6 Project Cost Management
6 Project Cost Management
90
80
70
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A) Zero days
B) Two days
`
C)
D)
Four days
One day
Standard deviation is a range that an estimate can vary +/- from the mean. The project needs
to be done in 40 days, and the schedule calls for 38 days, so the project float is 2 days. With a
standard deviation of two days, the project will take 38 +/- 2 days, or 36 to 40 days.
Therefore, project float could be 0 to 4 days.
Project Management Process
Project Cost Management
Project Cost Management Processes
In some projects, especially with smaller scope, cost estimation and cost
budgeting are so tightly linked that they are viewed as a single process.
Quick Fact Cost Management Processes
Some project costing may involve predicting and analyzing the future financial
performance of deliverables and may include techniques such as Return on
Investments (ROI), Discounted Cash Flow and Investment Pay Back Analysis.
7.1 Plan Cost Management
Analytical techniques
Developing the cost management plan may involve choosing strategic options to fund
the project such as: self-funding, funding with equity, or funding with debt. The cost
management plan may also detail ways to finance project resources such as making,
purchasing, renting, or leasing. These decisions, like other financial decisions affecting
the project, may affect project schedule and/or risks.
Organizational policies and procedures may influence which financial techniques are
employed in these decisions. Techniques may include (but are not limited to): payback
period, return on investment, internal rate of return, discounted cash flow, and net
present value.
Plan Cost Management called the “budget management plan” or “budget plan”
Cost Management Plan
Plan Cost Management called the “budget management plan” or “budget plan”
Specifications for how estimates should be stated – in what currency?
The level of accuracy needed for estimates.
Reporting format to be used
Guidelines for establishment of a cost baseline for measuring against as part of
project monitoring and controlling ( the cost baseline will ultimately be
established in Determine budget.)
Cost change control procedures
Funding decisions
Guideline for dealing with potential fluctuations in resource cost and exchange
rates.
Roles and responsibility for various cost activities.
Control threshold; Control threshold are the amount of variation allowed
before you need to take action.
7.2 Estimate Cost
Project Cost Estimating
Type of Cost
Cost can or Indirect be Direct
Direct costs These costs are attributed directly to the project work and cannot be
shared among projects (Wages, Material, Equipment etc).
Indirect costs Overhead costs that incurred for the benefit of more than one project
(Taxes, Training, project management software license, and so on).
Variable costs Costs that vary depending on the amount of work or production
(Cost of materials, supplies, wages etc..).
Fixed costs These costs remain constant throughout the project (Cost of office
setup, rentals etc...).
Cost Estimating – Inputs
Scope Baseline
You need to know,
What are you estimating?
What is in your scope?
What constrains have been placed on the project?
All these information can be found in project scope statement, WBS and WBS
dictionary.
Project Schedule
You need to know,
When the work will occur?
Timing of when you buy something effect its cost?
You need to develop a time phase spending plan to control project expenditures
(budget) so that you knowhow much money will be spent during specific period
of time (e.g. January next month etc.)?
Cost also can effect the schedule e.g. the price of material or equipments may vary
due to factors like seasonal pricing fluctuations, new model release, etc. if you know
in advance that something going to be expansive and it is time to purchase. You
might need to change the schedule.
Cost Estimating – Inputs
Human Resources Plan
You need to know,
What rates paid to worker?
What resources and when you need to plan add costs in budget?
What constrains have been placed on the project?
Risk Register
There are cost associated with the effort to deal proactive with risk (both
opportunities and threats). Risk are an inputs to this process because they influence
how cost are estimated, but they can also be an output because our choice related
to estimating cost have associated risk.
Cost Estimating - Tools and Techniques
Expert judgment
Expert judgment , guided by historical information , provides valuable insight about
the environment and information from previous similar projects.
Parametric Estimating
Parametric estimate uses statistical relationship between historical data and other
variables
Per sq.ft cost of previous project of similar nature was XYZ and hence the new projec
shall cost XYZ multiplied by new total area.
Parametric estimate can be applied to total project or part of project.
Cost Estimating - Tools and Techniques
Bottom-up Estimating
Cost estimation starts from bottom level.
Each WBS work package is estimated and rolled up to higher level.
While this method is more expensive, it is also one of the most accurate.
Each resource in the project must be accounted for and assigned to a cost category.
Categories include the following:
Labor costs
Material costs
Travel costs
Supplies
Hardware costs
Software costs
Special categories (inflation, cost reserve, and so on)
Cost Estimating – Outputs
Estimating Accuracy
Accuracy of estimate is normally refined during the course of project to reflect additional
details as it becomes available.
Rough order of magnitude This estimate is “rough” and is used during the initiating
processes and in top-down estimates. The range of variance for the estimate can be from
+/- 50%.
Later the estimate can be refined to a range of +/- 10%
Refinements and range of accuracy depends on policies of individual organizations.
Basis of estimates
Once the estimates have been completed, supporting detail must be organized and
documented to show how the estimates were created.
Specifically, the supporting detail includes the following:
Document basis of estimate (how it was developed)
Information on the assumptions and constraints made while developing the cost
estimates.
Information on the range of variance in the estimate For example, based on the
estimating method used, the project cost may be $220,000 ± $15,000.
Indication of the confidence level of the final estimate
7.3 Determine Budget
Cost Aggregation
Activity costs are rolled up to work package costs. Work package costs are
rolled up to control account cost and finally into project cost.
Reserve Analysis
Budget reserves are kept for both contingency reserve and management
reserve.
Contingency Reserves
Monetary reserves kept for identified but unplanned changes (risks).
Project manager will normally have the authority to utilize contingency
reserves.
Contingency reserves are placed for changes that can result from an
identified risk.
Contingency reserves address the cost impact of the risk remaining
during risk response planning.
7.3 Determine Budget – Tools and Techniques
Management Risk
Budget set aside to cover unforeseen risks or changes to the project. This is
the budget kept for unidentified risks.
Management reserve will not be part of project budget and hence project
manager need approval from management for using this reserve.
The cost baseline will contain the contingency reserve and the cost budget will
include the management reserve.
Management reserves are not part of earned value calculations (since it is not
part of cost baseline & measurements are based on baselines)
Management reserves are additional funds set aside to cover unforseen risks
to the project.
7.3 Determine Budget – Tools and Techniques
7.3 Determine Budget – Tools and Techniques
7.3 Determine Budget – Tools and Techniques
Historical Relationships
A historical knowledge of previous project of similar nature can be used for
determining budget.
Parametric or Analogous estimates can be used. This method used the
statistical relationship between historical data and variable (Data multiplied by
variable)
Funding Limits Reconciliation
Funding Limit Reconciliation is and organization’s approach to managing cash
flow.
Budgeting will result in S curve showing time phased cost requirements and
project manager shall negotiate fund requirements with organization prior to
finalization of cost baseline and schedule.
Changes in funding may results in changes to project management plan and
schedule.
An realistic budget is project manager’s fault.
Funding normally happed in steps where are expenditure follow S curve.
7.3 Determine Budget – Tools and Techniques
Cost baseline forms the shape of an S-curve indicating low spending in the
initial stages of project and increasing towards end of the project.
7.3 Determine Budget – Outputs
Total funds required are cost baseline plus management reserve, if any.
Questions and Answers
The main focus of life cycle costing is to:
A project manager is responsible for all that goes on in the project. One of the most
important duties that the project manage can perform is the function of:
A. Risk management
B. Quality management
C. Cost management
`
D. Integration
Questions and Answers
Resource leveling will generally:
A. Reduce the time needed to do the project
B. Increase the total time necessary to do all the tasks
`
C. Reduce the over utilization of resources
D. Reduce resources to the lowest skill that is possible
Decisions as to the types of projects that should be accomplished and strategic plans as to the
quality of the projects that are required should be the decision of which of the following?
A. Project manager
B. Procurement manager
`
C. Upper management
D. Stakeholders
210. You have been asked to take charge of project planning for a new project, but yo have very
little experience in managing projects. What will be the best source of help for you?
A. Your education.
B. You on-the-job training.
`
C. Historical information.
D. Your functional manager.
7.4 Control Cost
Work package XX have a 4 stages and each stage will take one week to
complete with $500 estimated cost per stage.
Total Planned Value for project will be approved total budget (Remember
– Management reserve is not part of EVM) and is known as Budget at
completion (BAC)
7.4 Control Cost – Tools and Techniques
Earned Value (EV)
Estimated (not actual) value of work actually complete terms.
Work package XX have a 4 stages and each stage will take one week to
complete with $500 estimated cost per stage. End of 2nd week 3 stages
were completed what is the PV and EV.
Work package XX have a 4 stages and each stage will take one week to
complete with $500 estimated cost per stage. End of 2nd week 3 stages
were completed and contractor has spend 1700. What is the PV, EV & AC
Tips
EV comes first in all equations.
For Schedule related equation there is PV and AC for cost related
7.4 Control Cost – Tools and Techniques
Forecasting
Using the earned value analysis, team can now forcast the project
performance.
3. Here team considers that remaining work will be completed at the same
efficiency rate considering cost and schedule performance. EAC = AC +
(ETC/CPI x SPI) & ETC = BAC – EV.
TCPI predicts the efficiency that must be achieved for remaining work to
complete the remaining works with availble budget.
TCPI (based on original estimate or forecasted budget) will set a new baseline
for performance efficiency to be achieved to complete the works with funds
remaining.
If CPI falls below TCPI baseline, remaining works will not be completed with
available funds. All future works shall be accelerated to bring CPI within range.
TCPI TCPI value >1 means in future, more work must be achieved per every
dollar spent in the future compared to actual work achieved previously per
dollar.
TCPI value <1 means in future lesser work need to be achieved for every dollar
spent compared to past performance
7.4 Control Cost – Tools and Techniques
Examples
A project has the following Earned value data assessed: AC: $ 4,000,000
CV: $ -500,000 SPI: 1.12 BAC: $ 9,650,000 What is the Earned value of the
project? What is the CPI? What is the TCPI?
In your project, there have been several changes in the cost and schedule
estimates and the original estimating assumptions are no longer valid.
What is the Estimate at Complete for your project? BAC = $ 300,000, AC =
$100,000, EV = $ 150,000, CPI = $ 1.2, ETC = $ 120,000
7.4 Control Cost – Tools and Techniques
7.4 Control Cost – Tools and Techniques
Next Week Test