Boq Bny Jeans
Boq Bny Jeans
Boq Bny Jeans
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
Project: BNY Hipshop 1.15
Location: SM Sangandaan, Caloocan City
Package:
Duration: 6 months
Materials Labor
Item Description Unit Qty Unit Rate Total Amount
Unit Cost Total Unit Cost Total
1.0 Division 1 - Preliminaries 326,600.00 5,175.00 331,775.00
TILING WORKS
Materials Labor
Item Description Unit Qty Unit Rate Total Amount
Unit Cost Total Unit Cost Total
Royal Blue Paint Finish; CF-02 m2 15.00 1,066.50 15,997.48 533.25 7,998.74 1,599.75 23,996.22
Faux Concrete Finish; CF-03 m2 36.00 722.20 25,999.20 361.10 12,999.60 1,083.30 38,998.80
Glossy White Paint Finish; CF-04 m2 39.00 1,066.50 41,593.44 533.25 20,796.72 1,599.75 62,390.16
- - - - - -
PAINTING AND COATING - - - - -
- - - - -
Skim coating - - - -
Wall m2 262.11 102.47 26,858.62 149.70 39,236.94 252.17 66,095.56
-
Paint Finish
WF01 m2 64.50 542.65 35,000.78 498.99 32,184.74 1,041.64 67,185.52
WF02 m3 46.15 529.81 24,450.50 498.99 23,028.31 1,028.79 47,478.81
WF03 m2 20.85 645.12 13,450.72 199.60 4,161.56 844.71 17,612.28
WF04 m2 130.61 645.12 84,258.94 199.60 26,069.14 844.71 110,328.08
-
SUNDRIES -
-
Painting due to exposed pipes lm 30.00 194.69 5,840.84 149.70 4,490.89 344.39 10,331.73
Consumables lot 1.00 11,500.00 11,500.00 5,175.00 5,175.00 16,675.00 16,675.00
BNY Signage set 1.00 5,750.00 5,750.00 2,587.50 2,587.50 8,337.50 8,337.50
- - - - - -
Supply and installation of refrigerant copper pipe item 1.00 34,500.00 34,500.00 17,250.00 17,250.00 51,750.00 51,750.00
type L hard drawn, including supports and other
miscellaneous items as required to complete the
system.
Supply and installation of refrigerant pipe sleeve no 22.00 85.39 1,878.63 42.70 939.32 128.09 2,817.95
including supports and other miscellaneous
items as required to complete the system
Supply and installation of HVAC equipment including set 1.00 51,750.00 51,750.00 25,875.00 25,875.00 77,625.00 77,625.00
supports, applicable vibration isolators, markings,
paintings, applicable controller, electrical works and
other miscellaneous items as required to complete
Project: BNY Hipshop 1.15
Location: SM Sangandaan, Caloocan City
Package:
Duration: 6 months
Materials Labor
Item Description Unit Qty Unit Rate Total Amount
Unit Cost Total Unit Cost Total
the system.
HVAC Fans
RH-1, Range Hood set 14.00 3,707.60 51,906.40 1,853.80 25,953.20 5,561.40 77,859.60
air flow capacity: 140 lps, 0.25 kW
230V/1P/60Hz (Kitchen)
SUNDRIES
- -
Hangers & Supports lot 1.00 15,459.47 15,459.47 7,729.74 7,729.74 23,189.21 23,189.21
Consumables lot 1.00 14,799.56 14,799.56 7,399.78 7,399.78 22,199.34 22,199.34
Materials Labor
Item Description Unit Qty Unit Rate Total Amount
Unit Cost Total Unit Cost Total
THHN, 5.5mm sq. m 30.00 41.40 1,241.95 18.63 558.88 60.03 1,800.82
- -
Power - -
- -
THHN, 5.5mm sq. m 100.00 41.40 4,139.82 18.63 1,862.92 60.03 6,002.74
- -
THHN, 3.5mm sq. (G) m 50.00 27.05 1,352.61 12.17 608.68 39.23 1,961.29
- -
Lighting - -
THHN, 3.5mm dia. m 300.00 27.05 8,115.69 12.17 3,652.06 39.23 11,767.75
THHN, 3.5mm dia. (G) m 150.00 27.05 4,057.84 12.17 1,826.03 39.23 5,883.87
- -
16130 Raceways and boxes - -
- -
Supply and install raceways and boxes as shown on - -
accessories as shown on drawings and in accordance with - -
the specifications provided by the designer. - -
- -
Power and Lighting - -
IMC, 20mm dia. m 10.00 171.70 1,717.00 77.26 772.65 248.96 2,489.64
IMC, 15mm dia. m 69.00 117.41 8,101.60 52.84 3,645.72 170.25 11,747.32
Consumables lot 1.00 11,287.25 11,287.25 5,079.26 5,079.26 16,366.51 16,366.51
- -
Wiring devices - -
- -
Supply and install of wiring devices as shown on - -
drawings and in accordance with the specifications - -
provided by the designer. - -
- -
Switches - -
1 gang switch nr 2.00 280.77 561.54 126.35 252.69 407.12 814.23
2 gang switch nr 1.00 449.85 449.85 202.43 202.43 652.28 652.28
- -
Receptacle - -
Duplex Convenience Outlet, grounding type nr 12.00 549.24 6,590.92 247.16 2,965.91 796.40 9,556.84
- -
Enclosed switches and breakers - -
- -
Supply and install of electrical utility system as shown on - -
and in accordance with the specifications provided by the - -
designer. - -
- -
MCB, 40AT, 1P, 230V, Nema-3R nr 1.00 43,283.66 43,283.66 19,477.65 19,477.65 62,761.31 62,761.31
- -
ECB 20AT, 2P, 220V for ACCU, Nema 3R nr 8.00 4,908.76 39,270.09 2,208.94 17,671.54 7,117.70 56,941.63
- -
Project: BNY Hipshop 1.15
Location: SM Sangandaan, Caloocan City
Package:
Duration: 6 months
Materials Labor
Item Description Unit Qty Unit Rate Total Amount
Unit Cost Total Unit Cost Total
ighting luminaires - -
- -
Supply and install of lighting luminaires including all - -
necessary accessories as shown on drawings and in accordance - -
with the specifications to make the system operational. - -
- -
Pinlight nr 9.00 1,535.23 13,817.09 690.85 6,217.69 2,226.09 20,034.78
Striplight ( Warm White) nr 8.00 2,021.75 16,173.99 909.79 7,278.30 2,931.54 23,452.29
Double Head Recessed Downlight nr 52.00 598.00 31,096.00 269.10 13,993.20 867.10 45,089.20
Tracklights nr 41.00 1,536.04 62,977.53 691.22 28,339.89 2,227.25 91,317.41
- - - - -
Fire Detection Alarm System (Roughing- Ins Only) - - - - -
- - - - -
Raceways and Boxes - - - - -
Supply and Install of Raceways and conductors including - - - - -
all necessary accessories and fittings as shown in drawings - - - - -
and in accordance in the specifications provided by the designer - - - - -
- - - - -
IMC Pipe, 20mm dia m 30.00 117.41 3,522.43 52.84 1,585.10 170.25 5,107.53
G.I., Entrance Cap 20mm dia. nr 320.22 - 144.10 - 464.32 -
IMC Coupling, 20mm dia. nr 20.00 11.80 236.05 5.31 106.22 17.11 342.27
IMC Locknut, 20mm dia. nr 20.00 8.87 177.49 3.99 79.87 12.87 257.37
IMC Bushing, 20mm dia. nr 20.00 6.04 120.77 2.72 54.35 8.76 175.12
Octago Junction Box w/ Cover, 4x4 nr 5.00 50.32 251.60 22.64 113.22 72.96 364.82
Square Box w/ cover 4x4 nr 7.00 68.62 480.33 30.88 216.15 99.50 696.48
Project: BNY Hipshop 1.15
Location: SM Sangandaan, Caloocan City
Package:
Duration: 6 months
Materials Labor
Item Description Unit Qty Unit Rate Total Amount
Unit Cost Total Unit Cost Total
Utility Box w/ cover 2x4 nr 7.00 86.00 602.02 38.70 270.91 124.70 872.92
Painting for Exposed pipe lot 1.00 5,750.00 5,750.00 2,587.50 2,587.50 8,337.50 8,337.50
- - - - -
Miscellaneous lot 1.00 3,202.21 3,202.21 1,441.00 1,441.00 4,643.21 4,643.21
Hanger and Support lot 1.00 12,900.34 12,900.34 5,805.15 5,805.15 18,705.49 18,705.49
- - - - -
SUNDRIES - - - - -
- - - - -
Fire Detection Alarm System - - - - -
Fire Alarm Control Panel - 4 zone set 1.00 39,915.45 39,915.45 17,961.95 17,961.95 57,877.40 57,877.40
Smoke detector set 7.00 3,645.50 25,518.50 1,640.48 11,483.32 5,285.97 37,001.83
Fire Alarm Manual Puch Button with Motorized Alarm Bell set 1.00 4,646.85 4,646.85 2,091.08 2,091.08 6,737.93 6,737.93
Annunciator set 1.00 30,679.76 30,679.76 13,805.89 13,805.89 44,485.65 44,485.65
- - - - -
Lighting Fixtures - - - - -
Emergency Light set 3.00 1,537.06 4,611.19 691.68 2,075.03 2,228.74 6,686.22
- - - - -
Miscellaneous lot 1.00 20,480.46 20,480.46 9,216.21 9,216.21 29,696.67 29,696.67
Hanger and Support lot 1.00 24,140.13 24,140.13 10,863.06 10,863.06 35,003.19 35,003.19
- - - - - -
7.0 Division 7 - CCTV lot 1.00 92,626.56 41,681.95 134,308.51
- - - - - -
Dome type Camera pcs 5.00 8,625.00 43,125.00 3,881.25 19,406.25 12,506.25 62,531.25
16 Channel NVR set 1.00 13,800.00 13,800.00 6,210.00 6,210.00 20,010.00 20,010.00
- - - - - -
Wires and Cable - - - - - -
UTP Cable Cat5e box 1.00 7,072.50 7,072.50 3,182.62 3,182.62 10,255.12 10,255.12
- - - - - -
CONDUITS AND FITTINGS (PVC) - - - - - -
20mmØ lght 192.00 40.58 7,791.06 18.26 3,505.98 58.84 11,297.04
20mmØ Adapter w/ Locknut pair 32.00 40.25 1,288.00 18.11 579.60 58.36 1,867.60
Hangers, Supports & Consumables lot 1.00 13,800.00 13,800.00 6,210.00 6,210.00 20,010.00 20,010.00
Consumables lot 1.00 ### 5,750.00 5,750.00 2,587.50 2,587.50 8,337.50 8,337.50
Project: BNY Hipshop 1.15
Location: SM Sangandaan, Caloocan City
Package:
Duration: 6 months
Materials Labor
Item Description Unit Qty Unit Rate Total Amount
Unit Cost Total Unit Cost Total
BRANCHLINE, DROPPINGS - - - - -
B.I. Pipe Sch.40 "SUPERIOR" - - - - -
50mmØ x 6m pc/s 1.00 3,667.63 3,667.63 1,650.43 1,650.43 5,318.06 5,318.06
40mmØ x 6m pc/s 2.00 2,911.25 5,822.50 1,310.06 2,620.12 4,221.31 8,442.62
32mmØ x 6m pc/s 3.00 2,438.67 7,316.00 1,097.40 3,292.20 3,536.07 10,608.20
25mmØ x 6m pc/s 5.00 1,956.15 9,780.75 880.27 4,401.34 2,836.42 14,182.09
B.I. Tee/Reducer "MECH" - - - - - -
40mm x 32mm (threaded) pc/s 1.00 241.50 241.50 108.67 108.67 350.17 350.17
32mm x 25mm (threaded) pc/s 4.00 170.20 680.80 76.59 306.36 246.79 987.16
25mm x 25mm (threaded) pc/s 4.00 59.80 239.20 26.91 107.64 86.71 346.84
25mm x 13mm (threaded) - - - - - -
25mm x 90° (threaded) pc/s 4.00 64.40 257.60 28.98 115.92 93.38 373.52
50mm x 40mm (threaded) pc/s 2.00 211.60 423.20 95.22 190.44 306.82 613.64
50mm x 25mm (threaded) pc/s 2.00 155.25 310.50 69.86 139.73 225.11 450.23
40mm x 32mm (threaded) pc/s 3.00 148.35 445.05 66.76 200.27 215.11 645.32
40mm x 25mm (threaded) pc/s 2.00 128.80 257.60 57.96 115.92 186.76 373.52
32mm x 25mm (threaded) pc/s 2.00 125.35 250.70 56.41 112.82 181.76 363.52
B.I. Cap - - - - - -
Sprinkler Heads, Pendent "GLOBE" pc/s 31.00 690.00 21,390.00 310.50 9,625.50 1,000.50 31,015.50
Escutcheon Plate pc/s 31.00 - - - - - -
Consumables lot 1.00 17,250.00 17,250.00 7,762.50 7,762.50 25,012.50 25,012.50
RISER STANDPIPE
SUPPLY & INSTALLATION OF WET STAND PIPE,DRY STAND PIPE
INCL. DRAIN LINE STACK AND INSPECTOR DRAIN LINE
B.I. Pipe Sch.40 - - - - - -
50mmØ x 6m pc/s 2.00 3,667.63 7,335.25 1,650.43 3,300.86 5,318.06 10,636.12
40mmØ x 6m pc/s 1.00 2,911.25 2,911.25 1,310.06 1,310.06 4,221.31 4,221.31
32mmØ x 6m pc/s 1.00 2,438.67 2,438.67 1,097.40 1,097.40 3,536.07 3,536.07
25mmØ x 6m pc/s 1.00 1,956.15 1,956.15 880.27 880.27 2,836.42 2,836.42
B.I. Elbow/Reducer x 90°
50mm x 90° (threaded) pc/s 3.00 284.05 852.15 127.82 383.47 411.87 1,235.62
40mm x 90° (threaded) pc/s 2.00 64.40 128.80 28.98 57.96 93.38 186.76
32mm x 90° (threaded) pc/s 1.00 56.35 56.35 25.36 25.36 81.71 81.71
25mm x 90° (threaded) pc/s 1.00 50.60 50.60 22.77 22.77 73.37 73.37
Union Patente
25mmØ pc/s 7.00 57.50 402.50 25.87 181.12 83.37 583.62
B.I. Threadolet pc/s - - - - - -
25mmØ pc/s 7.00 97.75 684.25 43.99 307.91 141.74 992.16
Consumables pc/s 1.00 17,250.00 17,250.00 7,762.50 7,762.50 25,012.50 25,012.50
Materials Labor
Item Description Unit Qty Unit Rate Total Amount
Unit Cost Total Unit Cost Total
Butterfly Valve w/ built in supervisory switch,UL/FM "FIREKING" 300 psi
100mmØ - - - - - -
75mmØ pc/s 4.00 24,150.00 96,600.00 10,867.50 43,470.00 35,017.50 140,070.00
65mmØ - - - - - -
Fire Hose Cabinet (FHC) surfaced type,Incl. Accessories pc/s 4.00 27,600.00 110,400.00 12,420.00 49,680.00 40,020.00 160,080.00
Waterflow Switch, 75mmØ "SYSTEM SENSOR" pc/s 4.00 8,280.00 33,120.00 3,726.00 14,904.00 12,006.00 48,024.00
Supervisory Switch, "SYSTEM SENSOR"
Grip Anchor 10mmØ pc/s 207.00 24.15 4,999.05 10.87 2,249.57 35.02 7,248.62
Clevis Hanger,25mmØ pc/s 7.00 316.25 2,213.75 142.31 996.19 458.56 3,209.94
Clevis Hanger,32mmØ pc/s 4.00 457.70 1,830.80 205.97 823.86 663.67 2,654.66
Clevis Hanger,40mmØ pc/s 4.00 517.50 2,070.00 232.88 931.50 750.38 3,001.50
Materials Labor
Item Description Unit Qty Unit Rate Total Amount
Unit Cost Total Unit Cost Total
TOTAL AMOUNT (NET OF VAT) 1,948,013.01 798,027.53 2,746,040.54