Full-Paper 117
Full-Paper 117
Full-Paper 117
Abstract: There are several benefits that are associated with precast prestressed concrete including
structural performance, cost, efficiency and improved sustainability. However, to facilitate efficient
manufacture, the concrete needed for daily production cycles tends to have high Portland cement
contents to achieve high early age strength for the transfer of prestress forces. This results in concrete
having a higher embodied carbon per cubic metre when compared with more conventional in-situ
concrete. In recent years a large emphasis has been placed on sustainability and reduction of carbon
emissions in the concrete industry which contributes up to 8% of global emissions [1] [2]. One of the
primary and most effective methods of reducing the embodied carbon in concrete is to increase the use of
supplementary cementitious materials (SCM’s) and reduce the amount of Portland cement. The reduction
in Portland cement content reduces the early age strength, resulting in longer production cycle times,
which reduce the efficiency of precast pretensioned prestressed construction [3]. This paper examines
different girder construction methodologies, processes and materials used to construct a two-lane bridge
in Newcastle NSW spanning 37m and the impacts they have on sustainability.
1. Introduction
Concrete is a versatile material and is used in a variety of applications due to its high compressive strength
and durability. Per kilogram, concrete has lower embodied carbon emissions than other construction
materials like steel this is illustrated in Figure 1. Due to the high usage of concrete, the concrete industry
contributes up to 8% of global CO2 emissions, 80-90% of these emissions comes from the manufacture of
Portland cement. With the increase in urbanisation, cement production is forecast to increase by 25-50%
globally [1] [2] [3], therefore there is a need for the construction industry to provide improved sustainability
in design, construction methodologies and asset management.
The details of the girder cross sections for the three different construction methodologies investigated in this
study are presented in Figure 2&3.
1850 Deep Reinforced Concrete 1450 Deep Welded Steel
I Girder I Girder
Figure 2.
Factory manufactured Super-Ts provide a very economical and sustainable solution to other forms of
construction because they are able to be manufactured on a 24-hour cycle. To maintain this cycle, however,
there is a need to utilize a concrete technology which is capable of the achievement of high early strength,
nominally 35-40MPa in 12-15 hours. This is achieved by the use of high Portland cement content / low water
cement ratio mix designs coupled with heat accelerated curing. Heat accelerated curing is provided by
applying steam (or other heat source) to the PSC element at a temperature range of 50-70 °C for 8 hours.
To avoid the risk of thermal cracking and DEF (Delayed Ettringite Formation) limits are imposed on the heat
cycle, minimum pre-setting period 2hrs, maximum temperature rise of 24°C / hr and a maximum temperature
of 70 °C. Transfer of prestress can occur when the element has achieved its minimum transfer strength (as
determined by representative test specimens cured under identical conditions) and the cured maturity of the
concrete is ≥ 350 °C-hrs. Factory manufactured reinforced concrete elements also need to achieve minimum
strengths prior to demoulding sufficient to ensure that the element can support its own weight without
unacceptable cracking due to demoulding and handling forces. In both cases the mix designs are controlled
by the achievement of early strengths necessary to achieve these conditions rather than the ultimate 28-
day strength criterion. [12] [13]
It is for these reasons that the CO2 emission targets imposed on in-situ cannot be fairly compared to the
precast alternatives. Put another way the 50MPa concrete specified for PSC Super T’s is better compared
to a 75MPa high early strength mix on the construction site.
Design was undertaken considering deflection requirements for the girders where calculated pre-
cambers and deflections are presented in table 4.
Table 4. Girder Deflection
Girder Type Pre- DLLong term Permanent LL Total LL +
camber/ Deflection Sag (mm) Deflection Permanent
Hog (mm) (mm) (mm) Sag (mm)
Steel1 -942 Min 94 0 61 61
In-situ Concrete1 -1143 Min 114 0 53 53
Prestressed Concrete -514 24 5
-27 61 34
Super-T
1
Beam pre-cambered to achieve AS5100 requirement for no sag under permanent loads (i.e. minimum
pre-camber to match deflection for DLLongterm).
2
Prior to application of girder self weight and weight of deck slab (i.e. girder fabricated on its side).
3
Slab cast integral with beam.
4
Hog at 28 days without concrete slab.
5
Includes long term creep/hog under permanent loads (100 years).
2.4 Girder Strength
The bending strengths of the girders were calculated in accordance with AS 5100.5 and AS 5100.6. The
capacity of the girders may be compared through the use of a rating factor, which presented in table 5.
Table 5. Girder Load rating Summary
Girder Type Rating Factor (ULS
Bending M1600)
Steel 1.661
In-situ Concrete 1.03
Pre-stressed Concrete Super-T 1.06
1
Steel beam controlled by deflection under live load.
2.5 Emission Analysis
This assessment has focused on the production phase of a product only as outlined in BS EN 15978:2011
(Sustainability of construction works - Assessment of environmental performance of building - Construction
method.) referred to as Module A1-A3 see Figure 4 below.
Results
Embodied Carbon values were calculated for girder components and are presented in Table 7 for a single
girder and the total for seven girders required for the bridge. The analysis presented considers the options
described previously with additional bridge design variations as follows:-
A steel girder bridge
A reinforced concrete bridge made with concrete containing 100% GP cement;
A reinforced concrete bridge with concrete composed of 70% slag by mass of binder;
A prestressed Super-T bridge with concrete incorporating a binder composed of 25% fly ash by
mass of binder, and
A prestressed Super-T bridge with concrete incorporating a 450 kg/m3 total ternary binder
composed of 55% SCM by mass of binder.
In addition to the above, bridge options have been assessed for embodied carbon relative to the
prestressed Super-T bridge (from which the embodied carbon values have been normalised to ease
comparisons). Also presented in Table 7 is an estimate of the required production cycle (in days) for
girders manufacture within each bridge option
Further analyses on embodied carbon of the various design options were carried out and are summarised
in Figure 5. Embodied carbon results for the bridge have been normalised and compared with the reference
value for the Super-T bridge. The design options are those set out in Table 7 with further analyses presented
for Super-T girder bridges including:-
Steel with improved properties that are relevant to facilitating optimised girder design;
Having the ability to improve concrete batching to optimise concrete performance, and
Enabling higher and improved binder types specific to precast applications and enabling early age
strengths to facilitate more efficient production.
Relative Embodied Carbon Value Normalised to Super-T Girder
Figure 5. Evaluation of Bridge Design for Embodied Carbon Normalised to Super-T Girder
6. References
[1] A. Adesina, “Recent advances in the concrete industry to reduce its carbon dioxide
emissions,” Enviromental Challenges, vol. 1, 2020.
[2] G. Hammond and C. Jones, “Embodied energy and carbon in construction materials,” Proc.
Inst. Civ. Eng. Energy, 2008.
[3] l. Keyte, R. Lloyd, C. Holt, J. Chandler, D. Hocking and T. Thomas, “Low-carbon post-
tensioned concrete,” in Concrete Institute of Australia, Adelaide, 2017.
[4] T. Wiedmann and S. H. Teh, ICM Database – Integrated Carbon Metrics Embodied
Carbon Life cycle Invetory Database, Sydney: UNSW Sydney, 2019, 2019.
[5] L. Huang and G. Krigsvoll, “Carbon emission of global construction sector,” Renewable
and Sustainable Energy Reviews, vol. 81, no. 2018.
[6] D. Jenkins, J. Portella and D. Baweja, “Optimising Precast Bridge Girders for Sustainability
with the use of High Performance Concrete,” in 8th Australian Bridge Conference, Sydney,
2011.
[7] D. Jenkins and J. Portella, “Optimising Precast Bridge Girders for Sustainability with the
Use of High Performance Concrete,” in Australian Bridge Conference, Sydney, 2011.
[8] A. J. Schteinman, D. Baweja, A. Hajimohammadi and R. Fisher, “Improving Embodied
Emission Rating Tools for Concrete: Design and Constructional Considerations,” in
Concrete Institute of Australia, 2021.
[9] C. I. o. A. a. N. P. C. A. o. Australia, Precast Concrete Handbook, Sydney: Concrete
Institute of Australia, 2002.
[10] V. Sirivivatnanon, D. W. Ho and D. Baweja, The Role of Supplementary Cementitious
Materials in Australian Concrete Construction Practice Supplementary Cementitious
Materials in Concrete, A Practical Seminar on the Specification, Use and Performance of
Ground Granulated Blast Furnace Slag, Fly Ash, Perth, Adelaide, Melbourne, Canberra,
Sydney and Brisbane: Cement and Concrete Association of Australia, 1991.
[11] V. Sirivivatnanon, H. T. Cao, D. Baweja and D. Hassell, “Production of Australian Silica
Fume and its Utilisation in Concrete,” in International Conference on Fly Ash, Slag, Silica
Fume and Other Siliceous Materials in Concrete, CIA and CSIRO Division of Building,
Construction and Engineering, Leura, 1990.
[12] Z. Arneil, D. Baweja and E. Capelli, Optimising Steam Curing For Precast Prestressed
Concrete Girders, 2018.
[13] Transport for NSW, “Roads and Waterways - Transport for NSW,” 22 06 2022. [Online].
Available: https://roads-waterways.transport.nsw.gov.au/business-industry/partners-
suppliers/documents/specifications/nb80.pdf. [Accessed 28 03 2023].
[14] I. L. Larsen, I. G. Aasbakken, R. O’Born and K. Vertes, “Determining the Environmental
Benefits of Ultra High Performance Concrete as a Bridge Construction Material,” IOP
Conference Series: Materials Science and Engineering, vol. 245 (2017) 052096, 2021.
[15] G. Habert, D. Arribe, T. Dehove, L. Espinasse and R. L. Roy, “Reducing environmental
impact by increasing the strength of concrete: quantification of the improvement to concrete
bridges,” Journal of Cleaner Production, vol. 35, pp. 250-262, 2012.
[16] F. U. A. Shaikh, S. Luhar, H. S. Arel and I. Luhar, “Performance evaluation of Ultrahigh
performance fibre reinforced concrete – A review,” Construction and Building Materials,
vol. 232, 2020.
[17] A. P. Fantilli, O. Mancinelli and B. Chiaia, “The carbon footprint of normal and high-
strength concrete used in low-rise and high-rise buildings,” Case Studies in Construction
Materials, vol. 11, 2019.
[18] I. L. Larsen, “Determining the Environmental Benefits of Ultra High Performance Concrete
as a Bridge Construction Material,” in IOP Conference Series: Materials Science and
Engineering, 2017.
[19] G. Habert, E. Denarié, A. Šajna and P. Rossi, “Lowering the global warming impact of
bridge rehabilitations by using Ultra High Performance Fibre Reinforced Concretes,”
Cement & Concrete Composites, vol. 38, pp. 1-11, 2013.
[20] N. Randl, T. Steiner, S. Ofner, E. Baumgartner and a. T. Mészöly, “Development of UHPC
mixtures from an ecological point of view,” Construction Building Material, vol. 67, pp.
373-378, 2014.
[21] M. Hourigan, R. Heywood, P. Shaw and L. O'Moore, “Assessment and Behaviour of
Prestressed Concrete Bridge Beams in Shear with Less than Minimum Shear
Reinforcement,” in The International Federation for Structural Concrete 5th International
FIB Congress FIB 2018 Better Smarter Stronger, Melbourne, VIC Australia, 2018.