Flow Assurance Management and Benchmarki
Flow Assurance Management and Benchmarki
Flow Assurance Management and Benchmarki
Table 2: Stock Tank Component Phase Split and Thermodynamic Properties (@ 0% Water Content)
Mole
Thermodynamic Phases
Components (%)
Properties
Vapour Liquid Vapour Liquid
Methane (C1) 79.779 0.520 Mass Rate (kg/s) 4.82 27.41
Ethane (C2) 9.247 0.371 Density (kg/m3) 1.00 722.11
-5
Propane (C3) 4.836 0.741 Viscosity (Pa.s) 1.0453 ×10 4.9937 × 10-3
Iso-Butane (IC4) 0.938 0.374 Enthalpy (J/Mol) -474.74 -37,271.06
Butane (NC4) 0.168 0.098 Entropy (J/Mol.K) 5.0841 -99.76
Iso-Pentane (IC5) 0.513 0.800 Thermal Cond (W/m.K) 0.0350 0.1000
Pentane (NC5) 0.518 1.089 Isobaric Heat Cap (J/Mol.K) 46.27 227.02
Hexane (NC6) 0.605 4.442 Isochoric Heat Cap (J/Mol.K) 37.78 201.09
C7+ 3.396 91.565 Compressibility 0.9949 0.0065
-6
H2O 0.000 0.000 Joule Thompson Coef. (K/Pa) 7.7560 × 10 -4.8386 × 10-6
Total 100 100 Gas Liquid Ratio (sm3/sm3) 127.15
Ki Ki Xi Ki Ki Xi
Mole Fraction Pc Tc Accentric P
Components Temperature
Xi Bar °K Factor Bar
°K
213 203
Methane 0.3650 45.99 190.43 0.0115 3.3932 1.2385 2.6713 0.9750
Ethane 0.0440 48.72 305.17 0.0995 0.1571 0.0069 0.1035 0.0046
Propane 0.0260 42.48 369.68 0.1523 0.0186 0.0005 0.0110 0.0003
i-Butane 0.0063 36.48 407.99 0.177 0.0046 0.0000 0.0026 0.0000
n-Butane 0.0013 37.96 424.97 0.2002 24.1 0.0026 0.0000 0.0014 0.0000
i-Pentane 0.0067 33.8 460.25 0.2279 0.0007 0.0000 0.0003 0.0000
Pentane 0.0083 33.7 469.55 0.2515 0.0004 0.0000 0.0002 0.0000
Hexane 0.0270 30.25 507.45 0.3013 0.0001 0.0000 0.0000 0.0000
C7+ 0.5154 25.64 541.00 0.3462 0.0000 0.0000 0.0000 0.0000
Total 1.00 1.2460 0.9799
From table 3 above, the bubble point temperature at the inlet condition of the wellhead was calculated
to be, 𝑇𝑏 = 203°𝐾 ≈ −69.24℃ with a corresponding bubble point pressure from the phase envelope
to be, 𝑃𝑏 = 23.24 𝑏𝑎𝑟.
3.0 Methodology
Using the pipeline architecture and compositional fluid base data discussed in the previous sections,
detailed analysis was carried out to determine the adequate riser and pipe sizing required to meet the
desired pressure demand at the topside whilst taking into account the erosional velocity of the flowing
stream in accordance with API RP 14E [2, p. 24]. Furthermore, using the outputted data presented by
PIPESIM (see appendix I) and in conjunction with sound engineering judgment and past technical
articles on the subject, further kinematic properties of the fluid were established. It is noteworthy that
this analysis is concerned with only fluid transportation from the production manifold on the seabed to
production platform at the surface. In addition, it has not taken into account pressure losses due to the
effects of fittings and bends in the system due to unavailability of key subsea hardware data.
3.1 Riser and Pipeline Sizing
The first task here is to establish the pipeline and riser sizing in order to achieve the desired production
rate. This was done by performing a series of sensitivity analysis for the three (3) available pipeline
sizes (0.241 m, 0.292 m, and 0.343 m) on a case by case bases from the minimum through to maximum
anticipated production throughputs (3280, 2460, 1640 and 820) sm3/day. As mentioned earlier and
As shown in tables 5 and 6 and figures 3 and 4, the pipe ID with the lowest pressure drop is 0.343 m.
Figure 3: Plot of Pipe ID Vs. Outlet Pressure Figure 3: Plot of Pipe ID Vs. Outlet Pressure
@ 0% Water Cut @ 90% Water Cut
Further justification to the choice of line size is in accordance to API RP 14E sizing criteria for
gas/liquid two phase lines which stipulates that flowlines transporting gas and liquid in two phase flow
should be sized primarily on the basis of flow velocity. The velocity above which erosion may occur is
determined using the following empirical equation [2];
1.22𝑐
𝑣𝑒 = 𝑒𝑞. 3. 1
√𝜌𝑚
Where c is an empirical constant and ρm is the no slip gas/liquid mixture density at flowing pressure and
temperature expressed in kg/m3. Ve which is the erosional velocity is expressed in m/sec. For continuous
service and assuming a solids free fluid, the empirical constant c is given as 100 m5/2 sec-1 kg-1/2. Results
from output files (see appendix 1.1 and 1.3) of the computational fluid dynamics (CFD) simulation
carried out using PipeSim reported a maximum no slip liquid hold up fraction 𝐻𝑙 of 0.24 at 0% water
cut and 0.79 at 90% water cut. These values are maximum at the lowest production throughput (820
m3/day) and around the riser base. The no slip mixture density can be calculated from the gas 𝜌𝑔 and
liquid 𝜌𝑙 density as;
𝜌𝑚 = 𝐻𝑙 𝜌𝑙 + (1 − 𝐻𝑙 )𝜌𝑔 𝑒𝑞. 3.2
Similarly, the phase densities are maximum for the lowest production throughput and at the riser base
(see appendix 1.1 and 1.3). Using equation 3.2, the no slip mixture densities were calculated to be
174.77 kg/m3 and 768.49 kg/m3 for 0% and 90% water cut respectively (see appendix III). Substituting
these values into equation 3.1 gave a projected value of 9.22 m/sec and 4.4 m/sec for erosional velocity
at 0% and 90% water cut respectively (see appendix IV). For the selected pipe ID of 0.343 m and in
accordance with results from the summary file of the CFD simulation (see appendix 1.2 and 1.4), the
mixture velocity of the hydrocarbon fluid at maximum throughput of 3280 sm3/day was found to be 2.9
m/sec (< 9.22 m/sec) and 0.9 m/sec (<4.4 m/sec) for 0% and 90% water cut respectively (see appendix
Figure 7: Pressure-Distance Profile @ 0% Water Cut Figure 8: Pressure-Distance Profile @ 90% Water Cut
Figure 9: Temperature-Distance Profile @ 0% Water Cut Figure 10: Temperature-Distance Profile @ 90% Water
Cut
Furthermore and as earlier mentioned, since the hydrate formation temperature T h was calculated to be
lower than the wax formation temperature T wax (see table 10), the desired arrival temperature, T a which
is the wax formation temperature plus a safety margin of 15 °C was used to estimate the required
minimum OHTC. As shown on table 10, the minimum OHTC was projected to be 0.331 W m-2 °C-1
(see appendix VIII).
To achieve the desired OHTC for this system, the pipe-in-pipe system shown in figure 11 is
recommended. Assuming the inner and outer convective coefficients are negligible, the heat transfer
will be dominated by the insulating material (Izoflex™ in this instance) which has an ultra-low thermal
conductivity. The overall heat transfer coefficient putting into consideration the layers of the pipe
system can also be calculated as;
𝑟
1 𝑟𝑝 𝑙𝑛 ( 1⁄𝑟𝑝 )
= 𝑒𝑞. 4.5
𝑈𝑚𝑖𝑛 𝑘𝑖
Where 𝑘𝑖 is the thermal conductivity of the insulating material (0.007 W m-1°C-1) and 𝑟𝑝 is the outer
radius of the inner pipe (𝐷𝑂 ⁄2 = 0.184𝑚). Substituting these values into equation 4.4 produced an
estimated outer radius of the insulating material 𝑟𝑝 to be 0.206m. Thus, the insulation thickness was
calculated as;
𝑡𝑖 = 𝑟𝑝 − 𝑟𝑖 = 0.206 𝑚 − 0.184 𝑚 = 0.022 𝑚 = 22 𝑚𝑚 𝑒𝑞. 4.6
As seen from the calculations, due to the low thermal conductivity of Izoflex™, only a thin layer of
insulation is required to obtain highly insulated systems, which reduces the outer pipe size and
thickness, thus reducing weight and costs (less welding time, less steel). This compact and efficient
insulation allows long tiebacks and long cool down time for a subsea production pipelines.
As mentioned during the introduction, the separator’s slug handling capacity was stated to be 8.5 m 3.
Based on the results highlighted in table 11, the slug handling capacity of the separator is insufficient
even at 100% utilization. My recommendation therefore is for the operator to consider upgrading the
separator vessel to have a slug handling capacity of at least (1.5 ×14.55 m3) ≈ 22 m3 or incorporate
another slug catcher vessel with fluid handling capacity up to 13.5 m3 to the system at the platform if
there is sufficient space on deck
Furthermore, in addition to the impact of water cut on pressure drop, high water cut will often lead to
challenges associated with handling produced water at the production platform and a significant
reduction in hydrocarbon production as most of the pipeline valuable space will be occupied by the
produced water. The operator should consider developing produced water management strategies with
goal zero impact on the environment. Strategies such as incorporating produced water handling systems
into the production facility should be considered. In addition, the produced water can be treated and re-
injected into the hydrocarbon reservoir for pressure maintenance.
6.0 Conclusions
The methodology considered in this report have mainly focused on hydrate, wax and slugging
management for flow assurance targeted from the subsea production manifold to the host platform.
However, similar approach may be inferred for flow assurance management targeted from the bottom
of the wellbore to the wellhead. Based on the results from the analysis carried out in this report, the
following operational constraints should be addressed prior to finalizing the subsea tieback architecture;
Cost/benefit decision for flow assurance benefits should be integrated into the risk management
strategies.
Where cost of flow assurance intervention and remediation are anticipated to be high, flow
assurance management strategies should be an essential part of the subsea production system
design and operations planning process.
For very high flow assurance risk, the subsea production system should be effectively managed
by analysis, design and operational constraints.
8.0 Appendices
Appendix I: Output and Summary Files
Appendix Title of Document Embedded Document Note
Please double
Output File for 0% click embedded
Appendix 1.1 Ouput File @ 0% Water Content.pdf
Water Content document to
open
Please double
Summary File for click embedded
Appendix 1.2 Summary File @ 0% Water Content.pdf
0% Water Content document to
open
Please double
Output File for 90% click embedded
Appendix 1.3 Output File @ 90% Water Content.pdf
Water Content document to
open
Please double
Summary File for click embedded
Appendix 1.4 Summary File @ 90% Water Content.pdf
90% Water Content document to
open
Methane 0.8247 16.043 13.23 1.5500 0.5320 1.8500 0.4458 2.00 0.4123
Ethane 0.0994 30.070 2.99 0.1750 0.5681 0.6000 0.1657 1.35 0.0736
Propane 0.0587 44.096 2.59 0.0270 2.1757 0.0900 0.6527 0.40 0.1469
i-Butane 0.0142 58.123 0.83 0.0125 1.1387 0.0350 0.4067 0.15 0.0949
n-Butane 0.0029 58.123 0.17 0.0600 0.0490 0.2000 0.0147 Infinity -
Total 1.00 19.81 4.4635 1.6855 0.7277
Gas Relative Density 0.68
8.06 × 1,982.76 50 − 4
𝑈𝑚𝑖𝑛 = 𝑙𝑛 ( ) = 0.331 𝑊 𝑚 −2 ℃−1
11,805.10 40 − 4
𝑟
1 𝑟𝑝 𝑙𝑛 ( 1⁄𝑟𝑝 )
=
𝑈𝑚𝑖𝑛 𝑘𝑖
𝐷𝑜⁄
Where; 𝑘𝑖 = 0.007 W m−1 ℃−1 , 𝑟𝑝 = −2 −1
2 = 0.184𝑚, 𝑈𝑚𝑖𝑛 = 0.331 𝑊 𝑚 ℃
𝑘𝑖 0.007
( )
𝑟1 = 𝒆 𝑟𝑝 ×𝑈𝑚𝑖𝑛
× 𝑟𝑝 = 𝒆(0.184×0.331) × 0.184 = 0.206 𝑚