CO2 Sensor Testing Method Statement

This three-sentence summary provides the key details about commissioning CO2 sensors: The document presents a method statement for commissioning CO2 sensors to verify their wiring and operation through on-site testing procedures. It outlines recommended general checks of the sensor installation and components. Detailed procedures are provided to test the sensor's operation in both manual and automatic modes, including adjusting CO2 levels and simulating a fault to confirm the sensor's performance and alarm functions.

Uploaded by

Regina
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
63 views3 pages

CO2 Sensor Testing Method Statement

This three-sentence summary provides the key details about commissioning CO2 sensors: The document presents a method statement for commissioning CO2 sensors to verify their wiring and operation through on-site testing procedures. It outlines recommended general checks of the sensor installation and components. Detailed procedures are provided to test the sensor's operation in both manual and automatic modes, including adjusting CO2 levels and simulating a fault to confirm the sensor's performance and alarm functions.

Uploaded by

Regina
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Commissioning Methodologies (CM) – MUBS-08

CO2 Sensor Testing Method Statement

Client: Project Name: Project No:

Area: Drawing No’s: Date: Sheet: 1 of 3

Check Conducted By: Signature: Check Approved By: Signature:

INTRODUCTION

CO2 Sensor
The on-site commissioning procedure aims to check the operation of a CO2 Sensor to verify their wiring and
operation.

For each CO2 Sensor control point, the corresponding equipment’s should be controlled by the
software online tool to manually command outputs to be driven to the desired value. The following
procedures describe the best practice steps to commissioning each device to verify its correct
operation.

It is expected that the point’s lists are used to record the results of the point to point commissioning.

Procedure recommended general checks

1. Visibly check installation against approved shop drawings


2. Check that general construction and standard of finish is acceptable
3. Record name point information and compare against the approved specification
4. Confirm no damage to the electric components
5. Check cabling for insulation stripped back satisfactorily, no stray copper strands and terminals are tight with no
loose wires
6. Check power supply is isolated, has the correct power source, voltage, cable sizing
7. Check ductwork installation is complete (if duct mounted unit)

Procedure recommended for testing operation

Each test should be performed in both manual and automatic modes.

1. Control the equipment being monitored to run under normal operating conditions by generating the appropriate
control command. Verify the value of the analogue input point against the control criteria and verify the
operational performance of the equipment.

If the analogue input point displays the desired value (within tolerances noted) then the test has been
successful and "S" should be recorded in the commissioning schedule/inspection and test plans. If the
analogue input point does not display the desired value then the test has failed and "F" should be recorded in
the commissioning schedule/inspection and test plans. If the analogue input point does not change to the

1
Commissioning Methodologies (CM) – MUBS-08
CO2 Sensor Testing Method Statement

expected value then offset should be recorded in the controller & commissioning schedule/inspection and test
plans.

2. While the analogue input point displays the desired value adjust the device or equipment that the point is
monitoring, e.g. increase or decrease the CO2 levels on the transducer monitored system.

If the analogue input point changes its value to the expected value then the test has been successful and "S"
should be recorded in the commissioning schedule/inspection and test plans.

3. While the analogue input point displays the desired value, simulate a fault condition at the equipment or the
FPU. E.g open circuit a data cable. (This test need only be performed on one point per virtual group).

If the analogue input point changes state and reports a fault condition and an alarm is generated on the alarm
summary then this test has been successful and "S" should be recorded in the commissioning
schedule/inspection and test plans. If the analogue input point does not change to fault condition or if an alarm
is not generated on the alarm summary then this test has failed and "F" should be recorded in the
commissioning schedule/inspection and test plans.

4. At the conclusion of the test return the equipment and the BMCS to displaying the status, condition and
desired values for normal operating conditions.

When a point is commissioned tick the Checked Out box which will indicate the user, time and date checked out,
then add comments in the Checkout Notes box (Actual, Recorded, and Offset)

ACCURACY:

For CO2 Sensor, with your certified meter take a pressure reading at the sensor and compare to what is reading
on the BMCS. Calibrate accordingly. Once the sensor calibration is verified write Reading xx Actual xx Adjust +/-
xx % in the Checkout Notes.

Measured Variable Reported Accuracy

Carbon Monoxide (CO) ±3% of full scale

Carbon Dioxide (CO2) ±50 ppm

REFERENCE STANDARDS

CIBSE Commissioning Code C – Automatic Controls

2
Commissioning Methodologies (CM) – MUBS-08
CO2 Sensor Testing Method Statement

CHECKLIST

Generic Analogue Input Testing

BMCS Drawing Number

VERIFICATION
ITEM
METHOD
RESULT RESULT

1 Check installation against approved shop drawings Site Inspection

2 Check that general construction and standard of finish is acceptable Site Inspection

Record name point information and compare against the approved


3 Site Inspection
specification

4 Confirm no damage to the electric components Site Inspection

Check cabling for insulation stripped back satisfactorily, no stray


5 Site Inspection
copper strands and terminals are tight with no loose wires
Check power supply is isolated, has the correct power source,
6 Site Inspection
voltage, cable sizing

Disconnect sensor cable to verify that you get an open circuit reading
7 on the point at the corresponding equipment that the sensor is meant Site Inspection
to control.

Once the sensor is verified write Proved True in the Checkout Data / Point
8
Sheet Record
Data / Point
9 Check jumper setting on controller input is set (eg 0-10V or 0-5V)
Sheet Record

Check point is configured for analogue input in the point’s checkout, Data / Point
10
depending on the type of controller you are using. Sheet Record

Check the min and max scale parameters in the point setup match the Data / Point
11
devices scale. Sheet Record
Data / Point
12 Confirm correct calibration of device
Sheet Record

Certified By Sub Contractor (initial):


Date:

Confirmed By (Head Contractor / Client) (initial):


Date: