SUB-2 Marine Technical Specification
SUB-2 Marine Technical Specification
SUB-2 Marine Technical Specification
SUB-2
CABLE SYSTEM
TECHNICAL SPECIFICATIONS
Chapter 8
Marine Operations
8 MARINE OPERATIONS
8.1 GENERALITIES
8.1.1 Introduction
The Bidder shall be responsible for the overall satisfactory performance of all marine
operations necessary for the installation of the Submerged Plant between the beach
manholes. In order to meet the requirements defined in the Technical Specifications, the
Bidder shall provide suitable vessels, personnel and equipment, which shall be subject to
approval by the Purchasers.
The Purchasers welcome and encourage the use of the latest technologies, in particular
those proven technologies which enable the Bidder to exceed these requirements.
The requirements defined in this Sub-section 8.1 are generic and remain valid for all vessels,
personnel and equipment involved in all marine operations under the Contract, except if
specified in the specific Sub-section, numbered from 8.2 to 8.5, devoted to the specific
marine operation.
Additional requirements for each specific marine operation shall be found in the specific
Sections.
Where requirements of the work are not specified in this Chapter 8, the Bidder shall perform
these requirements in the most efficient, economical and professional manner possible,
consistent with accepted practices. No exclusions to this requirement are given or implied
except those that may be agreed with the Purchasers.
The Bidder shall be solely responsible for identifying and obtaining all necessary approvals
and permissions for vessels, equipment, personnel and procedures to fulfill these
specifications. This shall include, but not be limited to, all necessary licenses, permits and
consents to carry out all aspects of the work in all required areas. The Bidder shall be
responsible for Customs clearances, publication of intent and payment of any applicable
duties, taxes and fees for all equipment, supplies and consumables to be used. A
comprehensive list of permits shall be provided by the Bidder within one month after Contract
Signature, to be completed if needed by the Purchasers.
Any associated delays and consequential damages due to difficulties in obtaining licenses,
permits, consents, Customs clearances shall be treated as defined in the Terms and
Conditions of this Contract.
Any damage to the environment, fishing equipment, existing sub-sea installations, etc shall
be treated as defined in the Terms and Conditions of this Contract.
The Plan of Work shall include an allowance for weather downtime as part of any operations
to be performed at sea, which shall be based minimally on historical weather norms.
All vessels shall comply with the latest International Maritime Organisation (IMO) and Safety
of Life at Sea (SOLAS) requirements for their classification and with any national
requirement of the territorial or continental / EEZ waters to be operated in. The Bidder shall
provide within the SOP or SLLI a copy of a recent audit in accordance with the International
Marine Bidders Association (IMCA) or equivalent for all vessels. The Purchasers shall have
the right to require deficiencies to be rectified.
All equipment to be used for the works shall be approved by an independent authority or
classification society as fit for the intended use. The Bidder shall provide access to
documentation proving such evidence onboard each vessel. The Purchasers shall have the
right to refuse the equipment not so approved.
The vessels’ officers and crew shall comply with relevant merchant shipping legislation
applicable to the area of marine operations. All personnel shall be made aware of their
obligations under the ISM and HES regulations, and shall possess the appropriate protective
clothing and safety equipment. They shall be in possession of a recent medical certificate.
The Bidder shall provide an alcohol and drugs policy statement that shall be compliant with
any rules or laws applicable to the countries of marine operations, and shall include this
within the SOP and SLLI.
The Purchasers shall have the right to audit safety procedures and documentation at any
stage of the Contract. If the Purchasers consider that any operation is in breach of safety
legislation, or that the safety of the vessel or any personnel is compromised by any
operation, the Purchasers shall have the right to halt the work.
The Purchasers’ representatives shall be regarded as supernumerary personnel rather than
ship’s crew. Any requirement for the purchasers’ representatives to comply with crew
member safety or medical certification shall be the responsibility of the Bidder.
viii) adequate space for at least two purchasers representatives / personnel and
equipment accommodation and working.
ix) Halal food & drink for Muslim purchasers representatives.
x) Submarine cable tank capacity should be minimum 2,000 (two thousands) of
kilometers of submarine communication cables.
The Bidder shall provide full details on the operating characteristics and capabilities of the
vessels that he will operate. This description shall include but not be limited to:
i) name, age, owner, and call-sign;
ii) flag (Bidder shall anticipate and subject to the cabotage law of Indonesia);
iii) length, breadth, draught, tonnage;
iv) endurance, fuel and fresh water capacities;
v) operating draught limits;
vi) passage and operating speeds;
vii) main propulsion unit and auxiliary equipment;
viii) bridge navigation and vessel control equipment;
ix) working space and power supply available;
x) cranes, winches and associated lifting and deck equipment;
xi) communications facilities;
xii) document reproduction facilities;
xiii) details of accommodation facilities;
xiv) facilities available to the Purchasers’ Representatives;
xv) previous experience in similar work.
xvi) recent vessel upgrades and related sea trial results.
For each proposed vessel, the Bidder shall specify the wind, weather and sea conditions
that would force curtailment of the work. The Beaufort wind scale and sea state codes shall
be used for fulfilling this requirement.
The Purchasers shall have the right to reject any of the proposed vessels.
The Bidder shall provide a computer system and software with the capability of accepting
and storing the multi-parameter data for real-time display, on-board processing and post-
processing. A complete time-correlated record of all navigation and other data acquired shall
be maintained throughout the work. Hard and soft copies of this data shall be provided as
requested by the Purchasers’ Representatives.
All equipment and systems described in paragraphs above shall be connected to an
uninterrupted power supply.
Other parties such as pipeline or cable owners, fishermen organisations, state agencies or
military organisations, etc. may require the presence of their own representatives onboard
the vessels during the whole or part of the works.
The Bidder shall advise the maximum number of representatives that can be accommodated
onboard each vessel.
The Bidder shall advise at least 3 months before boarding if any official Transfer Knowledge
certificate are needed such as BOSIET.
8.1.6 Reporting
8.1.6.1 Daily reports
The Bidder shall submit to the Purchasers a written daily report during all the works
performed by all vessels.
The contents of the daily report shall include:
i) geographical position of the vessel at the time of the report;
ii) weather conditions during the preceding 24 hours and weather forecast;
iii) summary of the work performed during the preceding 24 hours;
iv) Red Flag items in the preceding 24 hours, if any;
v) summary of the work planned for the next 24 hours;
vi) time spent on effective work during each 24 hour period and the cumulative total;
vii) weather downtime during each 24 hour period and the cumulative total;
viii) vessel/equipment downtime during each 24 hour period and the cumulative total;
ix) other non-operational time during each 24 hour period and the cumulative total;
x) list of events logged in the last 24 hours;
xi) report of progress against Plan Of Work and estimated completion;
xii) endorsement of the report by the Purchasers’ Representatives;
xiii) space for comment by the Purchasers’ Representatives;
xiv) vessel contact numbers.
viii) environmental conditions observed, including wind and sea conditions and
surface currents;
ix) shipping traffic, offshore engineering activities and fishing activities observed
together with any exchange of radio messages regarding these.
Additional items to be provided in the reports are detailed in the Sections devoted to each
specific marine operation.
The exact content of the reports, including the presentation of charts, shall be agreed by the
Purchasers prior to the commencement of each marine operation.
The preliminary reports shall be issue 0(zero). Any subsequent amendments shall reflect
change of issue together with a margin note of the amendment.
Paper copies
The written reports shall be compiled in A4 ring binders and the charts shall be delivered in
boxes of the same dimension.
One copy of the reports, including charts, shall be provided to each Purchaser.
As an option, the Bidder shall provide the unit price of additional paper copies.
Electronic copies
The reports shall be provided to each Purchasers under the following electronic formats :
i) the full report in Acrobat Reader format, allowing easy and direct access from the
table of contents to all chapters of the written report and from overview charts to
all charts;
ii) the written report only, including the Route Position Lists and the Straight Line
Diagrams, in mix-media format latest version of Microsoft Office (Word, Excel,
Project, as appropriate);
iii) the charts in a Acrobat Reader format; each chart shall correspond to an unique
file, be presented as in paper and be accessible from an overview chart;
iv) the charts in a Autocad and/or Microstation format, compatible with a
geographical information system (G.I.S.), at each Purchasers’ discretion; each
chart shall correspond to an unique file;
v) the bathymetry data shall be provided in a format compatible with the Makai
software;
vi) the morphology data shall be provided in a format compatible with the Intergraph
Geomedia software.
The reports shall be provided on USB Flash Drive or HDD or other digital storages as per
each Purchasers’ request.
The USB Flash Drive or HDD or other digital storages shall be labelled accordingly. Three
copies of the electronic reports are required for each Purchaser.
• preliminary reports for review by the Purchasers are provided in electronic format only
• paper charts are provided only in the final issue of reports and are combined for :
i) Surveys (ES and BAS)
ii) Installation (RC, PLGR, Shore-Ends, Main Lays and PLIBs)
The Purchasers and the Bidder shall agree on this process prior to the start of any marine
operations.
8.2.1 Introduction
Hydrographic route Surveys are required to provide detailed information for use in the
engineering, construction and subsequent maintenance of submarine cables. The
engineering of the marine parts of the entire system is directly dependant on the information
yielded by the surveys. End to end route survey must be conducted by one sub-contractor
(single responsibility).
These paragraphs specify the requirements and minimum acceptable standards for
conducting the route survey.
The Bidder shall in any circumstances be fully responsible for the final selected route, which
shall be both economical and viable.
8.2.2 Objectives
The principle objective of the route survey is to confirm or amend the preliminary cable route,
as defined in the preliminary route provided by the Purchasers, in order to ascertain a
suitable route for the system design, installation, protection, survivability and subsequent
maintenance.
The survey shall also allow decisions to be made regarding the procedures for marine
installation, the extent of cable armouring and the burial.
Since the route cannot be precisely determined prior to the work, the assessment of data
acquired during the survey will determine deviations from the preliminary route. The Bidder
shall perform all necessary data acquisition until a route is found that is acceptable to the
Purchasers.
The final route shall be free of excessive slopes, strong sea currents and obstacles such as
wrecks, outcrops, areas of unstable seabed, etc and shall allow for cable burial to the
required depth.
An acoustic tracking system shall be used to accurately determine the layback of any towed
system.
The Bidder shall indicate the type and provenance of the vessels used for the inshore
surveys.
8.2.6 Reporting
A detailed and narrative report shall be prepared by the Bidder to supplement and explain
thoroughly the data presented on the charts.
In addition to those already indicated in the Sub-section 8.1 ‘GENERALITIES’, the survey
report shall include, but not be limited to, the following items:
Human activities
• fishing activities (type of vessels, type of fishing gears, etc)
• shipping activity observed including vessels at anchorage and on passage
• navigation restrictions
• off-shore oil and gas activities, submarine resources development
• any other offshore activities observed including dredging, dumping, drilling,
construction, etc
• dumping areas in use, abandoned or planned
• military exercise areas
• wrecks
Hydrographic survey
i) tabulated list of all sonar contacts and isolated features found (organised into
columns showing latitude and longitude, dimensions, type of contact and chart
number applicable; each contact shall be numbered)
ii) tabulated list of all cores and grab samples; each sample shall be fully described;
it shall be photographed in colour with a unique identification number and a scale
in centimetre legibly shown
iii) route deviations and development
An appendix to the report including, but not be limited to, the following:
i) charts (as described under)
ii) bibliography of all references
It is recommended that, where applicable, the above information is categorised according
to chart number (or chart limits) to facilitate an organised review. This approach will clearly
assist reviewers as they need access only one chart at a time when comparing the written
plotted/imaged data.
8.2.7 Charting
8.2.7.1 General
The following charts are required:
• overview charts
• index charts
• a set of North-up charts for the entire route
• a set of strip charts for the Shallow Water and Inshore Water sections, down to the
planned limit of burial
• charts for each landing point (beach)
• charts at in-service pipe-lines crossings in shallow waters
• charts at Branching Unit locations
• continuous vertical profiles of the Post-survey agreed routes
Size: international A0
• Datum: WGS84
• Spheroid: WGS84
• Projection: Mercator
Scale of charts:
• Deep Water (north-up chart) : 1:100,000 in areas of little relief
1:50,000 in areas of significant relief
• Shallow Water (north-up chart) : 1:20,000
• Shallow Water (strip chart) : 1:10,000
• Inshore Water (north-up chart) : 1:5,000
• Landing point (north-up chart) : 1:1,000
• Pipe-line crossing (north-up chart) : 1:20,000
• Branching Units (north-up chart): 1:50,000 in deep waters
1:20,000 in shallow waters
• Overview (north-up chart) : of appropriate scale
• Index (north-up chart): of appropriate scale
• Graticules: Full graticule for latitude and longitude;
Tick marks for Mercator grid.
Chart presentation
i) The Bidder shall propose to the Purchasers the method of depicting the data and
include a sample of this in the SOP. In particular, consideration shall be given to
depicting the different seabed materials by different colours;
ii) Kilometre points shall be shown;
iii) The selected route shall be indicated as a faint line. No other route lines are to
be shown;
iv) Alter courses shall be shown as a numbered symbol;
v) Where possible and practical, contour intervals shall be as follows:
• Deep Water: 10 metres, using 50 metres index contouring as appropriate.
• Shallow Water: 1 metre, using 10 metres index contouring as appropriate.
• Inshore Water: 1 metre, using 5 metres index contouring as appropriate.
vi) For graphical clarity the contour interval can be increased in areas of high relief
and be annotated accordingly;
vii) Slopes over 5° and their direction shall be clearly noted;
viii) For areas of extremely low relief, the surveyed area shall be outlined and labelled;
ix) All cables and pipe-lines and their status (in-service, out-of-service or planned)
shall be shown on the charts. The origin of data shall be stated in the legend box;
x) Vertical stratigraphic cross sections of each core along with sediment
descriptions and torvane measurements shall be plotted on the charts and cross-
referenced to the identification number. Cross-hatching and shading shall be
used to differentiate the various sediment types on the cross sections. Vertical
scale shall be 1:10 (10 cm of core to 1 cm of drawing).
Prior to the mobilisation of the vessels, the Purchasers shall review and approve sample
charts produced by the Bidder.
Definition of Strips
i) The charts shall depict 4 horizontal strips detailing the following specific information:
• first (top) strip: bathymetry and vessel track;
• second strip: shallow geology and seabed features;
• third strip: bathymetric and geological profile, indicating sediment layers
and thickness, vertical scale 1:40;
• fourth (bottom) strip: blank for burial assessment or installation burial
information.
• Sufficient vertical spacing shall be allowed for the bottom strip to show clearly the
burial depth and tow tension, when as-laid burial data is added to the survey
charts.
ii) Graticules and scaling graduations are required on the first and second strips.
The route selected from the survey shall be depicted as a faint horizontal centre line.
At all alter course points which involve a strip to be re-orientated, an overlap of 500 metres
between adjoining sections shall be allowed. With the Purchasers’ agreement, the Bidder
may recommend a reduced overlap area to optimize chart production and ease of use.
Bathymetric and geological profiles shall be presented with the mean seabed line displayed
at approximately half height.
The north direction of the chart must be oriented up from the cable route.
8.3.1 Introduction
These paragraphs identify the requirements and minimum acceptable standards for
conducting the Route Clearance.
The Route Clearance shall preferably be performed prior to the Burial Assessment Survey.
It shall be performed prior to the laying and burial operations to enable these operations to
be undertaken with a high degree of confidence.
The Route Clearance shall be a separate operation from the Pre-Lay Grapnel Run.
8.3.2 Objective
The objective of the Route Clearance is to clear of surface and sub-surface out of service
cables the post-survey route in such a manner that installation by burial tools and
subsequent maintenance operations are not hindered by the presence of such hazards.
8.3.4 Requirements
The Bidder shall ensure that a safe corridor equal to either twice the water depth or 500
metres, whichever is the greatest, centred on the post-survey route, is cleared of any out-
of-service submarine cables. Changes to this requirement due to specific reasons or in-field
limitations shall be agreed by the Purchasers.
Any out-of-service submarine cables located/detected shall be recovered on either side of
the selected route in order to obtain a safe corridor as defined above. The out-of-service
cables shall not be pulled or dragged out of this corridor.
The cable ends remaining shall be re-laid flat on the seabed in accordance with ICPC
Recommendation No 1 in order to minimise future liability to the Purchasers from third
parties and to minimise problems for other seabed users. In the SLLI, the Bidder shall advise
the method to be used for re-laying the cable ends which shall be subject to the agreement
of the Purchasers, unless local regulations require alternative procedures to be followed
(e.g. burial of cable ends).
In the event that the out-of-service submarine cables are not located/detected, the route
clearance tools shall be pulled through the seabed to ensure that there exists a safe corridor
as defined above. A detrenching grapnel set nominally at 0.8 metres (or less at the discretion
of the Purchasers’ Representatives if the seabed conditions require it) shall also be pulled
through the seabed along the planned route on either side of the charted crossing point, on
a safe distance, to be agreed between the Purchasers’ and the Bidder’s Representatives,
depending of the seabed conditions, the water depth, and the supposed accuracy of the out-
of-service cable position.
In the event that out-of-service submarine cables are charted as being within twice the water
depth or 500 metres, whichever is the greatest, of the safe corridor, but not crossing the
route, the area shall be proved as above. This shall ensure that the out-of-service submarine
cables are either not present or, if present, are cleared within the limits of the corridor.
Whenever other seabed debris is encountered during the clearance of out-of service cables,
this shall, as far as practical and reasonable, be cleared to the limits described above.
All cable and materials including repeaters recovered during the operation shall be stowed
on board the vessel for disposal ashore in accordance with applicable legislation and at no
cost to the Purchasers. In particular, the method of disposal of any repeaters recovered shall
be notified to the Purchasers and be subject to their approval.
All Route Clearance activities shall be undertaken as close to the landings as is safe and
practical and at least as close as the 10 metre contour line unless otherwise agreed with the
Purchasers’ Representatives.
In all circumstances, no towed equipment shall be used within a security distance equal to
500 metres of any known and proven pipeline or in-service submarine cable. Whilst within
the security zone all towed equipment shall be recovered to and secured on deck.
8.4.1 Introduction
The target burial depth for the SUB-2 shall be 1.5m of cover depth. The Bidder shall perform
a Burial Assessment Survey to assess the possibility of burial and to determine the
armouring of the system in Shallow Waters based on the mentioned target cover depth.
The Burial Assessment Survey shall be performed as the Electronic Route Survey data is
collected and analysed by the Parties’ onboard representatives. The BAS target areas will
be reviewed and agreed between the Purchaser and Bidder representatives such that burial
assessment may be carried out as the route survey proceeds.
These paragraphs specify the requirements and minimum acceptable standards for
conducting the Burial Assessment Survey.
8.4.2 Objectives
The first objective of the Burial Assessment Survey is to assess part of the route which has
been surveyed and to determine its suitability for the burial of the Submersible Plant either
during or after the laying operation.
The post-survey route may be amended within the surveyed corridor, in order to allow a
better protection of the system by improving the length of the route that can be buried, and/or
enhancing the method of burial (e.g. plough versus jetting ROV or other burial tools).
The second objective of the Burial Assessment Survey is to provide information for the
selection of the cable types along the route which has been assessed.
The third objective of the Burial Assessment Survey is to gain information for the
engineering, the installation and the subsequent maintenance of the Submersible Plant.
8.4.4 Requirements
The work shall be performed in order to assess the route into the following categories:
Burial
Category A: Cable burial to a target cover depth of 1.5 metre;
Category B: Cable burial to a target cover depth greater than 1.0 metre but less than 1.5
metre;
Category C1:Cable burial to a target cover depth of greater than 0.5 metre but less than 1.0
metre;
Category C2:Cable burial to a target cover depth of less than 0.5 metre.
Category D: Risk of uncontrolled cable burial to a cover depth of greater than 1.5 metre;
Risk
Category 1: No identified risk of damage to the burial equipment due to seabed conditions;
Category 2: Minimal risk of damage to the burial equipment due to seabed conditions.
Category 3: High risk of damage to the burial equipment due to seabed conditions. Scale
of possible damage in excess of category 2.
The work shall provide all necessary information to:
i) determine the target cover depth achievable by the selected burial equipment along
the specified portions of the cable route and assignment of the categories described
above;
ii) determine the appropriate method of cable protection throughout the cable route, e.g.
plough burial, post-lay burial (by jetting or other methods);
iii) determine the planned plough-up and plough-down positions;
iv) predict the wear down of the plough share and therefore plan the positions for
maintenance of the plough;
v) provide an estimation of sediment density and shear strength; this will be used to
predict burial depths achievable by submersible jetting or trenching equipment and
assessment of de-trenching requirements for subsequent maintenance operations;
vi) predict towing tensions based on the type of plough to be used during installation;
vii) identify areas where burial equipment would be at risk of damage and quantify that
risk in accordance with the relevant defined categories.
The Bidder shall ensure that, as far as reasonable and practical, the data acquired is
continuous along the specified route. Where gaps occur in any data category, due to
corruption, course deviation or other failure to log valid data, the operation shall be repeated
to provide the missing information.
The operations shall be undertaken as close to the landings as is safe and practical and at
least as close as the 10 metre contour line unless otherwise agreed with the Purchasers’
Representatives.
In all circumstances, no towed or penetrative equipment shall be used within a security
distance equal 500 metres of any known pipeline or in-service submarine cables. Whilst
within the security zone all towed equipment shall be recovered to and secured on deck.
The Bidder shall make available to the Purchasers and their representatives the raw data
obtained during the operation and a full explanation of the method used to interpret the data
into the above categories. Any equipment specialist required for the interpretation of the
data shall also be supplied to enable the Purchasers and their representatives to interpret
the data independently. The final assignment of categories shall be subject to the agreement
of the Purchasers.
8.5.1 Introduction
This document specifies the requirements and minimum acceptable standards for
conducting all the necessary operations from the assembly of the Submerged Plant to its
complete and safe installation on the seabed.
The Purchasers outline their requirement for a proper installation that shall reduce the need
for future maintenance of the Submerged Plant due to external hazards.
The Bidder shall be responsible for rectification of any damage sustained by the
Submersible Plant during its passage between the point of departure from the manufacturing
site(s) to the place of final installation, irrespective of the cause.
8.5.2 Objectives
The main objective of this work is the installation of the Submerged Plant on the planned
route and according to the burial plan, as agreed by the Purchasers and the Bidder during
the engineering phase.
This includes the provision of the complete and accurate installation report, which is required
for the future maintenance of the Submerged Plant.
8.5.6 Requirements for the loading and stowage of the Submerged Plant
8.5.6.1 General
The requirements shall apply to all loading and off-loading operations and the stowage of
the whole or part of the Submersible Plant, which include, but shall not be limited to:
i) the loading operations for the main lays;
ii) the loading operations for separate shore-end installations, if applicable;
iii) the loading operations for delivery of spares, if applicable
iv) the ship-to-ship transfer operations, if applicable;
v) the off-loading operations, if applicable, including the off-loading of spares in
depots.
8.5.7 Loading
The Bidder shall be responsible for loading the Submersible Plant on to the vessels
witnessed by Purchasers’ Representatives in accordance with the approved detailed plans
and loading procedures.
The Bidder shall indicate the loading ports and the number of loading lines available. The
loading facilities shall be subject to the approval of the Purchasers' Representatives.
At the times detailed in the Plan of Work, the Bidder shall supply the quantities and types of
Submersible Plant for loading into the vessels of complete cable sections within the SLLI
document. Alternatively, cable sections may be loaded separately in order to be jointed
onboard the vessels as a complete assembly. This shall be subject to the approval of the
Purchasers' Representatives.
Where cable sections are to be assembled on board a vessel, cable sections shall be loaded
by a method agreed between the Purchasers' Representatives and the Bidder.
The Bidder shall ensure that the use of any equipment and the loading techniques do not
cause deterioration of the Submersible Plant. The provision of necessary materials for the
loading and safe stowage of the Submersible Plant shall be the responsibility of the Bidder
and shall be to the satisfaction of the Purchasers' Representatives.
Should any Submersible Plant be damaged or subjected to excessive shock, strain or
bending, the Bidder shall stop loading immediately and notify the Purchasers'
Representatives. When the Submersible Plant sustains damage or is subjected to forces
which may cause deterioration at a future date, the Bidder shall agree with the Purchasers'
Representatives the remedial action to be taken.
Stops in transfer of Submersible Plant for periods greater that 1 hour shall be subject to the
following conditions:
• no cable transitions, repeaters, equalizers or splice boxes shall be in transit anywhere
between stowage locations;
• the vessel shall be moored such that no tension shall be applied to the cable in transit
at any stage during the stop and there shall be no excessive vessel motion;
• protection shall be provided to all cable in transit during the stop against the effects of
actinic radiation;
• protection shall be provided against excessive variations in temperature to all cable in
transit;
• at no time shall the performance envelope of the cable in transit be exceeded.
In the event of significant delays during the operation, the Bidder shall give the Purchasers'
Representatives at least 30 minutes notice of his intention to restart work, unless otherwise
agreed by the Purchasers' Representatives.
Positions of markers shall not be altered subsequent to the measurements specified above
except with the agreement of the Purchasers' Representatives.
The cable-ship shall keep a separate log of cable markers similar to that specified above.
The data shall be taken from counters on the cable-ship which will also be the ones used
during cable installation. Under no circumstances will marker positions be altered after
passage and recording in this set of counters. Measurement accuracy and calibration
requirements are as stated above.
A report shall be prepared by the Bidder containing all the data specified in this section in
tabular form, together with a log/diary of all significant activities and events from the start to
the finish of the agreed loading Plan of Work. The report shall be made as soon as possible
after completion of the load and no later than 12 hours before sailing unless agreed by the
Purchasers' Representatives. Load data shall be provided both as a hard copy and in
electronic format compatible with standard office computing equipment and software
packages.
8.5.7.2 Stowage
The Submersible Plant shall be properly stowed in a safe manner with the cable turns closely
spaced and the bights to the housings of the submerged equipment (Repeaters, BUs,
Equalizers, etc.) carefully controlled and protected. The repeaters, BUs, Equalizers should
not be placed in area where temperature and humidity exceeds the specifications. If the
Purchasers' Representatives judges that the stowage is unsatisfactory, the Bidder shall stop
loading and rectify or re-stow the Submersible Plant to the satisfaction of the Purchasers'
Representatives.
The Bidder shall provide within the SLLI full details of the procedures, including for shore-
end operations, to be used to ensure that the Submerged Plant is installed with the required
positional accuracy when subject to external forces due to weather conditions and sea
currents.
For each cable-ship, the Bidder shall provide the following additional information:
i) details of all navigation aids on board including echo-sounding equipment, depth
chart recorders and radars;
ii) details on the machinery for the laying and recovery of the Submerged Plant;
iii) details on the software used for the laying of the Submerged Plant(e.g Makai,
etc);
iv) details of the test equipment for the electrical and optical tests of the Submerged
Plant;
v) details of the Power Feed Equipment including maximum voltage, current,
stability and shut-down characteristics;
vi) details of the jointing tools and spare kits, including the equipment and
procedures for checking the integrity of all joints;
vii) description of the methods to control and/or monitor the temperature of the
repeater and branching unit stacks;
viii) description of the method to control and/or monitor the cable temperature in the
cable tanks;
ix) description of all the auxiliary facilities and support crafts used to lay the cable as
well as the facilities used on land for the laying of the shore-end cable.
The Bidder shall provide details of any other vessels and services required during the laying
operations, including, but not limited to, guard ships, diving support vessels, etc.
The Bidder shall propose methods to maximise the plough burial and minimise post-lay
burial operations, in particular at shore-ends. The Bidder shall provide the speed of cable
burial as a function of the depth of burial.
The Bidder shall provide details of the proposed burial methods, including the method of
controlling, indicating and recording the depth of cover over the cable and position of cable
entering the sea bed at any point along the route. These details shall be subject to inspection
and approval by the Purchasers' Representatives.
The Bidder shall attempt to meet the target depth of burial, as indicated in the burial plan,
on a best endeavours basis where best endeavours are defined in the following.
As the soil type will determine the combination of burial speed, tow tension and plough share
penetration, the plough burial operation shall be conducted as follows:
i) The target depth of burial should normally be obtained with a speed of 600 metres
per hour.
ii) If the speed of ploughing has to be reduced to less that 600 metres per hour to
meet the target burial depth (and remains so for 30 minutes), then the plough
share may be graded out in 100 mm steps until the 600 metres per hour speed
is regained.
iii) If the tow tension frequently exceeds the winch render setting, then the burial
depth may be reduced in steps of 100 mm at a time, until ploughing can continue
at reduced tension.
iv) If the speed of ploughing exceeds 600 metres per hour then the plough share
depth can be lowered in 100 mm steps, provided the tension remains at
acceptable levels, until the target depth of burial is reached.
v) At all times a speed exceeding 600 metres per hour is acceptable, provided the
target depth of burial is being achieved and the process is in control.
The residual cable tension shall be as low as practicable but shall not exceed an average of
20 kN or peaks of 30 kN during plough burial operations.
In places where the plough is recovered for repairs/maintenance, the amount of Submersible
Plant not buried shall be kept to the minimum and shall be subject to further remedial burial
by the Bidder.
The Bidder shall provide the methods he proposes for ensuring that sufficient slack is
installed in the cable when the plough is recovered for surface lay, in order to allow effective
Post-Lay Burial, if required.
The Bidder shall maintain a real time analysis of burial performance. The geographical
positions and the amount of the unburied lengths of the Submersible Plant shall be clearly
noted in the laying log together with a full explanation of the incident.
In all circumstances, no towed equipment shall be used within 500 metres of any pipeline or
in-service submarine cable unless agreed otherwise with the third party Representatives.
When within these regions all towed equipment shall be recovered from the sea bed.
Should any plant be damaged or subject to excessive stress, strain, bending or exceed
qualified design limits in any respect, the Bidder shall immediately notify the Purchasers'
Representatives and agree on the remedial action to be taken.
• joints
• transitions
• submerged housings (repeaters, equalizers, etc.)
• other cables and pipelines crossings
• plough recoveries/launches
• plough maintenance points
For these events, the position on the seabed shall be directly recorded. When not possible,
the Bidder shall indicate the method used to derive or determine the seabed position.
The data entries shall be logged against a common clock source. Events shall be recorded
as accurately as practicable and shall be labelled to permit future identification.
Data points shall be provided every 10 m in water depths less than 1000 m. Data points
shall be provided every 50 m in water depths greater than 1000 m.
Data shall be in a format and media which is compatible with standard office computing
equipment and software packages and shall be made available to the Purchasers'
Representatives as soon as practicable during the operation, if requested.
The Bidder shall ensure that, during the pull ashore of the cable, good co-ordination exists
between the beach and the vessel, such that no spikes of tension occur to impair the
reliability of the Submerged Plant. A continuous record of the cable tension is required during
the shore-end operation.
In case of separate shore-end operations, the vessels used shall be capable of installing the
shore-end cable in a continuous operation. No cable joint shall be deployed in any shore-
end operations where more than 2 metre burial is required.
Immediately at the end of the installation operation, the Bidder shall inspect by video the
shore-end lay. In the event of kinks, loops or suspensions in the shore-end cable, the Bidder
and the Purchasers shall mutually agree to any remedial measures and methods. The
Bidder shall endeavour to provide a video with good seabed visibility to allow for a clear
video record of the cable situation, although this may not be possible in all cases due to
undersea conditions. The Bidder shall be responsible for the elimination of anomalies in the
cable disposition.
• The areas where burial was carried out according to the plan but need to be assessed
due to any doubt on the achieved depth or any particular risk such as intense fishing
activities;
• Sample areas at regular intervals in extended buried lengths.
The Post-Lay Burial operations shall be performed in order to bury lengths of the submerged
Plant that were not buried according to the burial plan. The operation shall be carried out up
to 5% of the planned plough buried areas as indicated in the burial plan. Areas where Post-
Lay Burial operations are to be performed include areas such as:
• initial, final or intermediate splices,
• crossings of in-service power and telecommunication cables and pipe-lines,
• areas where seabed conditions are more conducive to jet burial than plough burial
• branching units,
• plough skips,
• between the low water mark and start of plough burial, if applicable,
• any other lengths of the Submerged Plant that was not properly buried according to
the burial plan.
The areas to be inspected and buried during the PLIB operations shall be discussed and
determined by the Bidder’s and Purchasers’ Representatives onboard the cable-ships
during the laying operations. The information shall be passed to the Bidder and the
Purchasers ashore for further discussions and final agreement. The PLIB operations shall
not start before such agreement has been reached and a PLIB Plan has been issued.
At the discretion of the Purchasers’ Representatives and according to data and/or
information acquired during the course of the PLIB operations, the scope of work of the PLIB
operations shall be modified in order to achieve the burial requirements.
8.5.13.2 Vessels
In addition to the general requirements stated in the section 8.1 “Generalities”, the vessels
shall be equipped with a full dynamic positioning class 2 (DP-2) system.
For each vessel, the Bidder shall provide the following additional information:
i) details of all navigation aids on board including echo-sounding equipment, depth chart
recorders and radars;
ii) details on the machinery for the deployment of the submersible vehicle;
iii) details of the weather conditions for launch and recovery of vehicles.
The Bidder shall provide details of any other vessels and services required during the PLIB
operations, including, but not limited to, guard ships, tugs, diving support vessels etc.
The ROV shall be capable of operating on a continuous 24 hour operation in all water depths
where burial has been planned according to the burial plan. The Bidder shall provide the
frequency and duration of maintenance.
The Bidder shall state any operational limitations e.g. maximum operational water depth,
seabed slope, currents, etc.
8.5.13.4 Operations
The Bidder shall provide details of the proposed methods for the PLIB operations, including
the method of controlling, indicating and recording the depth of cover over the cable. These
details shall be subject to inspection and approval by the Purchasers.
Unless agreed by the Purchasers Representatives, the following operations shall be
performed on the areas where Post-Lay Burial is required:
i) one inspection pass, in order to assess the initial burial depth and/or the seabed
configuration and conditions;
ii) two jetting passes;
iii) one inspection pass, in order to log the final burial depth.
The Bidder shall maintain a real time analysis of burial performance. The geographical
positions and the amount of the unburied lengths of the Submersible Plant shall be clearly
noted in the operational log together with a full explanation of the incident.
The Bidder shall be responsible for all electrical, optical and transmission tests during the
laying operation(s) and the provision of testing, power feeding and associated equipment
and the interpretation of test results. The Bidder shall allow to the Purchasers full access to
all operations during cable laying, as well as test results, and any other information on which
the Bidder is basing its decisions. The Bidder may also seek the cooperation or opinion of
the Purchasers on any matter relevant to the operation. In addition, the Purchasers shall
have the right to comment to the Bidder on any matter relevant to the operation.
The Bidder shall provide a temporary voice order wire circuit on the cable for communication
between the cable ship and the terminal station from which the cable is being laid during the
laying operations.
The Purchasers reserve the right to have extra tests carried out which it deems necessary
in order to ensure the correct control of laying operations.
• summary of the Submerged Plant inspected during the last 24 hours and the
cumulative total;
• summary of the Submerged Plant buried in the last 24 hours and the cumulative total;
• burial profile performed in the last 24 hours;
• summary of Submerged Plant remaining to be inspected;
• summary of Submerged Plant remaining to be buried.
viii) video reports on USB Flash Drive or HDD showing the salient seabed features
encountered during the PLIB operations;
ix) video reports on USB Flash Drive or HDD for the Shore-End cable sections.
The Bidder shall add on the survey charts:
i) the position of the Submersible Plant on the seabed; surface-laid sections and buried
sections shall be depicted differently;
ii) the burial depth achieved at any point along the installed route, shown as a profile in
the 4th bottom strip of the charts; data from the laying operations and from the PLIB
operations shall be shown in different line features and/or colours; the vertical scale
shall allow easy reading of the burial depth;
iii) the plough tow wire tension at any point along the route where plough burial was
performed;
iv) in the legend box, the names of the vessels used for the installation (laying, post-lay
burial), the dates of operations and the company’s names;
v) any pertinent and important margin notes.
Bidder shall register the SUB-2 to Hydro Oceanograhic of Indonesian Navy Map after the
completion of Marine Installation.
END OF CHAPTER 8