Maag S Series - Disassembly AssemblyUSA
Maag S Series - Disassembly AssemblyUSA
Maag S Series - Disassembly AssemblyUSA
& Reassembly
S Series
Twin Screw Pumps
W h e r e I n n o v a t i o n F l o w s
www.maag.com
MAAG-14020-E-01
s e c t i o n X
Ta b l e o f c o n t e n t s
Section 1 INTRODUCTION.............................................................................................................................................................. 1
Safety Precautions................................................................................................................................................... 1
Special Tools................................................................................................................................................................. 1
Section 2
2H…B/F/G SERIES PUMPS......................................................................................................................................... 2
Disassembly..................................................................................................................................................................... 2
Reassembly....................................................................................................................................................................... 3
Cross-Sectional Diagrams.................................................................................................................................. 4
2H...B/F PUMPS....................................................................................................................................................... 4
2H...G PUMPS........................................................................................................................................................... 4
Section 3
2HE, 2HCE AND 2VE SERIES PUMPS..................................................................................................................... 6
Disassembly..................................................................................................................................................................... 6
Reassembly....................................................................................................................................................................... 7
Cross-Sectional Diagrams.................................................................................................................................. 8
2VE PUMPS............................................................................................................................................................... 8
2HE...A PUMPS......................................................................................................................................................... 9
2HE...B PUMPS.......................................................................................................................................................10
Section 4
2HM, 2HC, 2HR and 2VM SERIES PUMPS.......................................................................................................11
Disassembly...................................................................................................................................................................11
REassembly.....................................................................................................................................................................12
Cross-Sectional Diagrams................................................................................................................................14
2HC...AP PUMPS....................................................................................................................................................14
2HC...BP PUMPS....................................................................................................................................................15
2HCG...B PUMPS....................................................................................................................................................16
2HC...P PUMPS.......................................................................................................................................................17
2HM...A PUMPS.....................................................................................................................................................18
2HMB PUMPS.........................................................................................................................................................19
2HM...B PUMPS......................................................................................................................................................20
2HMG...C PUMPS..................................................................................................................................................21
2HM...P PUMPS......................................................................................................................................................22
2HRA PUMPS.........................................................................................................................................................23
2HRG PUMPS.........................................................................................................................................................24
2VM PUMPS............................................................................................................................................................25
Section 5
I NDIVIDUAL PUMP COMPONENTS.....................................................................................................................26
DIsassembly/Reassembly for Independent, Pressure-Limited Valves...................................26
Internal Spring Structure (Side-In, Top-Out).............................................................................26
Internal Spring Structure (Side-In, Side-Out)............................................................................27
External Spring Structure.....................................................................................................................28
DISassembly/Reassembly for Built-in Pump Casing, Pressure-Limited Valve...................29
Internal Spring Structure (Welded)................................................................................................29
Internal Spring Structure (Casted).................................................................................................30
External Spring Structure.....................................................................................................................31
Disassembly/Reassembly FOR Mechanical SealS.................................................................................32
Single Mechanical Seal.............................................................................................................................32
Single Cartridge-Type.................................................................................................................................33
Double Cartridge-Type..............................................................................................................................34
s e c t i o n 1
introduction
These pumps have been designed for safe and reliable operation
when properly used and maintained in accordance with the Pump Operating Parameters
instructions contained within this manual. A pump is a pressure- Unless there is written admission by S Series, the pump must not
containing device with rotating parts that can be hazardous. Failure be operated at higher parameters than specified. Adhering to
to read and comply with installation, operation and maintenance these specifications prevents danger to personnel and equipment
instructions will void the responsibility of the manufacturer and damage.
may result in bodily injury or equipment damage.
Pump Monitoring
NOTE: In addition to the Safety Precautions identified in this
Suitable measuring devices must be installed to inspect and
section, special safety information is included within proceeding
control the pump during operation. Generally, pressure gauges
chapters where appropriate.
are to be installed on suction and discharge lines near the pump.
Markings and Instructions on Pump Unit
Special Tools Required for
Direct instructional references regarding direction of rotation,
fluid-flow orientation, safety warning, etc., are clearly marked on
Disassembly/Reassembly
the pump. Please observe and follow all indicated safety markings Please refer to the table below for the appropriate tools to be used
and instructions. during disassembly or reassembly of pump.
NOTE: Failure to observe safety references can result in the No. Name Qty.
following dangers: 1 Sleeve for Mechanical Seal 1
• Equipment failure
• Maintenance and service policies voided 2 Inner Sleeve for Oil Seal 2
• Environmental pollution due to hazardous-substance leakage 3 Outer Sleeve for Oil Seal 1
• Personal endangerment by subject of electrical, mechanical 4 Bushing for Bearing 1
and chemical influences
5 Set Bushing for Bearing 1
6 Dismantling Screw 2
7 Anti-Rotation Copper Pipe 1
NOTE: For part reference, please refer to the appropriate pump in See Section 2 Cross-Sectional Diagrams and Figure 2.
Section 2 Cross-Sectional Diagrams.
Disassembly of Gear Box
See Figure 1. Unscrew drain plug (130), loosen air strainer (107)
and drain lubricating oil from gear box (04). Collect the lubricating
oil in a suitable container. Lift off gear box (04) after lock nuts (121)
have been removed.
ATTENTION: If the pump has an end-side coupling half, disas-
semble before disassembling the gear box. Remove the key on the Figure 2
shaft end at this time.
Jam the teeth of the gear wheels (13 & 14) with a copper sheet,
loosen and remove the back-stop washer (129) and locking nut
(128) on the driving shaft (05), remove bolt (115) and spring
washer (116) on the driven shaft, use tools (such as a drag wheel
tool) to remove gear (13 & 14), remove key (134). Loosen screw
(126), remove bearing cover (11) and spacer (17). Be sure to label
all disassembled components.
ATTENTION:
• Only when the replacement of new timing gears is required,
bolts (112) can be unscrewed so that gear wheel (14) and gear
sleeve (15) are separated. At this time, bolts (112) must be
replaced.
• Mark the starting point of meshing before removing the
timing gears.
Figure 1
• Immediately label all dismantled parts in order to avoid confu-
sion during reassembly.
Disassembly of Pump Casing
Disassembly of Bearings
Disassemble hexagon nut (118) with plain washer (119) of pump
casing (01) and bearing housing (03). Disassemble pump casing See Section 2 Cross-Sectional Diagrams.
(01) by tightening two forcing screws.
Affix the appropriate-sized auxiliary tool on the side of the screw
ATTENTION: Threaded holes are located in bearing housing (03). sleeve that is on the shaft (05 & 06), use special tool to hit the
auxiliary tool, hit out the shafts (05 & 06) from bearing housing
Disassembly of Screws
respectively.
See the applicable Cross-Sectional Diagram in Section 2; loosen
Disassemble bearings (101 & 102) and internal, external spacer
bolt (141), disassemble pressing board (21) of screws and then
bushing (18 & 19) from the driving and driven shafts (05 & 06).
disassemble left-hand screw and right-hand screw together.
Next, label the dismantled items.
Remove key (135), screw adjusting ring (20) and mechanical seal
adjusting ring (26). Next, label the dismantled items. ATTENTION: Immediately label all dismantled parts in order to
avoid confusion during reassembly.
Disassemble the rotating and stationary ring unit of the mechani-
cal seal. If space plate (50) is present, unscrew screw (146) and
disassemble spacer plate (50).
ATTENTION:
• Immediately label all dismantled parts in order to avoid
confusion during reassembly.
• If seal boxes (09) are in good condition, do not disassemble
them! Otherwise, loosen socket screws (110) and
disassemble the seal boxes respectively.
Reassembly Place the gasket between bearing housing (03) and pump casing
(01), secure with bolts (117), nuts (118) and flat washers (119).
NOTE: For part reference, please refer to the appropriate pump
Cross-Sectional Diagrams; see Section 2 for pump diagram. I ndividually mount spacer bushings (17) on shafts (5 & 6) and
insert key (134) onto shafts. Mount gear wheels (13 & 14) on shafts
I nstall O-rings (103) and oil seal (104) on sealing box (09). Fasten (5 & 6), fasten gear wheel (13) to driving shaft (05) with lock nuts
sealing box (09) to bearing housing (03) with screw (110). (If spacer (128) and lock washers (129). Next, mount the pressing board (16)
plate (50) is present, fasten sealing box (09) to spacer plate (50) on the driven shaft, fasten with spring washers (116) and screw
and then fasten both of them to bearing housing). bolts (115).
I nstall bearings (101) onto driving and driven shafts (05 & 06), and F asten gear box unit (04) and gasket (28) to bearing housing (03)
then strike outer ring of the bearing (101) with appropriate tool, with stud screw bolts (120), screw nuts (121) and flat washers
insert them into driving (shaft) and driven (shaft) bearing bores of (122).
bearing housing (03).
Fasten drain screw plug (130), open feed screw plug and
I n sequence, assemble the internal and external spacer bushings pour clean gear oil. For oil level reference, please see
(18 & 19) and the bearings (102) to driving and driven shafts (05 & Figure 3.
06) with appropriate tools.
Tighten bearing cover (11) onto bearing housing (03) with screws
(126).
ssemble the labeled stationary ring of mechanical seal into the
A
sealing box (09) and rotating ring of mechanical seal onto driving
and driven shafts (05 & 06) at the original location.
I nstall the labeled mechanical sealing adjustment ring (20) and
max
min
screw sleeve adjustment ring (26) onto the driving and driven
shafts (05 & 06) according to the original location marked during
disassembly.
Position the screws (07 & 08) onto the driving and driven
shafts (05 & 06) by the key (135). Use bolt (141) and spring Figure 3
washer (142) to push the plate (21) allowing the screws FIGURE 6 Oil Level of the Gear Casing
(07 & 08) to be located on the driving and driven shafts
(05 & 06).
c r o ss - s e c t i o n a l d i a g r a m s
2H...B/F PUMPS
c r o ss - s e c t i o n a l d i a g r a m s
2H...G PUMPS
emove screw bolts (120), hexagon nuts (121) and spring washer
R Remove gears (13 & 14) with the appropriate pulling mechanism
(122) that connect pump casing (01) and pedestal (45). Next, from shafts (05 & 06) separately. Remove key (134).
remove pedestal.
Disassembly of Bearing Housing Unit
Disassembly of Back Bearing Housing Disassembly of Front Bearing: Remove hexagonal bolt (110)
L oosen hexagon nuts (118) and washer (119) that connect the and spring washer (111). Next, remove positioning bearing cover
pump casing and the back bearing housing. Next, remove the (09 & 10) from the front bearing housing. Remove front bearing
back bearing housing. (101) from front bearing housing with the appropriate tools.
ATTENTION: Threaded holes are located on the back Disassembly of Back Bearing: Remove screw (140), spring
bearing housing. washer (141) and back-positioning bushing (32). If necessary, pull
the shaft assembly from pump casing, including shafts (05 & 06)
Disassembly of Back Bearing and screws (07 & 08).
L oosen bolts (115), remove spring washer (116) and end plate (40).
Remove bearing (102) from the driving and driven shaft by a pull-
ing device. Remove spacer bushings (16 & 17).
ATTENTION: Immediately label all dismantled parts in order to
avoid confusion during reassembly.
I nsert O-rings into driving and driven shaft bearing cover (11 & 12). Lock this bearing with round nut (128) and tab washer (129). Place
Mount mechanical sealing stationary ring and O-ring into drive mechanical seal adjustable ring (19) onto driving shaft (05), mount
shaft bearing cover to form drive shaft bearing cover assembly. the rotary casing, O-ring and rotary ring of the mechanical seal.
Fasten the assembly of driving shaft bearing cover into the front
Affix the twin shaft assembly together and insert into the bearing housing (02) with bolts (126) and spring washer (127).
appropriate mounting holes.
I nstall the adjustable ring (29) of bearing (which was labeled
ount key (134) into driving and driven shafts assembly
M during disassembly) onto driven shaft (06) and push bearing (101)
separately. Next, mount the timing gears into the drive shaft with the appropriate tool. Fasten the assembly of bearing cover
together in accordance with the meshing position marked during (12) into the front bearing housing (02) with bolts (126) and spring
disassembly. washer (127).
F asten back bearing housing (03) and gasket (22) onto pump
casing (01) with double-ended studs (117), plain washer (119) and
nuts (118).
I f applicable, mount pedestal (45) onto pump casing (01) with
bolts (120), nuts (121) and spring washer (122).
c r o ss - s e c t i o n a l d i a g r a m s
2VE PUMPS
c r o ss - s e c t i o n a l d i a g r a m s
2HE...A PUMPS
c r o ss - s e c t i o n a l d i a g r a m s
2HE...B PUMPS
Figure 5 T ighten rear bearing housing (03) to pump casing (01) by two
nuts (118), install gear (13), space sleeve (17) onto shaft (05), let
gear flank contact bearing housing flank, tighten the other flank
Disassembly of Timing Gears of gear with end plate (16) and bolt (115) in place to prevent the
axial movement of driving and driven shaft.
S ee Figure 6. Jam the teeth of the gear wheels (13 & 14) with a
copper sheet. Loosen the set screw in the coupling of pump side, pull the
coupling off driving shaft with tools, remove key (136).
Remove bolt (115), spring washer (116) and end plate (16).
Loosen bolts (126), spring washer (127) and remove bearing
Remove gear wheels (13 & 14), keys (134) and space bushing (17). covers (11 & 12). Next, remove O-rings (103) from bearing covers
Next, label the dismantled items. (11 & 12) and oil seal (105) from bearing cover (11).
ATTENTION: If applicable, loosen set screws (138) and remove shaft sleeve (25).
• Only when the replacement of new timing gears, new shafts L oosen locking washers (129) and locking nuts (128) from driving
or new screws is required, bolts (112) can be loosened and shaft (05). Next, loosen locking washers (129) and locking nuts
the gear wheel (14) and gear sleeve (15) can be separated. In (128) from idle shaft (06).
case of reassembly, normally, the removed bolts (112), spring
washers (113) and flat washers (114) must be replaced.
max
min
FIGURE 6 OilFigure
Level of 9the Gear Casing
Figure 8
I nstall space sleeve (17) on driving and driven shaft (05 & 06).
Install key (134) on driving shaft (05); install driving gear wheel
(13) on driving shaft (05); install end plate (16), spring washer
(116) and tighten with bolt (115). By the meshing point between
gear wheel (13) and (14), install driven gear wheel unit (14); install
key (134) on driven shaft (06); install end plate (16), spring washer
(116) and tighten with bolt (115).
I nstall stud screws (120) and oil glass (106) on gear box (04) to
form gear box unit. Next, install the gear box unit and gasket (28)
onto rear bearing housing (03). Tighten with stud screw (120), nuts
(121) and flat washers (122).
c r o ss - s e c t i o n a l d i a g r a m s
2HC...AP PUMPS
c r o ss - s e c t i o n a l d i a g r a m s
2HC...BP PUMPS
c r o ss - s e c t i o n a l d i a g r a m s
2HCG...B PUMPS
c r o ss - s e c t i o n a l d i a g r a m s
2HC...P PUMPS
c r o ss - s e c t i o n a l d i a g r a m s
2HM...A PUMPS
c r o ss - s e c t i o n a l d i a g r a m s
2HMB PUMPS
c r o ss - s e c t i o n a l d i a g r a m s
2HM...B PUMPS
c r o ss - s e c t i o n a l d i a g r a m s
2HMG...C PUMPS
c r o ss - s e c t i o n a l d i a g r a m s
2HM...P PUMPS
c r o ss - s e c t i o n a l d i a g r a m s
2HRA PUMPS
c r o ss - s e c t i o n a l d i a g r a m s
2HRG PUMPS
c r o ss - s e c t i o n a l d i a g r a m s
2VM PUMPS
Figure 10
Figure 11
Figure 12
NOTE: The following instructions apply only to the following ATTENTION: If any nicks, gouges or abrasive wear is identified, the
pumps: 2HM, 2HC and 2HR-series. O-ring (319) and gasket (308) must be replaced.
ATTENTION: Only the when the spring of the valve is relaxed can Install valve core (303).
the spindle base (343) be opened. In order to keep spring tension I nstall guide sleeve (342) into valve bonnet (304) and tighten
after reassembly (to ensure the release pressure is the same) S locating plate (345) with screw (324).
Series suggests to record the number of revolutions completed to
relax the spring. I nstall O-ring (319) on the push bar (341) and insert into guide
sleeve (342) to form valve bonnet unit.
Disassembly of Pressure-Limited Valve
Install valve bonnet unit and gasket (308) into valve casing (301),
Loosen screws (323) and remove cover (344). then fasten with screws (310) and spring washers (311).
emove the nut (322), turn the adjusting spindle (306) counter-
R I nstall spring holder (305) on push bar (341) and place spring (307)
clockwise until it cannot be turned and record the number of on the holder.
revolutions completed.
T urn adjusting spindle (306) into adjusting spindle base (343) until
L oosen screws (320) and spring washers (321). Remove adjusting it cannot turn.
spindle base (343), adjusting spindle (306) and spring holder (305) as
one unit. Remove spring holder (305) from adjusting spindle (306). I nstall spring holder (305) and spring (307) on adjusting spindle
Turn adjusting spindle (306) out of adjusting spindle base (343). (306).
Remove spring (307) and the spring holder (305). Tighten adjusting spindle base unit with screws (320) and spring
washers (321) to the valve bonnet (304).
Loosen screws (310) and spring washers (311). Then, remove valve
bonnet (304), push bar (341), guide sleeve (342) and locating plate djust the tension of the spring (307), readjust spindle (306) clock-
A
(345) and O-ring (319) as one unit. wise by the number of revolutions completed that was previously
recorded.
L oosen screws (324) and remove locating plate (345), guide sleeve
(342), push bar (341) and O-ring (319). Locate the spindle (306) by turning the nut (322) toward the
surface of spindle base (343).
Remove valve core (303).
Install cover (344) and tighten with screw (323).
Figure 13
NOTE: The following instructions apply only to the following ATTENTION: If any nicks, gouges or abrasive wear is identified, the
pumps: 2HE, 2HCE, 2VE, 2HM, 2HC, 2HR and 2VM-series. O-ring (319) and gasket (308) must be replaced.
ATTENTION: Only when the spring of the valve is relaxed can the I nstall O-ring (319) into the groove of adjusting spindle (306).
bonnet (304) be opened. In order to keep spring tension after Place into the hole of valve bonnet (304) and assemble spring clip
reassembly (to ensure the release pressure is the same) S Series (318) to form valve bonnet unit.
suggests to record the number of revolutions completed to relax I nstall valve core (303), spring (307), gasket (308) and valve bonnet
the spring. (304) unit. Tighten this unit to valve casing (301) with screws (310)
Disassembly of Pressure-Limited Valve and washers (311).
T urn the adjusting spindle (306) counter-clockwise until it cannot Adjust the tension of the spring (307), readjust spindle (306)
be turned and record the revolutions quantity. clockwise by the number of revolutions completed that was
previously recorded.
Loosen screws (310) and spring washers (311). Remove valve bonnet
(304), adjusting spindle (306) and spring holder (305) as one unit.
Remove spring (307) and valve core (303).
emove spring holder (305) and spring clip (318). Pull adjusting
R
spindle (306) from valve bonnet (304), and remove the O-ring
(319) and gasket (308).
Figure 14
ATTENTION: Only when the spring of the valve is relaxed can the I nstall O-ring (319) into the groove of adjusting spindle (306), put
bonnet (304) be opened. In order to keep spring tension after them into the hole of valve bonnet (304) and assemble spring clip
reassembly (to ensure the release pressure is the same) S Series (318) to form valve bonnet unit.
suggests to record the number of revolutions completed to relax I nstall valve core (303), spring (307), gasket (308) and valve bonnet
the spring. (304) unit. Tighten this unit to valve casing (301) with screws (310)
and washers (311).
Disassembly of Pressure-Limited Valve
Adjust the tension of the spring (307), readjust spindle (306)
T urn the adjusting spindle (306) counter-clockwise until it cannot
clockwise by the number of revolutions completed that was
be turned and record the number of revolutions completed.
previously recorded.
Loosen screws (310) and spring washers (311). Remove valve
bonnet (304) and adjusting spindle (306) and spring holder (305)
as one unit.
Remove spring (307) and valve core (303).
emove spring holder (305) and spring clip (318). Pull adjusting
R
spindle (306) from valve bonnet (304), and remove the O-ring
(319) and gasket (308).
Figure 15
NOTE: The following instructions apply only to the following ATTENTION: If any nicks, gouges or abrasive wear is identified,
pumps: 2HM, 2HC, 2HR and 2VM-series. O-rings (319 & 320) and gasket (308) must be replaced.
ATTENTION: Only when the spring of the valve is relaxed can the Install valve core (303).
bonnet (304) be opened. In order to keep spring tension after Install O-ring (319 & 320) onto push bar (341). Insert into valve
reassembly (to ensure the release pressure is the same) S Series bonnet (304) to form valve bonnet unit.
suggests to record the number of revolutions completed to relax
the spring. Place gasket (308) between valve and valve bonnet unit and
tighten with screw (310) and spring washer (311).
Disassembly of Pressure-Limited Valve
Install spring holder (302) onto push bar (341).
T urn the adjusting spindle (306) counter-clockwise until it cannot
be turned and record the number of revolutions completed. T ighten sleeve casing (315) to valve bonnet (304) with screws
(321) and spring washers (322).
Loosen screws (323) and washers (324). Remove spring cover
(316), adjusting spindle (306), spring holder (305) and spring clip T urn spring holder (305) to the end of adjusting spindle (306) and
(318) as one unit. Next, remove spring (307). insert into spring cover (316). Next, install spring clip (318) to form
spring cover unit.
emove spring holder (305) from adjusting spindle (306) and
R
remove spring clip (318). Pull the adjusting spindle (306) out of lace spring (307) onto spring holder (302) and tighten spring
P
spring cover (316). cover unit to sleeve casing (315) with screws (323) and washers
(324).
L oosen screws (321) and spring washers (322). Next, remove
sleeve casing (315) and remove spring holder (302). Adjust the tension of the spring (307), readjust spindle (306)
clockwise by the number of revolutions completed that was
Loosen screw (310) and spring washer (311). Remove valve bonnet previously recorded.
(304), push bar (341), gasket (308) and O-ring (319 & 320) as one
unit. Pull push bar (341) from valve bonnet (304) and remove
O-ring (319 & 320) from push bar (341).
Remove valve core (303).
Figure 16
ATTENTION: It is necessary to dismantle some parts of the pump ATTENTION: Clean the sliding interface of the mechanical seals
prior to the disassembly of the mechanical seal. Mechanical seals with silicon oil or water.
must be disassembled with care to ensure that the sealing slide Install the rotating casing (204) of the mechanical seal onto shafts
rings are not damaged. Immediately mark or label all disassembled (05 & 06), adhere to the adjusting ring (19) and fasten with set
parts in order to avoid confusion at time of reassembly. After screw (202). Assemble rotating ring and O-ring to the rotating
disassembling, all parts should be carefully cleaned and checked casing.
prior to reuse; any defective parts should be replaced.
Press stationary ring (206) and O-ring (205) into sealing box (09)
Single Mechanical Seal by hand.
NOTE: The following instructions apply to the following pumps: ATTENTION: The stationary ring must be affixed by doweling (208).
2H, 2HE, 2HCE, 2VE, 2HM, 2HC, 2HR and 2VM-series. Mount the pressing board (38) (if present) on the sealing box (09)
Disassembly of Mechanical Seal with screw (150) and spring washers (151).
If screws (150) are present, loosen the screws (150) and spring Continue with appropriate pump assembly instructions.
washers (151) before removing pressing board (38).
Disassemble stationary seal ring (206) and O-ring (205).
Disassemble rotating ring and O-ring.
Loosen set screws (202) and remove the rotating casing (204).
Remove adjusting ring (19) and label appropriately.
Figure 17
NOTE: The following instructions apply only to the following ATTENTION: Clean the sliding interface of the mechanical seals
pumps: 2HE, 2HCE, 2VE, 2HM, 2HC, 2HR and 2VM-series. with silicon oil or water.
Disassembly of Mechanical Seal Press stationary seal ring (206) and O-ring (205) into sealing box
(60) by hand.
L oosen screws (150) and set screw (154) and remove sealing box
(60), shaft sleeve (61) and mechanical seal unit. ATTENTION: The stationary seal ring must be affixed by doweling
(208).
ATTENTION: Before disassembly, install pressing board (62) onto
the groove of the shaft sleeve (61). ount rotating ring units of mechanical seal onto shaft sleeve
M
(61) and fasten with set screw (202) as originally marked in disas-
Loosen set screws (202) and disassemble rotating rings unit (204). sembly section.
ATTENTION: Before further disassembly, label and measure the Fasten cartridge-type singe mechanical seal with screw (150);
relative position of set screw (202) and shaft sleeve (61). fasten set screw (154).
nscrew screw (153) and disassemble shaft sleeve (61) and
U ount pressing board (62) onto sealing box (60) with screw (153)
M
pressing board (62). and fasten shaft sleeve (61).
Disassemble the stationary seal ring (206) and O-ring (205). Loosen screw (153), move pressing board (62) out of the groove in
shaft sleeve (61), then fasten screw (153).
Continue with appropriate pump assembly instructions.
Figure 18
NOTE: The following instructions apply only to the following ATTENTION: Clean the sliding interface of the mechanical seals
pumps: 2HM, and 2HR-series. with silicon oil or water.
ATTENTION: These instructions will only be applicable to 2HM Press stationary ring (206) and O-ring (205) into sealing box (60)
and 2HR series Pumps. by hand.
Disassembly of Mechanical Seal ATTENTION: The stationary ring must be affixed by doweling
(208).
Disassemble screw (151) and spring washer (152) then loosen set
screw (154). Next, remove the cartridge-type mechanical seal. I nstall rotating ring (204) unit and adjusting ring (19) on shaft
Remove gasket (27) and O-ring (164). sleeve (61), fasten with set screw (202) at the original position
(marked during disassembly) and install O-ring (165).
ATTENTION: Before disassembly, install pressing board (62) onto
the groove of shaft sleeve (61). lace the pressing board (62) into the groove of the sleeve (61)
P
and tighten to sealing box (60) with bolt (153).
nscrew (150) and disassemble sealing box (09) and sealing box
U
(60) unit. Remove gasket (26). I nsert stationary ring (206) and O-ring (205) into sealing box (09)
by hand. Next, install pressing board (38) and C-clip (149).
Disassemble C-clip (149), pressing board (38), stationary ring (206)
and O-ring (205). ATTENTION: The stationary ring must be affixed by doweling
(208).
L oosen screw (153) and disassemble pressing board (62). Remove
shaft sleeve (61) and rotating ring (204) unit; remove O-ring (165). Place gasket (26) between sealing box (09) unit and sealing box
(60) unit and tighten with screw (150).
Loosen set screw (202) and disassemble rotating ring (204) unit
and adjusting ring (19). Label and measure the relative position I nstall O-ring (164) in the groove on the space plate (50), install
of set screw (202). Label these parts to avoid confusion during cartridge-type mechanical seal and gasket (27) on space plate
reassembly. (50); tighten with screw (151) and spring lock washer (152).
Disassemble the stationary seal rings (206) and O-ring (205). Fasten set screw (154) to the shaft.
L oosen bolt (153), remove pressing board (62) out of the groove in
shaft sleeve (61), then fasten bolt (153).
Continue with appropriate pump assembly instructions.
Maag, a Dover Company, warrants its products free from defects in materials and workmanship under normal use
and service for which its products were designed. This warranty is for a period of 12 months after installation or
18 months after shipment from the factory, whichever comes first. This standard warranty applies unless specific
warranty conditions are granted in writing by Maag. If its products should fail through defect in workmanship or
material within the stated warranty period, Maag must be notified in writing within the warranty period of such
defects and shall have the option of requiring return of parts or product to its factory for verification of any claim. The
warranty is in lieu of any other liability for defects.
MAAG MAKES NO WARRANTY OF MERCHANTABILITY AND NO WARRANTY THAT ITS PRODUCTS SHALL BE
APPROPRIATE FOR ANY PARTICULAR PURPOSE, nor are there any other warranties, expressed or implied, by
operation of law or otherwise. This warranty does not cover any expense (labor, lost production, travel expenses,
etc.), incurred in repairs or alteration made outside the Maag factory without prior authorization, nor does it cover
in any way the performance of equipment which has been revised or altered by others. The customer is wholly
responsible for establishing the suitability of the product for his particular application and for operating conditions,
which do not exceed published product limitations. Maag shall not be liable for damages or delay resulting from or
related to defective products, nor for consequential, special or contingent damages for breach of warranty.
Item # Serial #
Y o u r I n f o r m at i o n
Company Name
Industry
Name Title
Street Address
Types of pumps in facility (check all that apply): Diaphragm Centrifugal Gear Submersible Lobe
Other
How did you hear of Wilden Pump? Trade Journal Trade Show Internet/Email Distributor
Other
Authorized Representative: