CM Assignment 2

The document provides instructions and data for five construction management problems and five PERT problems. For each construction management problem, students are asked to draw a network diagram, identify the critical path and project duration, and calculate event times. For each PERT problem, students are given activity time estimates and asked to calculate expected durations, earliest and latest event times, slack, and standard deviation and variance. The problems provide data on activities, durations, and precedence relationships for scheduling analysis exercises.

Uploaded by

moviesuploaderzz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views2 pages

CM Assignment 2

The document provides instructions and data for five construction management problems and five PERT problems. For each construction management problem, students are asked to draw a network diagram, identify the critical path and project duration, and calculate event times. For each PERT problem, students are given activity time estimates and asked to calculate expected durations, earliest and latest event times, slack, and standard deviation and variance. The problems provide data on activities, durations, and precedence relationships for scheduling analysis exercises.

Uploaded by

moviesuploaderzz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

CONSTRUCTION MANAGEMENT

ASSIGNMENT
CPM Problems
The activities with their time estimates and their precedence relationship are given below for small projects.
For all the problems

a) Draw the network diagram


b) Find the critical path and project completion time
c) Calculate EST, EFT, LST, and LFT for all activities and mark in the diagram.
d) Calculate total floats and free floats for each activity.
e) Open a tabular column and enter all reading
f) Mark the critical path in the network diagram

Problem - 1

ACTIVITY 1-2 1-3 2-3 2-5 3-4 3-6 4-5 4-6 5-6 6-7
DURATION
15 15 3 4 8 12 1 14 3 14
IN DAYS

Problem - 2

ACTIVITY A B C D E F G
PRE ACTIVITY NONE A A A B C&E D&F
DURATION IN
4 7 18 12 10 7 5
DAYS

Problem - 3

ACTIVITY 1-2 2-3 2-4 3-5 4-5 4-6 4-7 5-7 6-7 7-8
DURATION
1 3 3 4 2 5 9 4 2 2
IN DAYS

Problem - 4

ACTIVITY 1-2 2-3 2-4 3-4 3-5 4-5 5-6


DURATION IN
3 6 9 4 8 5 4
DAYS

Problem - 5

A project consists of the following activities from A to H. The precedence relationships between the
activities are as Follows: A and B is starting activities; H is the end activity; C follows A; E follows B; F
follows C; G follows D and E; H follows G and F. The duration in days of various activities are A=7, B=8,
C=9, D=5, E=4, F=6, G=9 and H=3
PERT Problems
The given projects consists of the following activities.

a) Calculate the expected time and mark on the network.


b) Find the project completion time and Identify the critical path
c) Find earliest expected time and latest allowable time for all events.
d) Calculate slack for all events. Open a tabular form and enter all details.
e) Compute standard deviation (S) and variance (V).

Problem - 1

ACTIVITY 1-2 2-3 2-4 3-5 4-5 4-6 5-7 5-8 7-9 8-9 6-10 9-10
t0 4 1 8 3 0 3 3 4 4 2 4 4
tl 8 4 12 5 0 6 6 6 8 5 6 10
tp 12 7 16 7 0 9 9 8 12 8 8 16

Problem - 2

ACTIVITY 1-2 1-3 1-4 2-4 2-5 3-5 3-6 4-6 5-6
t0 2 3 2 5 6 1 3 3 5
tl 5 12 5 14 15 4 6 6 8
tp 14 21 8 17 30 7 21 9 17

Problem – 3

ACTIVITY 1-2 1-6 2-3 2-4 3-5 4-5 6-7 5-8 7-8
t0 3 2 6 2 5 3 3 1 4
tl 6 5 12 5 11 6 9 4 19
tp 15 14 30 8 17 15 27 7 28

Problem - 4

ACTIVITY 1-2 2-3 2-4 3-4 3-5 4-5 5-6


DURATION IN
3 6 9 4 8 5 4
DAYS

Problem - 5

ACTIVITY 1-2 1-3 2-4 2-5 4-7 5-7 7-8 3-6 6-8
DURATION
5 10 1 6 12 3 4 7 6
IN DAYS

*In PERT problems if only one time estimate is given, assume the value as expected time and proceed
further

LAST DATE FOR SUBMISSION – 19.02.2024