Guidelines On Decommissioning Cost Estimation - Issue 2 (2011)
Guidelines On Decommissioning Cost Estimation - Issue 2 (2011)
Cost Estimation
Issue 2
April 2011
Whilst every effort has been made to ensure the accuracy of the information contained in this
publication, neither Oil & Gas UK, nor any of its members will assume liability for any use made
of this publication or the model agreement to which it relates.
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system,
or transmitted in any form or by any means, electronic, mechanical, photocopying, recording or
otherwise, without prior written permission of the publishers.
Crown copyright material is reproduced with the permission of the Controller of Her Majesty’s
Stationery Office.
Copyright 2010 The United Kingdom Offshore Oil and Gas Industry Association Limited trading
as Oil & Gas UK
Prepared by the following Oil and Gas UK Workgroup members:-
Aberdeen Office:
rd
Exchange 2, 3 Floor, 62 Market Street, Aberdeen, AB11 5PJ
Tel: 01224 577250 Fax: 01224 577251
Email: [email protected]
Website: www.oilandgasuk.co.uk
Guidelines on Decommissioning
Cost Estimation
Contents
1. Introduction 1
2. Objective of the Guideline 3
3. Application of the Guideline 5
4. Offshore Decommissioning Cost Estimation 7
4.1 Check List 7
4.2 Cost Estimate Evolution 8
4.3 Field Development Plan (FDP) stage 8
4.4 During Field Operation 8
4.5 Asset Sale or Transfer 9
4.6 End of Development Life 9
5. Offshore Decommissioning Cost Estimate Checklist 11
5.1 Stages 11
5.2 Cost Estimating Checklist Structure 11
Appendix 1: Abbreviations 13
Appendix 2: Definitions of Terms Used in this Guideline 15
Appendix 3: Overall Decommissioning Schematic 17
Appendix 4: Cost Estimating Guidelines 19
Appendix 5: Supplementary Notes to Checklist 29
Appendix 6: Regulatory Regime 33
Intentionally Blank
1. Introduction
Oil & Gas UK have recognised that decommissioning in the UKCS is becoming
a major part of the industry and needs coordination in order to provide timely
advice to the Government and provide a consistent voice from the Industry on
decommissioning matters. In 2005, a Steering Committee and
Decommissioning Workgroups were set up to coordinate future work.
The first issue of the Decommissioning Cost Estimating Guidelines was issued
by the Efficiency and Effectiveness Workgroup WG4 in 2006. It was based on
typical work breakdown structures from the represented companies and their
collective experience. Development of the Guidelines was facilitated by Turner
& Townsend.
Four years after the first issue, a subgroup to WG4 (now entitled Infrastructure)
has been formed to review the Decommissioning Cost Estimation Guidelines.
This revision is based on project experience in UK and Norway, reflects
changes in legislation and government and industry bodies and feedback
based on four years of use. The intention is to capture lessons learned,
provide clarification and to make the Guidelines more user friendly.
Guidelines on the methodology for the cost estimating of well abandonment
work have been developed by Work Group 5 (WG5). Their document provides
guidance on the preparation of a cost estimate to plug and abandon the
different types of wells in the UKCS. Guidance on estimating costs for the
abandonment of the wells is not included in the WG4 document. Reference
must be made to the WG5 document (Guideline on Well abandonment cost
Estimation).
Introduction
Issue 2, December 2010 1
Guidelines on Decommissioning
Cost Estimation
Intentionally Blank
Introduction
2 Issue 2, December 2010
Guidelines on Decommissioning
Cost Estimation
Intentionally Blank
Intentionally Blank
Intentionally Blank
In the above extract from the removal of a pipeline, each of the Activity Level 1
items (Surveys, Engineering, DSV Support Vessel, etc.) is applied to each
Element (Pipelines, Flowlines, Umbilicals & Cables) i.e. all 10 activities are
carried out for each of the 4 elements.
This form of abbreviation of the hierarchy may occasionally result in some
redundancy, but this is judged to be worth the benefit in brevity.
Supplementary notes providing further explanation of the activities detailed in
the Check List are provided in Appendix 5.
Appendix 1
Abbreviations
Appendix 1
Issue 2, December 2010 13
Guidelines on Decommissioning
Cost Estimation
Intentionally Blank
Appendix 1
14 Issue 2, December 2010
Guidelines on Decommissioning
Cost Estimation
Appendix 2
Definitions of Terms Used in this Guideline
STAGES - LEVEL 1
Preparation (for CoP): The initial stage of decommissioning including
Cessation of Production, DECC approval,
Decommissioning Programme DECC
approval and internal and JV co-venturer
Sanction prior to Cessation of Production.
Wells will often be abandoned after CoP has
been granted. However some wells may be
abandoned earlier prior to CoP approval.
Suspension (Live): This stage can occur immediately after
ceasing production but prior to well plug and
abandonment (P&A) and disconnection and
cleaning. Live Suspension occurs when there
is a delay in the commencement of
decommissioning whilst the facilities are still
live i.e. they have hydrocarbons present. The
facility will still require maintaining as a live
installation.
Well Abandonment: All activities comprising plugging and
abandoning the wells including platform rig
upgrade, mobile rig mob / demob, well scale
and decontamination treatment and
conductor removal.
Cleaning: All activities including shut-down,
depressurisation, making hydrocarbon-free,
disposal of hazardous wastes, flooding of
pipelines, etc.
Appendix 2
Issue 2, December 2010 15
Guidelines on Decommissioning
Cost Estimation
Appendix 2
16 Issue 2, December 2010
Guidelines on Decommissioning
Cost Estimation
Appendix 3
Overall Decommissioning Schematic
Decommissioning
WBS Structure
• Decommissioning • Care and • All activities related to • Depressurization • Closing down of all • Cold Phase or • Make-safe activities. • Offloading. • Establish and carry
method studies for maintenance of a P&A of the wells. hydrocarbon freeing utility and safety Lighthouse Mode, out a monitoring
FOCUS wells and each facility facility that has isolation, purging and systems after well awaiting removal. • Major hookdown • Cleaning and program for the
element. ceased production • Includes platform rig cleaning of the P&A if applicable. activities including handling of site(s) and any
but has yet to be upgrades, well scale process systems. • Typical activities are module separation, hazardous waste. facilities that remain.
• Reservoir studies to decommissioned. and decontamination • Disconnection of maintenance of removal of obstruct-
justify CoP. treatment, conductor • Cleaning and treating process and utility navigational aids, ions in way of rigging, • Deconstruction.
• The facility will still removal, etc. pipelines. pipework, cabling structural integrity refurbishing of
• Preparation of a contain hydro- crossing module and ongoing padeyes etc. • Recycle and/or
Cessation or carbons and is thus • Also includes rig • Early disposal of boundaries, etc. monitoring. disposal.
Decommissioning considered live. contracting activities hazardous waste, etc. • Removal of facility
Plan. as applicable. • Prep. for normal elements and
• Waste accounting unmanned installation transport to disposal
• Internal and • Rigless options. system. (NUI) or minimum site.
stakeholder manned installation
approvals. • Post Production • Post Production (MMI). • Sea bed clean up.
Operations Support. Operations Support.
• Regulatory approval. • Removal of loose
items.
• Cessation of
Production. • Post Production
Operations Support.
• Topside/ Jacket
Surveys.
• Environmental
Impact.
Appendix 3
Issue 2, December 2010 17
Guidelines on Decommissioning
Cost Estimation
Intentionally Blank
Appendix 3
18 Issue 2, December 2010
Guidelines on Decommissioning
Cost Estimation
Appendix 4
Cost Estimating Guidelines
The Oil and Gas UK Cost Estimating Work Book consists of three work sheets
• Basis of Estimate to define the salient facts of the estimate (Appendix
4.1)
• Check list to assist in preparation of the estimate (Appendix 4.2)
• Check list with notes to clarify activities (Appendix 4.3)
Appendix 4
19 Issue 2, December 2010
Guidelines on Decommissioning
Cost Estimation
Appendix 4.1
Facility Information
Asset name:
No. Of Wells ea.
Water Depth m
Topside Weight Mt
No. Of Modules ea.
No. Of Lifts ea.
Jacket Weight Mt
Template weight Mt
Delayed removal
List any items that will not be removed at the same tiem as main facility
e.g. pipeline crossings or subsea tie-in
Ownership
Company %
Details of ownership and % interest
Include details were ownership is different for part of the facilities
Key Assumptions
e.g.
Derogation
Pipelines removed or left in situ
Type of rig Jack-up, Semi, platform, workover
Flotel
Appendix 4
20 Issue 2, December 2010
Guidelines on Decommissioning
Cost Estimation
PM Approval
Client
Well Abandonment
Wells (Final Well Decommissioning)
Platform Wells Engineering
Platform Rig Upgrade
Surveys
Mob-Demob Mobile Rig
Rig Hire
Well Inspection / Survey
Plug & Abandon (Rig or Rigless)
Conductor Cut/Removal (Rig or Rigless)
Transport to Shore
Logistics
LSA Scale treatment & Decontamination
Reuse/Recycle/Disposal
PPOS
Cleaning
Field
Method Studies Engineering
Platform
Topsides Engineering
Jackets Surveys
Hazardous Waste Management
Shutdown & Depressurisation
Isolation
Flushing & Cleaning
Accommodation
Support Vessels
Logistics
Floater
Vessel As for platform
Risers
Subsea
Subsea Structure As for platform
DSV / Vessel
Pipeline
Pipelines Engineering
Flowline Surveys
Umbilical DSV / Vessel
Cable Flushing & Cleaning
Isolation
Logistics
Offshore Loading
Risers Engineering
Offtake Systems Surveys
Mooring Systems Flushing, Cleaning & Flooding
Isolation
Accommodation
Logistics
PM Approval
Client
Appendix 4
Issue 2, December 2010 21
Guidelines on Decommissioning
Cost Estimation
Disconnection
Field
Method Studies Engineering
Platform
Topsides Engineering
Jackets Surveys
GBS Offshore Deconstruction
NUI/MMI Preparation Accommodation
Support Vessels
Modifications
Logistics
Floater
Vessel Engineering
Mooring Systems Surveys
Risers Disconnection
Accommodation
Support Vessels
Logistics
Subsea
Subsea Structure Surveys
Engineering
Logistics
Pipeline
Pipelines Engineering
Flowline Surveys
Umbilical DSV / Vessel
Cable Cut & Recover Spools & Assoc Eqpt
Logistics
Offshore Loading
Risers Engineering
Offtake Systems Surveys
Mooring Systems Disconnection
Accommodation
Logistics
PM Approval
Client
Suspension (Cold)
(NUI / MMI) Field
Field Field Monitoring
PM Approval
Client
Appendix 4
22 Issue 2, December 2010
Guidelines on Decommissioning
Cost Estimation
Removal
Field
Method Studies Engineering
New Technology eg. Removal Studies
Platform
Topsides Surveys
Jackets Engineering
Lifting Preparation
Offshore Deconstruction
Lift Vessel
Transportation Barges
Support Vessels
Accommodation
Debris Clearance
Jacket Post Removal Survey & Trawl
Drill Cuttings
Conductor, Riser, Caisson Removal
Template Removal
Logistics
Floater
Vessel Surveys
Mooring Systems Engineering
Risers Offshore Deconstruction
Anchor Handling
Lift Vessel
Towing Spread
Transportation Barges
Support Vessels
Accommodation
Transport to Shore
Logistics
Debris Clearance
Post Removal Survey & Trawl
Subsea
Subsea Structures Surveys
Engineering
DSV Support
Lift vessel
Transport to Shore
Drill Cuttings
Debris Clearance
Post Removal Survey & Trawl
Logistics
Pipeline
Pipelines Surveys
Flowlines Engineering
Umbilicals DSV Support Vessel
Cable Reel / SJ Lift Vessel
Transport to Shore
Trench & Backfill
Rockdumping
Debris Clearance
Post Removal Survey & Trawl
Logistics
Offshore Loading
Risers Surveys
Offtake Systems Engineering
Mooring Systems Offshore Deconstruction
Lift Vessel
Transportation Barges
Support Vessels
Upending Operations
Transport to Shore
Debris Clearance
Post Removal Survey & Trawl
Logistics
PM Approval
Client
Appendix 4
Issue 2, December 2010 23
Guidelines on Decommissioning
Cost Estimation
Disposal
Field
Method Studies Engineering
Platform
Topsides Inshore Deconstruction
Jacket Offloading
GBS Onshore Deconstruction
Drill Cuttings Reuse/Recycle/Disposal
Hazardous Waste Handling
Resale Value
Scrap Value
Floater
Vessel Inshore Deconstruction
Mooring Systems Offloading
Risers Onshore Deconstruction
Drill Cuttings Reuse/Recycle/Disposal
Hazardous Waste Handling
Resale Value
Scrap Value
Subsea
Subsea Structure Inshore Deconstruction
Wells Offloading
Drill Cuttings Onshore Deconstruction
Reuse/Recycle/Disposal
Hazardous Waste Handling
Resale Value
Scrap Value
Pipeline
Pipelines Offloading
Flowline Onshore Deconstruction
Cable Reuse/Recycle/Disposal
Umbilical Hazardous Waste Handling
Resale Value
Scrap Value
Offshore Loading
Risers Inshore Deconstruction
Offtake Systems Offloading
Mooring Systems Onshore Deconstruction
Reuse/Recycle/Disposal
Hazardous Waste Handling
Resale Value
Scrap Value
PM Approval
Client
Continuing Liability
Field
Field Method Studies
Field Monitoring & Maintenance
Appendix 4
24 Issue 2, December 2010
Guidelines on Decommissioning
Cost Estimation
Suspension (Live)
Including Insurance
Field
Post Cessation of
Production
Field Method Studies
Field Monitoring
PPOS
Cleaning
Field
Method Studies Engineering
Includes Contractor Project Management
Platform
Topsides Engineering Other Surveys may be included in Contractor's
Jackets Surveys Scope under headings below
Hazardous Waste Management
including Radioactive Sources, PCB's, Mercury, LSA and any
Shutdown & Depressurisation Trans-Frontier shipment of Waste.
Isolation
Flushing & Cleaning
Accommodation
Support Vessels Helicopters, Supply Boats,
Onshore Supply Base
Logistics
Floater
Vessel As for platform
Risers
Subsea
Subsea Structure As for platform
DSV / Vessel
Includes Contractor Project Management
Pipeline
Pipelines Engineering
Other Surveys may be included in Contractor's
Flowline Surveys Scope under headings below
Umbilical DSV / Vessel
Cable Flushing & Cleaning
Helicopters, Supply Boats,
Isolation
Onshore Supply Base
Logistics
Offshore Loading Includes Contractor Project Management
Risers Engineering
Offtake Systems Surveys Other Surveys may be included in Contractor's
Mooring Systems Flushing, Cleaning & Flooding Scope under headings below
Isolation
Accommodation
Logistics Helicopters, Supply Boats,
Onshore Supply Base
PPOS Standby Boat
Offshore Operations Support
Includes Offshore Crew
Onshore Support
Maintenance
Fuel
Appendix 4
Issue 2, December 2010 25
Guidelines on Decommissioning
Cost Estimation
Subsea
Subsea Structure Surveys Includes Contractor Project Management
Engineering
Helicopters, Supply Boats,
Logistics
Onshore Supply Base
Appendix 4
26 Issue 2, December 2010
Guidelines on Decommissioning
Cost Estimation
Removal
Field
Method Studies Engineering Other Surveys may be included in Contractor's
Scope under headings below
New Technology eg. Removal Studies
Platform Including Cutting & Lifting Schemes & Contractor Project
Topsides Surveys Management
Jackets Engineering Spreader Beams, Reinforcement, Pad Eyes, Rigging.
Lifting Preparation
Offshore Deconstruction Topsides - Module Separation
Jackets - Cutting & Pile Cuttting
Lift Vessel
GBS - External Metalwork Removal,
Transportation Barges
Support Vessels May include transportation to shore if applicable.
Accommodation Could include Heavy lift, buoyancy techniques, or other
Debris Clearance new emerging technologies
Jacket Post Removal Survey & Trawl
Includes preparation and grillage
Drill Cuttings
Conductor, Riser, Caisson Removal Surveys, Relocation, Removal
Template Removal
Logistics Helicopters, Supply Boats,
Onshore Supply Base
GBS As above plus -
Cell Cleaning
Possible Derogation Reinstate Deballasting systems for Refloating
Pipeline
Other Surveys may be included in Contractor's
Pipelines Surveys Scope under headings below
Consider phasing and scope of Flowlines Engineering
pipeline crossings Umbilicals DSV Support Vessel Includes Contractor Project Management
Cable Reel / SJ Lift Vessel
Transport to Shore Cut & Recover Spool Pieces & Equipment. Mattress
Trench & Backfill Removal.
End protection
Rockdumping
Debris Clearance
Post Removal Survey & Trawl
Helicopters, Supply Boats,
Logistics Onshore Supply Base
Offshore Loading
Other Surveys may be included in Contractor's
Risers Surveys Scope under headings below
Offtake Systems Engineering
Mooring Systems Offshore Deconstruction Includes Contractor Project Management
Lift Vessel
Could include Heavy lift, buoyancy techniques, or other
Transportation Barges
new emerging technologies
Support Vessels
Upending Operations Including Barge Rental, clean up, mob/demob,
Transport to Shore Grillage, Sea Fastening, etc
Debris Clearance
Post Removal Survey & Trawl Helicopters, Supply Boats,
Logistics Onshore Supply Base
Appendix 4
Issue 2, December 2010 27
Guidelines on Decommissioning
Cost Estimation
Disposal
Field Includes Contractor Project Management
Method Studies Engineering
PM Approval
Client
Continuing Liability
Field
Field Method Studies Includes Inspection, Provision of Navaids & Repairs
Field Monitoring & Maintenance
Including Insurance
PM Commercial Setup Costs
Client
Legacy Costs
Appendix 4
28 Issue 2, December 2010
Guidelines on Decommissioning
Cost Estimation
Appendix 5
Supplementary Notes to Checklist
These notes are listed under the relevant Stage and they are intended to clarify
Checklist item contents. It is expected that they will be used as a supplement to
the Checklist which can be added to in order to reflect the up to date
experience of users.
Suspension (Live)
1. PPOS activities will include maintenance and preservation of facilities &
equipment for future use: Cranes, accommodation, walkways, safety
equipment, etc.
Appendix 5
Issue 2, December 2010 29
Guidelines on Decommissioning
Cost Estimation
Well Abandonment
1. Well Engineering includes Contractor Project Management, review of well
files, review of well categorisation (both platform and sub-sea wells).
2. In general, where a workover vessel / rig is necessary for
decommissioning, wells are generally treated, plugged and abandoned
and, where relevant, conductor removed in one mob/demob.
3. Work on wells during the Preparation stage (Rig or Rigless) is included in
case the option to decommission some wells before Cessation of
Production is exercised.
4. Site Preparation for subsea wells includes net removal, leak check, tree
preparation and protective structure check.
Cleaning
1. Disposal routes for the cleaning medium for topsides and pipelines need
to be considered early in the process to identify optimum efficiency and to
maximise use of existing equipment.
2. Hazardous Waste Management should include Radioactive Sources,
PCB's, Mercury, Isocyanates (paint), LSA (Low Specific Activity
radioactivity) and any Trans-Frontier shipment of Waste.
Disconnection
1. Topsides Offshore disconnection includes disconnection from production
systems and module separation. Where single lift is possible scope will
be limited.
2. Gravity Base Structures - Offshore deconstruction includes the
reinstatement of de-ballasting systems if re-floating.
3. In addition to manpower, hire of temporary equipment may be required to
support disconnection activity.
Suspension (Cold)
1. The scope that applies to the suspension of activities with no
hydrocarbons present. PPOS Maintenance includes maintenance and
preservation of facilities & equipment for future use: Cranes,
accommodation, walkways, safety equipment, etc.
Removal
1. Engineering includes cutting and lifting schemes and contractor project
management.
2. Lifting preparation includes supply and installation of spreader beams,
reinforcement, pad eyes and rigging.
Appendix 5
30 Issue 2, December 2010
Guidelines on Decommissioning
Cost Estimation
Disposal
1. Inshore Deconstruction is the partial deconstruction in sheltered waters
prior to onshore disposal of the components.
2. Offloading includes craneage and cost of mobilisation of trailers to the
yard.
3. Reuse / recycle / disposal and Hazardous waste handling should include
the transportation costs.
Continuing Liability
1. Field Monitoring and Maintenance includes provision, inspection and
repairs of navaids (buoys and lights) and inspection of any remaining
pipelines.
2. Client costs include insurance and commercial set up costs (e.g.
redefining Joint Operating Agreements post removal).
Appendix 5
Issue 2, December 2010 31
Guidelines on Decommissioning
Cost Estimation
Intentionally Blank
Appendix 5
32 Issue 2, December 2010
Guidelines on Decommissioning
Cost Estimation
Appendix 6
Regulatory Regime
Appendix 6
Issue 2, December 2010 33