classes of users in order to allocate the cost of ancillary in a fairer manner. For example,
in Australia, the cost of the “lower frequency control contingency” ancillary sendees is
charged to loads, while generators pay for the “raise frequency control contingency”
ancillary sendees [NEMMCO (2001)]. However, despite a better allocation, such an
arrangement is not likely to give enough incentives to individual users of the network to
improve their behaviour. Indeed, it still consists of only a single price for a whole category
of users and therefore encourages free riding.
Strbac and Kirschen (2000) have proposed to allocate the cost of frequency control
SS to producers as afunction of their si^e and their availability. This method thus allocates the SS
costs to generators that are likely to use them (i.e., differentiation between “bad” and
“good” producers). The proposed method could be extended to consumers. However,
three issues have to be addressed for such a cost allocation. First, no perverse incentive
should be given to users. For example, an AS provider should not have any incentive to
increase the SS needs in order to benefit from the sale of additional ancillary services.
Second, the period considered to calculate the availability of generators has to be chosen
carefully, since the availability of a unit may vary a lot, depending on the operating
conditions and the maintenance. Last, the capacity of a unit can be hard to define, since a
generator is unlikely to produce at its maximal output all the time. And if the payment is
based on the declared capacity for, say, the next hour, generators may be tempted to under
schedule, as happened in the early designs of the Californian AS market [Singh (1999)].
4 . 8 . 2 . 3 A llo c a t io n o f t h e a c t u a l utilisation c o s t
The method described in section 4.8.2.2 allocates only the potential SS utilisation cost.
However, the SS actual utilisation cost varies in real-time, depending on the availability of
cheap AS providers. Therefore, two users of the system can have the same potential
utilisation, but one can use SS when they are expensive (e.g., during a consumption peak),
while another can use them when there are cheap (e.g., at night, see section 3.5.2). Note that
226 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
The Cigre Task Force (2001) proposed three methods to allocate the cost of actual
SS utilisation, namely: (a) marginal cost allocation, (b) Shapley-value pricing; and (c)
Aumann-Shapley pricing130. It is assumed here that the SS cost function is known, which is
not necessarily easy, as shown in Chapter 3. First, the marginal cost allocation method charges
users in proportion to the marginal cost they induce because of their SS use. This method
usually gives a higher amount recovered than the actual cost because the SS cost function is
usually convex (the marginal cost is thus higher than the average cost). If a revenue
adjustment is done, revenue and actual cost would match but the cost allocation would not
be efficient.
Second, the Shapley-value method calculates the cost induced by each user as a function
of their entrance order. All the entrance combinations are tried and then an average is
performed. This scheme, in addition to its high computational requirements, is not neutral
with respect to the size of similar users (two users with the same impact on the cost
function but with different sizes would have different rates). This latter drawback can be
resolved by splitting the users into equal sizes (agent splitting method). However, this
increases the computational efforts required.
us p o r example, frequency variations are generally o f low am plitude in large interconnected systems
(e.g., the U C T E o r the N orth-A m erican systems), so solicitations for providers o f primary frequency control
are m ost o f the time relatively low.
129 T he frequency o f an interconnected system is kept centred around its nom inal frequency, so the
deployed quantities o f "u p active pow er balancing” and “ dow n active pow er balancing” (see section 2.3.2) are
relatively similar. O n the other hand, users cannot easily procure reactive p ow er by themselves and the
netw ork naturally uses reactive pow er. Therefore, the deployed quantities o f “up reactive pow er balancing”
and "dow n reactive pow er balancing” are generally very different.
130 Y oung (1994) describes in m ore details and from an econom ic p o in t o f view these cost allocation
methods.
4.8 PROVIDING APPROPRIATE INCENTIVES 227
Third, the Ajtmann-Shapky method is the limit case of the agent splitting method
where the size of agents tends to zero. The price n} charged to each user i is given by (4.1).
j 3 c y r ) dt (4l)
o %
where q* represent the SS actually used (it is a vector that represents the SS utilisation at
every bus of the network), C{g) is the SS cost in function of the SS used and y is the SS
used by the user i. The main drawback of the Aumann-Shapley pricing is that it requires the
SS cost curve. This curve can only be calculated through a centralised algorithm and only if
providers give a complete offer curve. For example, Lin et al (2005) have applied this
method to the reactive power SS in an eight-bus system. In this case, the price of voltage
control SS is computed for each bus and only the opportunity cost of the reactive power AS
is considered.
Second, who should have access to the data} The same data should be available to all
participants of a class (e.g., AS providers) to avoid any discrimination. However, because of
their specific position, the SOs and the market monitoring entity should be allowed to
gather more information than other participants (which thus creates asymmetrical
information). In the case of AS trading across systems, the transmission of data between
SOs is getting very sensitive.
Third, when should be the data published? They can be disclosed either ex-ante or ex-post,
as discussed in section 4.6.5.
4.8.4 Monitoring
Monitoring of ancillary services covers both technical and economic aspects. Indeed, on the
one hand, AS providers have to actually provide the contracted ancillary services. The goal
of this technical monitoring is to detect non-complying AS providers that might endanger the
security of the system. This technical monitoring is thus more important than the one for
energy, because AS are directly related to the security o f the network. On the other hand,
participants should behave fairly by not abusing their dominant position. In addition,
131 H ow ever, generating companies are likely to be reticent about providing the reliability inform ation
on their units.
4.8 PROVIDING APPROPRIATE INCENTIVES 229
market flaws have to be detected as soon as possible. Note that such an economic monitoring is
efficient only when it is associated with a system of penalties and rewards, which is
discussed in section 4.8.5.
4 . 8 . 4 . 1 T e c h n i c a l m o n ito rin g
As shown in section 2.3, the definition of ancillary sendees includes numerous parameters.
Therefore, AS monitoring requires specific equipments such as Phasor Measurement Units
(PMU) to assess the efficiency of the AS provider132. Since the SO is in charge of the
security of the system and is the only entity to have sufficient technical means to monitor
the AS delivery, it should be in charge of the AS technical monitoring. Note that in case of
cross-border trading (see section 2.5), monitoring may be difficult and does require a strong
cooperation between the TSOs involved.
The SO’s technical monitoring may be split into three components. First, the SO
should cany out a preliminary monitoring in order to test the actual capability of the AS
provider [e.g., Robert and Prestat (2004)]. Alternatively, the AS provider may give enough
proof of its capability to fulfil the various criteria. In every case, this preliminary monitoring
should be compulsory for any new provider in the market.
132 F o r detailed explanations on the actual im plem entation o f the technical m onitoring o f AS, see for
example Sterpu (2005) or M argotin ct at (2006).
230 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
Third, because AS are principally used when the system is stressed, AS monitoring
is effective only during system events such as the sudden loss of a large generating unit. As
such an event is unpredictable, a SO has to wait for an event of this kind to actually
monitor an AS provider. Therefore, the SO may carry on instead an extraordinary monitoring
by both stressing the AS provider (e.g., through the variation of the regulation signal sent to
the units from the secondary frequency control) and monitoring its output. This type of
monitoring should be exceptional because it stresses the system.
Lastly, since SOs cannot monitor everything, the proposed scheme should be
complemented by incentives for self-improvement and transparency {self-monitoring). In fact,
AS providers should be encouraged to declare any problem to the SO. However, AS
providers would need sufficient means to monitor their service, which is not always the
case, especially for small providers. Note that this lack of self-monitoring also means that
the AS provider is not in a position to able to argue against the SO’s figures.
4 . 8 . 4 . 2 E c o n o m i c m o n ito r in g
The economic monitoring is usually the task of the regulator or/and the anti-trust bodies
(see section 1.2). The SO can also be involved, but obviously only if it is independent. The
economic monitoring helps both give an incentive to participants and improve the
procurement method. It can be split into four activities [Perrot and Molinier (2005)]: (a)
detecting anti-competitive behaviours; (b) investigating in case of suspicion; (c) imposing
sanctions against proven anti-competitive behaviours (e.g., by using penalties described in
section 4.8.5); and (d) correcting the market design (see section 4.9).
First, the nature of the incentives has to be decided. In fact, penalties and rewards
may be either financial or in other terms. For example, a unit which falls to provide a
contracted sendee may have to provide free sendee (or receive a reduced payment) for a
given period of time or until its next good response [Proctor (2001)]. In New Zealand, the
party responsible for a disturbance pays some event charges determined annually by the
TSO. Then, this fee is redistributed amongst the providers of the frequency control
ancillary sendees during the two months prior the event [Electricity Commission of New
Zealand (2005)]. Other schemes may be imagined, such as a redistribution of the fee
amongst the “good” users during the event. Unfortunately, the literature does not seem to
provide any discussion on this particular issue.
Third, the intensity of the incentives varies with the measured performance. Keller
and Franken (2006) have proposed four different incentive schemes, as shown in
Figure 4.9.
Lastly, the volatility of the incentives should be determined. Indeed, penalties and
rewards can be either fixed or variable over time. For example, they can be high when AS
resources are scarce and low when the resources are abundant [DePillis (2006)], such as
balancing mechanisms that provide volatile penalties (the price to pay for an imbalance
depends on the market conditions).
232 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
2. Continuous
1. Standard 4. Dead Band
3. Capped
Measured
performance
High U E Low
■E
(0
©
a:
Figure 4,9: Four in ten sities o f an incentive sch em e [Keller and Franken (2006)]
4 .9 A s s e s s in g th e P rocurem en t M ethod
Once a complete procurement method has been set up, it should be assessed against the
following three goals: effectiveness (section 4.9.1), minimal running cost (section 4.9.2) and
economic efficiency (section 4.9.3). It is important to perform this assessment regularly
since the various parameters o f the market evolve over time, such as power system
operating conditions, the number and types of AS providers, or the behaviour of
participants. This assessment should be followed by an improvement of the market design.
gains from setting up a complex market for ancillary sendees rather than keeping a simple
framework should therefore be considered carefully. To give an idea, the British balancing
market is said to cost ^80m/year to run [Thomas (2003)]
4 .9 .3 .1 M e a su r in g th e e c o n o m ic efficien cy
To measure the economic efficiency, tire deviation from the simulated competitive price can
be assessed, with, for example, the Lerner index. The Lerner index L I is calculated as in (4.2),
where rt* is the actual price and 7t the simulated competitive price [Liu el ai (2006)].
Sometimes, the competitive price may be hard to determine, so benchmark prices can be used
instead. For instance, generator’s reactive power offers in Australia are compared to
benchmark prices based on the cost of SVCs [Cigre Task Force (2001)]. Deviations of the
actual price from the simulated or benchmarked competitive price can be due to the abuse
of a dominant position. However, some participants may have a dominant position but still
can behave acceptably by helping to reach the competitive price. The parameters affecting a
dominant position are discussed in section 4.9.3.2.
* > *
n
It may be useful for SOs, regulators and AS providers to be able to benchmark their
own markets for ancillary sendees against others and over time. By rising questions and thus
initiating debates amongst participants, such a benchmark may improve the efficiency of
234 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
a ^ = |f- (4-3>
tmrgf
where C Z
AS (in € /year) is the annual ancillary service cost and C* (in € /year) is the annual
wholesale energy cost. CIJ is obtained by multiplying the average wholesale market price
in the same year as CI'AS by the energy consumption of the country in 2003133 PEA (2005)].
The wholesale energy cost is taken instead of the cost for end users in order to avoid price
distortion due to taxes or specific agreements. CAS is either estimated by multiplying the
average price by the average volume of ancillary services or obtained directly from reports.
Figure 4.10 shows the cost indicators in 2004-5 for primary frequency, secondary
frequency and voltage control ancillary services for some systems considered in this thesis.
The results are of the same magnitude as those reported in the study by Hirst and Kirby
(1996) on the AS cost for twelve US utilities. The cost indicators for primary frequency
control are fairly similar across all systems. This Cl is comprised between 0.5 and 0.7 % of
the energy cost, except in Australia where it is 0.35 %. This can be explained by a low price
and a low negative reserve volume. Because of the lack of data on the new British market
for ancillary services, the average cost of the pre-October 2005 system is used.
Secondary frequency control costs are rather high in Spain (more than 4 % of the
energy cost). Indeed, the TSO bought large volumes at high prices in 2005. These high
prices may be explained by the drought that affected Spain during that year. The French
cost indicator is one of the lowest (0.5 %) mainly because of a volume that is more
optimized than the average (see section 2.4.5). Cost incurred in Germany, PJM and New
Zealand are equivalent (from 1 to 2 %). Lastly, the Australian cost indicator is the lowest
because the amount of secondary frequency control reserve is very low.
Australia is the country with the highest voltage control cost. New Zealand cost is
very low, even if the basic voltage control is remunerated, probably because of the large
133 More recent data were not available at the time o f the study.
4.9 ASSESSING THE PROCUREMENT METHOD 235
proportion of cheap hydro units. PJM and France have a similar and intermediate position,
while Great Britain is among the cheapest. Lastly, since the Swedish TSO does not
remunerate voltage control, no cost indicator can be calculated.
4.5 n
Primary frequency control
= 2.5
o 2 .0
« 0.5 ■■
FR DE* ES* GB $
*: V oltage control co st unknown
The parameters given in this section influence the dominance of some participants and are
intrinsic to the market. First, the market concentration quantifies the diversity of possible AS
providers and is usually measured using indicators such as the Herfindahl-Hirschman
Index1'4 (HHI) or the Residual Supply Index1'0 (RSI). A high market concentration is often
mentioned as the main reason of dominance. This lack of competitors is said to lead to an
inefficient market.
Market concentration can be reduced by several means. First, large suppliers may be
split into smaller ones. Besides having vert7strong political consequences, such a policy may
be unfavourable for investments, which are often large in the electricity sector, rely
economies of scales and depend on the control of technology. Second, less restrictive
134 The H erfindahl-H irschm an Index o f a market is calculated by summing the squares o f the
individual m arket shares (in %) o f all participants. It is thus com prised betw een 0 and 10,000. The
correspondance betw een values o f the H H I and the generally agreed concentration o f the market is as follows:
0-999: low; 1,000-1,800: m oderate; 1,801-10,000: high [Newberv et al (2004)].
135 The Residual Supply Index o f a company at a given time is calculated by subtracting the
com pany’s capacity’ (in MW) from the total capacity (imports included and in MW), and by dividing this
difference by the total dem and (in MW). Therefore, if the RSI is inferior to 1, the company is pivotal and has
thus a strong im pact on the market [Newberv et aL (2004)].
236 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
technical requirements may also decrease market concentration because they increase the
number of potential AS providers. As explained in section 2.3.1, a trade-off has to be found
between requirements that are too general or too restrictive. Third, barriers to entry (such as
compulsory connecting conditions that are too complex or long-term bilateral contracts)
decrease the number of potential AS providers. Therefore, removing these barriers may
help decrease market concentration. Lasdy, appropriate incentives, e.g. through a fair
remuneration, have to be given in order to foster competition in the markets for AS.
In practice, Thomas (2003) and Haas et al. (2006) highlight that the electricity sector
is strongly concentrated in Europe. The situation is worse in markets for ancillary services
because fewer units are able to provide AS. However, demand for energy is much more
important than for AS, which makes a comparison between markets for energy and AS
difficult. Nevertheless, actual markets for voltage control suffer from intrinsic high market
concentrations because of their local nature (see section 1.5). On the other hand, markets
for primary and secondary frequency controls are generally less concentrated because
participants located anywhere can provide this service as long as transmission capacities are
sufficient. However, primary frequency control has to be uniformly spread around the
network and technical requirements are more demanding for primary frequency control
than for secondary frequency control (see Chapter 2), so more units are able to provide this
latter sendee.
Second, the liquidity of the market also influences the dominance of participants.
Indeed, even small agents can easily change clearing prices of a non-liquid market by selling
or buying small quantities of AS. Good transmission and standardised products help
increase the liquidity of the market. Note that a market can be both liquid and concentrated.
Third, the topology of the network is an important parameter because the dominance of
an actor increases with network limitations (e.g., congestions). For instance, a non-meshed
network is more easily subject to strategic behaviours because it is easier to create
constraints in such a network. In addition, predictable network events such as the utilisation
of large amount of secondary frequency control at a given hour of the day are also likely to
increase the dominance of participants. Consequently, system operators have a key role to
play in the mitigation of dominant positions through a network design and operation that
foster competition. However, this mitigation of dominant positions has to be at any time in
concordance with the system security.
4.9 ASSESSING THE PROCUREMENT METHOD 237
Fourth, the characteristics of the demand are also very important. First, it is desirable to
have a demand for AS much lower than the supply in order to increase competition [Cali et
al. (2001)]t36. Second, an appropriate demand responsiveness reduces the incentives to
deviate from the competitive price. However, the demand is often inelastic in practice (see
section 2.4). Nevertheless, competition between ERAPs may help introduce more demand
elasticity. For instance, section 2.5 discusses the procurement of AS across different areas,
which implies a competition amongst TSOs. For a further discussion on demand curve for
reserves, Hogan (2006) discusses the definition of such a curve for operating reserves.
Fifth, along with the restructuring of electricity markets, the separation of responsibilities
is an important issue, in particular the unbundling of network and generation/supply
activities (see section 1.2). In the particular case of ancillary sendees, trading AS across
systems can raise similar questions. Indeed, the TSO usually manages the transmission
capacities at its borders. It is also the natural buyer of AS within its territory. Therefore, it
would be relatively easy for the TSO to have a right of pre-emption over the cheap AS
providers within its territory because the TSO would be both deciding the rules and playing
the game.
Lastly, the market design has an obvious impact on the influence of some actors. For
instance, the repetitiveness of the auction in similar conditions may favour strategic
behaviours (see section 4.6.6). As discussing the various issues related to the design of
markets for AS is the principal motivation of the whole chapter, no details are given here.
Broadly speaking, it is important that participants trust the market.
136 See section 4.3 for a discussion on how foster the supply o f AS.
238 CHAPTER 4 PROCUREMENT OF SYSTEM SERVICES
4 .1 0 Sum m ary
This chapter has reviewed in a structured manner most of the issues and solutions related to
the design of the procurement of system services. It is clear that an ideal market design does
not exist, so tire choice of one method over another one deeply relies on the history, the
policy of the legislator, the design chosen for other related products (e.g., energy,
transmission or balancing markets) and the particularities of the power system considered.
To improve current market designs, a fully independent body (e.g., the regulator)
should describe and justify the methods adopted in its system area to solve every issue listed
below. Flaws will then become obvious and thus stakeholders will have strong incentives to
propose improvements.
V Nominating the entity responsible ofprocurement (ERAP): the SO is the best candidate since it
is a natural buyer of AS;
^ Matching supply and demand: long-term supply is achieved with compulsory connecting
conditions. Though it is not the optimal solution, this policy is currently the most
practical. However, reduction of the long-term demand is desirable but rarely
implemented in practice. Concerning short-term procurement, demand response is
compulsory if the ERAP has not covered its supply against risks. More generally,
demand for AS does not reflect the true value of SS in all the surveyed systems;
V Choosing the relevant procurement methods to contract AS provision: various methods are
possible for the ERAP, namely: (a) compulsory provision, (b) self procurement, (c)
bilateral contract, (d) tendering and (e) spot market. None of these solutions is perfect,
so it may be desirable to select a few of them and use them concurrently;
V Defining the structures of offers and payments to remove price distortions: six structures of
offer and payment have been proposed, namely: (a) a fixed allowance, (b) an availability
price, (c) an utilisation payment, (d) the opportunity cost, (e) an utilisation frequency
payment and (f) a price for kinetic energy. The choice amongst these components
depends on the cost structure of the ancillary services considered (e.g., high fixed costs
or high variable costs).
V Organising the market clearing procedure to fix the prices and amounts of transactions
between participants: In conclusion, because of the number of possible methods that
are still under debate, designing the most appropriate market clearing procedure is a
complex task.
4.10 SUMMARY 239
■ Monitoring of the participants in markets for AS: the SO usually performs the
technical monitoring, which is divided into a preliminary, a continuous and an
extraordinary monitoring. Since it is very difficult to monitor all the AS providers,
incentives have to be given to encourage self-monitoring. The regulator and the
anti-trust body are usually in charge of the economic monitoring, which is split into
four functions: detecting, investigating, imposing sanctions and correcting;
S Assessing theprocurement method to improve it. The procurement method should fulfil three
goals; effectiveness, minimisation of running cost and economic efficiency. The
optimum between these three goals is currently searched through an iterative process.
However, assessing these three indicators of the procurement method is actually very
difficult and it is almost impossible to guarantee a competitive price for AS. Actual AS
prices are thus often obtained with the help of acceptable behaviours of the participants
or regulatory decision. ■
CHAPTER 5
CONCLUSIONS AND FUTURE
RESEARCH
From consumers to generating units, including system operators and transmission owners,
all users of an electricalpower system expect an appropriate standardforfrequency and voltage. The global
frequency and the local voltages can be controlled by acting on the balances between
consumption and generation of active and reactive powers across the power system. The
frequency and voltage control sendees are called system sendees (SS). In addition to
expecting a certain standard, the power system users affect the balances of reactive and
active powers. Therefore, any user can both perturb and help controlfrequency and voltages. When
users help control frequency and voltage, they provide the so-called ancillary sendees (AS).
While the responsibility of users to provide ancillary services was less clear twenty years ago,
die development of information technologies, power electronics and electricity markets
force now all users to face tiieir double responsibilities as consumers of system services and
A Comprehensive Assessment of Marketsfor Frequency and Voltage Control Ancillaty Services, Yann Reborns, 2008 241
242 CHAPTER 5 CONCLUSIONS AND FUTURE RESEARCH
providers of ancillary services. However, users need a consistent framework to manage ancillary
services in order tofully grasp opportunities and hence maximize the global welfare.
So far, academic and industrial research was concentrated on specific issues and
sometimes ignored the relations between technique, cost and market design. A global
framework was thus missing. To fill this gap, this thesis provides a comprehensive assessment of
markets for frequency and voltage control ancillary services along three axes: (a) defining the needs for
system services and the ancillary services that can fulfil these needs; (b) assessing the cost of
ancillary services; and (c) discussing the design of an efficient market-based procurement of
system services.
Such a framework exhibits several advantages', (a) stakeholders can grasp quickly the issues
related to ancillary services; (b) stakeholders benefit from a standardised method to assess their
system', (c) solutions are proposed to improve current arrangements', and (d) theoretical limitations
that need future work have been identified.
5 .2 C ontributions to K n o w led ge
First, this thesis has formulated the problem of the needs of users. To meet these needs,
given qualities and quantities ancillary services have to be provided at appropriate locations.
The issues raised by these technical specifications have been discussed and compared with
actual requirements across systems. In particular, the thesis has led to the following
conclusions:
Second, this thesis has reviewed the main cost components of ancillary sendees and
has proposed a methodology to estimate the day-ahead de-optimisation cost incurred by a
producer because of frequency control. This methodology has been successfully applied to
EDF Producer, and has provided several interesting results. The main findings are:
K Estimating accurately the total cost of ancillary sendees is extremely difficultfor aproducer because:
244 CHAPTER 5 CONCLUSIONS AND FUTURE RESEARCH
n The quantity of reserves provided by hydro units, when hydro cannot be used
extensively to provide reserves for some critical time steps, the de-optimisation
cost tends to be high. However, this trend is due to a somewhat simplistic
modelling of hydro units in the optimisation algorithm that does not reflect the
actual cost of hydro units.
■ The demandfor reserves can be the most binding constraint. It may thus be useful to develop
storage or load control strategies in order to allow a conversion of the cheaper
energy into reserves;
■ The reserve constraint may not be binding at all’ so the security of the system can be
increased at very low cost by increasing the demand for reserves during periods
when the marginal costs of reserves are low;
■ The de-optimisation cost due to time control represents tens of millions of euros peryear in France.
The value of such an expenditure needs to be proven.
Third, this thesis has proposed a comprehensive and structured analysis of the
features of a market for ancillary sendees. To improve current market designs and to
balance the information sent to participants, a fully independent body (e.g., the regulator)
should describe and justify the methods adopted to solve the design issues listed below:
>4 Nominating the entity responsible of procurement (ERAP): the system operator is the best
candidate since it is a natural buyer of AS;
'T Matching supply and demand: long-term supply should be ensured to have access in the
long run to sufficient AS capabilities at the appropriate locations. In addition, reduction
of demand for ancillary sendees should be pursued. Furthermore, an efficient short
term procurement mechanism is also essential;
T Choosing the relevantprocurement methods to contract AS provision: five methods have been
listed. Since none of them is perfect, it may be desirable that the ERAP selects a few of
them and uses them concurrently;
T Defining the structures of offers and payments to remove price distortions: six possible
structures of offer and payment have been proposed. The optimal choice amongst these
components depends on the cost structure of the ancillary sendees considered;
T Organising the market clearing procedure to fix the prices and amounts of AS transactions
between participants: Several choices have to be made:
246 CHAPTER 5 CONCLUSIONS AND FUTURE RESEARCH
■ The auction defines how the offer and the demand for AS are submitted and
matched. Classical sealed-bid auctions are preferred in practice, even if such
auctions are not Pareto efficient;
■ The settlement rule organises the payment of the AS providers selected in the auction.
Non-remunerated procurement and administrative prices have to be avoided. The
best settlement rule is still under debate (e.g., discriminatory or uniform price, zonal
or nodal price, etc...);
■ The timing of the market has to be chosen carefully. Higher frequencies are likely to
increase the efficiency o f the market, but also the potential for abuse of dominance
and the operating cost.
"C Ptice caps of any kind should be avoided as much as possible. An appropriate demand
curve is much more desirable;
■ The allocation of SS costs should ideally be performed with three components: (a) the
fixed cost of SS through the transmission tariff, (b) the variable AS reservation costs
through an allocation based on the potential utilisation of the users, and (c) the
actual utilisation of SS through to the users that make the actual use o f these
services necessary;
■ Monitoring of the participants in markets for AS: the SO usually performs the
technical monitoring and incentives have to be given to encourage self-monitoring
and transparency. The regulator and the anti-trust body are usually in charge of the
economic monitoring;
5.3 SHORT-TERM EVOLUTIONS DESIRABLE IN FRANCE 247
By applying the assessment framework to the French power system, various short-term
evolutions become obvious candidates for improving current arrangements (the thesis
discusses in more details the issues related to the following propositions):
complement the current system of long-term bilateral contracts. This would help
increase the global welfare;
■ Structures of offers and payments: symmetrical prices should be removed. The voltage
control availability payment (i.e., in €/M var/h) should be a function of the distance
from the unity power factor;
■ Settlement ride: the energy utilisation of the secondary frequency control should be
indexed on the price of balancing mechanism since the objectives of these two
controls are similar.
This thesis has left open various issues. First, this thesis focused on the description of an
assessment method. Therefore, the developed framework will be particularly useful if it is
applied to actual systems (the thesis applied the framework only partially to actual systems).
Furthermore, the structures of systems vary over time. Therefore, the proposed assessment
should be applied regularly on power systems to improve current arrangements, balance information and
share goodpractices. Such an assessment would be particularly interesting for systems that are
likely to benefit from a common market for AS in the future, such as Belgium, France,
Germany, Luxembourg and The Netherlands. For example, a dedicated taskforce funded by
regulators could be set up. Note that particular attention should be brought to the operating
cost of markets, which is usually ignored in the restructuring process.
Fourth, the limit between negotiable and non-negotiable products is not clear. For
example, stability is not remunerated in some systems, whereas some units are useful for
stability and others do not contribute to it. Therefore, it seems important to draw the limit
between negotiable and non-negotiableproducts and to evaluate the price of potential new sendees.
Fifth, the exchange of ancillary sendees across systems is an important feature to help
increase the global welfare. However, such an arrangement is challenging for several
reasons: (a) it necessitates product standardisation across systems; (b) it needs market
standardisation; and (c) it faces the strong engineering challenge to co-ordinate energy,
transmission and ancillary services markets in a decentralised manner. In addition, the best
organisation to tackle this issue is not clear. For example, should a dedicated entity or
informal networks perform such studies?
Sixth, markets for ancillary sendees suffer from structural dominant positions.
Therefore, economic research has to develop methods that guarantee an efficient procurement of
ancillaiy services despite structural issues.
Seventh, the cost of ylS should be better understood. In particular, OTESS could be used
to determine the annual supplemental cost of frequency control reserves (i.e., the cost to
provide one supplemental MW over one year). The study could also be completed with
additional data since August 2007 and improved by better taking into account hydro
constraints. Moreover, AS price forecasting should be improved to better negotiate long
term contracts.
Eight, to make the system as efficient as possible, it is essential to investigate all the
technicalpossibilities to controlfrequency and voltage. In particular, research should be performed to
increase contributions by intermittent generation, loads and storage.
Ninth, the diesis was concentrated on the markets for ancillaiy sendees. However,
other electricity markets, such as enetgy, transmission or C 02 could benefit from similar comprehensive
assessmentframeworks. ■
250 CHAPTER 5 CONCLUSIONS AND FUTURE RESEARCH
REFERENCES
Abbott (2001) M. Abbott, "Is the Security of Electricity Supply a Public Good?" The
Electricity Journal\ vol. 14 (7), pp. 31-33, August-September 2001.
Anderson (1999) P. M. Anderson, Power System Protection, New York, NY: Wiley-IEEE
Press, 1999.
Arnott et al. (2003) I. Arnott, G. Chown, IC. Lindstrom, M. Power, A. Bose, O. Gjerde,
R. Morfill, and N. Singh, "Frequency control practices in market environments", in
Proc. 2003 C IG R E /IE E E PES International Symposium. Quality and Security of Electric
Power Delivety Systems, pp. 143-148.
251
252 REFERENCES
Arroyo and Galiana (2005) J. M, Arroyo and F. D. Galiana, "Energy and reserve pricing
in security and network-constrained electricity markets", IE E E Transactions on
Power Systems, vol. 20 (2), pp. 634-643, May 2005.
Bakken and Faanes (1997) B. Bakken and H. Faanes, "Technical and economic aspects of
using a long submarine HVDC connection for frequency control", IE E E
Transactions on Power Systems, vol. 12 (3), pp. 1252-1257, August 1997.
Belgium economic department (2002) Ministere des affaires economiques, Arrete royal
etablissant nn reglement technique pour la gestion du reseau de transport de Peledricite et Pacces a
celui-ci, Moniteur Beige, 2002, pp. 58471-58541. Available:
http://www.ejustice.just.fgov.be/
Berry and Lindgren (1990) D. A. Berry and B. W. Lindgren, Statistics: tbeoiy and method.
Pacific Grove, Calif: Andover : Brooks/Cole ; International Thomson Pub.
Sendees, 1990.
Billinton and Allan (1996) R. Billinton and R. N. Allan, Reliability evaluation ofpower systems.
New York; London: Plenum Press, 1996.
Brien (1999) L. Brien, "Why the Ancillary Services Markets in California D on't Work and
What to Do About It", The Electricity Journal, vol. 12 (5), pp. 38-49, June 1999.
British Electricity International (1991) British Electricity International, Modem power station
practice : incorporating modernpower systempractice, 3rd ed. Oxford: Pergamon, 1991.
Bushnell and Oren (1994) J. B. Bushnell and S. S. Oren, "Bidder cost revelation in
electric power auctions", Journal of Regulatory Economics, vol. 6 (1), pp. 5-26,
February 1994.
Chao and Wilson (2002) H.-P. Chao and R. Wilson, "Multi-Dimensional Procurement
Auctions for Power Reserves: Robust Incentive-Compatible Scoring and
Settlement Rules", Journal of Kegulatoy Economics, vol. 22 (2), pp. 161-183,
September 2002.
Cigre Task Force (2001) Task Force 38.05.07, "Methods and tools for costing ancillary
services", Report No 190, Conseil International des Grands Reseaux Electriques
(Cigre), Paris, France, June 2001.
Cramton and Stoft (2005) P. Cramton and S. Stoft, "A Capacity Market that Makes
Sense", The Electricity Journal, vol. 18 (7), pp. 43-54, August-September 2005.
256 REFERENCES
CRE (2008) "Observatoire des marches de l’electricite et du gaz - 4eme trimestre 2007",
Commission de Regulation de l'Energie (CRE), Paris, France, 29 February 2008.
Available:
http://w w w .cre.fr/fr/content/ download/5342/118109/file/dmspObsT407.pdf
DePillis (2006) M. S. DePillis, "The New Ancillary Services Markets of New England",
presented at the Midwest ISO Ancillary Services Roundtable, Carmel, IN, USA,
26-27 April 2006. Available:
http://www.midwestmarket.org/publish/Document/469a41_10a26fa6cle_-
74c30a48324a/7%20-
%20Midwest%20ISO%20Ancillary%20Services%20Roundtable_ISO-
NE.pdfPaction^downloadiS^property^ Attachment
DTe (2005) "Netcode", Directie Toezicht Energie, The Hague, The Netherlands, 1 July
2005. Available:
http://www.dte.nl/images/NETCODE%20per%2001072005_tcm7-74895.pdf
E.ON (2005) "Procurement of control power and energy in Germany", E.ON Netz
GmbH, Bayreuth, Germany, 07 July 2005. Available: http://www.eon-
netz.com/Ressources / downloads/procurement_controlpower_energy.pdf
ETSO tariffs task force (2006) "ETSO Overview of transmission tariffs in Europe:
Synthesis 2005", European Transmission System Operators (ETSO), Brussels,
Belgium, June 2006. Available: http://www.etso-
net.org/upload/documents/benchmarking2005.pdf
French economic and industry department (2003) Ministere de Peconomie, des finances
et de l’industrie, Arrete du 4 juillet 2003 relatif auxprescriptions techniques de conception et
de fonctionnement pour le raccordement au reseau public de transport d’une installation de
production d’energie electrique, Journal Officiel de la Republique francaise n° 201, 2003,
pp. 14896-14902. Available:
http://www.legifrance.gouv.fr/WAspad/UnTexteDeJorf?numjo=INDI0301719A
French economic and industry department (2005) Ministere de Peconomie, des finances
et de Pindustrie, Decision du 23 septembre 2005 approuvant les tarifs d’utilisation des
reseauxpublics de transport et de distribution d''electricite, Journal Officiel de la Republique
frangaise n° 233, 2005, pp. 15888-15917. Available:
http://www.legifrance.gouv.fr/WAspad/UnTexteDeJorf?numjo=INDI0505749S
REFERENCES 259
Frontier Economics and Consentec (2005) "Benefits and practical steps towards the
integration of intraday electricity markets and balancing mechanisms", Frontier
Economics Ltd, London, U.K., December 2005. Available:
http://europa.eu.int/comm/energy/electricity/publications/doc/frontier_consen
tec_balancing_dec_2005.pdf
Fuller (1976) W. A. Fuller, Introduction to statistical time series. New York ; London: Wiley,
1976.
Gautier (1990) A. Gautier, "Le fonctionnement des centrales a eau sous pression -
Adaptation de la centrale aux besoins du reseau", Institut National des Sciences et
Techniques Nucleaires (INSTN), Saclay, France, 1990 (approximate date).
Goel et al. (2004) L. Goel, Z. Song, and P. Wang, "Impact of Transmission Line Failures
on the Cost/Risk-Based Spinning Reserve Allocation", International Journal of
Emerging Electric Power Systems, vol. 1 (1), May 2004.
Grainger and Stevenson (1994) J. J. Grainger and W. D. Stevenson, Power system analysis.
New York ; London: McGraw-Hill, 1994.
260 REFERENCES
Haas et al (2006) R. Haas, J.-M. Glachant, N. Keseric, and Y. Perez, "Competition in the
Continental European Electricity Market: Despair or Work in Progress?" in
Electricity market reform: an international perspective, Elsevier global energy polity and
economics series, F. P. Sioshansi and W. Pfaffenberger, Amsterdam: Elsevier, 2006,
pp. 265-315.
Hamilton (1994) J. D. Hamilton, Time series analysis. Princeton, N.J.: Princeton University
Press, 1994.
Hao and Papalexopoulos (1997) S. Hao and A. Papalexopoulos, "Reactive power pricing
and management", IE E E Transactions on Power Systems, vol. 12 (1), pp. 95-104,
February 1997.
Hirst and Kirby (1996) E. Hirst and B. Kirby, "Costs for electric-power ancillary
services", The Electricity Journal, vol. 9 (10), pp. 26-30, December 1996.
Hirst and Kirby (1997) E. Hirst and B. Kirby, "Creating competitive markets for ancillary
services", ORNL/CON-448, Oak Ridge National Laboratory, Oak Ridge, TN,
USA, October 1997. Available:
http://www.ornl.gov/sci/btc/apps/Restructuring/con448.pdf
Hirst and Kirby (1998) E. Hirst and B. Kirby, "Unbundling Generation and
Transmission Services for Competitive Electricity Markets: Ancillary Services",
ORNL/CON-454, National Regulatory Research Institute, Colombus, OH, USA,
REFERENCES 261
Hogan (2006) W. W. Hogan, "Reliability and scarcity pricing: operating reserve demand
curves (continued)", Harvard University, Cambridge, MA, USA, 3 March 2006.
Available: h ttp ://www.hks.haivard.edu/hepg/Papers/Hogan_hepg_030206.pdf
Hoinkis and Lindner (2007) J. Hoinkis and E. Lindner, Chemie fur Ingenieure, 13 ed.
Weinheim: Wiley-VCH, 2007.
IEEE Std 1159-1995 (1995) IEEE Working Group on Monitoring Electric Power
Quality, IE E E Std 1159-1995 - IE E E Recommended Practice for Monitoring Electric
Power Quality. New York: The Institute of Electrical and Electronics Engineers,
Inc., 1995.
Ingleson and Ellis (2005) J. W. Ingleson and D. M. Ellis, "Tracking the eastern
interconnection frequency governing characteristic", in Proceedings of the 2005 IE E E
Power Engineering Society General Meeting, pp. 2484 - 2489.
Joskow and Tirole (2004) P. joskow and J. Tirole, "Reliability and competitive electricity
markets", Report No CSEM WP 129, University of California Energy Institute
(UCEI), Berkeley, CA, USA, April 2004. Available:
http://repositories.cdlib.org/ ucei/csem/CSEMWP-129/
Kariuki and Allan (1996) K. K. Kariuki and R. N. Allan, "Evaluation of reliability worth
and value of lost load", IE E Proceedings: Generation, Transmission and Distribution, vol.
143 (2), pp. 171-180, March 1996.
Keller and Franken (2006) K. Keller and B. F. C. Franken, "Quality of supply and market
regulation; survey within Europe", 30630505-TDC 06-59095A, KEMA
Consulting, Arnhem, The Netherlands, 7 December 2006. Available:
h ttp ://www.leonardo-energy.org/drupal/files/2006/06-59095A.pdf?download
Kirby and Hirst (1996) B. Kirby and E. Hirst, "Ancillary-Service Costs for 12 U.S.
Electric Utilities", ORNL/CON-427, Oak Ridge National Laboratory, Oak Ridge,
TN, USA, April 1996. Available:
http://w w w .ornl.gov/ sci/btc / apps/Restructuring/con427.pdf
REFERENCES 263
Kirby and Hirst (2000) B. Kirby and E. Hirst, "Customer-specific metrics for the
regulation and load-following ancillary sendees", Report No ORNL/CON-474,
Oak Ridge National Laboratory, Oak Ridge, TN, USA, January 2000. Available:
h ttp ://certs.lbl.gov/pdf/ornl-con-474.pdf
Kirby and Hirst (2003) B. Kirby and E. Hirst, "New England Demand Response
Initiative: Technical issues related to retail-load provision of ancillary sendees", 10
February 2003. Available:
http://www.raponline.org/Pubs/NEDRI/AncillaiyBackground.pdf
Kirschen (2002) D. S. Kirschen, "Power system security", Power Engineering Journal, vol. 16
(5), pp. 241-248, October 2002.
Kirschen and Strbac (2004a) D. S. Kirschen and G. Strbac, Fundamentals ofpower system
economics, 1st ed., Chichester: Wiley, 2004.
Kirschen and Strbac (2004b) D. S. Kirschen and G. Strbac, "Why Investments D o Not
Prevent Blackouts", The Electricity Journal, vol. 17 (2), pp. 29-36, March 2004.
Klemperer (2002) P. Klemperer, "What really matters in auction design", The Journal of
Economic Perspectives, vol. 16 (1), pp. 169-189, winter 2002.
Kluge (2006) T. Kluge, "Pricing Swing Options and other Electricity Derivatives", PhD
Thesis, Mathematical Institute, St Hugh's College, University of Oxford, Oxford,
UK, 2006. Available: http://eprints.maths.ox.ac.uk/246/01/kluge.pdf
264 REFERENCES
Kundur (1994) P. Kundur, Power system stability and control. New York; London: McGraw-
Hill, 1994.
Lemarechal (2004) C. Lemarechal, "Saving Energy", in ERCIM News, vol. 56, January
2004, p. 43. Available:
http://www.ercim.org/publication/Ercim_News/enw56/EN56.pdf
Lin et al. (2005) X. J. Lin, C. W. Yu, and C. Y. Chung, "Pricing of reactive support
ancillary services", IE E Proceedings-Generation, Transmission and Distribution, vol. 152
(5), pp. 616-622, September 2005.
Liu et al (2006) J. D. Liu, T. T. De, and K. L. Lo, "An empirical method o f dynamic
oligopoly behavior analysis in electricity markets", IE E E Transactions on Power
Systems, vol. 21 (2), pp. 499-506, May 2006.
Luh et al. (2006) P. B. Luh, W. E. Blankson, Y. Chen, J. H. Yan, G. A. Stern, S.-C. Chang,
and F.Zhao, "Payment cost minimization auction for deregulated electricity
markets using surrogate optimisation", IE E E Transactions on Power Systems, vol. 21
(2), pp. 568-578, May 2006.
Meeus and Belmans (2008) L. Meeus and R. Belmans, "Electricity market integration in
Europe", Rome E tijdschrift, vol. 124 (1), March 2008.
National Grid (2007) "Short-term operating reseive: general description of the sendee",
National Grid, Warwick, U.K., 14 December 2007. Available:
http: / / www. nationalgrid. com/ N R / rdonlyres / 72D4386B-2027-474C-B 281 -
2384F5B21A5E/22123/STOR_Sentice_Des crip tionJFinal.pdf
National Grid (2008a) "The Grid Code", Issue 3, Revision 25, National Grid, Warwick,
U.K., 1 February 2008. Available:
http:/ / www. nationalgrid. com /N R / rdonlyres /1403354E-3 6F2-4010-A7 2C-
F36862ElFF3E/23088/zFullGBGridCodeI3R25.pdf
National Grid (2008b) "Firm Frequency Response Market Information for Tenders for
April 2008", National Grid, Warwick, U.K., 2008. Available:
http://www.nationalgtid.eom/NR/rdonlyres/F4649A84-1580-4E15-B411-
0FAE9159608A/23984/FFR_Market_Info_Apr_2008_vl .pdf
National Grid (2008c) "Reactive Power Market. Obligatory and Enhanced Reactive
Power Sendees: Invitation to Tender and Guidance Notes for the Completion of
Tenders for Reactive Power Market Agreements Commencing 1 October 2008",
266 REFERENCES
NEMMCO (2004) "Market Ancillary Service Specification", Version 1.5 Final, National
Electricity Market Management Company Limited, Australia, 27 February 2004.
Available: http://www.nemmco,com.au/anciUary_services/160-0163.pdf
Newbery et al (2003) D. Newbery, N.-H. von der Fehr, and E. van Damme,
"Transparency and monitoring o f security and adequacy of supply", Directie
REFERENCES 267
Toezicht Energie (DTe), The Hague, The Netherlands, 25 August 2003. Available:
http://www.dte.nl/images/12_12720_tciTi7-3712.pdf
Newbery et al. (2004) D. Newbery, R. Green, K. Neuhoff, and P. Twomey, "A Review of
the Monitoring of Market Power: The Possible Roles of TSOs in Monitoring for
Market Power Issues in Congested Transmission Systems", European
Transmission System Operators (ETSO), Brussels, Belgium, November 2004.
Available: http://www.etso-
net.org/upload/documents/ETSO%20Market%20Power%20£inal.pdf
Nordel (2004) "Nordisk Regelsamling (Nordic Grid Code)", Nordel, Helsinki, Finland,
18 June 2004. Available:
http://www.statnett.no/Resources/Filer/Dokumenter/Div.%202004/Nordisk%
20regelsamling%20rev%20161104.pdf
Numerical Algorithms Group (2007) (October). "NAG Add-Ins for Excel". [Online]
Available: http://www.nag.co.uk/downloads/aedownloads.asp
NZIER (2005) "Market Design Report: Initial Stock-take Paper Report to the Electricity
Commission", NZIER, Wellington, New Zealand, August 2005. Available:
http: / / www.electricitycommission.govt.nz/pdfs/opdev/wholesale/market-
design/Initial-Stocktake.pdf
268 REFERENCES
Oren (2001) S. Oren, "Design of ancillary service markets", presented at the 34th Annual
Hawaii International Conference on System Sciences, Maui, HI, USA, 3-6 January
2001.
Oxford Dictionary (2001) 0>ford Paperback Dictionary, Thesaurus and Wordpower Guide. New
York: Oxford University Press Inc., 2001.
Peradotto (2001) A. Peradotto, "Data mining : etat de l’art", Internal report No HE-
72/2001/016/A, Electricite de France Research and Development (EDF R&D),
Clamart, France, 24 July 2001.
Perrot and Molinier (2005) D. Perrot and P. Molinier, "Surveillance des marches de
gros", Internal report No H-Rl 6-2005-01546-FR, Electricite de France Research
and Development (EDF R&D), Clamart, France, July 2005.
PJM (2005a) "PJM eMKT Users Guide", PJM Interconnection, Norristown, PA, USA,
June 2005. Available:http://www.pjm.com/etools/downloads/emkt/ts-
userguide.pdf
PJM (2006) "Manual 35: Definitions and Acronyms", Revision 13, PJM Interconnection,
Norristown, PA, USA, 1 November 2006. Available:
http://w w vrpjm .com /contributions/pjm-manuals/pdf/m35.pdf
PJM (2007) "Manual 12: Balancing Operations", Revision 16, PJM Interconnection,
Norristown, PA, USA, 01 November 2007. Available:
http: / / www.pjm.com/ contributions/pjm-manuals/pdf/ml 2.pdf
270 REFERENCES
PJM (2008) "Manual 11: Scheduling Operations", Revision 34, PJM Interconnection,
Norristown, PA, USA, 21 February 2008. Available:
http://www.pjm .com /contributions/pjm -m anuals/pdf/m ll.pdf
Raineri et al. (2006) R. Raineri, S. Rios, and D. Schiele, "Technical and economic aspects
of ancillary services markets in the electric power industry: an international
comparison", Energy Polity, vol. 34 (13), pp. 1540-1555, September 2006.
Rious (2007) V. Rious, Ee developpement du reseau de transport dans un systeme electrique liberalise,
un probleme de coordination avec la production, PhD Thesis, Faculte Jean Monnet, Paris-
Sud XI and Supelec, Paris, France, 2007. Available:
http://www.grjm.net/index.php?option=com_content&task=view&id=455&Ite
mid=65
Robert and Prestat (2004) G. Robert and B. Prestat, "Conformity evaluation method of
power plants performance for grid stability", in Proceedings of the 2004 IE E E PES
Power Systems Conference and Exposition (PSCE), vol. 2, pp. 1109-1112.
REFERENCES 271
RTE (2007a) (February). "RTE - Clients & acteurs du marche - Vie du systeme .
[Online]. Available: http://www.rte-
france.com /htm /fr/vie/ vie_mecanisme_historique.jsp
RTE (2007b) RTE, "Contrat type de participation aux services systeme", Reseau de
Transport d'Electricite (RTE), La Defense, France, 21 December 2007. Available:
http:/ / www. rte-
france.com /htm /fr/offr e/telecharge/Contrat_services_systeme__trame_type_2007
_12_21.pdf
RTE (2007c) "Dossier de presse : Le bilan electrique francais 2006", Reseau de Transport
de l'Electricite (RTE), La Defense, France, January 2007. Available:
http: / / www.rte-
france.com/htm/ fr/journalistes/telecharge/dossiers/DP_bilanElec_2006.pdf
Saporta (1990) G. Saporta, Probability, analyse des donnees et statistique. Paris, France:
Editions Technip, 1990.
Singh (1999) H. Singh, "Auctions for ancillary services", Decision Support Systems, vol. 24
(3-4), pp. 183-191, January 1999.
Staropoli and Jullien (2006) C. Staropoli and C. Jullien, "Using Laboratory Experiments
to Design Efficient Market Institutions. The case of wholesale markets", presented
at the Journees de la section electrotechnique du club EEA 2006, Gif-sur-Yvette,
France, 15-16 March 2006.
Stoft (2002) S. Stoft, Power system economics: designing markets for electricity. Piscataway, N.J.;
New York, N.Y.: IEEE Press: Wiley-Interscience, 2002.
Strbac and Kirschen (2000) G. Strbac and D. S. Kirschen, "Who Should Pay for
Reserve?" The Electricity Journal\ vol. 13 (8), pp. 32-37, October 2000.
SvIC (2005) (December). "Svenska Kraftnat keeps the electricity system in balance".
[Online]. Available: littp ://www.svk.se/web/Page.aspx?id=5216
TenneT (2003) "Samenvatting uit "Summary of the current operating principles of the
UCPTE" met betrekking tot de primaire en secundaire regeling", TenneT,
274 REFERENCES
Tesseron (2008) J*-M. Tesseron, "Mission : Surete - Lutter contre les blackouts",
presented at the IEEE France General Meeting, Paris, France, 14 March 2008.
Thomas (2003) S. Thomas, "The Seven Brothers", Energy Policy, vol. 31 (5), pp. 393-403,
April 2003.
Tirole (1988) J. Tirole, The theory of industrial organisation. Cambridge, Mass. ; London: MIT
Press, 1988.
Tyagi and Srivastava (2006) B. Tyagi and S. C. Srivastava, "A decentralised automatic
generation control scheme for competitive electricity markets", IE E E Transactions
on Power Systems, vol. 21 (1), pp. 312-320, February 2006.
UCPTE (1991) "Active power control in the UCPTE system - Inventory", Union for the
Co-ordination of Production and Transmission of Electricity (UCPTE), Brussels,
Belgium, 1991.
REFERENCES 275
UCTE (2004a) "Final report of the Investigation Committee on the 28 September 2003
blackout in Italy", Union for the Co-ordination of Transmission of Electricity
(UCTE), Brussels, Belgium, April 2004, Available:
h ttp ://www.ucte.org/_library/otherreports / 20040427_UCTE_IC_Final„report.p
df
UCTE (2004b) "UCTE Operation Handbook", Version 2.5E, Union for the Co
ordination of Transmission of Electricity (UCTE), Brussels, Belgium, 20 July 2004.
Available:
http://www.ucte.org/_library/ohb / Operation_Handbook_20.07.2004.pdf
UCTE (2005) "Geographical Distribution of Reserves", Version 1.0, Union for the Co
ordination of Transmission of Electricity (UCTE), Brussels, Belgium, July 2005.
Available:
http:/ / www.ucte.org/_library / otherreports / Geograp hical_Dis tribution_o f_Reser
ves.zip
UCTE (2006) UCTE, "Geographical Distribution of Reserves", Version 1.0, Union for
the Co-ordination of Transmission of Electricity (UCTE), Brussels, Belgium, July
2005 (available since June 2006). Available:
h ttp://www.ucte.org/_libraiy/otherreports/Geographical_Distribution_of_Reser
ves.zip
UCTE (2007) "Final Report - System Disturbance on 4 November 2006", Union for the
Co-ordination of Transmission of Electricity (UCTE), Brussels, Belgium, January
2007. Available: http://www.ucte.org/_libraiy/otherreports/Final-Report-
20070130.pdf
U.S.-Canada Power System Outage Task Force (2004) U.S.-Canada Power System
Outage Task Force, "Final Report on the August 14, 2003 Blackout in the United
States and Canada: Causes and Recommendations", April 2004. Available:
https://reports.energy.gov/BlackoutFinal-Web.pdf
276 REFERENCES
Varian (1999) R. Varian Hal, Intermediate microeconomics: a modem approach, 5th edition, New
York; London: W.W. Norton & Co, 1999.
Weisman (2005) D. L. Weisman, "Price regulation and quality", Information Economics and
Polity, vol. 17 (2), pp. 165-174, March 2005.
Williams and Lane (2004) H. E. Williams and D. Lane, Web Database Applications with PHP
and MySQL,, 2nd ed. Sebastopol, CA, USA; Cambridge, MA, USA: O'Reilly, 2004.
Wilson (2002) R. Wilson, "Architecture of power markets", Econometrica, vol. 70 (4), pp.
1299-1340, July 2002.
Yan and Stern (2002) J. H. Yan and G. A. Stern, "Simultaneous Optimal Auction and
Unit Commitment for Deregulated Electricity Markets", The Electricity Journal, vol.
15 (9), pp. 72-80, November 2002.
Young (1994) H. P. Young, "Cost Allocation", in Handbook of game theoiy with economic
applications, vol. 2. Amsterdam; Oxford: Elsevier, 1994, pp. 1193-1235.
Zhong (2003) J. Zhong, "On some aspects of design of electric power ancillary service
markets", PhD Thesis, Department of Electric Power Engineering, Chalmers
REFERENCES 277
Zhong et al. (2005) Z. Zhong, C. Xu, B. J. Billian, L. Zhang, S.-J. S. Tsai, R. W. Conners,
V. A. Centeno, A. G. Phadke, and Y. Liu, "Power system frequency monitoring
network (FNET) implementation", IE E E Transactions on Power Systems, vol. 20 (4),
pp. 1914-1921, November 2005.
Zhu et al (2000) J. Zhu, G. Jordan, and S. Ihara, "The market for spinning reserve and its
impacts on energy prices", presented at Power Engineering Society Winter
Meeting, Singapore, 2000.
Zobian and Ilic (1997a) A. Zobian and M. D. Ilic, "Unbundling of transmission and
ancillary sendees. I. Technical issues", IE E E Transactions on Power Systems, vol. 12
(2), pp. 539-548, May 1997.
Zobian and Ilic (1997b) A. Zobian and M. D. Ilic, "Unbundling of transmission and
ancillary sendees. II. Cost-based pricing framework", IE E E Transactions on Power
Systems, vol. 12 (2), pp. 549-558, May 1997. ■
278 REFERENCES
REFERENCES BY CATEGORIES 279
REFERENCES BY
CATEGORIES
G eneral
M a th em atics
P ow er s y s te m s
R eliability o f p o w er s y s te m s
E co n o m ics
P ow er s y s te m e c o n o m ic s
A ustralia
B elgium
California
France
G erm any
G reat Britain
T he N eth erlan d s
N ew Z ealand
PJM
Spain
Spanish industry and energy department Spanish industry and energy department
(1998) (2006a)
Spanish industiy and energy department Spanish industry and energy department
(2000) (2006b)
OMEL (2005)
REFERENCES BY CATEGORIES 285
S w ed en
Europe
North A m erica
Jou rn als
Y. Rebours, D. Kirschen, M. Trotignon, and S. Rossignol, "A Survey of Frequency and
Voltage Control Ancillary Sendees—Part I: Technical Features”, IE E E Transactions
on Power Systems, vol. 22 (1), pp. 350-357, February 2007.
C o n feren ces
Y. Rebours, "Some salient features of the management of frequency and voltage control
ancillary sendees", presented at the IEEE Power Engineering Society General
Meeting, Tampa, FL, USA, 2007.
Working p ap ers
287
288 PUBLICATIONS
289
290 THE AUTHOR
APPENDICES
Since the definition of some statistic indicators may vary [Berry and Lindgren (1990)], the
statistics and data analysis method used in this thesis, as well as their abbreviations and
symbols are presented in this section. Note that we consider that all the existence
conditions are met to calculate these various statistics (e.g., no division by zero, vectors
have an appropriate size and sums do not tend toward the infinity).
(A.1.1)
'ri The sample mean tends to the expected value of the random variable X when the number
of observation increases [Berry and Lindgren (1990)];
'ri The sample variance ( a 2) represents the weighted scattering of the data137:
137 N o te that the sample variance is defined slighdy differently in com parison to die variance o f the
random variable X (also called population variance). T he variance o f die random variable generally cannot be
calculated because m ost o f the time the complete population is unknow n [Berry and Lindgren (1990)].
291
292 APPENDICES
(A.1.2)
^ The sample standard deviation (p) gives a friendlier picture of the dispersion than the
variance because the standard deviation is homogeneous to X:
(A.1.3)
^ The sample median (5?), also called second quartile, is the value that splits a sample in two
parts, with 50 % o f the sample on each side. It is calculated as follows [Berry and
Lindgren (1990)]:
N +1
if N is odd => x
(A.1.4)
~N~ [N 1\
if N is even => — x + X — +1
2 _2 _ 2 J
S The first quartile (FQ) is the median of the samples below the median (the median
excluded)138. It thus represents the boundary that holds the 25 % first sample values;
'd The third quartile (TQ) is the median of the samples above the median (the median
excluded)538. It thus represents the boundary that gathers the 75 % first sample values;
^ More generally, the nthpercentile (p,) is the boundary for the n % first values of the
sample. It is calculated as follows in our study [Mathworks (2007)]:
We define:
j W = M xL _ I (A.1.5)
N
A = x Ul+ — :* G M - jM ) (*[*'+!] - *[*']) (A. 1.7)
138 ]\f0 t;e that M icrosoft Excel does n o t use exactly the same algorithm to define th e first and third
quar tiles.
A.l BASICS OF STATISTICS 293
A The interquartile range (IQR) represents how the majority of the data dose to the centre
are spread. It thus a good indicator of the dispersion of the “reasonable” data. The
interquartile range may be used to find outliers, i.e. observations that are standing out of
the crowd. The IQR is defined as follows:
%2&=TJ2-F& (A-1-8)
A The interquartile mean (IQM) is the average of the 50 % samples that are around the
median and is defined as follows, where N* represents the set of the natural numbers
except zero:
3N
N 2 -± -
if e n * => — Yx[k]
4 N r=—
n +i
3N +1
N -1 2 -4 -
if— - e N £ * •[£ ]
N + 1 /i—
N -l
----H
4 i
IQM ~ 3 N -2
(A.1.9)
N -2 *
if eN
AT —2 X:—
a:+2
..... +1 4
3 N -1
N - 3 2 *
if —— - e N
IV —1 ^_n+i+1
4
A A range of values is called a class interval The number of samples in a given class interval
gives the frequency of this class. When the frequencies are divided by the size of the sample,
the relative frequencies are obtained, that are called probability in this report by misuse
of language;
A The relative frequencies are plotted in many figures in this thesis. Such a figure gives a
so-called frequency distribution and an example is given in Figure A.1.1. Note that several
frequency distributions could be defined since different class intervals may be chosen.
In addition, contrary to histograms, the areas in a frequency distribution do not mean
anything. However, class intervals in this report have all the same size for a given
frequency distribution to facilitate the reading. Lastly, the sum of the relative
frequencies is obviously equal to one.
294 APPENDICES
Probability
Value
Class interval
Figure A.1.1: E xam ple o f a frequency distribution
(A.1.10)
^ It is important to keep in mind that Cxy and rx? can be equal to zero despite a clear non
linear relationship between the two variables;
Y Cxy and rxy represent the strength of the linear relationship between X and Y, but do not give
information about the significance of the strength of the linear relationship. The
significance can be estimated with for example a one-tailed test (t-test);
139 The general term to designate data with observations on several variables is multivariate data.
140 The sample covanance is som etimes called cross-covanance to make the distinction with the
covanance m atnx o f a time series [Fuller (1976)]
A.l BASICS OF STATISTICS 295
■A A significant strong linear relationship between X and Y does not mean that X causes Y
or vice-versa;
Y A scatter plot shows the relation between two variables by plotting each observation in a
two-dimensional graph, where the horizontal axis represents one random variable and
the vertical axis the second one. This kind of graph may be very helpful to detect
specific patterns.
A time series is a sequence of observations made at regular interval of time [Open University
(1988)]. When the observations of the random variables are made over time, the basic
statistics presented in the previous sections can be misleading in some cases, although they
can give a good insight of some particular data arrangements (e.g., see section 3.4.3).
Y Let us consider a univariate time series defined by Al elements, noted from x[/] to x[N\,
classified in chronological order;
£=1
Y From the previous formula, the autocorrelationfunction (ACF) can be drawn with the lags
on the horizontal axis and the corresponding autocorrelation coefficients on the vertical
axis;
Y The ACF shows the influence of all the observations from x[k—la£^ to x"[/^—1] on x[C].
To estimate the specific influence of x[k—laf\ on v[X^], the partial autocorrelation function
(PACF) should be used instead. Since its formulation is not straightforward [Hamilton
(1994)], its mathematical formulation is not given here. To calculate the PACF in this
thesis, the Microsoft Excel statistical add-in from Numerical Algorithms Group (2007)
was used;
296 APPENDICES
In this thesis, the following steps are performed to analyse the computed de
optimisation cost:
Y Data selection', in this process, data are extracted from the OTESS database and some
basic calculations are performed (e.g., subtraction between two costs). Most o f the data
are defined for each time step of the day whereas the de-optimisation cost has a
meaning only over a day. Therefore, basic statistics for each parameter are taken, such
as the minimum, the maximum, the mean, the standard deviation and the difference
between the minimum and the maximum over the 48 first steps (the 48 following steps
A.l BASICS OF STATISTICS 297
ate ignored, as explained in section 3.3.6). In total, around 100 variables have been
defined;
C Handling missing data: the missing data are completed as explained in section 3.3.4.3;
T Calculation of basic statistics', the frequency distributions are plotted for the valid data and
basic statistics are given to evaluate the quality of the series;
T Seasonality', the seasonality of the time series is analysed with the ACF and the PACF (see
section 3.4.2);
Data smoothing (or filtering): in order to remove the noise around the main variation of
the series, a smoothing is performed with a window-moving average according to
(A. 1.13). In other words, this technique tries to remove the stationary component from
the original series. For example, Figure 4.4 represents the smoothing process with a 3-
element window. Note that the new set of data is smaller than the window since the
beginning and the end of the series cannot be smoothed. In this report, the window is
chosen according to the seasonality period;
nwdtm'—1
y
/ i *xwigm!w
I .. ,
;/'/WflW'“ l
k=/—
’ smoothed |7] —-------- y—;------ , where window is odd (A. 1.13)
window
Original series
2-element window
0
1 1
Smoothed series
>|C
Ti < >c
X
T Getting the stationary component this is done by removing the trend and seasonal
components of each series over time and any correlation correction. Seasonal patterns
can be detected by calculating the auto-correlation coefficients of the series or by
performing a Fourier Transform or a caterpillar decomposition [Garcia (2005)]. In this
298 APPENDICES
study, the trend and seasonal components are removed by simply subtracting the
smoothed series from the original one;
S Normalisation', this makes possible comparing data with different units or orders of
magnitude. The normalization used in this report is shown in (A.I.14), where x and a
are respectively the mean and the standard deviation of the series to be
normalized [Garcia (2005)].
r n x\t} —x
'd Multidimensional analysis', this report relies on a basic multidimensional analysis, for which
correlation coefficients are calculated and scatter plots are drawn. More complex
techniques such as clustering (e.g. with the help of Kohonen networks) could be
performed for further studies [Garcia (2005)]. ■
A.2 TECHNICAL DESCRIPTION OF OTESS 299
This section gives an overview of OTESS from a technical point of Hew. It is assumed here
that the reader is familiar with the optimisation process described in section 3.3. OTESS
stands for OuTilpour /’Etude des Sendees Systime (Tool for the study of ancillary sendees). This
software has been initially developed to manipulate the operating data of EDF Producer in
order to estimate its de-optimisation cost because of frequency control reserves (see
Chapter 3). However, because it is object-oriented architecture, this softaware could be
quickly adapted to any information system. Furthermore, the studies possible with OTESS
are not limited to ancillary sendees. In fact, any kind of research related to the generation
optimisation algorithm can be performed, such as assessing the impact of a new portfolio or
different market prices.
141 CSV stands for Com m a-Separated Values and XM L for Extensible M ark-up Language
300 APPENDICES
Operation 1: the operational data are stored as zipped text files on a specific server. They
are thus transferred via FTP to the main machine, where they are unzipped;
Operation 2: the datasets are modified by OTESS according to a given script. For
example, the demand for reserve can be set to zero (see section A.2.6);
S Operation 3: the modified datasets are sent via FTP to several simulation machines in
order to reduce the computation time (see section 3.3.5.1 for more details on these
machines);
S Operation 4: a KSH script launches automatically ED F’s dispatch alogorithm for the
modified datasets. Following the optimisation process, new datasets are created as
outputs;
^ Operation 5: the results are sent back via FTP to the main machine;
S Operation 6: only a part of the dispatch results are used to feed in the relational database
of OTESS (see section A.2.3 for more details on the database structure);
S Operation 7: the user makes use of the functionalities of OTESS in order to extract the
data that are useful via tailored-made scripts and a generic web-based interface (see
section A.2.5 for a few screenshots).
A.2 TECHNICAL DESCRIPTION OF OTESS 301
EDF’s
historical
Dataset Datasets
datasets
generator
Storage server
Database
feeder >■
Datasets EDF’s
] Batch [ dispatch
algorithm
S i Database
\ Simulation machines
Database
analyser
Main machine
142 F o r m ore inform ation on entity relation modelling, see for example Williams and Lane (2004).
302 APPENDICES
provides
global_dispatch 1 X fo r th e ^ s.
_statement \a iv e n
M M
1
dataset
for t h e ^ ' x .
demand
for the
timestep_dispatch for the
timestep given
statement given
supply
T able A.2.4: Structure o f the table “glob al_d isp atch _statem en t”
X'R = —- ------- ----------- 1-------------- (in €/M W /h). See section 3.4.3.1 for more
l )ri AiijHiuh ^ M dhpakb
Xi x R . + Xi x R ( ,
X'R = — - -— ^ ------------------ (in €/M W /h). See section 3.4.3.1 for more
RPn' tthpnhh + Rm' dispatch,
A.2.5 Screenshots
In order to illustrate some of the basic functionalities of OTESS mentioned in
section A.2.1, Figure A.2.5 to Figure A.2.10 display a few sreenshots from OTESS (note
that OTESS is compatible with most of web browsers).
308 APPENDICES
E 9B S -I#Ix<
; ::.m
“3 in
3*—-«g e ■ 0 Paroton-*
Q 9C IO »»ith the script ‘2. Set PRI & SEC reserves to zero’
\C urrm utB & t |: i.*-'*. i -E : it '^ j m&ry Q+m O m r t mw r o w ]
\Soim *naW *lorr TW* >cn» « » s t » darnrwil m larrnt or sacanrtary aid pntnary»aquan<yeo»*olreserves a l t MWf<y a»»e97 areas |
O tttfn tn U n o h ftn Date—t i erew tf wmh th* kct$a and wmtgng for DaUMCt m aty to JnMrtiraoffw OM Asm stnthe
toktm APOGEE (itusfmufBtWH iiti cUttawarehQus*
Ht-OtOMKMB » N ccx a a sseso NCofaawses C Nb of datasets. 893
VKOftg V'«W to VlBHVtg V l««tg
1 1 Origin toAtm » tor APOGEE 2. After APOGEE » Oatwrerehoujc
'4 » c /n a n da ta se ts t& c re a * 0 I (s*>of new d& asflts to a r o a t 0 . - ••« | 1
I V im I S »«">«
iloerl
*Tac«j
Figure A .2.5: M odification and im port o f datasets w ith O T E SS (operations 2 and 6 in sectio n A.2.2)
Datawarehouse: 2. Demand
zJ ItedBr a n Cant, ww war]
mu Mont> (d ay ’MONTH')
Power (MW) (-demand NRJ")
(day~YEAP~)
Starr (sm e step START)
OaUMtfO Kear Nontf) Day Starr P tm m lM W ) APOGEE Input P iim tty (MW) APOGEE input Secondary f»M )
r J . • *• • m •• * ' • ■* • •
• ts/xtf 20C« 06 09 11 3000000 54811 9 6710 620
• a y r Jon 2006 06 09 113000000 S2S449 671.0 620
• U / x « 2006 06 06 1 2 0 0 00000 55370* 674 675
• a / X 2061 2006 06 09 120000000 53514 15 674 675
• B -/* » 2061 2006 06 09 123000000 54978 1? 674 675
• a / x « 2006 06 06 123000000 56792* 674 675
■ H B S
Rdner Edbon Afftchoge Fevens Outfc >
^ ^ e c e a e rtr . 4 * £ Wj -
AdfiM I 4 i http f) i:7 0.0 l/OTESS/outrU.KWMwe.pho ■»] ^CK Dsn*
C o .'j k C - K - O H m lm m - j5> I t W a M I TF <*!»»«»» . » b w o y > r.
I B ia jO T E S S
O utput scripts
T hese scripts select appropriate data from the datawarehouse. transform It and then store the result into the table output_dala' T hese scripts are thus
useful to show complex relationships between data
Description:
Description:
Description:
Launch script: t - * * I
SWMCHh-ihR (OTESS
C alculation: 1 .M ean » s y x
Filter: VALID = 'V AND DATE >= '2007-01-01' AND DATE <= '2007-06-31'
Order:
Limit:
» Number o f records: 8352
equals 706.01727490425
Filter: VALID - 1 ' AND DATE > '2006-07-31' AND DATE < '2007-08-01'
Order:
Limit:
» Number of records 352
0 18-
I
0 16j
0 14.
0 12 -
r
0.4
0 08*
0 06-
0 04.
0 02 *
450
—
500
^riTftn
550 600 6 5 0 700 750 800 850 900 950 1000
P rm a ry rese rv e d em and (MW)
(Vj Prim ary rese rv e distnbution
new datasets with the demand fot reserves set to zero (note the object-oriented
programming that allows any change in the structure of the dataset text files):
<?php
/* *\
d a ta s e t/s c r ip t/r e s e r v e _ d e m a n d _ a t_ z e r o .php
/////////////
// MODULES //
/////////////
re q u ire_ o n ce 1p a r a m e t e r s . i n c ' ; / / P a ra m e te rs
re q u ire_ o n ce ' S y s t e m / F o l d e r . p h p 1; / / To m a n a g e f o ld e rs and f i l e s
re q u ire_ o n ce 'H T T P /I n p u t.p h p 1; / / To h a v e a c c e s s t o th e a rg u m en ts
re q u ire_ o n ce ’D a t a s e t / S c r i p t . p h p ' ; / / C la ss t h a t m anages s c r ip t s
re q u ire_ o n ce 'D a ta s e t/F ile _ C o n s o .p h p ' ; / / To h a v e a c c e s s t o t h e CONSO f i l e
////////////////
// PARAMETERS / /
////////////////
/ / W e g e t t h e ID o f t h e s c r i p t
$ i d _ s c r i p t = H T M L _ In p u t: : g e t l n p u t s ( "S C R IP T _ ID ", "P O S T ");
/ / We g e t t h e l i s t o f d a t a s e t s t o c o p y
$ a r r a y _ d a t a s e t s _ t o _ c o p y = H T M L _ In p u t:: d e c o d e U r l V a r ia b l e ( H T M L _ I n p u t: : g e t l n p u t s ( " d a t a s e t s ",
"P O S T "));
/ / We g e t t h e i n f o r m a t i o n o n t h e s c r i p t
$ s c r i p t = new S c r i p t ( $ i d _ s c r i p t ) ;
/ / We c r e a t e a f o l d e r o b j e c t r e l a t e d t o t h e d e s t i n a t i o n f o l d e r
$ d e s t i n a t i o n _ f o l d e r = new F o l d e r ( $ p a t h _ d e s t i n a t i o n _ f o l d e r ) ;
//////////////////////////////
// C R E A T I O N OF TH E D A T A S E T S //
//////////////////////////////
/ / We d e f i n e t h e e m p t y r e s e r v e a s a n a r r a y o f 9 7 e l e m e n t s
$ e m p t y _ r e s e r v e = a r r a y _ p a d ( a r r a y ( ) , 9 7 , " 0 . QOOOOOOOOE+OO") ;
/ / We g o t h r o u g h t h e l i s t o f d a t a s e t s t o c o p y
fo re a c h ( $ a rra y _ d a ta se ts_ to _ c o p y as $ c u rre n t_ d a ta se t ) {
/ / We c h e c k w h e t h e r t h e d a t a s e t t o c o p y i s v a l i d a n d w h e t h e r th e ta rg e t d ataset does
n o t alread y e x is t
if ( i s _ d i r ( $ p a t h _ i n i t i a l _ f o l d e r . $ c u r r e n t _ d a t a s e t ) && !
is _ d ir($ p a th _ d e s tin a tio n _ fo ld e r . $ cu rren t_ d ata se t) } {
/ / We c o p y t h e d a t a s e t
$ d e s tin a tio n _ f o ld e r - > c o p y F o ld e r ($ p a t h _ i n i t i a l _ f o l d e r . $ c u rre n t_ d a ta se t ,
$ p ath _ d e stin a tio n _ fo ld e r . $ c u rre n t_ d a ta se t);
/ / We s e t t h e d e m a n d a t 0 i n t h e CONSO f i l e
$ f i l e _ c o n s o = new F i l e _ C o n s o ( $ p a t h _ d e s t i n a t i o n _ f o l d e r . $ c u rre n t_ d a ta se t .
" /C O N S O " ," e d it" );
$ file _ c o n s o -> se tS e c o n d a ry D e m a n d ($ e m p ty _ re s e rv e );
$ file _ _ c o n s o -> se tP rim a ry D e m a n d ($ e m p ty _ re s e rv e );
/ / W e f re e th e m em ory
/ / N o te : t h i s step is p a rtic u la rly im p o rtan t when th e re are hundreds of d a ta se ts
to m anage
312 APPENDICES
unset ($ file _ c o n so );
///////////////////
// RETURN HEADER / /
1111111111111111111
/ / W e r e t u r n to th e pag e t h a t h e lp s to m anage d a t a s e ts
h e a d e r ( " L o c a t i o n : " . 0TESS_L0CAT10N_R00T . " d a t a s e t / m a n a g e . p h p " ) ;
exit ;
?>
To give an idea, the APOGEE text file that defines the demand for reserves and
power for a given dataset looks as the following:
•C O N SO ' ' 2 8 / 0 3 / 2 0 0 7 * '1 3 : 1 6 '
• 2 9 /0 3 /2 0 0 7 ’
• CONSOMMATION•
6 . 10609000E+04
5 .7 9 0 4 3 0 0 0 E + 0 4 5 .66327000E+04 5 . 68756000E+04 5 . 67770000E+04 5 . 6 1 2 0 1 000E+04 5 .4 8171000E + 04
5 .4 7 6 7 3 0 0 0 E + 0 4 5 .37623000E+04 5 . 55873000E+04 5 .57700000E+04 5 . 5 7 5 4 8 000E+04 5 . 6 8 7 3 3 OOOE+04
S . 8 6 1 9 6 0 0 0 E + 04 6 . 11816000E+04 6 .52323000E+04 6 .59297000E+04 6 .6 7 4 8 4 000E+04 . 72475000E+04
6 . 814S4000E+04 6 . 81704000E+04 6 . 89083000E+04 6 . 87611000E+04 6 . 9 3 7 5 6 0 0 0 E + 04 .9 4 6 2 6 0 0 0 E + 0 4
6 .78709000E+04 6 . 90679000E+04 6 .77728000E+04 6 .74430000E+04 6 .66728000E+04 . 54041000E+04
6 .4 6 8 1 3 0 0 0 E + 0 4 6 .3 9915000E+04 6 .36389000E+04 6 .32568000E+04 6 . 2 8 6 4 5 0 0 0 E + 04 .2 9 8 5 7 000E+04
6 .32740000E+04 6 .44215000E+04 6 . 51604000E+04 6 .50362000E+04 6 .6 2 5 1 3 000E +04 ■70456000E +04
6 .5 0 1 8 1 0 0 0 E + 0 4 6 .3 7 3 4 1000E+04 6 . 32413000E+04 6 .46282000E+04 6 .2 6 9 3 1 000E +04 . 17510000E+04
5 .8 9 2 6 2 0 0 0 E + 04 5 . 73462000E+04 5 . 79264000E+04 5 .77593000E+04 5 .6 5 2 8 5 0 0 0E+04 5 .5 1 4 3 6 0 0 0 E + 0 4
5 .4 7 1 4 5 0 0 0 E + 0 4 5 . 37294000E+04 5 . 45065000E+04 5 .46943000E+04 5 .6 0 0 8 3 000E+04 5 . 69993000E+04
5 . 9 9 4 1 5 0 0 0 E + 04 6 .26598000E+04 6 .5 4 907000E+04 6 .6 5 4 09000E+04 6 .6 7 3 8 1 0 0 0 E + 0 4 6 . 7 6 1 5 0 000E+04
6 .8 4 9 7 2 000E + 04 6 . 87932000E+04 6 . 95726000E+04 6 .93596000E+04 6 .9 8 3 9 1 0 0 0 E + 0 4 6 . 9 7 8 4 1 000E+04
6 .8 0 6 5 7 0 0 0 E + 04 6 . 90857000E+04 6 . 80906000E+04 6 . 7 5 9 5 3 OOOE+04 6 .6 2 6 3 8 000E+04 6 . 4 7 1 8 4 000E+04
6 .3 6 2 8 5 0 0 0 E + 04 6 .27277000E+04 6 .21265000E+04 6 .14530000E+04 6 . 08399000E+04 6 . 0 9 2 2 4 000E+04
6 . 1 3 7 0 1 0 0 0 E + 04 6 .2 6 4 96000E+04 6 . 31714000E+04 6 .28654000E+04 6 .5 5 0 3 0 0 0 0E+04 6 . 61970000E+04
6 . 4 4 2 7 3 0 0 0 E + 04 6 . 30994000E+04 6 .28869000E+04 6 .46170000E+04 6 .23045000E+04 6 .1 3 9 1 7 000E + 04
' P R IM A IR E '
5 .5 3 2 5 6 2 3 5 E + 0 2
5 .55831191E*02 5 . 65831191E+02 5 . 66911208E+02 5 . 66911208E+02 5 .6 6 9 1 1 2 0 8E+02 5 . 6 5 8 3 1 1 9 1 E + 02
5 .6 6 4 3 1 1 9 1 E + 0 2 5 .71131191E+02 5 .70051235E+02 5 . 69451235E+02 5 .7 0 5 3 1 1 9 1E+02 5 . 6 2 5 3 1 1 9 1 E + 02
5 .5 1 5 5 6 6 9 1 E + 0 2 5 . 50521708E+02 5 . S3721708E+02 5 .49621708E+02 5 .4 7 1 8 6 2 3 6E+02 5 .4 3 4 3 6 2 3 6 E + 0 2
5 .4 4 5 1 6 2 5 3 E + 0 2 5 .45116253E+02 5 .4 4 1 16253E+02 5 .44116253E+02 5 .4 4 616253E + 02 5 .4 4 6 1 6 2 5 3 E + 0 2
5 .4 9 1 8 1 2 5 4 E + 0 2 5 .49181254E+02 5 . 51001267E+02 5 .51471281E+02 5 .56166267E+02 5 . 5 7 9 4 6 2 5 4 E + 02
5 . 58996254E+02 5 .57916237E+02 5 . 54756691E+02 5 .55081691E+02 5 . 54 0 01735E + 02 5 . 53 3 0 1 7 3 5E +02
5 .4 8 3 0 1 7 3 5 E + 0 2 5 .4 7 7 0 6 6 9 1 E + 0 2 5 .46626734E+02 5 .46076735E+02 5 .4 1 0 5 6 691E +02 5 .4 1 0 5 6 6 9 1 E + 0 2
5 .4 7 8 7 6 7 3 5 E * 0 2 5 .4 7876735E+02 5 .48956691E+02 5 .4 9256691E+02 5 .5 1 1 3 6 7 0 8 E + 0 2 5 .5 2 7 8 6 7 0 8 E + 0 2
5 . 83 9 1 1 2 0 8 E + 02 5 . 93911208E+02 5 . 93911208E+02 5 . 93911208E+02 5 .9 7 9 1 1 2 0 8 E + 0 2 5 . 9 7 9 1 1 2 0 8 E + 02
5 . 95911208E+02 5 . 96611208E+02 5 . 92611208E+02 5 . 92611208E+02 5 . 90611208E+02 5 . 9 0 6 1 1 2 0 8 E + 02
5 . 8 0 6 2 1 7 0 8 E + 02 5 .78746708E+02 5 .69661708E+02 5 .69111708E+02 5 . 7343 6253E+02 5 . 7 3 4 3 6 2 5 3 E + 02
5 .6 8 8 6 6 2 5 3 E + 0 2 5 .68866253E+02 5 .67866253E+02 5 . 67866253E+02 5 .6 7 4 6 6 2 5 3 E + 0 2 5. 746625
6 3E+ 02
5 . 7 1 3 4 6 2 5 4 E +02 5 .71346254E+02 5 . 71346254E+02 5 . 76826254E+02 5 . 77376254E+02 5 . 81196254E+02
5 . 8 1 9 9 6 2 5 4 E +02 5 .81996254E+02 5 . 80536708E+02 5 . 80951708E+02 5 .8 1 3 3 6 7 0 8E+02 5 . 8 0 6 3 6 7 0 8 E + 02
5 .7 9 2 5 1 7 0 8 E + 0 2 5 .77761708E+02 5 . 77761708E+02 5 .77761708E+02 5 . 6 8451708E +02 5 . 6B 451708E +02
5 .7 4 4 2 1 7 0 8 E + 0 2 5 . 78136708E+02 5 . 78136708E+02 5 .78136708E+02 5 .7 8 1 3 6 7 0 8 E + 0 2 5 . 7 9 4 0 1 7 0 8 E + 02
' TELEREG LA G E'
8 . 38000000E+02
6 .2 2 0 0 0 0 0 0E»02 6 . 62000000E+02 6 . 62000000E+02 6 .62000000E+02 6 . 62000000E+02 6 . 62000000E+02
6 . 62000000E+02 6 . 62000000E+02 6 . 62000000E+02 6 . 62000000E+02 6 .6 2 0 0 0 0 0 0E+02 6 .6 2 0 0 0 0 0 0 E + 0 2
6 . 6 2 0 0 0 0 0 0E<-02 7 . 16000000E+02 7 . 70000000E+02 7 .68919983E+02 7 .6 8 9 1 9 9 8 3 E + 0 2 7 . 6 8 9 1 9 9 8 3 E + 02
7 . 68919983E+02 7 . 68919983E+02 7 . 68919983E+02 7 .68919983E+02 7 . 68 9 19983E + 02 7 . 6 8 9 1 9 9 8 3 E + 02
7 .6 8 9 1 9 9 8 3 E + 0 2 7 . 68919983E+02 7 . 14919983E+02 7 .14919983E+02 7 . 14 9 1 9 9 8 3 E + 0 2 7 . 1 6 0 0 0 0 0 0 E + 02
7 .1 6 0 0 0 0 0 0 E + 0 2 7 . 16000000E+02 7 . 16000000E+02 7 .16000000E+02 7 .1 6 0 0 0 0 0 0E+02 7 . 1 6 0 0 0 0 0 0 E + 02
7 .1 6 0 0 0 0 0 0 E + 0 2 7 . 16000000E+02 7 . 16000000E+02 8 . 78000000E+02 8 .78000000E+02 8 .7 8 0 0 0 0 0 0 E + 0 2
7 .1 6 0 0 0 0 0 0E+02 7 . 16000000E+02 7 . 16000000E+02 7 .16000000E+02 7 .1 6 0 0 0 0 0 0E+02 7 . 1 6 0 0 0 0 0 0 E + 02
6 .2 2 0 0 0 0 0 0E+02 6 . 62000000E+02 6 . 62000000E+02 6 . 62000000E+02 6 .6 2 0 0 0 0 0 0E+02 6 .6 2 0 0 0 0 0 0 E + 0 2
6 .6 2 0 0 0 0 0 0E + 02 6 . 62000000E+02 6 . 22000000E+02 6 . 22000000E+02 6 .6 2 0 0 0 0 0 0 E + 0 2 62000000E+02
7 . 7 0 0 0 0 0 0 0E + 02 7 . 70000000E+02 7 .70000000E+02 7 .70000000E+02 7 .7 0 0 0 0 0 0 0E+02 70000000E+02
7 .7 0 0 0 0 0 0 0E + 02 7 . 70000000E+02 7 . 70000000E+02 7 .70000000E+02 7 . 70000000E+02 70000000E+02
7 .7 0 0 0 0 0 0 0 E * 02 7 . 70000000E+02 7 .70000000E+02 7 .70000000E+02 7 .7 0 0 0 0 0 0 0E+02 70000000E+02
7 .70000000E+02 7 . 70000000E+02 7 . 70000000E+02 7 .70000000E+02 7 . 70000000E+02 70000000E+02
7 .7 0 0 0 0 0 0 0 E + 02 7 . 70000000E+02 7 . 70000000E+02 7 .70000000E+02 7 . 70000000E+02 70000000E+02
7 . 70000000E+02 7 .70000000E+02 7 . 70000000E+02 7 .70000000E+02 7 . 70000000E+02 7 0 0 0 0 0 0 0E+02
Lasdy, to show how data from the database can be easily change, the following code
was used to calculate the percentage of time when the marginal cost of energy was higher
than the marginal costs of reserves (see section 3.5.1):
<?php
m i ntm m
/ 1 MODULES 1 1
nm u nun
req u ire_ o n ce 'p a r a m e te r s .in c '; / / P a ra m e te rs
req u ire_ o n ce 1D a t a b a s e / D a t a b a s e _ O t e s s . p h p 1 ; / / To a c c e s s t o th e O tess d a ta b a se
req u ire_ o n ce /o u tp u t_ s c rip t/O u tp u tD a ta .p h p '; // To s a v e t h e o u t p u t
////////////////
// PARAMETERS //
////////////////
/ / We g e t co n n e cted to th e d a ta b a s e
$ d atab ase = n e w D a t a b a s e _ O t e s s ( ) ,-
/ / We d e f i n e t h e t a b l e s t o s e l e c t
$ a rra y _ ta b le s_ to _ se le c t =
A rray ("d a y ", " tim e s te p _ d is p a tc h _ s ta te m e n t" , "tim e ste p ", " d a ta s e t" ) ,-
/ / W e d e fin e th e f ie ld s to s e le c t
$ a rra y _ fie ld s_ to _ se le c t = a rra y (
A r r a y ( " T a b l e " => " d a y " , " F i e l d " => "D ATE") ,
A r r a y ( " T a b l e " => " t i m e s t e p 1i , " F i e l d " = > " S T A R T " ') ,
A r r a y ( " T a b l e " => " t i m e s t e p d i s p a t c h s t a t e m e n t " , " F i e l d " => " N R J MC" ) ,
A r r a y ( " T a b l e " => " t i m e s t e p d i s p a t c h s t a t e m e n t " , " F i e l d " => " SEC" MC" ) ,
A r r a y ( " T a b l e " => " t i m e s t e p _ _ d i s p a t c h _ s t a t e m e n t " , " F i e l d " => " P R I " "MC" )
);
/ / We s e l e c t t h e d a t a o n t h e m a r g i n a l c o s t s
$ arra y _ a rra y _ m a rg in a l_ c o sts = $d atab ase-
> s e l e c t E l e m e n t s ( $ a r r a y _ t a b l e s _ t o _ s e l e c t , $ a r r a y _ f i e l d s _ t o _ s e l e c t , " ' S C R I P T _ I D ' = ’ 1 1 AND
' t i m e s t e p ' . ' S T A R T ' < 12 4 : 0 0 : 0 0 : 0 0 0 ’ " ) ;
/ / I n i t i a l i s a t i o n of th e co u n ters
$ a r r a y _ t o t a l = a r r a y ()?
$ a rra y _ n rj_ h ig h e s t = a r r a y ();
/ / We g o t h r o u g h a l l t h e d a t a ( i . e . , 4 8 x 8 7 9 d a y s )
fo re a c h ( $ a rra y _ a rra y _ jn a rg in a l_ c o sts as $ array _ m a rg in a l_ c o sts ) {
/ / I n i t i a l i s a t i o n of th e a rra y s
if ( e m p ty ($ a rra y _ n rj_ _ h ig h e st[$ a rra y _ m a rg in a l_ c o sts["S T A R T "]]) ) {
$ a r r a y _ n r j _ h i g h e s t [ $ a r r a y _ m a r g i n a l _ c o s t s [ "STA R T"]] = 0 ;
/ / A c tu a lis a tio n of th e d a ta
$ a r r a y _ t o t a l [ $ a r r a y _ m a r g i n a l _ c o s t s [ " S T A R T " ] ] ++;
if ( $ a r r a y _ m a r g i n a l _ c o s t s [ " N R J _ M C " ] > $ a r r a y _ m a r g i n a l _ c o s t s [ " P R I M C"] &&
$ array _ m arg in a l_ _ co sts["N R J_ M C "] > $ a rra y _ m a rg in a l_ c o sts[" S E C _ M C " ] ) J
$ a r r a y _ n r j _ h i g h e s t [ $ a r r a y _ m a r g i n a l _ c o s t s [ "START"] ] ++;
/ / We c r e a t e t h e a r r a y w i t h t h e r e s u l t
$ a r r a y _ d a t a _ t o _ i n s e r t = a r r a y (),■
$ t i m e s t e p = 1 ,-
fo re a c h ( a rray _ k e y s($ a rray _ n rj_ h ig h e st) as $ s ta r t ) {
a r r a y _ p u s h ( $ a r r a y _ d a t a _ t o _ i n s e r t , A r r a y { "X "= > $ tim e ste p ,
"Y "= > 1 0 0 * $ a rra y _ n rj_ h ig h e st[$ sta rt]/$ a rra y _ to ta l[$ sta rt] ) );
$ tim e s te p ++;
}
/ / We i m p o r t t h e d a t a i n t o t h e d a t a b a s e
$ o u tp u t _ d a ta = new O u tp u tD a t a {);
/ / N o te : we d e l e t e t h e p r e v i o u s r e s u l t s
314 APPENDICES
////////////
// RETURN 1 1
illin iu m
315
316 INDEX
Bilateral, 50, 52, 92,188, 191, 193,194, 213,214,219, 226, 244, 245
Duration, 203, 219 200, 201, 203, 209, 219, 227, 238
Controller, 58, 92, 93, 104, 105, 106, 107, Utilisation, 147,149,184, 200, 224, 225
108,109,110,111,116
Variable, 146, 149, 151, 154, 159, 184,
Distributed generation, 47, 114, 126, 136, 218, 222, 226, 234, 236
229
Secondaiy, 92, 94, 97, 101, 102, 107,
108, 109, 110, 120, 122, 123, 124,
125, 133, 134, 137, 138, 140, 144,
Economic efficiency, 230, 232, 233, 235, 153, 157, 177, 192, 193, 196, 198,
237, 240, 247 200, 201, 202, 212, 215, 216, 217,
218, 221, 222, 224, 230, 234, 236,
EENS See Expected Energy N ot Served
248
Elasticity, 127, 141, 185, 189, 192, 211,
Supplemental regulation service, 138
220, 237, 243, 247, 248
FACTS, 80,116
318 INDEX
55, 56, 58, 59, 60, 63, 64, 68, 70, 71, 72,
Kolmogorov test, 125
77, 78, 79, 80, 81, 92, 93, 94, 95, 98, 99,
101, 103, 105, 111, 116, 120, 122, 138, — L—
139, 147, 148, 173, 187, 190, 198, 215,
218, 225, 230, 241, 248 Lagrange multiplier, 158
Reserve, 133,134,135
Spot, 49, 52, 147, 150, 188, 193, 194,
Insecurity See Security 195, 196, 200, 208, 219, 230, 233,
238
INDEX 319
Over-the-counter, 50, 51, 52, 54,194 Prime mover, 55, 58, 69,114
— P— Problem
Pareto efficiency, 51, 88, 128, 129, 205, Primal, 157, 209
206, 207, 208, 239, 246
Product substitution, 117, 128, 210, 211
Payment
Profit, 147,199, 223
Structure of, 197
Property rights, 187, 213, 215, 239
Pool See Market, Centralised
Public good, 43, 84, 87, 127, 128, 129,
Price 130,141, 222, 223, 243
320 INDEX
— Q— —T—
Quality Tax
Power, 84, 86, 87, 118, 129, 140, 242, Tendering process, 105, 191, 194, 195,
248 196, 206, 208, 228
Quasi-steady state, 57, 58, 59, 61, 77, 103, Transformer, 47, 71, 72, 79, 86, 145, 146,
114 148
Risk, 50, 52, 86, 92, 127, 146, 149, 191, Marginal, 214, 215
193,194,195,219, 225, 238
O f lost load, 85, 221, 222
RSI See Index, Residual supply
VOLL See Value, O f lost load
— s —
Voltage control
Security, 242
Basic, 196, 201, 215, 216, 217, 218,
Cost of, 86,128,132 222, 234
Level of, 85, 86,119 Enhanced, 196, 200, 201, 215, 216,
217, 218, 222
Smart grid, 92
Primary, 71, 98, 111
Stability, 91, 92, 93, 97, 111, 114, 249
Secondary, 98
Stationarity, 141
Tertiary, 98
Substitution
Voting, 127
Rate of, 128
INDEX 321