PAT Booklet
PAT Booklet
PAT Booklet
Ministry of Efficiency
Bureau of Energy Power
Government
Ministry ofofPower
India
July 2012
Government of India
Contents
1. Introduction 1
5. PAT Sectors 6
i. Aluminium 6
ii. Cement 7
iv. Fertilizer 12
vii. Textile 19
6. Next Steps 23
7. Conclusion 25
2 Ministry of Power
3. Perform, Achieve and Trade PAT is a market based mechanism to enhance
cost effectiveness of improvements in
Designated Consumers, as notified under the energy efficiency in energy-intensive large
Energy Conservation Act, 2001, account for industries and facilities, through certification
25% of the national gross domestic product of energy savings that could be traded. The
(GDP) and about 45% of commercial energy genesis of the PAT mechanism flows out of
use in India. Since year 2000, industrial GDP the provision of the Energy Conservation
has been growing at the rate of 8.6% annually, Act, 2001, hereinafter referred to as the Act.
whereas energy use in industry is growing at a Section 14 (e) of the Act empowers the Central
comparatively lower growth rate of 5.8%. The Government to notify energy intensive
lower rate of growth of industrial energy use industries, as listed out in the Schedule to
can be attributed to many reasons. It has been the Act, as Designated Consumers (DCs).
observed that in recent years, industry has been The Ministry of Power (MoP) has notified
choosing state-of-the-art technologies, which industrial units and other establishments
are more energy-efficient. Also, there have been consuming energy more than the threshold
many in-house efforts made by the industry in 9 sectors namely Thermal Power Plants,
to become more energy-efficient. In order to Fertilizer, Cement, Pulp and Paper, Textiles,
further accelerate as well as incentivize energy Chlor-Alkali, Iron & Steel, Aluminum and
efficiency, the Perform Achieve and Trade Railways in March, 2007 as DCs.
(PAT) mechanism has been designed.
Aluminium 7500 10
Cement 30000 85
Chlor-alkali 12000 22
Fertilizer 30000 29
Textile 3000 90
Total 478
BEE used steps as mentioned in the diagram different designated consumers having regard
for the implementation of the PAT scheme. to such factors as may be prescribed] the
central government can stipulate energy usage
As per Section 14(g) of EC Act, 2001 [establish norms for designated consumers.
and prescribe such energy consumption
norms and standards for designated BEE had earlier conducted sector specific
consumers as it may be considered necessary: studies through various organizations to do the
provided that the central government may situation analysis. As per the studies, the wide
prescribe different norms and standards for bandwidth of specific energy consumption
4 Ministry of Power
(SEC) within an industrial sector is indicative improvement targets can be based on the trend
of the large energy-savings potential in the of energy consumption and energy-savings
sector. The wide bandwidth is also a reflection potential of the plants. In general, the higher
of the differences in the energy-saving the energy efficiency (or the lower the SEC),
possibilities amongst plants because of their the lower the energy-savings potential. Thus,
varying vintage, production capacity, raw it is evident that it is not feasible to define a
material quality, and product-mix. Such wide single norm/standard unless there is significant
variation also makes it difficult to specify a homogeneity amongst units in a sector.
single benchmark SEC for the sector as a whole: Therefore, the energy efficiency improvement
older plants will find the benchmark impossibly targets fixed are “unit specific”. Each DC is
high if it is set at the level of newer plants; mandated to reduce its SEC by a certain value,
newer plants will find it trivial if it is set at the based on its current SEC (or baseline SEC)
level of older plants. The broad bandwidth within the sectoral bandwidth.
of SEC within a sector, and the inability of all
plants to achieve a sectoral benchmark SEC, The SEC of an industry is calculated based
suggests that SEC improvement norms need on Gate-to-Gate concept with the following
to be set for individual plants. These SEC formula:
and expressed in terms of the metric ton of all energy sources is converted into single unit
oil equivalent (toe)/per unit of product. While i.e. toe (metric ton of oil equivalent) using
calculating the total energy input to the plant, standard engineering conversion formula.
Sector wise Energy consumption and Energy Saving Targets under PAT Cycle-1 (2012-15)
6 Ministry of Power
Specific Energy Consumption and Targets – Aluminium
In aluminium sector, to become a designated national energy saving targets assessed under
consumer the threshold limit is 7500 toe PAT.
and in PAT cycle-I, 10 nos. of designated
consumers from Odisha, Karnataka, ii. Cement
Jharkhand, Chhattisgarh, Maharashtra
and Uttar Pradesh have been identified for India is the second largest cement market
which the target have already been notified. in the world, accounting for about 6% of
Aluminium sector has been categorized on the world’s cement production. Despite its
the basis of their process in to four subsector potential for rapid growth, the per capita
i.e. Refinery, Smelter, Integrated and Cold cement consumption in India accounts for
sheet mill. The total average reported energy 136 kg, which is much lower than the world
consumption of these designated consumers average (396 kg) and the averages of other
is about 7.71 million ton of oil equivalent/year developing countries like Brazil (191 kg) and
in the baseline period (2007-10). By the end of Thailand (366 kg).
the first PAT cycle, the energy savings of 0.456 There are about 148 large cement plants in the
million ton of oil equivalent /year is expected country with an installed capacity of 219.17
to be achieved, which is around 7% of total MTPA and more than 350 mini-cement plants
8 Ministry of Power
Some of the important energy-efficient • Mechanical conveying system in place
technologies that can be adopted in cement of pneumatic conveying
plants are outlined below.
• Effective utilization of compressed air
• Blended cement can be manufactured and avoid idle running of equipment.
from wastes such as slag and fly ash.
• Utilization of waste heat to different
• Vertical Roller Mill (VRM) with high- processes such as drying of raw
efficiency separators and high-pressure materials/coal, pre-heater and cooler
roller press could be utilised. exhaust gases leads to successful
cogeneration as well.
10 Ministry of Power
The threshold limit of 30000 toe has been year 2009-2010 was 23.26 lakh MTPA. The
defined in PAT for cement sector, and 85 nos. production of caustic soda is associated with
of designated consumers have been identified chlorine. This inevitable co-production has
from various States. been an issue for the chlor-alkali industry.
Both products are used for very different end
Cement sector has been categorized on users with differing market dynamics and it is
the basis of their product/process in to only by rare chance that demand for the two
seven subsectors i.e. Portland Pozzolana coincides. The Indian chlor-alkali industry is
Cement(PPC), Ordinary Portland driven by the demand for caustic soda, and
Cement(OPC), Portland Slag Cement (PPC), chlorine is considered a by-product.
Wet Plants, White Plants, Grinding Plants and
only Clinkerization Plants. The total reported Some of the important energy-efficient
energy consumption of these designated technologies that can be adopted in Chlor-
consumers is about 15.01 million ton of oil Alkali plants are outlined below
equivalent ( million toe). By the end of the first
PAT cycle, the energy savings of 0.816 million • Change of membranes & Electrodes re-
ton of oil equivalent /year is expected to be coating
achieved, which is around 12% of total national • Use a centrifugal chlorine compressors
energy saving targets assessed under PAT. in place of multiple liquid seal ( H2
SO4) chlorine compressors
iii. Chlor – Alkali
• Use MEG based chlorine evaporators
The chlor-alkali industry consists of the instead of using steam to supply
production of three inorganic chemicals: chlorine gas to user industry or in-
caustic soda (NaOH), chlorine (Cl2) and soda house consumers
ash (Na2CO3). Caustic soda and chlorine are
produced simultaneously while soda ash is • Optimization of Electrolysers for current
produced during a different process. consumption by monitoring cell voltages
and replacing membranes in time
Chlor-alkali plants are further divided into for 83 % of the total nitrogen production.
two categories i.e. captive based plants and Other nitrogenous fertilizers are ammonium
non-captive i.e. Grid connected plants. Specific sulphate (AS) and calcium ammonium
energy consumption varies from 0.262to 0.997 nitrate (CAN), which are produced in smaller
toe/t of these 22 designated consumers. By the quantities. Among complex fertilizers, di-
end of the first PAT cycle, the energy savings ammonium phosphate (DAP) and various
of 0.054 million ton of oil equivalent /year is grades of NP/NPK are produced. Apart from
expected to be achieved, which is 0.81% of these, single super phosphate (SSP), also
total national energy saving targets assessed contributes to the phosphate production.
under PAT. There are about 141 fertilizer plants in
operation in India. Out of these, 29 units
iv. Fertilizer produce urea, 19 units produce diammonium
phosphate (DAP) and NP/NPK complex
Fertilizer industry in India has grown to its fertilizers, 82 units produce single super
present size during five decades starting phosphate (SSP), 11units produce ammonium
with 1960s. With the total production of sulphate, calcium ammonium nitrate and
about 38.6 Million Tons (MT) of fertilizer ammonium chloride. The addition of urea
products containing 16.5 Mt of plant nutrients capacity remained unchanged since 1999.
(N + P2 O5), India is the second largest
producer of fertilizers in the world. India
with consumption of 28.12 MT of nitrogen
(N), phosphate (P) and potash (K) is the
third largest consumer of fertilizers in the
world. Fertilizer industry in India is world
class in terms of size of plant, technology
used and efficiency levels achieved. India
produces both nitrogenous and phosphatic
fertilizers with installed capacity of 12.947
MT nitrogen and 6.201 MT of P2 O5. Urea is
the major nitrogenous fertilizer and accounts
12 Ministry of Power
India is completely dependent on import of nitrogenous fertilizers. Globally, over
of potassic fertilizers mainly as potassium 80% of all ammonia manufactured is used
chloride. India produced about 22 MT urea in the production of nitrogenous fertilizers,
in 2010-11. About 18 MT urea was produced and urea is the main nitrogenous fertilizer
using gas as feedstock, while balance about 4 manufactured in India. The feedstocks used
MT is produced using naphtha and fuel oil as for ammonia production are natural gas,
feedstock. naphtha, and fuel oil. Coal based units have
been closed due to non-economic viability and
Among all the processes in the fertilizer high specific consumption levels. Among the
industry, production of nitrogenous fertilizers feedstock, natural gas-based fertilizers are the
is the most energy intensive. Ammonia is most energy efficient, followed by naphtha-
used as the basic chemical in the production based fertilizers.
14 Ministry of Power
v. Iron and Steel as compared to the previous year. In 2003/04,
an average growth of 7.3% in the production of
The Indian iron and steel industry can be
total finished steel was registered. The domestic
broadly categorized into integrated steel
consumption of the total finished steel declined
producers and secondary steel producers.
marginally (by 0.53%) at 51.85 MT. India
Integrated steel producers have traditionally
exports about 3.75 MT of finished steel, which
integrated steel units with captive plants
has decreased by 26%, while imports were
for iron ore and coke, which are the main
estimated at 5.77 MT, a decline of 18%.
inputs. Secondary producers use steel scrap,
sponge iron/ direct reduced iron (DRI) or
hot briquetted iron (HBI) as raw materials. It
mainly comprises electric arc furnace (EAF)
units and induction furnace units, apart from
other manufacturing units like independent
hot and cold rolling units, rerolling units,
galvanizing and tin plating units, sponge iron
producers, pig iron producers, and so on.
Indian steel plants have undertaken several • Installation of top gas recovery
energy efficiency improvement measures to turbines in blast furnaces.
reduce overall manufacturing costs. Some • Use of non-coking coal in iron making.
16 Ministry of Power
Specific energy consumption varies from capacity of 1.1 MT have been closed.
0.0527 to 1.907 toe/t for these 67 designated
consumers. By the end of the first PAT cycle,
the energy savings of 1.486 million ton of oil
equivalent /year is expected to be achieved,
which is around 22% of total national energy
saving targets assessed under PAT.
18 Ministry of Power
In Pulp & paper sector, to become a include the spinning mill or the composite
designated consumer the identified threshold mill. The decentralized power-loom/hosiery
limit is 30,000 toe and in first PAT cycle 31 and knitting sectors form the largest section
designated consumers from various states of the textile industry. The major sub-sectors
have been identified for which the target have of the Indian textile industry consist of the
already been notified. Pulp & paper sector organized cotton/man-made fibre textiles
has been categorized on the basis of their mill industry, man-made fibre/filament
Raw material in to three subsectors i.e. Wood yarn industry, wool and woolen textiles
based ,Agro based, and Recycled fiber based industry, sericulture and silk textiles industry,
(RCF). The total reported energy consumption handlooms, handcrafts, jute and jute textiles
of these designated consumers is about 2.08 industry, and textile exports.
million ton of oil equivalent.
20 Ministry of Power
In Textile sector, to become a designated viii. Thermal Power Plants
consumer, the threshold limit is 3000 toe and
India is the sixth largest in terms of power
in first PAT cycle 90 designated consumers
generation. About 65% of the electricity
from various states have been identified for
consumed in India is generated by thermal
which the target have already been notified.
power plants, 22% by hydroelectric power
Textile sector has been categorized on the
plants, 3% by nuclear power plants and rest
basis of their process in to four sub sector i.e.
10% from other alternate sources like solar,
Spinning, Processing, Composite & Fiber. The
wind, biomass etc. 53.7% of India’s commercial
total reported energy consumption of these
energy demand is met through the country’s
designated consumers is about 1.20 million
vast coal reserves. The country has also
ton of oil equivalent/year.
invested heavily in recent years on renewable
Textile plants are further divided into two sources of energy such as wind energy. As of
categories i.e. captive power plant based April 2012, India’s installed Renewable energy
plants and non-captive i.e. grid connected generation capacity stood at about 24,503 MW.
plants. Specific energy consumption varies
Due to India’s economic rise, the demand for
from 0.199 to 5.2 toe/t across the sector except
energy has grown at an average of 3.6% per
couple of outliers. By the end of the first PAT
annum over the past 30 years. At the end of
cycle, the energy savings of 0.066 million
April 2012, the installed power generation
ton of oil equivalent /year is expected to be
capacity of India stood at 2,01,637 MW, while
achieved, which is 0.99% of total national
the per capita energy consumption stood at
energy saving targets assessed under PAT.
813.5 kWh (2010-11).
22 Ministry of Power
Specific energy consumption (net heat rate) designated consumer, over and above the
varies from 1774 kcal/kWh to 5134 kcal/kWh target savings. Each certificate will be unique
for these 144 designated consumers. tradable commodity which will be traded in
two exchanges i.e. Indian Energy Exchange
(IEX) and Power Exchange of India (PXIL).
6. Next Steps First ESCert will be issued after completion of
one financial year in 2013-14. For the issuance
An ESCert will be an instrument issued by
of ESCerts and compliance of PAT scheme,
Ministry of Power/BEE for a one ton of oil
following time lines needs to be followed by
equivalent of energy savings achieved by the
each designated consumer.
After submission of Form 1 and Form A, B to BEE within 3 months from the last day of
the Designated Consumer has to hire an the financial year. This process is mandatory
accredited energy auditor, from the list of BEE after the last financial of the cycle, whereas
empanelled accredited energy auditors for the designated consumer can submit these
verification of these forms. Accredited energy documents after verification in the voluntary
auditor will verify Form 1 and Form A and phase for issuance of ESCerts.
submit certificate of verification through Form
24 Ministry of Power
The Rules for the PAT scheme were notified mechanism. The 478 designated consumer
by the Central Government on 30th March, plants offer an energy saving potential of
2012 and provides complete mechanism to 6,686,000 ton of oil equivalent/year(6.686
be followed by the designated consumer. The million toe/year) at the end of first phase of
notifications of the targets and the Rules are PAT Cycle (2012- 2015).
available at www.bee-india.nic.in
PAT is one of the most promising initiatives
to achieve the goal by implementing Best
7. Conclusion Available Practices and Technologies in the
identified sectors through economical viable
Introduction of Perform, Achieve and Trade projects. Broader implementation of sectoral
Scheme for Energy Intensive Industries crediting mechanisms could ensure that
improves energy efficiency and facilitates low‐carbon technologies are also used more
cost effectiveness by certifying energy saving widely, which in turn would encourage Indian
that could be traded due to its market based industries to invest in these technologies.
SECTOR TABLE
(i) Aluminum
S. No. Designated consumer Baseline energy Energy
consumption norms and consumption
standards in metric ton of norms and
oil equivalent (TOE) per standards in
unit of product for the metric ton of
baseline year (average of oil equivalent
three years). (TOE) per unit
of product for
target year.
(1) (2) (3) (4)
Name, Address and State Specific Product Specific energy
energy Output consumption
consumption (Ton) (TOE/Ton of
(TOE/Ton of product)
product)
1 Hindalco Industries Limited 0.241 376733 0.231
Post Bag-1, Belgaum, Pin-590010
Karnataka
2 Vedanta Aluminium Ltd 0.322 762195 0.304
P. O. Lanjigarh , via Biswanathpur
Dist .- Kalahandi, Pin-766027
Odisha
26 Ministry of Power
(1) (2) (3) (4)
28 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Specific energy Product Specific energy
consumption Output consumption
(TOE/Ton of (Ton) (TOE/Ton of
product) product)
8 Gujarat Alkalies and Chemicals Ltd. 0.262 266,402 0.249
At & PO: Dahej, Taluka: Vagara,Dist.
Bharuch, 392130
Gujarat
9 Gujarat Alkalies and Chemicals Ltd. 0.277 179,708 0.262
P.O. Petrochemicals, Dist. Vadodara,
391346
Gujarat
10 Gujarat Fluorochemicals Ltd. 0.286 54,736 0.271
Plot No: 12/A, Dahej GIDC Complex,
Vagra, Bharuch - 392130
Gujarat
11 Heavy Chemicals Division, TPL 0.571 60,682 0.548
Manali Express Highway, Chennai-68
Tamil Nadu
12 ABCIL Renukoot Chemical Div. 0.347 96,637 0.324
(Kanoria Chemicals and Industries
Ltd.)
P.O. Renukoot , Sonebhadar
Uttar Pradesh
13 Lords Chloro Alkali Ltd. 0.450 45,329 0.412
SP-460, M.I.A., Alwar, 301030
Rajasthan
14 Meghmani Finechem Ltd. 0.967 61,796 0.902
CH-1, CH-2; Dahej Industrial Estate,
Vill: Dahej, Ta: Vagra, Dist: Bharuch,
392130
Gujarat
15 Punjab Alkalies & Chemicals Ltd. 0.319 88,959 0.299
Nangal Una Road, Naya Nangal,Dist.
Ropar, 140126
Punjab
30 Ministry of Power
(iii) Textile
32 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Specific energy Product Specific energy
consumption output consumption
(TOE/T of (Ton) (TOE/T of
product) product)
16. Birla Cellulosic 1.080 76854 1.018
Birladam, Kharach, Kosamba(RS),
Bharuch, 394120
Gujarat
17. Birla Textile Mills (A Div. of Chambal 0.489 20175 0.464
Fertiliser & Chemicals Ltd.)
Sai road, Baddi, Dist-Solan, 173205
Himachal Pradesh
18. Bombay Rayon Fashions Ltd 2.298 6874 2.167
Doddaballa pura Area, Banglore
Karnataka
19. BSL LIMITED(Processing Division) 0.762 9446 0.716
PB no-16, Mandpum, Bhilwara,
311001
Rajasthan
20. BSL Limited 0.736 5058 0.697
PB no-17, Mandpum, Bhilwara,
311001
Rajasthan
21. BTM Industries Ltd. 0.811 6493 0.797
13 km stone, Vill-Pur, Gangapur
road, Bhilwara
Rajasthan
22. Century Enka Limited 1.055 22849 0.995
MIDC, Bhosari, Dist. Pune, 411026
Maharashtra
34 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Specific energy Product Specific energy
consumption output consumption
(TOE/T of (Ton) (TOE/T of
product) product)
32. J. C. T. Limited Phagwara 4.577 6513 4.196
G.T. Road, Phagwara, 144401
Punjab
33. Janki Corp Limited 0.596 15230 0.568
Mandpiya Choraha, Chittor road,
Bhilwara
Rajasthan
34. Jawahar Shetkari Sahakari Soot Girni 0.346 10292 0.327
Ltd
Hutatma Shirishkumar nagar,
Morane pr.L, Dist -Dhule, 424001
Maharashtra
35. Kanchan India Ltd. 0.714 13212 0.674
Pur-road, Bhilwara
Rajasthan
36. Kumar Cotton Mills Pvt. Ltd. 5.220 2700 4.667
SI No-108/1, BD, Narol Court, Narol,
Ahmedabad, 382402
Gujarat
37. L.S.Mills Ltd., ‘B’ 0.658 5447 0.626
B unit, Cumbum road, Muthu
Thevandatty, Theni, Dist. Madurai
Tamil Nadu
38. Loyal Textile Mills Ltd. 0.395 14689 0.384
21/4 Mills Street, PB no-1, Kovilpatti,
628501
Tamil Nadu
39. M/s Grasim Bhiwani Textiles Ltd. 2.448 10946 2.341
Unit: Bhiwani Textile Mills & Elegant
Spinners
PB No-#4, BTM road, Bhiwani, 127021
Haryana
36 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Specific energy Product Specific energy
consumption output consumption
(TOE/T of (Ton) (TOE/T of
product) product)
48. Nahar Spinning Mills Ltd. 0.681 10220 0.634
Village-Simrai, Mandideep, Dist-
Raisen, 464992
Madhya Pradesh
49. Nitin Spinners Limited 1.349 23531 1.216
16-17 km stone, Chittor road,
Hamirgadh, Dist-Bhilwara, 311025
Rajasthan
50. Orient Syntex (Prop: APM Industries 0.788 13379 0.723
Ltd.)
SP-147, industrial area, Bhiwadi, Dist.
Alwar
Rajasthan
51. PBM Polytex Limited 0.743 6745 0.686
Opp Station, Petlad, Dist-Anand,
388450
Gujarat
52. Pee Vee Textiles Ltd. 0.272 20090 0.267
N.H. 07, Post-Jam, Tal- Samudrapur,
Dist-Wardha, 442305
Maharashtra
53. Priyadarshini Sahakari Sootgirni 0.301 19655 0.291
At-Tande, Shirpur-Chopara road,
Shirpur, Dist. Dhule, 425405
Maharashtra
54. RSWM Ltd Unit Mandpam 0.946 7128 0.852
PB no-13, Chittorgarh road,
Mandpum, Bhilwara, 311001
Rajasthan
55. Ranjan Processors (A Unit of Ranjan 0.651 10250 0.617
Polyster Ltd.)
11-12 km stone, Vill- Guwardi,
Chittor road, Bhilwara
Rajasthan
38 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Specific energy Product Specific energy
consumption output consumption
(TOE/T of (Ton) (TOE/T of
product) product)
64. Ronak Processors (P) Ltd. 0.924 7047 0.856
G-138 to 142, 4th phase, Riico
industrial area, Bhilwara
Rajasthan
65. RSWM Limited, Ringas 0.533 7539 0.503
SP-1, industrial area, Ringas, 332404
Rajasthan
66. RSWM Ltd 0.598 20257 0.561
PB no-28, Kharigram, Gulabpura,
Bhilwara
Rajasthan
67. RSWM Ltd 0.865 14072 0.787
Rishabhdev, Udaipur Dist, 313802
Rajasthan
68. RSWM Ltd 2.175 2536 2.090
PB No-34, Vill-Lodha, Banswara,
327001
Rajasthan
69. RSWM LTD. (Fabric Div.) 1.688 2520 1.637
LNJ Nagar, Mordi, PB no-28, Dist-
Banswara, 327001
Rajasthan
70. Sangam (India) Ltd., (Processing, 0.908 10514 0.847
Flock & Weaving Division)
Outside Octroi post, Vill-Atun,
Chittorgarh road, Bhilwara, 311001
Rajasthan
71. Sanghi Spinners India Limited 0.402 11244 0.375
Post-Sanghi Nagar, Mandalhayath
Nagar, Ranga Reddy (Dist.), 501511
Andhra Pradesh
40 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Specific energy Product Specific energy
consumption output consumption
(TOE/T of (Ton) (TOE/T of
product) product)
80. Swastika Suitings Ltd 0.770 6190 0.723
7-14 industrial area, Pur road,
Bhilwara
Rajasthan
81. The Bombay Dyeing & 1.287 7280 1.253
Manufacturing Co. Ltd.
B-28, 5 star, MIDC, Ranjangaon, Tal.
Shirur, Dist.Pune, 412220
Maharashtra
82. The Bombay Dyeing & Mfg. Co. Ltd. 0.202 126560 0.191
Plot no-1, Industrial area, MIDC,
Patalganga, Tal. Khalapur, Dist.
Raigad, 410220
Maharashtra
83. TPL Industries Limited 11/12 km, 0.592 8901 0.564
Chittor road, Guwardi, Bhilwara,
311001
Rajasthan
84. Valli Textile Mills 0.293 14292 0.287
A unit of Loyal Textile Mills Ltd.,
N.Venkateshwara Puram, Post-
Sathur, 626205
Tamil Nadu
85. Vardhman Fabrics (Unit of 3.222 18940 3.036
Vardhman Textiles Limited)
Vill-Plikarar Talpura Rehti road,
Tehsil-Budhni, Dist. Sehore, 466441
Madhya Pradesh
86. Vardhman Spinning & General Mills 0.396 22081 0.384
Chandigarh road, Ludhiana, 141011
Punjab
42 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Specific energy Product Specific energy
consumption output consumption
(TOE/T of (Ton) (TOE/T of
product) product)
3 Tamil Nadu News Print and Papers 0.572 248461 0.550
Limited
Kagithapuram, Gram Newsprint,
Dist- Karur, Pin-639136
Tamil Nadu
4 Century Pulp and Paper 0.591 258965 0.568
Ghansyamdham, Lalkua, Dist.
Nainital, Pin-262402
Uttarakhand
5 JK Paper Ltd 0.601 96110 0.577
Unit: CPM, PO Central Pulp Mills,
Fort Songadh, Dist-Tapi, Pin-394660
Gujarat
6 BILT Graphic Paper Products Ltd. 0.609 137090 0.584
P.O. Ballarpur Paper Mills., Dist-
Chandrapur, Pin-442901
Maharashtra
7 Star Paper Mills Limited 0.636 70755 0.609
B.D. Bajoria Road, Saharanpur, Pin-
247001
Uttar Pradesh
8 The Andhra Pradesh Paper Mills 0.655 94096 0.627
Limited
Unit APPM, Rajahmundry, Pin-
533105
Andhra Pradesh
9 The West Coast Paper Mills Ltd. 0.218 172404 0.215
P.B. No. 5, Bangur Nagar, Dandeli,
Pin-581325
Karnataka
10 Seshasayee Paper and Boards Limited 0.684 120693 0.652
Pallipalayam, Erode, Pin-638007
Tamil Nadu
44 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Specific energy Product Specific energy
consumption output consumption
(TOE/T of (Ton) (TOE/T of
product) product)
20 Hindustan Newsprint Limited 0.660 108221 0.623
Kottayam
Kerala
21 Emami Paper Mills Limited 0.555 103931 0.528
Balgopalpur, Post-Rasulpur, Balasore,
Pin-756020
Odisha
22 Rama Newsprint and Papers Ltd., 0.616 123273 0.584
Village Barbodhan, Taluka Olpad,
Dist- Surat, Pin-395005
Gujarat
23 NEPA Limited 0.861 41522 0.797
Nepanagar, Dist. Burhanpur, Pin-
450221
Madhya Pradesh
24 ITC Ltd. , Kovai 0.348 89085 0.341
Thekkampatty Village,
Mettupalayam, Coimbatore, Pin-
641113
Tamil Nadu
25 Shree Bhawani Paper Mills Limited 1.402 20852 1.293
Industrial Area One, Sultanpur Road,
RaiBareili, Pin-229010
Uttar Pradesh
26 ABC Paper Ltd. 0.498 55039 0.481
Village Sailakhurd , Dist- Hoshiarpur
Punjab
27 Sukhumbari Straw Products Ltd. 0.518 74321 0.500
32 KM, Chanduasi Road, Village-
Devri, Dist- Moradabasd, Pin-
Uttar Pradesh
46 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Specific energy Product Specific energy
consumption output consumption
(TOE/T of (Ton) (TOE/T of
product) product)
4 SAIL, Bokaro Steel Plant 0.643 3766642 0.605
Ispat Bhawan, Bokaro steel city
Jharkhand
5 Bhilai Steel Ltd 0.632 5116000 0.595
Bhilai
Chhattisgarh
6 Tata Steel Limited 0.646 5741167 0.607
Bistupur, Jamshedpur
Jharkhand
7 Durgapur Steel Plant 0.663 1905000 0.623
Durgapur, Burdwan
West Bengal
8 JSW 0.663 2610000 0.622
Nagpur
Maharashtra
9 Jindal Steel & Power Limited 0.724 1653775 0.676
Post Box No. 16, Kharsia Road,
Raigarh
Chhattisgarh
10 SAIL, Burdwan 0.818 424935 0.757
Burnpur near Asansol, Dist-Burdwan,
West Bengal
11 Tata Sponge Iron Limited 0.581 359333 0.551
P.O. Joda, Dist- Keonjher
Odisha
12 Hare Krishna Metallics Ltd. 0.589 81271 0.557
Plot No.20, Kashan kandi road,
Village & Post Hirebaganal
Karnataka
13 Gopani Iron & Power Pvt Ltd. 0.626 86820 0.590
A-22 MIDC Growth Centre, Tadali,
Chandrapur
Maharashtra
48 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Specific energy Product Specific energy
consumption output consumption
(TOE/T of (Ton) (TOE/T of
product) product)
22 Welspun Steels Ltd. 0.592 134450 0.562
Welspun City, Survey No.650/652,
Village-Versamedi TA-Anjar (Kutch)
Gujarat
23 BMM Ispat Ltd. 0.637 176186 0.602
114, Danapur Village, Hospet Taluk,
Dist-Bellary
Karnataka
24 Monnet ISPAT & Energy Ltd. 0.693 316508 0.652
Monnet Marg Mandir, Hasoud,
Raipur
Chhattisgarh
25 Anjani Steel Ltd. 0.704 104391 0.662
Athagarh, Cuttack
Odisha
26 Top Worth Iron & Steel Pvt Ltd. 0.736 111420 0.691
Borai Industrial Growth Centre,
Village Rasmada, Durg
Chhattisgarh
27 Crest Steel & Power Pvt Ltd 0.739 74208 0.693
Village:Joratari, post:Mangatta,
Dist:Rajnandgaon
Chhattisgarh
28 Goa Sponge & Power ltd. 0.750 100126 0.703
Survey No. 58/59/60, village Santona
Goa
29 Gallent Metal Limited 0.752 147899 0.704
Near Toll Gate, Village - Samakhyali,
Taluka - Bhachau, Kutch
Gujarat
30 Nalwa Steel & Power Ltd 0.775 220856 0.724
Gharghoda Road, Taraimal, Raigarh
Chhattisgarh
50 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Specific energy Product Specific energy
consumption output consumption
(TOE/T of (Ton) (TOE/T of
product) product)
40 Indian Metal & Ferro Alloys 0.766 133673 0.725
P.O.KaliaPani, Sukinda, Jajpur
Odisha
41 Navabharat Ventures Ltd. 1.140 30640 1.050
Khadagprasad Meramandali Rly
Station, Dist:-Dhenkanal
Odisha
42 Balasore Alloys Limited 0.326 83936 0.306
Balgopalpur, Balasore
Odisha
43 Sunflag Iron & Steel Co. Ltd 0.235 797322 0.226
Bhandara Road, Nagpur
Maharashtra
44 Neelachal ISPAT Nigam Limited 0.297 2873603 0.283
Kalinga Nagar Industrial Complex,
Duburi, Jajpur
Odisha
45 ISPAT Industries Ltd. 0.469 249000 0.446
Gitapuram, Dis-Raigadh
Maharashtra
46 Jayaswal Neco Industries Ltd. 0.502 501713 0.461
Siltara Growth Centre, Siltara, Raipur
Chhattisgarh
47 JSW Ltd. 0.0527 624860 0.0511
Vasind
Maharashtra
48 VISA Steel Ltd. 0.551 694534 0.501
Kalinganagar Industrial complex
Odisha
49 Action ISPAT & power Pvt. 0.597 103318 0.567
Jharsuguda
Odisha
52 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Specific energy Product Specific energy
consumption output consumption
(TOE/T of (Ton) (TOE/T of
product) product)
59 Hariyana steel and power Ltd 0.738 45544 0.688
Kanchanahalli, Sathenahalli Post,
Shantugrana Hobli, Hassan TQ.
Karnataka
60 Aarti Steels Pvt. Ltd. 0.790 145758 0.743
Ghantikhal, PO:Mahakalabasta, Via-
Athagarh, Dist:Cuttack
Odisha
61 Usha Martin Limited 0.238 624301 0.229
PO.147, Jamshedpur, Phase V,
Aditya Indutrial Area, Gamharia,
Dist:Saraikela
Jharkhand
62 M/S Mukund Ltd. 0.079 406934 0.077
Thane- Belapur road, Dighe Kalwa
Maharashtra
63 Orrisa Sponge Iron & Steel limtied 0.685 119441 0.645
P.o : Palaspanga, DIST : Keonjhar
Odisha
64 SKS ISPAT & Power Limited 0.981 183667 0.932
Village:Siltara, Raipur
Chhasttisgarh
65 Adhunik Metaliks Limited 0.764 290533 0.741
Chadrihariharpur, Dist Sundergarh
Odisha
66 Visvesvaraya Iron and Steel Plant 1.187 136000 1.132
Bhadravathi, Shimoga
Karnataka
67 Llyods metals & Energy Limited 0.609 184742 0.575
Plot No. A 1-2, , M I D C Area,
Ghugus; Chandrapur
Maharashtra
54 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Specific energy Product Specific energy
consumption output consumption
(TOE/T of (Ton) (TOE/T of
product) product)
7 RCF, Thal 0.391 1839342 0.366
Rashtriya Chemicals & Fertilizers Ltd.
(Thal Unit), Tal Alibag, Dist Raigad
-Pin Code -402208
Maharashtra
8 KRIBHCO Hazira 0.340 1754549 0.323
Krishak Bharati Cooperative Ltd,
P.O. KRIBHCO NAGAR, Dist Surat ,
Pin Code- 394515,
Gujarat
9 NFL, Vijaipur - I 0.328 881318 0.319
National fertilizers Ltd, Vijaipur
Dist: Guna , Pin code: 473111
Madhya Pradesh
10 NFL, Vijaipur - II 0.298 918058 0.295
National fertilizers Ltd, Vijaipur
Dist: Guna, Pin code: 473111
Madhya Pradesh
11 RCF, Trombay -V 0.497 306905 0.487
Rashtriya Chemicals & Fertilizers
Ltd.,(Trombay). Mahul Road
Chembur, Mumbai ,Pin Code: 400074
Maharashtra
56 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Specific energy Product Specific energy
consumption output consumption
(TOE/T of (Ton) (TOE/T of
product) product)
20 CFCL, Gadepan - I 0.312 977947 0.309
Chambal Fertlizers and Chemicals
Ltd.
P.O :Gadepan , Dist. Kota, Pin Code:
325208
Rajasthan
21 NFCL Kakinada - I 0.303 761280 0.300
Nagarjuna Fertilizers & Chemicals
Ltd ,
Nagarjuna Road, Kakinada East
Godavari District Pin Code – 533003
Andhra Pradesh
22 IFFCO, Aonla - II 0.300 1002626 0.297
Indian Farmers Fertilizer Co-
Operative IFFCO Aonla unit,
P.O IFFCO Township , Bareilly Pin
Code - 243403
Uttar Pradesh
23 CFCL Gadepan -II 0.299 1005027 0.296
Chambal Fertilizers and Chemicals
Ltd.
Gadepan , Dist. Kota, Pin Code:
325208, Rajasthan
24 TCL, Babrala 0.268 1107238 0.265
Tata Chemicals Ltd,Babrala
Indira Dham, Babrala Dist -Budaun ,
Pin Code - 242021, Uttar Pradesh
25 IFFCO Aonla - I 0.317 954258 0.314
Indian Farmers Fertilizer Co-
Operative Ltd IFFCO Aonla unit
P.O IFFCO Township , Bareilly Pin
Code – 243403
Uttar Pradesh
58 Ministry of Power
(vii) Cement
60 Ministry of Power
(1) (2) (3) (4)
62 Ministry of Power
(1) (2) (3) (4)
64 Ministry of Power
(1) (2) (3) (4)
66 Ministry of Power
(1) (2) (3) (4)
68 Ministry of Power
(1) (2) (3) (4)
70 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Net Heat Net Product Net Heat Rate
Rate (Kcal/ Output (Kcal/KWH)
KWh) (Million Units)
6 NTPC Ltd. Ramagundam Super 2520 19990 2498
Thermal Power Station
P.O. Jyothi nagar, Dist. Karim
Nagar-505215
Andhra Pradesh
7 NTPC-Simhadri 2490 7820 2468
Vishakhapatanam-531020
Andhra Pradesh
8 Ramagundam Thermal Power 2885 446 2885
Station Ramagundam
Dist. Karim Nagar - 505208
Andhra Pradesh
9 Rayalaseema Thermal Power 2529 5804 2522
Project
V.V. Reddy nagar, Kadapa Dist.
- 516312
Andhra Pradesh
10 Reliance Smalakot Thermal 2106 1213 2080
Power Station
IDA Peddapuram, Samalkot
Andhra Pradesh
11 Spectrum Power Generation 2123 1452 2117
Ltd., East Godavari
Uppada beach Road, Kakinada
-533448
Andhra Pradesh
12 Vijaywada (Dr. Narla Tata Rao) 2571 9074 2566
Thermal Power Station
Ibrahimpatnam, Krishna Dist. -
521456
Andhra Pradesh
13 Kathalguri Gas Based Power 2683 1714 2561
Plant , NEEPCO
AGBP, NEEPCO Ltd, Bokuloni
Chariali, Dibrugarh - 786191
Assam
72 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Net Heat Net Product Net Heat Rate
Rate (Kcal/ Output (Kcal/KWH)
KWh) (Million Units)
22 Korba (East) Thermal Power 3334 2773 3199
Station
Korba East , Dist. Korba - 495677
Chhattisgarh
23 NTPC Ltd-Korba 2526 16722 2515
Vikas Bhawan, Jamnipali, Korba
- 495450
Chhattisgarh
24 NTPC Ltd-Sipat 2491 5877 2484
P.O. Ujjwal Nagar, Dist.
Bilaspur-495555
Chhattisgarh
25 NTPC SAIL Power Co. Pvt. Ltd. 2741 3178 2704
(500 MW)
Joint Venture of NTPC & SAIL,
Purena , Bhilai East-490021
Chhattisgarh
26 R R Energy Ltd., Raigarh 4084 105 3985
NH-200, Jharsuguda Road,
Near KIT College, Garhumaria,
Raigarh-496001
Chhattisgarh
27 Indraprastha Gas Turbine 2815 1308 2649
Power Station
Indraprasth Power Generation
Co. Ltd, IP Estate, Ring road ,
New Delhi-110002
Delhi
28 NTPC Ltd-Badarpur 2988 4897 2942
Badarpur, New Delhi, 110044
Delhi
29 Pragati Power Station - 1 2068 2352 2061
IP Estate, Ring Road, New
Delhi-110002
Delhi
74 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Net Heat Net Product Net Heat Rate
Rate (Kcal/ Output (Kcal/KWH)
KWh) (Million Units)
76 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Net Heat Net Product Net Heat Rate
Rate (Kcal/ Output (Kcal/KWH)
KWh) (Million Units)
50 Panipat Thermal Power Station - I 3060 2892
HPGCL, Assandh Road, Vill.
Assandh, Panipat-132105
Haryana
51 Yamuna Nagar Thermal Power 2878 2836
Station
Yamuna Nagar
Haryana
52 Bokaro Thermal Power Station, 3560 3180 3374
Damodar Valley Corporation
BTPS “B”, Bokaro Thermal, P.O.
Bokaro-829107
Jharkhand
53 Chandrapura Thermal Power 3188 2120 3038
Station , Damodar Valley
Corporation
Bokaro Dist.
Jharkhand
54 Jojobera Power Plant (TATA 2977 2649 2908
power Co.)
P.O. Rahargora,
Jamshedpur-831016
Jharkhand
55 Patratu Thermal Power Station 3534 992 3438
Hazaribagh
Jharkhand
56 Tenughat Thermal Power 2936 1850 2899
Station, TVNL
TVNL, Bokaro
Jharkhand
57 Bellary Thermal Power Station 3123 2694 2930
Kudathini, Bellary Dist. -583115
Karnataka
78 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Net Heat Net Product Net Heat Rate
Rate (Kcal/ Output (Kcal/KWH)
KWh) (Million Units)
66 NTPC Ltd - Kayamkulam (Rajiv 1994 2016 1988
Gandhi Combined Cycle Power
Plant)
P.O. Choolatharuvu, Dist.
Alappuzha-690506
Kerala
67 Amarkantak Thermal Power 3498 1662 3354
Station, Chachai, (Phase II + III)
Chachai
Madhya Pradesh
68 NTPC Ltd -Vindhyachal 2532 24892 2521
Vindhya Nagar, Dist.
Singrauli-486885
Madhya Pradesh
69 Sanjay Gandhi Thermal Power 3402 7138 3192
Station
MPPGCL, Birsinghpur , Dist
Umaria-484552
Madhya Pradesh
70 Satpura Thermal Power Station 3681 6408 3444
MPPGCL, Sarni
Madhya Pradesh
71 Bhusawal Thermal Power 3218 2801 3107
Station, MAHAGENCO
Deep Nagar, Tah. Bhusawal,
Dist. Jalgaon-425307
Maharashtra
72 Chandrapur Super Thermal 2920 13942 2827
Power Station , MAHAGENCO
Urja Nagar, Chandrapur-442404
Maharashtra
73 Dahanu Thermal Power Station 2535 2523
Thane Dist- 401608
Maharashtra
80 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Net Heat Net Product Net Heat Rate
Rate (Kcal/ Output (Kcal/KWH)
KWh) (Million Units)
81 Trombay Thermal Power 2570 2547
Station (Coal & Oil ) (Tata
Power Company )
Chambur-400074
Maharashtra
82 Uran Gas Power Station, 2046 2038
Mahagenco
Raigarh-400702
Maharashtra
83 IB Thermal Power Station, 2708 2699
Orissa Power Gen. Co. Ltd
Jharsuguda-768234
Odisha
84 NTPC Ltd -Talcher Kaniha 2492 22389 2480
P.O. Deepsika, Angul-759147
Odisha
85 NTPC Ltd-Talcher Thermal , 3196 3259 3130
Angul
P.O. Talcher, Angul-759101
Odisha
86 Puducherry Gas Power Plant 2699 236 2697
(Puducherry Power Corporation
Ltd.)
Puducherry
Puducherry
87 Guru Gobind Singh Super 2922 9008 2830
Thermal Power Station, Ropar
Roop Nagar- 140113
Punjab
88 Guru Hargobind Thermal 2672 7033 2637
Power Plant, Lehra Mohabbat
Dist. Bathinda-151111
Punjab
82 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Net Heat Net Product Net Heat Rate
Rate (Kcal/ Output (Kcal/KWH)
KWh) (Million Units)
98 Ennore Thermal Power Station 3891 1563 3682
Chennai
Tamil Nadu
99 GMR Energy Ltd, Chennai 2047 1214 2047
Basin Bridge , Chennai -600012
Tamil Nadu
100 Kuttalam Gas Turbine Power 2170 450 2067
Station
Nagapattanam
Tamil Nadu
101 Lanco Tanjore Power Co.Ltd, 2127 777 2127
ABAN Power Co.Ltd
Karuppur, Thanjabur Dist.
Tamil Nadu
102 Madras Aluminum Company 3624 686 3470
Salem
Tamil Nadu
103 Madurai Power Corporation Pvt 2141 547 2141
Ltd.
Samayanallur, Madurai-625402
Tamil Nadu
104 Mettur Thermal Power Station, 2739 5982 2715
Salem
Tamil Nadu
105 Neyveli Thermal Power Station 2999 2858 2938
- I (Expansion)
Neyveli Lignite Corp.,
Neyveli-600007
Tamil Nadu
106 Neyveli Thermal Power Station 4453 3335 4131
1
Neyveli Cuddalore
Tamil Nadu
84 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Net Heat Net Product Net Heat Rate
Rate (Kcal/ Output (Kcal/KWH)
KWh) (Million Units)
116 Valuthur Gas Turbine Power 2144 625 2058
Station
Ramanathapuram, -623536
Tamil Nadu
117 Agartala Gas Turbine Power 3788 648 3707
Plant, NEEPCO
NEEPCO, Agartala-799008
Tripura
118 Baramura Gas Thermal Power 3639 162 3631
Plant, Baramura
Teliamura, West Tripura-799205
Tripura
119 Rokhia Gas Thermal Power 3892 418 3852
Plant, Rokhia
Rokhia, Sonamura-799102
Tripura
120 Anpara Thermal Power Station, 2643 10579 2640
Sonebhadra
Sonebhadra Dist.
Uttar Pradesh
121 Harduaganj Thermal Power 4585 611 4247
Station
Kasimpur , Aligarh-202127
Uttar Pradesh
122 NTPC Ltd - Auraiya 2190 4017 2163
Dist. Auraiya-206244
Uttar Pradesh
123 NTPC Ltd - Dadri Gas 2037 5243 2031
GB Nagar Dist-201008
Uttar Pradesh
124 NTPC Ltd - Dadri Coal 2580 6903 2558
GB Nagar Dist-201008
Uttar Pradesh
86 Ministry of Power
(1) (2) (3) (4)
Name, Address and State Net Heat Net Product Net Heat Rate
Rate (Kcal/ Output (Kcal/KWH)
KWh) (Million Units)
134 Budge Budge Thermal Power 2669 4095 2644
Station
South 24 Parganas
West Bengal
135 Durgapur Thermal Power Plant 3317 2582 3214
( Durgapur Projects Ltd)
Durgapur
West Bengal
136 Durgapur Thermal Power 3278 1677 3134
Station , Damodar Valley Corp.
Ltd.
Durgapur
West Bengal
137 Kolaghat Thermal Power 3246 6632 3105
Station, WBPDCL
Salt Lake City, Kolkata-700098
West Bengal
138 Mejia Thermal Power Station , 2781 6163 2739
Damodar Valley Corporation
Durlavpur, Bankura Distt.
West Bengal
139 New Cossipore Thermal Power 3818 353 3743
Sattion
New Cossipore
West Bengal
140 NTPC Ltd -Farakka 2596 10144 2574
Murshidabad Dist
West Bengal
141 Sagardighi Thermal Power 3584 2912 3465
Station
Murshidabad Dist
West Bengal
The designated consumers referred to in column (2) of the sector table above shall comply with
the energy consumption norms and standards specified against their name in column 4 of the
said Sector Table by the target year 2014-15.
Notification
G.S.R. 269(E).- In exercise of the powers conferred by clauses (f),(g), (k), (la)and (laa) of section
56, read with clauses (g) and (o) of section 14, sub-section (1) of section14Aand section 14B of the
Energy Conservation Act, 2001 (52 of 2001), the Central Government hereby makes the following
rules, namely:-
1. Short title and commencement.- (1) These rules may be called the Energy Conservation
(Energy Consumption Norms and Standards for Designated Consumers, Form, Time
within which, and Manner of Preparation and Implementation of Scheme, Procedure for
Issue of Energy Savings Certificate and Value of Per Metric Ton of Oil Equivalent of Energy
Consumed) Rules, 2012.
(2) They shall come into force on the date of their publication in the Official Gazette.
88 Ministry of Power
2. Definitions.-(1) In these rules, unless the context otherwise requires, -
(b) “baseline year” means the year in which the base level of energy consumption is
used as a reference point for establishment and assessment of performance with
regard to compliance of energy consumption norms and standards under rule 4
and rule 6 respectively;
(c) “certification” means the process of certifying the verification report or check-
verification report by the accredited energy auditor to the effect that the
entitlement or requirement of energy savings certificate is quantified accurately
in relation to compliance of energy consumption norms and standards by the
designated consumer during the target year;
(e) “cycle” means the period of three years available to a designated consumer to
comply with the energy consumption norms and standards;
(h) “Rules 2007” means the Energy Conservation (the form and manner for
submission of report on the status of energy consumption by the designated
consumers) Rules, 2007 notified in the Official Gazette vide number G.S.R 174
(E), dated the 2nd March,2007;
(i) “Rules 2008” means the Energy Conservation (Form and Manner and Time for
Furnishing Information With Regard to Energy Consumed and Action Taken
on Recommendations of Accredited Energy Auditor) Rules, 2008 notified in the
Official Gazette vide number G.S.R 486(E), dated the 26th June,2008;
(l) “specific energy consumption” means the ratio of the net energy input into the
designated consumers’ boundary to the total quantity of output exported from
the designated consumers’ boundary, calculated as per the following formula:-
and expressed in terms of the metric ton of oil equivalent (toe)/per unit of product;
(m) “targetyear” means the year by which a designated consumer shall achieve
compliance with the energy consumption norms and standards;.
(o) “year” means the financial year beginning on the 1st day of April and ending on
the 31st day of March following.
(2) Words and expressions used herein and not defined but defined in the Act shall have
the meanings respectively assigned to them in the Act.
(2) The energy consumption norms and standards shall be specific for every designated
consumer and shall be determined as under:-
(a) where energy audit of the designated consumer’ plant has been completed,
energy saving measures and action plan for their implementation has been
finalised in consultation with the energy manager of the plant under regulations
4 and 5 of the Bureau of Energy Efficiency (Manner and Intervals of Time for
Conduct of Energy Audit) Regulations, 2010,the energy consumption norms and
standards shall be based on the timely submission of Form 2 and Form 3 under
Rules 2008;
(b) where energy audit of the designated consumers’ plant has not been completed
or undertaken, the energy consumption norms and standards shall be
determined taking into account the following factors, namely:-
(i) average rate of reduction in specific energy consumption across all the
designated consumer sectors’ determined on the basis of the analysis of
data of the last three years;
(ii) policy objectives of keeping the target of reducing the specific energy
consumption a few percentage points above the average rate of reduction
90 Ministry of Power
keeping in view the incentive provided through the issue of energy
savings certificate.
(3) Where the energy consumption norms and standards have been determined in
accordance with clause (a) or clause (b) of sub-rule (2),the said methodology shall not
be reviewed after the commencement of the energy consumption norms and standard
notified under clause (g) of section 14.
(4) The designated consumers shall achieve compliance with the energy consumption
norms and standards as notified under clause (g) of section 14 within a period of three
years from the date of commencement of the said notification.
(a) calculate specific energy consumption in the baseline year and projected specific
energy consumption in the target year covering different forms of net energy
going into the boundary of the designated consumers’ plant and the products
leaving it over the relevant cycle on a gate-to-gate basis;
(i) convert the calorific values of all forms of energy sources into a single
unit, namely, ton of oil equivalent using the conversion formulae specified
in the Government of India, Ministry of Power notification number
S.O.394(E), dated the 12th March, 2007;
(ii) consider all forms of energy that is, electricity, solid fuel, liquid fuel,
gaseous fuel, or any other form of energy imported into the plant for
consumption as energy for production of output;
(iii) not take into account energy consumed in the colony attached to the plant,
temporary or major construction work, and for outside transportation
system or energy consumed through renewable energy sources not
connected to the grid;
(iv) take into account the energy exported out of the designated consumers’
boundary;
(v) if any designated consumers’ plant does not have disaggregated figures
for energy consumed, consider the net energy consumed for calculation
both in baseline year and in the target year:
Provided that the said designated consumer shall give adequate reasons that
it was not feasible to make adjustment for energy consumed in the colony,
temporary or major construction work:
(vi) where more than one product is produced, select the main product
produced or an equivalent product worked out from the product mix as
per standard practice prevalent in the concerned designated consumers
sector:
Provided that where the production of the said main product is stopped, the
designated consumer shall inform the necessary details in that regard to the
Bureau and the concerned state designated agency;
(c) calculate the specific energy consumption for the baseline year as well as for
the target year and normalise it by taking into account the capacity utilisation,
mix of grid and captive electricity, and any other factor which affects energy
consumption as specified in the Schedule;
(d) calculate the annual specific energy consumption in the baseline year by
verifying the data in the previous three years, year-wise, using the data
submitted by the designated consumers’ under Rules 2007 and if verified, under
Rules 2008;
(e) calculate the effect of capacity utilisation and other factors if any, on the specific
energy consumption for the previous three years;
(g) take into consideration the effect on capacity utilisation or the plant load factor
or average energy consumption in the target year on account of any of the
following factors, namely:-
(iv) impact of market (shortage of raw material or sales) in any of the previous
three years.
(2) The said technical committee shall prepare a report containing designated consumer-
specific basis of methodology referred to in sub-rule 2 of rule 3, consultation with the
designated consumers, and submit the said report to the Bureau.
92 Ministry of Power
(3) The Bureau shall examine the report submitted under sub-rule (2) and finalise its
report containing its recommendation regarding the energy consumption norms and
standards for each designated consumers’ plant.
(4) The details regarding methodology used, formulae adopted, exceptions considered,
principles adopted, for preparation of energy consumption norms and standards shall
be as specified in the Schedule.
(5) The Bureau shall submit the report referred to in sub-rule (3) to the Central
Government.
(6) The Central Government after considering the said report shall by notification,-
(a) establish and specify the energy consumption norms and standards for every
designated consumers’ plant under clause (g) of section 14;
(b) give direction to all designated consumers for compliance with the energy
consumption norms and standards under clause (n) of section 14and inform the
Bureau and all the State designated agencies.
5. Form, manner and time for preparation of scheme for implementation of efficient use of
energy and its conservation.-(1) Every designated consumer, within three months of the
issue of notification under sub-rule (6) of rule 4 shall submit a scheme to State designated
agency with a copy to Bureau, which may include -
(a) action plan containing inter-alia, a brief description of identified energy saving
measures to comply energy consumption norms and standards by the target year;
(c) implementation plan to achieve energy consumption norms and standards through
implementation of energy saving measures or through purchase of energy savings
certificates.
(b) proof of timely submission of reports in Form 1 under Rules 2007 for the
previous three years;
(c) proof of timely submission of reports in Form 1, Form II and Form III under
Rules 2008 along with copies thereof including the reports for the target year;
(f) name and particulars of the energy manager, his date of appointment, details
of duties performed including initiatives undertaken for improvement in energy
conservation and energy efficiency.
(2) The designated consumer, within three months after the end of first or second year
of the relevant cycle, may submit performance assessment document in Form ‘A’ to
the State designated agency, with a copy to the Bureau, for issuance of proportionate
energy savings certificates covering the performance for a period of not less than
one year from the date of notification specifying the energy consumption norms and
standards, duly verified together with certificate in Form ‘B’ given by accredited
energy auditor along with the documents mentioned in sub-rule (1).
(3) The accredited energy auditor shall independently evaluate each activity undertaken
by the designated consumer for compliance with the energy consumption norms and
standards and entitlement or requirement of energy savings certificate, to ensure that
they meet with the requirements of these rules.
(4) The accredited energy auditor, in order to assess the correctness of the information
provided by the designated consumer regarding the compliance with energy
consumption norms and standards shall-
(b) follow the rules and regulation framed under the Act;
(d) make independent technical review of the opinion and decision of the
verification team;
94 Ministry of Power
(e) also take into consideration, a situation where a particular activity may or
may not form part of the activities related to the compliance with the energy
consumption norms and standards, and the procedure for the assessment shall
include,-
(i) review of data and its source, and information to verify the correctness,
credibility and interpretation of presented information;
(ii) cross checks between information provided in the audit report and,
if comparable information is available from sources other than those
used in the audit report, the information from those other sources and
independent background investigation;
(5) The accredited energy auditor shall report the results of his assessment in a
verification report and the said report shall contain,-
(a) the summary of the verification process, results of assessment and his opinion
along with the supporting documents;
(b) the details of verification activities carried out in order to arrive at the
conclusion and opinion, including the details captured during the verification
process and conclusion relating to compliance with energy consumption
norms and standards, increase or decrease in specific energy consumption with
reference to the specific energy consumption in the baseline year;
(c) the record of interaction, if any, between the accredited energy auditor and the
designated consumer as well as any change made in his assessment because of
the clarifications, if any, given by the designated consumer.
(6) If the accredited energy auditor records a positive opinion in his verification report,
the Bureau shall consider that all the requirements with regard to the compliance
with energy consumption norms and standards, entitlement about issue or liability to
purchase energy savings certificate have been met.
(ii) on the internal field audits of plant and production processes for the
purpose of identification of factors inhibiting improvements in energy
efficiency and conservation, and taking of measures to reduce energy
consumption and to improve energy efficiency.
(ii) on the outcome of internal field audits of plant and production processes
identifying factors inhibiting improvements in energy efficiency and its
conservation, and taking of measures to reduce energy consumption and
improve energy efficiency and measures taken to improve the efficiency of
the production processes during each year;
(c) preparation and maintenance of the end of the cycle data reports on production
achieved, energy consumed, specific energy consumption achieved, specific
energy consumption reduction achieved, measures adopted for energy
conservation and quantity of energy saved.
(2) All the activities undertaken by the designated consumers under these rules shall
be scrutinised by the accredited energy auditor for the purpose of preparation of
verification report and the designated consumer shall furnish the full and complete
data, provide necessary documents and other facilities required by the accredited
96 Ministry of Power
energy auditor for the purpose of performing the function of verification under these
rules.
(2) The Bureau shall initiate action in accordance with the following procedure, namely-
(a) a notice shall be issued to the designated consumer as well as to the accredited
energy auditor who had submitted the verification report with a copy to
relevant state designated agency, to provide comments in reply to the said
notice within ten working days from the date of receipt of aforesaid notice;
(b) the comments furnished by the designated consumer and accredited energy
auditor shall clearly state that-
(i) they stand by the compliance report and verification report submitted
by them and submit a confirmation report giving point wise replies with
necessary documents in response to the said notice; or
(c) within ten working days from the date of the receipt of the comments referred
to in clause (b),Bureau shall after taking into consideration the said comments,
decide to undertake or not to undertake review and the Bureau shall record the
reasons in writing for its decision;
(d) where the Bureau, in consultation with state designated agency, decides to
undertake review,
(i) it shall appoint an accredited energy auditor, who has not performed the
verification functions with respect to the concerned designated consumer,
to conduct the check-verification;
(ii) on a complaint, the said check-verification shall be carried out at the cost
of the complainant;
(e) where the Bureau decides not to undertake the said review, the designated
consumer, his accredited energy auditor, and the complainant shall be informed
in that regard in writing.
(a) the activities relating to the compliance with energy consumption norms and
standards have been performed and the issue or purchase of energy savings
certificate are in accordance with the provisions of these rules;
(b) the monitoring and verification process are in accordance with the provisions of
rule 6;
(c) the details of the data and the activities referred to in rule 7 are evaluated and
conclusion made that errors, omissions or misrepresentations or aggregation
thereof in the said data do not affect the energy consumption norms and
standards achieved by the activities and issue or purchase of energy savings
certificates by more than the threshold limit specified in the Schedule.
(4) The said accredited energy auditor shall assess and verify that the activities
performed by the designated consumer for compliance with the energy consumption
norms and standards are in accordance with these rules, and the assessment and
check-verification process shall involve–
(e) are view of the monitoring and verification process referred to in rule 7.
(5) The designated consumer shall furnish full and complete data, provide necessary
documents and other facilities required by the accredited energy auditor for the
purpose of performing the function of check-verification under these rules.
98 Ministry of Power
(6) The accredited energy auditor in-charge of check-verification function shall report
the results of his assessment in a check-verification report and the said report shall
contain,-
(a) the summary of the verification process, results of his assessment and his
opinion along with the supporting documents;
(b) the details of check-verification activities carried out in order to arrive at the
conclusion and opinion including the details captured during the verification
process and conclusion relating to compliance with energy consumptions
norms and standards, increase or decrease in specific energy consumption with
reference to the specific energy consumption in the baseline year, entitlement
about the issue or liability to purchase energy savings certificate.
(7) If the accredited energy auditor records in his check-verification report, a positive
opinion, it shall be concluded that all the requirements with regard to the compliance
with energy consumption norms and standards and the issue or purchase of energy
savings certificates have been met.
(8) If the accredited energy auditor records in his check-verification report, a negative
opinion, the effect of such opinion on the energy consumption norms and standards,
issue or purchase of energy savings certificate, the liability of the accredited energy
auditor in giving the verification report and amount of the unfair gain gained by the
designated consumer as a result of such verification report shall be calculated by the
accredited energy auditor conducting the check-verification.
(9) The accredited energy auditor in-charge of check-verification shall submit his report
with due certification in Form ‘C’ to the Bureau and the concerned State Designated
Agency.
(10) Where the verification report given by the accredited energy auditor secures an unfair
or undue gain due to the deficiencies or inconsistencies or errors or misrepresentation
by the designated consumer, the quantum of such gain shall be calculated having
regard to the following factors, namely:-
(a) the value of the amount payable by such designated consumer shall be as
worked out in the verification report plus twenty-five per cent. of such value
because of unfair practice used by the said designated consumer for obtaining
unfair advantage;
(b) the amount of metric ton of oil equivalent of energy specified because of unfair
gain identified due to check-verification;
(11) The State designated agency may furnish its comments on the report within ten
days from the receipt of the report from the said accredited energy auditor and in
(12) The Bureau after the expiry of ten days referred to in sub-rule (11), shall issue show
cause notice to the designated consumer as well as to his accredited energy auditor
specifying the deficiencies or inconsistencies or errors or misrepresentation noticed
against the designated consumer and his accredited energy auditor.
(13) The designated consumer as well as his accredited energy auditor shall submit their
replies to the said show cause notice within a period of fifteen working days to the
officer of the Bureau who has issued that show cause notice.
(14) The Bureau after examining the said replies to the show cause notice referred to in
sub-rule (13), shall forward the report to the concerned State designated agency
specifying the following details for the purpose of initiating the penalty proceedings,
namely:-
(a) the number of energy savings certificates wrongfully obtained by the designated
consumer on the basis of verification report found to be wrong and false on
check-verification;
(b) the number of energy savings certificates which the designated consumer was
liable to purchase for non-compliance with the energy consumption norms and
standards as found in the check-verification report;
(c) details of the misrepresentation, if any and the unfair gain due to such
misrepresentation;
(15) The State designated agency within two months from the date of the receipt of the
report referred to in sub-rule (9) shall initiate-
(a) action to recover from the designated consumer the loss to the Central
Government by way of unfair gain to the designated consumer;
(b) penalty proceedings against the persons mentioned in the said report, under
intimation to the Bureau;
(c) register complaint for such fraudulent unfair gain if designated consumer does
not pay penalty and loss to the exchequer in the specified time mentioned in the
penalty proceedings.
(16) Where the check-verification has been initiated on the basis of a complaint received
by the Bureau, the cost of check-verification shall be borne by the complainant, in
case it was found on check-verification that the designated consumer has submitted
correct information in Form ‘A’.
9. Procedure regarding compliance with energy consumption norms and standards and issue
of energy savings certificate.-(1) A firm registered under the Indian Partnership Act, 1932
(9 of 1932) or a company incorporated under the Companies Act, 1956 (1 of 1956) or any
other legal entity competent to sue or to be sued or enter into contracts shall be entitled
to undertake verification and check-verification regarding compliance with the energy
consumption norms and standards and issue or purchase of energy savings certificate if it,-
(a) has at least one accredited energy auditor whose name is included in the list of
the accredited energy auditors maintained by the Bureau under regulation 7 of
the Bureau of Energy Efficiency (Qualifications for Accredited Energy Auditors
and Maintenance of their List) Regulations, 2010;
(c) has adequate expertise of field studies including observations, probing skills,
collection and generation of data, depth of technical knowledge and analytical
abilities for undertaking verification and check-verification;
(d) has a minimum turnover of ten lakhs rupees per annum in at least one of the
previous three years or in case of a newly formed organisation, a net worth of
ten lakhs rupees.
(2) The Bureau shall invite applications from the firms, companies and other legal
entities to undertake the work of verification and check-verification for the purpose of
preparing a panel of such firms, companies and other legal entities.
(4) The applications so received shall be scrutinised in accordance with the provisions
of sub-rule(1) and a panel of eligible applicants shall be prepared which shall be
displayed on the web site of the Bureau, that is, www.bee-india.nic.in.
(5) The selected applicants shall be issued a certificate of empanelment in support their
selection to undertake the function of verification and check-verification as accredited
energy auditor.
(6) A unique identification number shall be issued to the accredited energy auditors
referred to in sub-rule (5).
Provided that a person who was in the employment of a designated consumer within
the previous four years, shall not be eligible to perform the work of verification or check-
verification for such designated consumer;
Provided further that any person or firm or company or other legal entity, who was
involved in undertaking energy audit in any of the designated consumer within the
previous four years, shall not be eligible to perform the work of verification or check-
verification for such designated consumer.
(2) The accredited energy auditor shall ensure that persons selected as team head and
team members must be independent, impartial and free of potential conflict of
interest in relation to activities likely to be assigned to them for verification or check-
verification.
(3) The accredited energy auditor shall have formal contractual conditions to ensure that
each team member of verification and check-verification teams and technical experts
act in an impartial and independent manner and free of potential conflict of interest.
(4) The accredited energy auditor shall ensure that the team head, team members and
experts prior to accepting the assignment inform him about any known, existing,
former or envisaged link to the activities likely to be undertaken by them regarding
verification and check verification.
(5) The accredited energy auditor must have documented system for determining the
technical or financial competence needed to carry out the functions of verification and
check -verification and in determining the capability of the persons referred to in sub-
rule (2), the accredited energy auditor shall consider and record among other things
the following aspects, namely:-
(e) type and amount of field work necessary for the verification or check-
verification.
(6) The accredited energy auditor shall have documented system for preparing the
plan for verification or check-verification functions and the said plan shall contain
(7) The names of the verification or check-verification team members and their bio-
data shall be provided by the accredited energyauditor to the concerned designated
consumer in advance.
(8) The verification or check-verification team shall be provided by the accredited energy
auditor with the concerned working documents indicating their full responsibilities
with intimation to the concerned designated consumer.
(ii) for dealing with the situations in which an activity undertaken for the purpose
of compliance with the energy consumption norms and standards or issue
of energy savings certificate shall not be acceptable as an activity for the said
purposes.
(10) The accredited energy auditor shall conduct independent review of the opinion of
verification or check-verification team and shall form an independent opinion and
give necessary directions to the said team if required.
(11) In preparing the verification and check-verification reports, the accredited energy
auditor shall ensure transparency, independence and safeguard against conflict of
interest.
(12) The accredited energy auditor shall ensure the confidentiality of all information and
data obtained or created during the verification or check verification report.
(13) In assessing the compliance with the energy consumption norms and standards and
issue of energy savings certificates, the accredited energy auditor shall follow the
provisions of the Act, rules and regulations made thereunder.
(14) After completion of the check-verification, the accredited energy auditor shall submit
the check-verification report, together with the certificate in Form-‘C’, to the Bureau.
11. Recommendation for issue of energy savings certificates.- (1) The Bureau on satisfying itself
about the correctness of verification report, and check-verification report, wherever sought
by it, send its recommendation under clause (aa) of sub-section (2) of section 13 to the
Central Government, based on the claim raised by the designated consumer in Form ‘A’,
within ten working days from the last date of submission of said Form ‘A’ by the concerned
state designated agency, for issuance of energy savings certificates under section 14A and
the recommendation shall specify.-
(c) the certification that all the requirements for issue of energy savings certificates
have been complied with, by the designated consumer and his entitlement has
been certified in the verification report by the accredited energy auditor.
(2) The designated consumer may seek issue of energy savings certificates in proportion
of its performance achieved during the first or second or target year with respect to
compliance with the energy consumption norms and standardsand the Bureau on
satisfying itself about the correctness of verification report, and check-verification
report, wherever sought by it, send its recommendation under clause (aa) of sub-
section (2) of section 13 to the Central Government, based on the claim made by the
designated consumer in Form ‘A’, for issue of energy saving certificates not exceeding
eighty percent. of the entitlement in a year other than the target year under section
14A.
(3) The total amount of energy savings certificates recommended under sub rule (2)
shall be adjusted against the entitlement on conclusion of the target year as per the
following formulae:-
12. Procedure for issue of energy savings certificate.-(1) The Central Government, on the receipt
of recommendation from the Bureau under rule 10, shall on satisfying itself in this regard,
issue energy savings certificates of required value to the concerned designated consumer
with in fifteen working days from the date of receipt of such recommendation from the
Bureau.
(3) The value of one energy savings certificates shall be equal to one metric ton of oil
equivalent of energy consumed.
(4) The designated consumer who has been issued energy savings certificates may sell
them through the power exchange.
(5) The designated consumer who has been issued the energy savings certificates during
the current cycle may use them for the purpose of banking until the next compliance
cycle.
(6) The energy savings certificates issued in a cycle period shall remain valid till the
completion of the compliance period of the next cycle.
(7) The energy savings certificates purchased by a designated consumer for the purpose
of compliance with the energy consumption norms and standards shall after their
submission to the Bureau stand expired.
13. Compliance of energy consumption norms and standards.- (1) The designated consumer
for the purpose of achieving the compliance with the energy consumption norms and
standards during the target year, in the relevant cycle shall take the following action and
after completing the said action, furnish the status of compliance to the concerned state
(b) where the measures implemented in terms of clause (a) are found inadequate
for achieving compliance with the energy consumption norms and standards,
the designated consumer shall purchase the energy savings certificates
equivalent in full satisfaction of the shortfall in the energy consumption norms
and standards worked out in terms of metric ton of oil equivalent.
14. Establishment of new baseline for next cycle.- The energy consumption norms and
standards achieved by the designated consumer on the completion of the target year, as
mentioned in the compliance report in Form-‘D’ shall be the baseline for establishment of
new plant specific energy consumption norms and standards for designated consumers for
the next cycle.
(a) for assessment of their performance for compliance with the energy consumption
norms and standards, get the work of verification done through accredited energy
auditors;
(c) furnish the full and complete data, provide necessary documents and other facilities
required by the accredited energy auditor for the purpose of performing the function
of verification and check-verification.
16. Specification of value of energy.-(1) The value of per metric ton of oil equivalent of energy
consumed shall be determined by applying the following formula, namely:-
P = Wc × Pc + Wo × Po + Wg × Pg + We × Pe
Where-
all prices shall be as on 1st April of the year for which value of energy is being specified.
(2) The value of per metric ton of oil equivalent of energy consumed for the purpose of
these rules shall be rupees 10154 for the year 2011-12.
(3) The value of per metric ton of oil equivalent of energy consumed shall be reviewed
every year for the purpose of sub-rule (2).
2. Registration number
3. Sector
4. Sub-sector
Name
Registration number
a. Mention -
the year
( )
b. Mention
the year
( )
c. Mention
the year
( )
a.
b.
c.
d.
e.
f.
Note 1: Form A may be filled in accordance with the following guidelines, namely:-
GUIDELINES
1. Name of designated consumer: As per notification under clause (g) of section 14.
3. Sector:
• Aluminium
• Cement
• Chlor Alkali
• Fertilizer
• Textile
(a) Baseline data (three years): Submitted to Bureau of Energy Efficiency for Target
Calculations
(b) Form I mention the year ( ): As per filing, attach acknowledgement of submission i.e.
after completion of 1st year after notification
(c) Form I mention the year ( ): As per filing, attach acknowledgement of submission i.e.
after completion of 2nd year after notification
(d) Form I mention the year ( ): As per filing, attach acknowledgement of submission i.e.
after completion of target year
7. Target: Enter target as notified by Government of India under clause (g)of section 11 (target
specific energy consumption). Enter energy savings certificates, if any, issued in last three
years). Adjusted target calculated as per formulae mentioned in rules.
(c) Revised target specific energy consumption (from 7.b): if any (in metric ton of oil
equivalent /unit production), or as notified by Government of India or enter 8.a
(e) Achieved specific energy consumption: Achieved specific energy consumption in the
year of submission of Form ‘A’
(f) energy savings certificates: calculate as per formulae provided in the rule 10.
Undertaking
I/We undertake that the information supplied in this Performance Assessment Document
is accurate to the best of my knowledge and if any of the information supplied is found to be
incorrect and such information result into loss to the Central Government or State Government
or any of the authority under them or any other person affected, I/we undertake to indemnify
such loss.
I /We agree to extend necessary assistance in case of any enquiry to be made in the matter.
Signature
Name
Designation
For and behalf of
Name of the Firm/Company/Organisation
SEAL of the Firm /Company/Organisation
CERTIFICATE OF VERIFICATION
(a) the verification of the data collection in relation to energy consumed and specific
energy consumption per unit of production in the baseline year and in the target
year in Form 1under Rules 2007 or Rules 2008, has been carried out diligently and
truthfully;
(b) the verification of the identified energy efficiency measures, and the progress of their
implementation given in Form II and Form III under Rules 2008 has been carried out
diligently and truthfully;
(c) the verification of the compliance with energy consumption norms and standards
during the target year has been carried out diligently and truthfully;
(d) the verification of the total amount of energy saved, year-wise, after the baseline year
and until target year or otherwise and request made by the designated consumer, the
entitlement of _________ (Nos) energy savings certificate (s) required to be issued or
purchased by him have been carried out diligently and truthfully;
(e) all reasonable professional skill ,care, and diligence have been taken in verifying
the various verification activities, findings and conclusions, documents, reports,
preparing the documents including the performance assessment document in Form
‘A’ and verification report and the contents thereof are a true representation of the
facts.
Signature:
Designation:
(a) the check-verification of the data collection in relation to energy consumed and
specific energy consumption per unit of production in the baseline year and in the
target year in Form 1under Rules 2007 or Rules 2008, has been carried out diligently
and truthfully;
(b) thecheck-verification of the identified energy efficiency measures, and the progress of
their implementation given in Form II and Form III under Rules 2008 has been carried
out diligently and truthfully;
(c) thecheck-verification of the compliance with energy consumption norms and
standards during the target year has been carried out diligently and truthfully;
(d) the check-verification of the total amount of energy saved, year-wise, after the
baseline year and until target year or otherwise and request made by the designated
consumer, the entitlement of _________ (Nos) energy savings certificate (s) required to
be issued or purchased by him have been carried out diligently and truthfully;
(e) all reasonable professional skill, care, and diligence have been taken in
check-verifying the various verification activities, findings and conclusions,
documents, reports, preparing the documents including the information given
in the Performance Assessment Document in Form ‘A’ and verification report
submitted by the accredited energy auditor appointed by the designated consumer
………………………… for verification and the contents thereof are a true
representation of the facts.
Signature:
Designation:
2. Registration number
3. Sector
4. Sub-sector
6. Compliance
GUIDELINES
1. Name of designated consumer: As per notification from Government of India (GoI) under
clause (g) of section 14
• Aluminium
• Cement
• Chlor Alkali
• Fertilizer
• Textile
4. Sub Sector:
6. Compliance
(a) Energy savings certificates: Enter +ve value if energy savings certificates issued to
designated consumer or enter -ve value in case recommended for purchase of energy
savings certificates
(c) Balance energy savings certificates:- Numbers of energy savings certificates balance. If
balance is ZERO than DC is in accordance for compliance of energy saving target and
if balance is -ve than DC will be recommended for penalty.
Undertaking
I/We undertake that the information supplied in compliance with energy consumption and
standard documents in this Form ‘D’ is accurate to the best of my/our knowledge and if any
of the information supplied is found to be incorrect and such information result into loss to
the Central Government or State Government or any of the authority under them or any other
person affected, I/we undertake to indemnify such loss.
I/we agree to extend necessary assistance in case of any enquiry is made in the matter.
Signature
Name
Designation
For and behalf of
Name of the Firm/Company/Organisation
SEAL of the Firm/Company/Organisation
(a) The specific energy consumption (SEC) gives the indication of efficient
utilisation of different sources of energy in a plant operational boundary to
produce one unit of product, which is defined as the ratio of total energy input
to plant boundary and the quantity of products produced and specific energy
consumption of an industry shall be calculated based on Gate-to-Gate concept
with the following formula:-
and expressed in terms of the metric ton of oil equivalent (toe)/per unit of
product;
(b) Once the designated consumers’ boundary has been fixed, the same boundary
shall be considered for entire cycle, and any change in the said boundary such
as capacity expansion, merger of two plants, division of operation etc. shall be
duly intimated to the Bureau of Energy Efficiency.
(c) The following designated consumers’ boundaries will be considered in the first
cycle:-
Case -III: Electricity generated by captive power plant and other energy
purchased and consumed, electricity partially sold to grid:-
Case -IV: Electricity generated by captive power plant(CPP), other energy purchased
and consumed, electricity partially sold to grid from captive power plant:-
CASE -VI: Energy purchased and consumed, heat energy partially met by waste
or by-product of the process-
(a) During the first cycle designated consumer having more than five years life,
data for the previous three years, namely, 2007-08, 2008-09, 2009-10 shall be
considered provided the capacity utilization is uniform. Normalisation, in a
suitable statistical approach, shall be done in case of abnormality in capacity
utilisation in any of the aforesaid three year (s).
(b) During the first cycle designated consumer having more than five years life
and less than three years data has been reported, the same shall be considered
provided the capacity utilisation is uniform and if the capacity utilisation
is abnormally low in any of the aforesaid three year(s), the same shall not be
considered.
(c) During the first cycle, designated consumer having less than five years life
and less than three years data has been reported, the available year’s data
shall be considered provided the capacity utilisation is uniform. If the capacity
utilisation is abnormally low in any of the year(s), the same shall not be
considered.
(d) During the first cycle, in case of new designated consumer, the data shall
be considered for those years where the capacity utilisation is greater than
seventy percent. (70%) and if only one year data is reported, the same shall be
considered irrespective of the capacity utilisation.
(e) In the next cycle, baseline specific energy consumption shall be calculated in
accordance with the provisions of rule 14.
(e) Few additional sector specific information like process technology, process flow,
raw material, product mix etc. shall also be collected.
(f) All forms of energy shall be converted into a single form i.e. metric ton of oil
equivalent (toe) by the use of standard engineering conversion formula and the
following general guiding principle shall be used in this regard:-
(i) The reported gross calorific value (GCV) of fuels by the designated
consumer shall be considered for estimating the equivalent thermal
energy.
(ii) If gross calorific value (GCV) is not reported, then the values mentioned
in the Government of India, Ministry of Power, notification number
S.O 394(E), dated the 12th March, 2007 shall be considered. Any other
information as required shall be taken from standard industrial practice.
(iii) The equivalent thermal energy of the electricity supplied to the grid shall
be deducted from the total energy input to the designated consumers’
boundary. The following expression shall be used:-
Energy input (toe) = Fuel consumed quantity (kg) x gross calorific value (kCal/kg)
10 7
(v) Once the total energy input to the designated consumers’ boundary is
estimated, the specific energy consumption shall be calculated by dividing
the product quantity.
(a) Variable factors as described in rule 4 may affect the energy consumption and
‘Normalisation Factors’ shall be considered in those cases. Capacity utilisation
is one of the most important parameters to have a normalisation factor.
The reported specific energy consumption (SEC) shall be normalised after
incorporating the normalisation factor.
(b) The specific energy consumption shall be normalised, during baseline and target
periods, based on statistical procedures.
(iv) the average capacity utilisation shall be used to identify the corresponding
specific energy consumption value;
(e) The “capacity utilisation” referred to in clauses (c) to (d) shall be replaced by
“Plant Load Factor” in case of designated consumers in the thermal power plant
sector;
(f) The above calculation determines the normalised specific energy consumption
for the designated consumers.
2.1 The designated consumersfor the thermal power plant sector shall be grouped based
on the fuel used and they are as under:-
2.2 The energy consumption norms and standards for power stations shall be specified in
terms of specific percentage of their present deviation of net operating heat rate,based
on the average of previous three years, namely, 2007-8,2008-9,2009-10 for the first
cycle ,and for cycles thereafter in accordance with the provision of rule 14from the net
design heat rate. The power stations shall be grouped into various bands according to
their present deviations, of operating heat rate from design heat rate and for power
stations with higher deviations the energy consumption norms and standards shall
be established at lower level and shall be grouped taking into account percentage
deviation as under:-
Deviation in net station heat rate from Reduction target for percentage
design net heat rate deviation in the net station heat rate
More than five per cent and upto ten Seventeen per cent (17%)
percent
More than ten per cent and upto twenty Twenty-one per cent (21%)
percent
2.5 Correction factor considered for effect on heat rate due to coal quality:
(a) Average “ash”, moisture, and gross calorific value for the previous three years
in case of baseline for first cycle and as per rule 14 for consequent cycles and
Where:
(b) The permissible error shall be ±0.05% in terms of toe for the purpose of
determining entitlement of energy savings certificates.
3. Cement sector.-
3.1 For establishment of energy consumption norms and standards for designated
consumers in the cement sector, the designated consumers shall be grouped based
on similar major output or product with the available data to arrive at a logical and
acceptable spread of specific energy consumption among the designated consumers
which shall be grouped as under:-
Normalization Factors
(iii) Conversion of Portland Slag Cement (PSC) or any other variety of cement
production equivalent to major product
PSC or any other variety cement produced (Lakh ton) ×
Conversion factor of PSC or any other variety cement
Equivalent major product =
Conversion factor of major product
[Lakh ton]
Where: Total Imported clinker = [Clinker Imported from other plants + clinker
Imported from clinker stock, equivalent to the quantity by which the clinker
opening stock gets reduced]
[Lakh ton]
Note: S.No. a(v) is already accounted in major product
Total thermal energy consumption = [Fuel consumed (Lakh ton) × Gross calorific
value of respected fuel (kcal/kg) × 100]
[Million kcal]
Notional energy required = {Total exported clinker to major product (Lakh ton) ×
Electrical SEC of cement grinding (kWh/ton of cement)
× Weighted average heat rate (kcal/kWh)}/10
[Million kcal]
Notional energy required = [Total clinker imported (Lakh ton) × {Thermal SEC
of clinkerization kcal/kg clinker) × 1000 + electrical SEC of clinkerization (kWh/
ton of clinker) × Weighted average heat rate (kcal/kWh)}/10] [Million kcal]
GtG energy consumption = b(i) + b(ii) + b(iii) + b(iv) + b(v) [Million kcal]
3.4 The permissible error shall be ±0.05% in terms of toe for the purpose of determining
entitlement of energy savings certificates.
4 Aluminum sector.
4.1 For establishment of energy consumption norms and standards for designated
consumers in the Aluminum sector, the designated consumers shall be grouped based
on similar major output or product with the available data to arrive at a logical and
acceptable spread of specific energy consumption among the designated consumers
which shall be grouped as under:-
4.2 The permissible error shall be ±0.05% in terms of toe for the purpose of determining
entitlement of energy savings certificates.
5.1 For Establishment of Energy consumption norms and standards in the Iron and
Steel sector, the Designated consumers are grouped based on similar characteristics
with the available data to arrive at a logical and acceptable spread of specific Energy
consumption among the designated consumers which may be grouped as under:-
A) Integrated Steel Plant:- The energy indices of the major integrated steel plants
captured from the annual reports and reported during the baseline audits
have been taken for the below calculations. The Gate to Gate Specific Energy
Consumption may be calculated as follows-
Gate to Gate Specific = Energy index of the plant Submitted to Ministry of Steel
Energy Consumption (SEC) (kcal/tone of crude steel).
As regards the total energy consumed in plant for these major integrated steel
plants, the following formula can be given-
Where, Total Thermal Energy (Mkcal) = [Fuel Quantity used (tonne) *Gross
Calorific Value of Fuel (kcal/kg)]/1000
B) Sponge Iron:- for this sub sector only those plants are considered which are
standalone sponge Iron plants with no downstream products. The gate to gate
SEC may be given as follows:
C) Sponge Iron with Steel Melting Shop:- for this sub sector those plants are
considered which are sponge Iron plants with SMS (Steel Melting Shop). The
gate to gate SEC may be given as follows:
In this Group first we convert sponge iron to Steel melting shop and again
equivalent Steel Melting Shop to sponge iron as follows-
D) Sponge Iron with Steel Melting Shop and others:- for this sub sector those plants
are considered which are sponge Iron plants with SMS (Steel Melting Shop) and
other products like Ferro Manganese, Silicon Magnanese, Pig Iron etc. . The gate
to gate SEC may be given as follows:
In this subsector first we convert equivalent Steel melting shop to Sponge Iron
and thereafter equivalent Ferro Alloy is converted to sponge Iron by given
formulae.
Sponge Iron = [{Electrical SEC of Pig Iron (kWH/Tonne)* CPP Heat Rate}*
production of Ferro Alloy Pig Iron}/(Total Specific Energy Consumption of
Sponge Iron)
Iron Production = Total energy Sponge Iron +Ferro Manganese to Sponge Iron +
Sponge Iron Manganese to Sponge Iron + Pig Iron to Sponge Iron
E) Ferro Alloy:-
Manganese = (Electrical SEC of Pig Iron * Production of Pig Iron)/ Electrical SEC
of Sponge iron Manganese)
F) Ferro Chrome:- The Gate to Gate SEC for this subsector is given as follows-
G) Mini Blast Furnace:- The G to G SEC for this subsector is given as follows-
H) Steel Processing Units:- This subsector contributes towards the many such steel
processing plants like rerolling, wiredrawing, cold rolling, hot rolling etc.
5.11 The permissible error shall be ±0.05% in terms of toe for the purpose of determining
entitlement of energy savings certificates
6.1 For establishment of energy consumption norms and standards in the Chlor-Alkali
sector, the designated consumers shall be grouped based on similar characteristics
with the available data to arrive at a logical and acceptable spread of specific energy
consumption among the designated consumers which may be grouped as under:-
Addition of 60 kWh per year: 60 kWh × 860 kCal (In case of Non CPP plants) × 3
years/10000000 MTOE/tonne
Addition of 60 kWh per year: 60 kWh × 2717kCal (In case of CPP plants) × 3
years/10000000 MTOE/tonne
6.4 The permissible error shall be ±0.05% in terms of toe for the purpose of determining
entitlement of energy savings certificates
7.1 For establishment of energy consumption norms and standards in the Pulp and Paper
sector, the designated consumers shall be grouped based on similar characteristics
(i) The input raw materials are Wood, Agro and Recycled Fibre (RCF);
(ii) The process outputs are of Chemical Pulping, Chemi-mechanical Pulping and
100% market pulping
(iii) The product output of specialty paper, non-specialty paper and newsprint.
7.2 The groups made for Pulp and Paper sector under are:-
7.3 The permissible error shall be ±0.05% in terms of toe for the purpose of determining
entitlement of energy savings certificates.
8 Textile sector.-
8.1 For establishment of energy consumption norms and standards in the Textile sector,
the designated consumers shall be based on similar characteristics with the available
data to arrive at a logical and acceptable spread of specific energy consumption
among the designated and the group made are as under:-
8.3 The permissible error shall be ±0.05% in terms of toe for the purpose of determining
entitlement of energy savings certificates.
9 Fertilizer sector.-
9.1 In Fertilizer Sector, for manufacturing of Urea fertilizer, out of total energy consumed
at designated consumer plant boundary, stoichiometric energy of 2.53 Gcal/MT Urea
is contained in urea product and goes out as such. Thus, the net energy utilized
in urea manufacture is total energy input at designated consumers’ boundary
reduced by 2.53 Gcal/MT Urea. The figure is worked out by considering heat energy
of ammonia as 4.46 Gcal/MT Ammonia and specific consumption 0.567 MT of
Ammonia/MT Urea.
9.2 The permissible error shall be ±0.05% in terms of toe for the purpose of determining
entitlement of energy saving certificates.
(Note: For all practical and legal purposes, the English Version of the concerned notified Rule in
the Gazette of India will be considered as final)