Gantt Chart School
Gantt Chart School
Gantt Chart School
16-May-2024
23-May-2024
30-May-2024
15-Feb-2024
22-Feb-2024
29-Feb-2024
14-Mar-2024
21-Mar-2024
28-Mar-2024
11-Apr-2024
18-Apr-2024
25-Apr-2024
13-Jun-2024
20-Jun-2024
27-Jun-2024
11-Jul-2024
2-May-2024
9-May-2024
1-Feb-2024
8-Feb-2024
7-Mar-2024
6-Jun-2024
4-Apr-2024
4-Jul-2024
Start Actual
Task Name Weeks End Date
Date Date
Land
Acquisition of Land 2 2/1/2024 2/8/2024 1 1
Design Phase
Preliminary Architechtural Design of Class Room, Labs, Exam Hall & RO Plant 3 2/8/2024 2/22/2024 1 1 1
Feasibility Studies 3 2/8/2024 2/22/2024 1 1 1
Final Architechtural Design of Class Room, Labs, Exam Hall & RO Plant 2 2/22/2024 3/3/2024 1 1
Detailed Engineering Design 5 2/22/2024 3/21/2024 1 1 1 1 1
BOQ's & Bidding Dacuments 2 3/21/2024 3/28/2024 1 1
Execution Phase
Hiring of Contractor 3 3/28/2024 4/12/2024 1 1 1
Construction work (Civil) 10 4/12/2024 6/21/2024 1 1 1 1 1 1 1 1 1 1
Electrcal work 4 4/19/2024 5/21/2024 1 1 1 1
Plumbing work 5 5/28/2024 6/27/2024 1 1 1 1 1
Furniture & Fixtures 6 5/21/2024 6/30/2024 1 1 1 1 1 1