Letter To Patel Regarding Status of Approval

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

SREPL/NH48/PIL/Mis/2023-24/18

Date: February 14, 2024

To,
Authorized Signatory,
M/s Patel Infrastructure Ltd.,
Patel Office, Beside Prakurti Resort,
Chhani Road, Chhani Vadodara,
Gujrat - 391740
Email: [email protected], [email protected]

Project: Strengthening /Overlaying on six lane Gurgaon-Kotputli-Jaipur section of


NH48 (Old NH-8) from Km 188+000 to 268+300 in the State of Rajasthan at
the Risk and Cost of Concessionaire.

Subject: Regarding various correspondence /pending approvals not being shared with us .

Ref: Sub Contract Agreement dated 21.08.2023

Dear Sir,

This is in reference to the provision of sub contract agreement clause 17(C), The main
contractor shall have to provide necessary support to Associate Contractor in management
of day-to-day correspondence being done for the sub contracted package (the Package-2).

It is very obvious that we as a sub-contractor don’t have any authority to write letters
directly to IE & NHAI and thus forwarding all letters to you as DRAFT for onward submission
to IE /NHAI for seeking their approval, necessary decisions regarding package -2 works. We
expect that the outcome of our draft letter shall be reverted back to us along with all
concerned correspondences without delays. Which is observed to be missing from your
side. In nutshell the correspondences related to our package is not being shared with us
timely which is a reason of rising complications to us for taking appropriate action related to
our works. In other words, this will be a direct impact on work progress.

We are still awaiting correspondence/response of our letters submitted to you as DRAFT


requiring approval or necessary action by the IE/NHAI. The necessary details are pending as
per following.

S.No. Draft Letter Date of submission Delays Correspondence with


submitted to M/s PIL to M/s PIL respect to SREPL draft
by SREPL (Sub cont) letter shared by M/s PIL

1 Draft letter with Sent via Email on 52 days No correspondence


credential for approval 16.12.2023 & provided yet.
of Expansion Joint again on
23.12.2023

2 Draft letter with Sent via Email on 49 days No correspondence


credential for 27.12.2023 provided yet.
approval of Bitumen
emulsion Royal
Bitumen Pvt Ltd.
3 DBM grade I & II JMF Submitted by PIL No correspondence
with 40% RAP letter 71 dated provided yet.
material 2.11.2023 &n PIL
letter 107 date
07.12.2023

4 Draft letter with Sent via Email No correspondence


DBM Grade II provided yet.
JMF/Design with
virgin aggregate
material

5 Draft letter with BBS Sent via Email on 50 days No correspondence


for MNB 213+506 26.12.2023 provided yet.

6 Draft letter with PQC Sent via Email on 22 days No letter provided yet.
design M 40 for rigid 23.01.2024
pavement works.

7 Draft letter with No correspondence


concrete mix design provided yet.
M-15, M-20 & M-35
with Wonder
cement.

8 Draft letter with No correspondence


design of BC grade-I provided yet.
& II with VG 40

9 Draft letter for No correspondence


approval source of provided yet.
aggregate from M/s
Bala ji Trading
10 Draft letter for No correspondence
approval source of provided yet.
aggregate from M/s
Bala Ji minerals
11 Draft letter for No correspondence
approval source of provided yet.
aggregate from M/s
Urmila Stone
Crusher
12 Draft letter for No correspondence
source approval of provided yet.
Antistripping Agent
from M/s Petrochem
13 Draft letter for Sent via Email on 12 Days No correspondence
source approval of 02.02.2024 provided yet.
Admixture from M/s
Don
14 Draft letter for Sent via Email on 11 Days No correspondence
Source approval of 03.02.2024 provided yet.
PMB from M/s
Jalnidhi & M/s IOTPL

15 Draft letter for Sent via Email on 11 days No correspondence


shifting existing 03.02.2024 provided yet.
utility at MNB
213+506 Urgent
requirement.
16 Draft letter for Sent via Email on 8 days No correspondence
approval of design of 06.02.2024 provided yet.
filter media
17 Draft letter for Sent via Email on 3 days No correspondence
approval of Concrete 11.02.2024 provided yet.
mix design M15,
M20, M25 M30 &
M40 with Ultratech
cement

18 Draft letter for Sent via Email on 3 days No correspondence


approval of Borrow 11.02.2024 provided yet.
Area No. 1
19 Draft letter for Sent via Email on 2days No correspondence
approval of Concrete 12.02.2024 provided yet.
Mix design for M 45
conducted by Hitech
Lab (Third party Lab)
20 Draft letter for Sent via Email on 2days No correspondence
requirement of 12.02.2024 provided yet.
shifting electric line
& pole for const of
Sr
21 Draft letter Sent via Email on 10days No correspondence
regarding public 04.02.2024 provided yet.
complaints issues for
the section not
under our scope

It is important to mention that the delays in sharing of correspondences/information to us


related to Package-2 will be a direct impact on work progress of package-2. We once again
request you to share all the letters/correspondence related to Package-2 received from IE
and NHAI to us without delays.

Thanking you and assuring you of our best services at all times.

For Shankar Ramchandra Earthmovers Pvt. Ltd.,

Project Manager

You might also like