Interview Notes For QAQC 28.8.23.

Download as pdf or txt
Download as pdf or txt
You are on page 1of 34

Interview Documents for QA/QC Position

QUALITY DASHBOARD
CONTENT

1. General information
a. Reporting Month
1. From this date to this date
2. Total number of days
b. PQP
a. Contractor PQP Approval date and revision 5
b. Consultant PQP Approval date and revision 3
c. Progress
 Planed progress. 99.92
 Actual progress 96.15
 This month progresses.
 Man, hours for this month 105500
2. Work inspection Request. (WIR)
3. Status of Material Inspection request (MIR)
4. Status of Equipment
5. Status of Material Testing
6. Status of Material Submittal
7. Status of quality inspection finding report
8. Status of NCR
9. Status of SOR
10. Status of quality inspection finding
11. Status of Method statement
12. Status of Sub Contractor pre-qualification submittal
13. Status of Shop drawing submittal

14. Status of RFI request for information approval


15. BI weekly Meeting
16. BI weekly site walk
17. Quality inspection closure status
18. Quality resource
19. Quality Training.

20. Appraisal
Closed out dashboard.
The content of the closed-out dashboard given below.
1. O & M Manual. (Operation and Maintenance Manual)
2. Testing and commissioning.
3. Training.
4. Authority Approval.
5. Asset register
6. As belt drawing.
7. Keys
8. Spare part.
9. Updated snag list.
10. Quality Assurance report.
11. HSE report.
12. Warranties.
13. Lesson learned.
14. Taking over certificate.
15. Close out report

Content of the Method statement

 Purpose.
 Scope
 Legislation & code of practice.
 Reference.
 Definition.
 Resources
 Material and there Approval.
 Sub-Contractor Approval.
 Shop Drawing Approval
 Equipment’s
 Human Resource.
 Safety precision/ Risk Assessment.
 Detailed Construction Sequence (Methodology).
 Inspection and Testing Plan (ITP).
 Related Form.
 Attachments.

Inspection Testing Plan


S.Nos Inspection Frequency of Acceptance Applicable Control Inspection Responsibility
/Testing the Criteria specification/Standard Data/ Method
carried out Test/Inspection Form
Contractor Engineer
1 Documents Review

Verify
Method
statement Prior Must be Project General Approved Visual
Verfy Shop commence the approved Specification Documents Inspection H R
Drawing work Submittal
Verify
related NOC
if Required
2 Material Sub Base
All quality Prior Compliance General Spec and Approved Inspection
test as per commence the to G.Spec, particular Spec as per Material and verify,
specification work Approved mention class Submittal, If material
should be Material Material his
completed Submittal, Inspection approved, H S/R
All test request Material
should be (MIR), Lab Submittal,
completed Test Material
and as per Reports Inspection,
spec. Lab Test
3 During construction Stage
Survey On start and Must Verify to
work/ Verify during the work comply comply
setting out , approved approved
elevation, drawing drawing W/R
alignment H
and
formation
level
4 ITP close out
ITP
verification

H, Hold point, W Witness, R Review, S Surveillance, A Approved, P Perform

Inspection /Testing carried out.

Frequency of the Test/Inspection

Acceptance Criteria.

Applicable specification/Standard.

Control Data/ Form.

Inspection Method.

Responsibility.
‫ﭨﯿﺴﭩﻨﮓ ﮐﯽ ﮔﺌﯽ۔‬/‫ﻣﻌﺎﺋﻨہ‬
‫ﻣﻌﺎﺋﻨہ ﮐﯽ ﻓﺮﯾﮑﻮﺋﻨﺴﯽ‬/‫ﭨﯿﺴﭧ‬
.‫ﻗﺒﻮﻟﯿﺖ ﮐﺎ ﮐﻠﯿہ‬
‫ﻣﻌﯿﺎری۔‬/‫ﻗﺎﺑﻞ اﻃﻼق ﺗﻔﺼﯿﻼت‬
‫ﻓﺎرم۔‬/‫ﮐﻨﭩﺮول ڈﯾﭩﺎ‬
‫ﻣﻌﺎﺋﻨہ ﮐﺎ ﻃﺮﯾﻘہ۔‬
‫ذﻣہ داری‬

Content of the PQP


16. Introduction
17. Scope
18. Major abbreviation and definition.
19. Reference documents
20. Schedule for coordination activities.
21. Quality management system (QMS).
22. Quality policy
23. ISO 9001 2015 CERTIFICATION.
24. Quality objective.
25. Process management
26. Quality roles and responsibility.
27. Sub-Contractor evaluation.
28. Quality Team.
29. Quality management procedure.
30. Technical standard & legislation.
31. Quality reporting.
32. Project specific procedure.
33. Complaints and compliments.
34. Project quality management system integrity.
35. Quality improvement.
36. Testing and commission procedure.
37. Final acceptance inspection and punch/snag list.
38. De-Snagging and final acceptance.
39. Authority inspection and approval procedure.
40. Documents following for handing over the project.
Responsibility of ME (QA/QC)

 Implementing/applying inspection, examination, and testing procedures.


 Routine quality site walks, site inspections and lead the quality meetings.
 Preparation of monthly quality dashboard. Review and comment Contractors
Monthly Quality Dashboard
 Review quality documents as submitted by Contractor.
 Review of material submittals, method statements, plant appraisal, Table-A &
Table-B submissions from Contractor.
 Evaluating the validity and acceptability of inspection, examination and testing
results.
 Ensure that quality of contractor’s products, services, and facilities, are inspected
and monitored.
 Evaluating the adequacy of specific programs used to train and test inspection,
examination, and testing personnel.
 Preparing and circulating quality bulletin to project team.
 Audit Contractors quality management system in the project.
 Ensure all testing equipment and measuring devices that are used at site &
Independent Lab have valid calibration.
 Ensure that proper identification, storage, and handling of materials are followed
by the Contractor.
 Issue non-conformance report and Site Observation Report on detecting non-
compliance to project specifications and requirements and ensure timely closeout
by the Contractor.
 Completing, checking, and processing test reports.
 Making geotechnical recommendations.
 Making quality control recommendations.
 Ensuring that field laboratories and laboratory personnel are responding to
technical requirements.
 Assisting in preparing inspectors for inspection of embankments, concrete, and
pavement.
 Ensuring that off-site testing and certifications are valid.
 Checking and reporting on compliance with Specifications for compaction,
gradation, mix proportions, strength, etc., in construction of embankments,
structures, pavements, and incidental items.
 Establishing laboratory and field-testing procedures.
 Reporting inspection, examination and testing results.
 Developing and implementing schedules for:
 Test frequency.
 Test coverage on all Contracts.
 Supervising the operations of the laboratory and maintenance of all equipment.
OR
1. Implementing inspection and testing procedure.
2. Quality daily report review and submitted to the client.
3. Routine quality site walks and inspection at site.
4. Ensure all the equipment in the site Lab have update calibration certificate.
5. BI weekly quality site walks and its report preparation than issue to the
contractor.
6. BI weekly quality meeting and preparation of its minutes of meeting than issue
to the contractor by letter.
7. Issue of NCR & SOR.
8. Review all quality documents submitted by contractor such as: Material
submittal, Method statement, PQP, Table A and B.
9. Inspection of material when contractor submit MIR.
10. Preparation of monthly quality dashboard.
11. Reviewing of contractor monthly quality dashboard, closed out dashboard.
12. Leading of all quality meeting.
13. BI weekly quality training as per ISO 9001 2015.
14. Visit of Independent Lab and Factory approval.
15. Visit of concrete Plant and Asphalt plant during production.
16. Visit of site during the laying of asphalt and poring of concrete.
17. Visit the Barrow pit area.
18. Visit of site store/Yard that contractor is storing the delivered material as per
manufacturer recommendation.

Material Inspector
 Inspect the appearance, characteristic and quality of materials used on Site.
 Check and approve Contractor’s material sampling and testing including laboratory
testing.
 Ensure all materials delivered to Site are in accordance with the approved material
submittals.
 Review and approve Contractor’s inspection requests and test reports.
 Review and approve Contractor’s material submissions.
 Witnesses and monitors all tests undertaken by the Contractor including materials,
plants and equipment and reports on any failing.
 Ensure the materials delivered to Site are stored as per the Contract.
 Maintain testing logs.
 Site inspections and ensure the works are carried out as per the approved method
statements and shop drawings.
 Ensure all materials delivered to site are inspected and conform to specified
requirements.

International Roughness Index (IRI) ASTM E1926


As per spec clause 3.3.3.10 (d)
Laser road surface machine will be used for this test.
Average value over 400m section
1. For posted speed ≥100 Km/hr ≤0.90
2. For posted speed 80 Km/hr ≤1.10
3. For posted speed 60 Km/hr ≤1.30
4. For posted speed ˂60 Km/hr ≤1.50
5. Peake value over a 25m section: ≤1.5 (not more than 2 value per 400m)

≤1.5
0+00 0+25
0+400
PMB used it our sit PG 82-22 (eight two mins twenty tow)
Advantage of PMB:

 Improve of temp sensitivity and resistance to rutting.


 Improve of low temp properties and resistance to crick.
 Batter resistance to fatigue crick.
 High stiffens in high summer temp.
 Low stiffens in low winter temp.
 Increase the age of Bitumen.

PG 82-22 Here PG means performance grade, 82 is the average 7 days Max pavement
temp it will checked below 22mm from the surface of the pavement, and 22 Min
pavement temp it will check at the surface of the pavement.
Mixing Temperature 175-185 and compaction temperature is 165 to 175
Bitumen Grade 40/50 Bitumen Grade 60/70 PMB Grade PB-88-22
Specific Gravity 1.035 1.044 1.049

1. If the average grading indicates a max of 3 sieves out from the JMF limit by max 1%.
2. If the max of 2 sieve out from the JMF by Max 2% the material shall be acceptable, and
contractor will be providing 1 year guaranty. Clause 3.3.3.10 (b)
If the same thing is happened twice in the 15 days, the work will be suspended, and hot
bin sample should be re-tested.
3. If the marshal density and GMM not found within JMF limit the production will be
rejected.
Q. What is the reason if loss of stability is high?
 If stripping value of aggregate is less than 95% then loss of stability will be high.
 If Natural sand is more in the Asphalt Mix.
 If plastic material is used in the Mix.
 If sand equivalent value is less, it will give high loss.
 If Bitumen content is less, it will give high loss.
 The compaction temperature of the marshal specimen will effect on the loss of stability.
 The weather temperature in which marshal specimen are kept will be effect on loss of
stability.
Q. If the %age of air void are more in the Mix how you will control it?
 Increase the bitumen content up to certain limit.
 Increase filler material in the Mix.

Q. If air void & stability is less in the Mix?

 Increase the coarse Aggregate and used the good quality of Aggregate.
Q. If stability is high (abnormal) & flow is less?

 Its mean pavement is rigid and brittle, under heavy traffic cricks will be produce in the
Mix. So, reduce the course Aggregate and increase fine Aggregate. Its mean low
penetration bitumen is used in the Mix. If marshal specimen compacted at high
temperature, it will give high stability.
Q. What is rigidity and stiffness?

 When low penetration bitumen is used in the Mix it will give high stability and low flow
value. The pavement will be rigid, under heavy traffic cricks will be produce in the
pavement.
Q. what is the difference between Modified and standard proctor?
Properties Modified proctor standard
proctor
Design for Heavy Traffic Light Traffic
Nos of Blows 56 25
Fall of 18 Inch 12 Inch
Hammer
Number of 5 3
Layer
Weight of 10 Ib 5 Ib
Hammer

Content of ISO 9001 2015

 Scope
 Normative reference (Standard reference)
 Term & conditions.
 Context of the organization.
 Leadership.
 Planning.
 Support.
 Operation.
 Performance evaluation.
 Improvement.
Content of ISO9001: 2015
1. Scope
2. Normative/standard reference.
3. Term & Condition.
4. Context of organization.
5. Leadership
6. Planning
7. Support.
8. Operation
9. Performance evaluation.
10. Improvement.
Audit
Audit is the examination or inspection of various books of accounts by an auditor followed by
physical checking of inventory to make sure that.
There are three types of Audit.

1st party Audit 2nd party Audit 3rd party Audit.

Internal Audit External provider Audit Certification/Accreditation


audit

Audit procedure:
The organization will be informed by email for audit. In the email the dated and time will be
mentioned, first you will conduct a kick of meeting. You will involve Organization pm, QA/QC
Engineer, ME, DC, Planner and QS.
Meeting: In the Meeting you will discuss scope of your audit, Attendance sheet will be sign
from involved people. Then you will visit the site, after that we will check the documentation
work in the office. We will see that organization chart ISO Certificate, quality policy, QHSE
policy are fixed on the display board. The ISO certificate and trade license are update are not.
With DC we will check the following items that they are update or not.

 All logs are maintained and update.


 Material submittal, Method statement, shop drawing, MIR, WIR, approved in Code, A,
B, C and D. If any submittal is approved in code B from long time why they did not
upgrade from B to A. Base line program approved or not, PQP is approved or not, the
issue NCR and SOR contractor return with in the specified time, site walk and quality
meeting properly maintain or not. The site Lab and independent Lab for QC and QA
test is properly approved or not.
 Material Testing frequency approved as the approved Table A. The storage area is
properly prepared or not, the material is stored as per manufactured
recommendation. The Labor and Engineer are following the safety roles and
regulation at site. The deep excavation is barricaded or not. All heavy machinery
registration is update or not.
Testing of fresh concrete:

 Workability
 Temperature measurement.
 Density.
 Air Content
 Bleeding.
 Chloride content.
 Setting time
Testing of harden concrete:

 Strength
 Air content
 Density
 Chloride content.
 ISAT (Max 0.15ml/m2/s)
 Absorption. (Max 1.5%)
 RCPT Rapid chloride permeability test. Max 700 coulombs)
 Water permeability test. (15mm for 7days cube and 10mm for 28 days cube)
 Moisture content.
 Petrographic analysis
Plasticizer: Increase strength and slump, while reducing W/C ratio, improve workability.
Retarder: improve workability and increase setting time.
Accelerator: To increase the setting time.
Standard CBR at 2.5 = 13.2 and 5.0 = 20.0 and at ASTM 2.54=6.9 AND 5.08 = 10.3
CBR MACHIN Machine rate of speed 1.2 +- .2 mm/min
0.64, 1.27, 1.90, 2.54, 3.81, 5.08 7.62
Interview question for Atkin consultant are given below.
1. Introduce yourself.
2. Hard scraping and soft scraping. A. Where we used interlock tile and Kerb stone that is
hard scaping and where the land is prepare for plantation is called soft scaping.
3. What is Wet utility and dry utility? Ans: (Water network, Storm Water, sewer network,
irrigation line) (Dry = Etisalat and street light pole)
4. Where we are using thrust block? (Where is the bend in pressure pipe there we are
using)
5. What is your responsibility in your project?
6. What is KPI means stand for what. Key performance indicator.
7. What is TOC ? Certificate of taking over
8. Content of close out report
9. PQP content?
10. How you will proceed Audit of any organization?
11. Asphalt Mix design and concrete Mix design detailed question.
12. Asphalt testing name.
13. What is prime coat and take coat.
14. If loss of stability values are high, what is the precaution?
15. What is Air Void and its formula?
16. From where you will know the mixing and compaction temperature?
17. Min laying temperature of asphalt, and what is the ambient temperature for asphalt.
18. Test of fresh concrete and hard concrete.
19. Durability test and its values.
20. ISO 9001 2015 content.
21. Admixture used in the concrete why?
22. What is penetration test of bitumen?
23. What is CBR?
24. What is difference between 200 passing and sand equivalent?
25. Monthly quality training we are giving to the site people and consultant site inspectors
as per ISO 9001 2015.
26. Asphalt Mixing and compaction Temp Mixing Temp 170±20 and Compaction Temp
280±30.

Super pave TM

Milestone

 USA 1984 TBR 202: American Highway.


 SHRP Foundation 1987
 AASHTO Task force formed 1991.
First Pavement 1993.
 SHRP completed 130 product 1993.

Milestone---USA.

 First Conference 1994.


 Center Establish 1195.
 95 project constructed 1996.
 Al Sp-2 & AASHTO M320 & M323 2001.
 Specification Adopted by 52 status & Mix design by 36.

Milestone---KSA.

 1409 OR 1989
 1417 OR 1997
 1425 OR 2005 super pave only.

Why Super pave ?

 Internationally
 SHRP From 1987 to 1993
 US, Canada, Europe, Australia, Iran & Japan.
 Locally KSA
 Mot First Circular No: 2253.
 Mot 2nd Circular No: 30789.
 Mot 3rd Circular No: 3335 dated 1-8-1426 (2006).

Why Super pave ?

Pre-super pave shortcomings.

 Viscosity Grading.
o Viscosity effect only.
 Penetration Pen grading.
o Empirical measure of viscosity & elastic effects.
 No low temperature properties measured.
 No consideration of long term aging.
 Problems with modified asphalt characterization.

Why Super pave ?

 Drawback of current design practices.


 Current procedures do not take Traffic or environmental condition into
consideration.
 Marshall
 Impaction Compaction.
 Shear strength of HMA is not adequately estimated.
 Haveem
 Important volumetric properties are not determined.
 Expensive and not portable.
 Pavement unsatisfactory performance.

Asphalt pavement performance.

 Low Temperature Cracking.


 Fatigue Cracking.
 Rutting.

SHRP defined super pave:

It is a Mix design system for new construction & overlays. This system employs a series
of new performance based specification, test method, and practice of material selection,
accelerated performance testing & Mix design 1994.

Different aspect of Super pave:

 Integrated approach includes specification and Mix design method.


 The use of formal aggregate evaluation procedure. (Consensus requirements).
 The use of PG Asphalt binder grading system & its associated asphalt binder
selection system.
 The use of gyratory compactor to simulate field compaction.
 Traffic load and environmental consideration.
 It volumetric approach to Mix Design.

Steps of Mix design.

Selection of Material.
Selection of DAS.
Selection of DAC.
Moisture Evaluation.

Step No 01: Selection of Material.

1. Asphalt Binder (PG).


 Neat Binder.
 PMB.
2. Aggregate.

Step No 02: Selection of DAS.

 Develop Trial Blend


 Compact blends.
 Evaluate Blends.
 Select confirm blend.

Step No 03: Selection of DAC.

 Compact Sample.
 Test and analyze.
 Select DAC.
 Ndes & Nmax verification.

Step No 04: Moisture Sensitivity.

Select Nx → Compact Sample → Evaluate Strength → Evaluate Moisture


Sensitivity.

Design Parameters:

 NMS
 Traffic.
 Location.

Nominal Maximum size of Aggregate (NMS).


One size sieve larger than the first sieve to retain more than 10%.

Six Mixture Gradation

MS NMS

50.0mm 37.5mm

37.5mm 25.0mm

25.0mm 19.0mm

19.0mm 12.5mm

12.5mm 9.5mm

9.5mm 4.75mm

Standard Axle: 8.2 Tone (18,000 Ib), Tire Pressure =75 psi

Design Parameter:

Traffic is the anticipated project traffic level in terms of ESALs expected on the
design lane over a 20 years period.

Design Parameter:

MOT has identified the following ESAL Classes

Class ESAL Range Traffic Typical Application


Designation Description
VL Less than 300,000 Very Light Agriculture road & Local
Street
L 300,000 to 3 Million Light Feeder, Collectors
M 3 Million to 10 Medium Main Road, City Streets
Million
H 10 Million to 30 Heavy Highways & Expressway
Million
VH More than 30 Million Very Heavy Heavily Trafficked
Highways

Design Parameter:

Location:
1. The geographical location of the project where the Hot Mix Asphalt (HMA) will be
used.
2. The position of the layer within the pavement.

Some data is remaining


here

Gyration Numbers

N initial
The number of gyration use is a measure of mixture compactability during construction, is
called Number of initial gyration.
Mix that compact too quickly (Air void at N initial are too low) may be tender (soft) during
construction & unstable when subject to traffic.

N Design:
The design number of gyration required to produce a sample with the same density as expected
in the filed after the indicated amount of traffic.
A mix with 4% air voids at N design is required in the Mix design.
N Maximum:
The number of gyrations required to produce a Lab density that should never be exceed in the
field.
If the air voids in the N maxim are too low, than the field mixture may be compact too much
under traffic resulting in excessively low air voids and potential (possible) rutting.
 % Gmm = (100-Air Voids)
ESAL Class % Gmm @
(Million) N ini N des N max
Very Light (VL) ≤ 91.5
˂0.3
Light (L) 0.3 to ˂3 ≤ 90.5 96.0 ≤89.0
Median (M) 3 to 10 ≤89.0
Heavy (H) 10 to
˂30
Very Heavy VH
≥30
 % VMA:

Nominal Maximum Size Required VMA %


NMS, mm Min Max
37.5 11.0 13.0
25.0 12.0 14.0
19.0 13.0 15.0
12.5 14.0 16.0
9.50 15.0 17.0
4.75 16.0 18.0

 % VFB:

ESAL Class
(Million) NMS NMS NMS NMS
19.0 & 9.5 25.0mm 37.5
12.5mm mm mm
Very Light (VL) 70-80 70-80 67-80 64 - 80
˂0.3
Light (L) 0.3 to 65-78 73 - 76 65-78
˂3
Median (M) 3 to 65-75 65-75
10
Heavy (H) 10 to
˂30
Very Heavy VH
≥30

 DP (Dust to Binder Ratio)

Gradation Type DP Ratio


Fine Line is above PCS 0.6 – 1.2
Coarse, line is below PCS .08 – 1.6

 Moisture sensitivity

Property Requirement
Dry indirect Tensile Strength, KPa 700 - 1400
Retained indirect Tensile Strength, KPa 80 % Min

Selection of Material:

1. Binder: As per ASTM D 8 Asphalt as defined as, ‟A dark brown to black cementitious material in
which major constituents are bitumen. They are occur in the nature or obtained in the
petroleum processing. Binder or Bitumen are the principle or main constituent of Hot Mix
Asphalt. Asphalt function as an inexpensive, waterproof, thermoplastic, viscoelastic adhesive.
2. Rheology: The branch of physics that deal with the deformation and flow of matter.
Determination & flow of asphalt binder in HMA is important in determining HMA pavement
performance.
3. Asphalt Binder grade selection:
 Generally one need to:
 Determine project weather data.
 Select reliability.
 Determined design temperature.
 Derive the performance grade.
 In the Kingdom:
 Selection of Asphalt Binder Grade is Based on the Kingdom
Temperature Zoning Map.
 Verify Asphalt PG.
 Determine temperature- viscosity relationship.

Pipes:
For NDRC we are using the following pipes.
1. We are using GRP and concrete reinforcement pipe for storm water and sewerage work.
The fluid is flowing in this pipe, while somewhere we are using concrete pipe in NDRC, in
this case we are using,
2. Concrete pipe is a sleeves and another pipe will pass in it.
3. HDPE pipe: it is use for potable/drinking water. It site we are testing doing test for
HDPE pipe, pressure test, Flashing test, disinfection test, and joint test.
4. GRP pipes: After installation we are checking deflection test at 2%, after backfilling we
are doing deflection at 3%, when road completed than check deflection at 5%. For big
dia we are using deflective meter for deflection test.
5. UPVC Pipe: After installation check the deflection test at 3% before backfilling, and after
final back filling deflection will be, check it 5%. Further information I will ask from
Abdullah.

For storm water pipe line, 800mm dia we have perform Air pressure test for leakage from
Manhole 07 to 7A. 100mm pressure given through gauge for 4 minutes and after 4 minutes
the level did not drop its means that there is no leakage. This pipeline was not for pressure
but we have check the leakages.
Sewerage water Pipe: There are 4 types of pipe
UPVC:
1. PN-10.

2. PN-16
GRP Pipe:
1. GRP Pipe stiffness 5000.
2. GRP Pipe stiffens 10000
UPVC pipe for sewerage and storm water we can use min 16mm dia uo to 300mm dia
abive 300 we will used GRP pipe.
UPVC pipe PN-10 we can used If the depth of trench is more than 4 meter and
From 4 meter up to the finishing level, we will use UPVC PIPE PN-16.

GRP Pipe.
From ground level up to 6 meter depth we can used 5000 stiffness GRP pipe, from 6 meter up
to 10 meter we can use 10000 stiffens GRP pipe, if the depth is more the 10 meter we will
change the stiffens value or we will make concrete in surrounding of the GRP Pipe.
Sewerage Pipe greater the 300 mm dia slope will be min 0.75% and for storm water, slop will be
3% min.
Sewerage line upvc pipe testing.
Hydro test or pressure test initial test before backfilling, after backfilling from Manhole to
Manhole pressure test or mirror test.

Storm water Chamber.


Are 3 types.
1. Manhole.
2. Catch basin: Catch basin are inter connected with several Inlet chamber and then catch
basin connected with Manhole.
3. Inlet chamber: Are two types flash chamber are level with asphalt, Carve inlet flesh with
kerb stone.
Storm water all chamber are epoxy coated inside and outside there is waterproofing
(Primer then Membrane then bit board.

Strom water
Strom water Catch basin
Inlet
Strom
water Inlet

Strom water

Manhole

Pipe use for storm water


1. Upvc pipe 100 mm to 350mm.
2. GRP use 400 and above.
3. RC reinforcement concrete Pipe: 500 and above.
Testing for storm water are UPVC pipe
1. Air test (Water leakage test)
2. Deflection Test.
3. Torch Mirror test
Testing for storm water are GRP pipe
1. Deflection test use by deflective meter.
From finishing level up to 6 meter, we will used Upvc pipe PN-10 and below
6 meter, we will use upvc pipe PN-16 as per our specification. While is per
ILF specification from finishing level up to 4 meter we will use upvc pipe PN-
10, and below 4 meter we will use upvc pipe PN-16.
Installation of storm water Manhole.
Storm water manhole
6

5 50mm thick cement sand screed


4 Primer, membrane & Bit board
3 75mm thick C-20 Blinding concrete
2 1000 Gauge polythene sheet
1 Compacted area (FDT)

GRP Sewerage Manhole


GRP Sewerage manhole
4

3 50mm dry mortar screed


2 75mm thick C-20 Blinding concrete
1 Compacted area (FDT)

Detailed of GRP sewerage manhole:


GRP Sewerage Manhole is prepared from glass reinforce material. The wall
thickness of the base plate is 10mm, and the sidewall thickness is min
18mm, inside bench thickness 7mm.
The manhole base will be filled by concrete C-40, the top slab/ cover slab
will be prepare by concrete C-40, GRP cover slab liner 7mm. opening
double triangle DI cover frame clear opening 300X300
Potable water pipe:
In potable water, we are using 2 types of pipe.
1. HDPE Pipe: PN-10 and PN-16 (PN-10 not used)
2. DI pipe (Ductile iron Pipe).
HDPE pipe: There is two type of pipe, PN-10 and PN-16. It is pressure pipe so we are not
using PN-10 but we are using PN-16. PN-16 is stronger than PN-10. We are using HDPE pipe
up to 400mm and above 400mm dia we are using DI Pipe for drinking or potable water. The
HDPE pipe we will consider outer dia while in DI we will consider internal dia.
DI pipe (Ductile iron Pipe) SDR 17 = PN-10 and SDR 11 = pn-16. SDR stand for standard
dimension ratio
For joint of HDPE pipe, we are using Butt fusion Machin and electro fusion Machin. Butt
Machin we are using normally in the open space while electro fusion machine we are using in
the complicated area just like trench.

Testing of HDPE Pipe:


Hydro test: we will use drinking water in the pipe for this test. The water will be filled in the
pipe from lower point to highest point, by this way all Air will be replace by water in the pipe.
Let us suppose that it is mention in the specification that working pressure will be 6bar in the
pipe.
Test Procedure for HDPE pipe:
The test of the pipe will start from Manhole to Manhole, the pipe will be little back filled, but all
joint will be expose means not backfilled to see the leakages in the joint.
Step No 01. Give pressure to the pipe = working pressure+1.5 = 6+1.5 =7.5 bar pressure to the
pipe for one hours than release the pressure.
Step No 02. Give pressure to the pipe = working pressure+1.5+1.5= 6+1.5+1.5=9 bar for one
hour, than release the pressure.
Step No.03. Give pressure to the pipe = working pressure + 1.5 = 6+1.5 = 7.5 bar for one hours
the release. If we did not found any leakage, its mean the line is pass or ok.

Test Procedure for DI pipe:


Before commencement of the test, the pipe should be backfilled up to 30cm only joint would
be expose.
In the DI pipe, we will put drinking water for 12 hours, after 12 hours we will start the test. This
test we can complete in one-step.
Step No 01. After 12 hours we will give the pressure in the pipe = Working pressure + 1.5 =
6+1.5 = 7.5 bar and we will maintain it up to 3 hours, after that we will check if the pressure
dose not drop its mean that the line is ok there is no leakage in the pipe. Two pressure gauge
will be fixed at lower end of the pipe and upper end of the pipe. The DI pipe have socket and
spiked (It mean one pipe have socket and the other pipe have spiked they are joint through
this). Warring tap will be put 30cm below from the ground level above the pipeline.

Potable water Chamber:


1. Gate valve.
2. Air release valve.
3. Washout chamber.
4. Control Valve.
5. Flow valve.
Flow valve and control valve are fixing to gather that is called sector-measuring point.
These two are fix where you are taking the connection of the pipe. All chamber should
be waterproof from outside and inside will be epoxy coated.
Any Main hole coming in the road the cover frame will be DI-400, and the main hole
coming in the footpath the cover frame will be use D-250.
Etisalat Chamber: pipe use for these activities is D-54 and D-55.
JRC-04 it is used for single or double pipe.
JRC-12 it is used for 4way & 2 Way.
JRC-14 it is used for above 4way pipe.
JRC stand for Joint research center

Q. What is wet utility and dry utility?

1. Sewerage water, storm water, Potable water, irrigation & Recycle water are wet
utilities.
2. Du, Etisalat (Telecommunication work) and streetlight are dry utilities.

Valves:
There are two types of valves.
1. Get Valves: up to 300mm dia we are using gate valves
2. Batter fly valves: Above 400 mm dia, we are using Batter fly valves.
DI fitting
Flange Adopter and Dismantle Joint use in Chamber, its use is only for maintenance
purpose. Dismantle joint use for washout.
Vent pipe are two types
1. L shape use in the urban area.
2. Vertical pipe use in the desert area.
Purpose: both are used for air ventilation
GRP Ladder never use in the sewerage manhole while use in the storm water
manhole. Sewerage manhole made from GRP material, while storm water
Manhole made from concrete.
Shutdown: shutdown is required where you want to connect you pipeline with active
pipeline. For should down approval we will submit the following documents to operation
maintenance authority.
1. Method statement.
2. Pipe test report.
3. Approved shop drawing.
4. NOC.
The contractor will submit the above documents to operation maintenance deportment
for approve. From 7 to 10 days they will visit the site and will give you the time for
shutdown, on shutdown day they will come to the site and will close the pipe after that
you will start the work.

Telecommunication network:
Pipe D-54 and D-55 used in the telecommunication network. GRC chamber used for
telecommunication work.

What is ISO 9001:2015 Quality Management system?


Technical committee 176 formed in 1980, ISO 9001 originally published by technical committee
in 1987, than revise in 1994, 2000 & in 2008. The latest revision of ISO 9001:2015 was publish in
September 2015.
ISO 9001 is the international standard that specifies the requirements for quality management
system (QMS). Organizations use the standard to demonstrate/establish/determine/prove the
ability to consistently (regularly) provide products & services that meet the customer and
regulatory (controlling) requirements.
ISO 9001 is the most popular standard of ISO 9000 series. ISO 9001 is the only standard in the
series to which organization can certify. ISO 9001:2015 certification means that an organization
has demonstration the following.
 Fallows the ISO 9001 standard.
 Fulfill its own requirements.
 Meet customer requirements & statutory/ legal and regulatory requirements.
 Maintain documentation.
ISO 9001 was first published/issued in 1978 by international organization for standardization
(ISO). The current version of ISO 9001 was release in September 2015. It is use in more than 160
countries.
ISO 9001 applies to any organization and industry, more than one million organizations from
more than 160 countries have applied the ISO 9001 standard requirements to their quality
management systems. All type and size of organization used ISO 9001 standard help them.
Those organizations that use ISO 9001 are encourage to move/transition to ISO 9001:2015 as
soon as possible. ISO 9001 based on the Plan-do-checked-Act Methodology & provide a
process-oriented approach, to documenting and reviewing the structure, responsibilities, and
process enquired to achieve effective quality management in an organization. Specific section
of the standard contains information of many topics, such as.
 Requirement for quality management system (QMS).
 Documents information
 Planning.
 Process interactions.
 Responsibilities of management.
 Management of sources.
 Human resources
 Organization work environment.
 Product realization.
 Steps from design to delivery.
 Measurement.
 Analysis & improvement of the QMS through activities like internal audits, and
corrective & preventive action.

IRCA : The International Register of Certificated Auditors

‫ﻣﺼﺪﻗہ آڈﯾﭩﺮز ﮐﺎ ﺑﯿﻦ اﻻﻗﻮاﻣﯽ رﺟﺴﭩﺮ‬


Quality management system.
The potential benefit to an organization of implementing a quality management system based
on this international standard are.
1. The ability to consistently provide product and service that meet customer and
applicable statutory and regularly requirements.
2. Facilitating opportunities to enhance or increase customer satisfaction.
3. Addressing risk and opportunities associated with it context and objective.
4. The ability to demonstrate conformity to specified quality management requirements.

The ability to consistently provide products and services that meet customer and applicable
statutory and regulatory requirements; ‫ﻣﺴﻠﺴﻞ ﻣﺼﻨﻮﻋﺎت اور ﺧﺪﻣﺎت ﻓﺮاﮨﻢ ﮐﺮﻧﮯ‬
‫ﮐﯽ ﺻﻼﺣﯿﺖ ﺟﻮ ﮔﺎﮨﮏ اور ﻗﺎﺑﻞ اﻃﻼق ﻗﺎﻧﻮﻧﯽ اور رﯾﮕﻮﻟﯿﭩﺮی ﺗﻘﺎﺿﻮں ﮐﻮ‬
‫ﭘﻮرا ﮐﺮﺗﯽ ﮨﯿﮟ؛‬

Facilitating opportunities to increase customer satisfaction;

Simplifying chance to increase customer satisfaction.


‫ﮐﮯ ﻣﻮاﻗﻊ ﮐﯽ ﺳﮩﻮﻟﺖ ﻓﺮاﮨﻢ ﮐﺮﻧﺎ؛‬ ‫ﮔﺎﮨﮑﻮں ﮐﯽ اﻃﻤﯿﻨﺎن ﮐﻮ ﺑﮍھﺎﻧﮯ‬

Addressing risks and opportunities associated with its context and objectives;

‫اس ﮐﮯ ﺳﯿﺎق و ﺳﺒﺎق اور ﻣﻘﺎﺻﺪ ﺳﮯ واﺑﺴﺘہ ﺧﻄﺮات اور ﻣﻮاﻗﻊ ﮐﻮ ﺣﻞ ﮐﺮﻧﺎ؛‬

The ability to demonstrate/prove conformity to specified quality management system


requirements.

‫ﮐﻮاﻟﭩﯽ ﻣﯿﻨﺠﻤﻨﭧ ﺳﺴﭩﻢ ﮐﯽ ﻣﺨﺼﻮص ﺿﺮورﯾﺎت ﮐﮯ ﻣﻄﺎﺑﻖ ﮨﻮﻧﮯ ﮐﺎ ﻣﻈﺎﮨﺮه ﮐﺮﻧﮯ ﮐﯽ‬
The ability to demonstrate/prove conformity to specified quality management system
requirements.

Principles of audit:
1. Integrity. (Professionalism)
2. Fire presentation. (Trustfully & accurately)
3. Due professional care. (Judgements)
4. Confidentiality. (Security)
5. Independence. (Impartiality)
6. Evidence base approach. (Reliable & reproducible audit conclusions)
7. Risk base approach. (Risk & opportunities)

ISO 9001 ISO 19011


4. Context of the organization 4. Principle of auditing
5. Leadership 5.Managing an audit program
6. Planning 6.Conducting an audit
7. Support 7.Compatance an audit
8. Operation
9. Performance & evaluation. 80 Auditee talk.
10. Improvement 20 Auditor talk
LPS-OPI

ISO 9001
Internal Interested Parties External interested Parties
Workers, Union, Top Management, Board of Consumers, Regulators, Legislators, Media,
Directors, Supplier, Contractor, Sub- Shareholder, Special interest parties,
Contractor, Management Team community

Term & definition as per ISO 19011


3.1. Audit.
3.2. Combined Audit.
3.3. Joint Audit.
3.4. Audit Program.
3.5. Audit scope.
3.6. Audit Plan.
3.7. Audit criteria.
3.8. Objective evidence
3.9. Audit Evidence
3.10. Audit finding.
3.11. Audit Conclusion
3.12. Audit Client
3.13. Auditee
3.14. Audit Team
3.15. Auditor.
3.16. Technical expert.
3.17. Observer.
3.18. Management system
3.19. Risk.
3.20. Conformity.
3.21. Nonconformity.
3.22. Competence
3.23. Requirements.
3.24. Process.
3.25. Performance.

Quick reference Guide as per ISO 19011


6.2-6.3 Audit Planning.
6.4. Audit Execution.
6.5 – 6.6 Audit report.
6.7 Audit Fallow up.

1st party Audit 2nd party Audit 3rd Party Audit


Internal Audit External provider Audit Certification, Statutory,
(Ex: Vendor End) Regulatory, Accreditation

Marks: 70% marks required from 90 Marks means 63 Marks for passing.
Part 3 & 4 = 60 Marks (Min 30)
Part 02 = 20 Marks (Min 10)
Part 01 = 10 Marks (Min 5)
Note: as per the instruction of auditor first solve Part 3 & 4 because they have high marks,
after that part 2 and part 01.
Exercise Content
Exercise 01 Mini Interview (General)
Exercise 02 QMS Term & definition (Quality, Interested parties)
Exercise 03 QMS Identification of requirements (Over all clauses)
Exercise 04 Audit term & definitions (Audit scope, plan, criteria)
Exercise 05 Analysis of key requirements (Leadership, resources, Competence &
Communication)
Exercise 06 Analysis of check point (6.1,8.1,9.1 &10)
Exercise 07 Conduct of Audit (Activities)
Exercise 08 Principle of Auditing
Exercise 09 Roles & responsibilities

Workshop Content
Workshop 01 Stage 01 Audit (Documentation Review)
Workshop 02 Planning Stage 01 Audit
Workshop 03 Conducting open meeting & site visit & observation
Workshop 04 Audit chick list (MR/DC/Top management)
Workshop 05 Stage 02 Auditing skill (MR/DC)
Workshop 06 Nonconformity report writing
Workshop 07 Conducting closing meeting
Workshop 08 Audit report & corrective action review

Plan-Do-check-Act Cycle
NDRC
Non-Disruptive Road Crossing NDRC by HDD Drilling Method

Pipes
As per general specification for civil works Abu Dhabi Sewerage company (ADSSC) Table2.1.1. – Design
Requirements uPVC

Nominal Outside Diameter(mm) Pipe Classification (Nominal Pressure)


Cover ≤ 4m 4m ˂ Cover ≤ 6m
160 Upvc PN 10) Upvc PN 16)
225 Upvc PN 10) Upvc PN 16)
280 Upvc PN 10) Upvc PN 16)
315 Upvc PN 10) Upvc PN 16)

It means that from ground level up to depth 4meter we will use Upvc pipe PN 10 and below 4 meter up
to 6 meter we will used PN 16 upvc pipe.

PIPES DETAILED

GRP: Pressure pipe as per ASTM D 3754 OR BSEN 14364. Its Nominal dimeter is 600m stiffness 5000 and
pressure PN 6 bar.

GRP 400 and above we are using for Drainage and sewerage line his PN 6 bar stiffness is 5000 and
10000. On the bases of kit mark we can give approvals.

There are 2 types of test

a. Non-destructive Test.

1. Visual Inspection ASTM D 2563

2. Dimensional Control ASTM D 3567.

3. Barcol Hardness ASTM D 2583. Ans 35 to 45

4. Hydrostatic Test. 2xpn for 5 minutes

b. Destructive Test.

1. Pipe stiffness or deflection test ASTM D 2412. Ans 5 %

2. Longitudinal Tensile Strength ASTM D638

3. Circumferential (Hoop) Tensile Strength ASTM D 2290

4. Loss on Ignition Test ASTM D 2584 (Composition Test)

Standard Installation
1. Installation Type 1. Full Gravels or crushed stone surrounding compacted to 70 % relative
density.

2. Type 2: Full sand with less than 12 % fine, surrounding compacted to 90 %.

3. Type 3. Full sand with more than 12 % fine, compacted to 90 %.

4. Type 4. Full sand with more than 12 % fine, compacted to 80 %.

UPVC Pipe: BSEN 1401

Pipe dia up to 315mm SDR (Standard Penetration Ratio 35- 42. No pressure is required its Gravity Pipes.
In the Road crossing we will use Class C UPVC Pipe. We can use upvc pipe for drainage work if its dia is
less than 350mm.

Class B 6 bar

Class C 9 bar

Class D 12 bar

Class E 15 bar

D54 & D56 Pipes

For Etisalat, DU and Telecommunication we are using D54 and D56.

D54 Dia is 96mm while dia of D56 is 50mm. In Road Crossing we will put concrete surrounding the Pipe.

GRE Pipes: (Glass Reinforcement Epoxy Coated Pipe)

For Testing give 10 bar pressure for one hours. When it crosses the road, we will put casing in the GRE
pipe and will put the grout in the middle of casing pipe and GRE pipe. If the dia of the portable water is
less than 450 mm no Geotextile is required if the dia is more than 450mm then we will use Geotextile.

This pipe is used for Portable and drinking water.

HDP Pipe

Used for Irrigation Line, and firefighting. For firefighting we will give 16bar pressure for 24 hours,
concrete used for firefighting 30/20

Gravity Line we can used GRP pipe its PN 6 Bar & stiffens 50000

DEVW electrical Pipe: Upvc pipe used its dia is 150mm class C.

Streetlight: 100 mm Dia Upvc pipe used.

WARNINGB TAPES:

Orange Colour for Irrigation

Yellow Colour for Drainage & Sewerage

Blue colour for Water Line.


Red Colour for Street Light & It is also used for Spare Duct.

Drainage Manhole

Main Hole cover: Sime circular Main Hole cover is used for Drainage, Its Ø600mm. Drainage Main Hole is
Epoxy paint in side, side wall is 300 micron while Benching is painted 10mm. while outside water
proofing are fallow

1. First Primer applied at outside Manhole Body. Then 2.1 mm Bitumen Membrane and then 6mm
Bit board.

Sewerage Main Hole & Cover: we can used upvc pipe for sewerage work up to dia 350mm more the
350mm we will used GRP pipe, we will use Geotextile around the pipe if it is Upvc or GRP.

Inside Manhole 7mm GRP lamination while outside applied primer then 2.1mm membrane and then
6mm bit board

Double Tringle Main Hole Cover is used for Sewerage. Its clear opening is 600mm. The Main Hole cover
is 375 Micron epoxy coated both side. For sewerage Line we can used Upvc and GRP, so we will use
Geotextile around the Pipe.

Portable water Chamber: Its submittal will be approved by DEW Department.

If the chamber height is up to 1.5m we will make it from solid block, if its height is more than 1.5m then
base will be prepared from concrete and the wall will be solid block Masonry, and the top slab will be
from concrete. Water proofing for portable chamber is, applied primer outside on the chamber, then 1.6
mm Membrane, after that 12mm Bit board will be applied.

IRRIGATION CHANBER:

For irrigation line up to 150mm dia upvc pipe used beyond 150mm we will used GRP. Upvc 12 bar
pressure while GRP 16 bar & stiffens 10000. Irrigation chambers have 5mm GRP lamination.

Note: In pump station the thickness of GRP pipe is 10mm.

Strom water & sewerage pipe PN 12br while Irrigation pipe 16 bar.

UPVC pipe Test: BSEN 1401

1. Dimension

a. Outer Dia 200-200.5mm

b. Wall thickness 4.9-5.6mm

2. Heat Reversion at 150C˚ for 60 minutes Change Max 5%

3. Resistance to Diocletian for 15C˚ at 30 minutes. No appear of whit bleeding.

4. Voicate softening Temp. >79C˚

5. Rubber ring at 23C˚ No Leakages.

6. Impact Resistance: When 2Kg Load fall down on pipe from 2m height no creaks occur in the pipe
GEOTEXTILE
1. Weight as per DIN 53854 135g/m2

2. Thickness as per DIN 53855 0.7mm

3. Tensile Strength as per ASTM D 1682 1.6 KN

4. Puncher resistance DIN 54307 1.5 KN

5. Permeability DIN 605020 50 l/sq.m/s

GRP Pipes:
We will used GRP pipes for Sewerage in all Dia.

For Drainage work we will used Upvc pipe dia up to 315mm, after 315mm we will used GRP pipe
because in the UPVC pipe maxim available pipe dia is 315mm.

Excavation of Trench for pipe:

Excavation of Trench will be done as per the below formula,

Width of the Trench =(1.5 X Pipe Dia) +500 Late us supposed that pipe Dia is 300mm now (1.5 X
300)+500 =950mm so width of the trench should be keep 950mm but as per Dubai specification each
trench dia should be min 700mm.

After this we will compact the bed and Lab will perform FDT Test, then spread Geotextile in such a
position that it can overlap 50cm at the joint. 15cm Aggregate will be put on Geotextile if pipe dia is
required up to Max 300mm and also 30cm aggregate will be on the top of pipe, then the Geotextile will
be overlap on each other. The first 2 Layer will be compacted by hand compactor and will be checked by
visual no FDT is required, after that up to 2 Mater used Plate compactor or babe roller & performed FDT
for compaction.

If pipe used in the trench is more than 300mm dia than after geotextile we will put Aggregate layer
20cm than we will put pipe and on the top of the pipe we will put 30cm aggregate layer than overlap the
geotextile 50cm on each other. The first 2 Layer will be compacted by hand compactor and will be
checked by visual no FDT is required, after that up to 2 Mater used Plate compactor or babe roller &
performed FDT for compaction.

Musanada question in interview by Mohmed

1. How CBR Test is done

2. How you will do asphalt mix design.

3. What is the formula of standard deviation of concrete?

4. What is the roll of air void in Asphalt

5. What are the test for GRP


A. Visual inspection, Dimensional inspection, Barcol hardness & Hydrostatic pressure.

B. Stiffens or deflection test (5%), longitudinal & circumferential tensile strength & Loss on ignition.

6. Distresses of asphalt.

7. What do you know about NDT.

8. Difference Between Sub grad & Subbase

9. How you will review material submittal

10. Road Marking Material Test.

Shams Ur Rehman
QA/QC Engineer
AECOM UAE
054-7869094

You might also like