JICA Method Statement
JICA Method Statement
The test borehole drilling program has been planned based on the results of the 1st Field
Survey (1999). An outline of drilling program, including location, depth planned and
drilled, is listed below.
J-1N
J-1 Christiana 39839 Nossob Auob 240 256.00
(J-1A)
J-9N
J-9 Klein swart modder 39857 Nossob Auob 145 141.50
(J-9A)
The drilling works started on 10 April 2000 and was completed at the end of November
2000. Such works also include pumping test, borehole head construction and
installation of water level recorder. The location of these boreholes and existing
boreholes which water level recorders were installed are shown in Fig. 6.1-1(s.p.6-31).
6-1
Chapter 6 Test Borehole
A total depth of 4,157m was drilled. In most location, except locations of J-4, J-5 and
J-9, the drilled depths are deeper than planned depth. The actual depths to the bottom
of targeted aquifer are deeper than estimated, at most of location.
No Nossob Member was found at the locations of J-1 and J-9. These boreholes,
therefore, were modified as Auob type boreholes.
1) Design Policy Based Upon the Results of the 1st Field Survey (1999).
i) The borehole shall be drilled independently to each aquifer. The own structure,
therefore, is needed for each type of borehole.
ii) The common materials on the each type of boreholes, however, shall be selected as
much as possible, in order to avoid a wasteful procurement.
iii) In order to examine the hydrogeological character of each aquifer, the correct data
such as water level, quality and yield shall be obtained from the borehole.
Therefore, “full hole cementing method” had been applied to seal the non-target
completely.
iv) Considering the limited availability of such test boreholes in the study area, the
newly drilled boreholes by this program must be multipurpose. A sufficient
diameter of the casing and screen pipe is needed, to be able to both of pumping and
water level measurement.
v) The great majority of the existing boreholes in the study area were constructed
without screen pipe installation. The main reasons of such structure are presumed
as the sufficient hardness of the formation (Auob and Nossob), and economic
viability. Considering the long-term use as monitoring borehole, however, any risk
of the collapse of the hole wall must be avoided. The screen pipe, therefore, shall
be installed for the any type of borehole.
6-2
Chapter 6 Test Borehole
vi) A good quality material shall be adopted for the major parts of the structure, in order
to utilize the borehole for long term monitoring.
vii) The local material and standard must be chosen in preference, to make easy
maintenance of the borehole. SABS (South African Bureau of Standard) standard
shall be applied as a major part of the specification of the boreholes.
Based on the aforesaid design policy, the structure and specification of the test
boreholes were determined. The structure and specification described hereunder are
the standard for the construction of each type of test borehole. The diameter, depth of
drilling hole and size of casing and/or screen pipe, however, were altered in order to
accept variety of drilling method and equipment, also depend on geological formation.
The followings are the adopted structure and specification for the boreholes drilled.
Item Specification
Structure : Single string, straight type borehole.
Setting of Pipes : Cement grout in casing pipe, gravel (1 to 3mm) packing in screen
pipe
Hole Size : φ12-1/4” (311.2mm)
Casing Pipe : φ6”, SABS719, Grade B, Zinc galvanized steel
Screen Pipe : φ6” (168mm), SUS304 Stainless steel, Johnson type screen
The formation of Auob Aquifer is composed of fine to coarse grain size sandstone
with minor intercalation of thin shale layer in local. The formation is,
unconformable underlying the Kalahari Beds. Thus, sealing of the Kalahari Aquifer
shall be required. Considering the necessity of the sealing of an overlying aquifer,
6-3
Chapter 6 Test Borehole
Water level recorders were installed on the each borehole. The instruments were
supplied by JICA. In order to protect top ends of conductor and casing pipe, a
borehole head block was constructed. The standard design of the borehole head
block is shown in Fig. 6.1-5.
The water level recorders were installed on the borehole after the construction of the
borehole head facilities. In the artesian boreholes of J-3N, J-6N and J-5N, however,
an another design for the head facilities was applied. A pressure probe type of
recorder was installed in upper chamber of the head facility.
A security fence was constructed around each individual test borehole. Figure 6.1-6
shows the design of the fence constructed.
The test boreholes were drilled using the rotary drilling method using a direct mud
circulation system. By such method, and to conform to the aforesaid structure, the
following procedure and specification were applied for each type of borehole.
6-5
Chapter 6 Test Borehole
8 Make gravel packing for the annular 2mm to 4mm grain size
space between the hole wall and
screen pipe.
9 Perform the development of a use air-lifting (surging or bailing
borehole. from time to time may be
necessary)
10 Make clay pack and cement grout Up to the ground level
packing for the annular space
between the hole wall and casing
pipe.
11 Perform the development of a By air-lifting (surging or bailing
borehole from time to time may be
necessary)
12 Carry out the pumping test by Step drawdown, constant discharge
submersible pump. and time recovery test.
13 Construct the borehole head
facilities and install the water level
recorder.
6-6
Chapter 6 Test Borehole
6-7
Chapter 6 Test Borehole
All materials required for drilling and construction of the boreholes was selected to
conform to the determined borehole structure and specifications. The followings are
the major materials used for the borehole drilling and construction.
1) Conductor Pipe
The conductor pipes installed are high-grade carbon steel, black, conforming to the
requirements of SABS1431. Pipes were supplied in standard lengths of 6 m. Grade
B steel was supplied, so that the nominal wall thickness of the casing was more than 6
mm. Bevelled ends were specified for the both ends of each pipe.
2) Casing Pipe
The casing pipes installed are high-grade Zinc Galvanized (SABS763) steel, conforming
to the requirements of SABS1431. The pipes were supplied in standard lengths of 6 m.
Grade B steel was specified, so that, the nominal wall thickness of all casing is more
than 6 mm. Bevelled ends were specified for the both ends of each pipe.
6-8
Chapter 6 Test Borehole
3) Screen Pipe
The screen pipe selected for the boreholes are wedge wire (Johnson) type, conforming
to the Zinc Galvanized carbon steel material with bevelled ends. The detailed
specification for screen pipe shall be as follows:
Sulphur resistant cement of CEM II ENV 197 was applied as cement grouting. The
cement slurry had a specific gravity within the range 1.74 to 1.8, and was made up with
water that has a total dissolved solids (TDS) concentration of less than 1,200 mg/l and a
sulphate concentration of less than 200 mg/l.
A mixture of Sulfur Resistant cement and aggregates was used for the head works
concrete. This concrete mixing was made up of not less than five sacks of 50 kg each
per cubic meter of finished concrete. The mix did not contain large amounts of fine
materials. Fresh, potable water was used as mixing water. The aggregates used were
durable and well graded in sizes ranging from sands to rock of less than 25mm.
Following drilling mud and chemicals were used, based on the geological formation and
drilling conditions.
6-9
Chapter 6 Test Borehole
7) Development Chemical
Following development chemicals were used based on the geological formation and
drilling conditions.
8) Centralizers
Steep hinged type centralizers which can be clamped onto the casing pipes, was used
only for the Kalahari boreholes.
The cement float shoe, with aluminum non-return valve were selected for the cementing
shoe of full hole cementing operation.
6 - 10
Chapter 6 Test Borehole
Only fresh quartz gravel was used as the gravel pack material of Kalahari boreholes.
No crushed stone was used. The grain size of the gravel was 1.4 mm to 3.0 mm.
1) Drilling
The rotary drilling method with a direct mud circulation system was applied as principal
method for the drilling. Drilling have been made basically in the diameters indicated
in aforesaid section of Construction Procedure above.
2) Drilling Fluid
The drilling fluid had the following properties; 1) a maximum specific gravity of 1.20,
2) a maximum of 40 sec. (500cc/500cc) of marsh funnel viscosity and 3) a maximum of
2 mm in 30 minutes of mud cake have been used for the normal drilling operation.
The sand content was kept within a maximum of 3% after filtering by 200-mesh sieve.
The chemicals, used during drilling, was non-toxic and fully biodegradable.
For the Kalahari boreholes, the gravel pack was made, in the annular space between the
hole wall and the screen pipe. The grain size of the gravel was 1.4mm – 3.0mm. The
annular space between the casing pipes and the drilled hole wall was sealed with clay
(max. 3 m thickness) and with cement from above the clay packing to ground level. .
On the boreholes for the Auob and Nossob Aquifers, the overlaying formation was
sealed off to examine the proper hydrogeological character of the targeted aquifer.
Therefore, full hole cementing was made in the annular space between the hole wall and
casing pipes, and/or the annular space between the two casing pipes, at the pump house
section of the drilled borehole. The methods of the full hole cementing shall be
basically applied either “Inner-string Method”
5) Borehole logging
6 - 11
Chapter 6 Test Borehole
records. The all measurements were made only in uncased borehole filled with drilling
fluid. Borehole logging have been performed for six parameters of 1) Natural Gamma,
2) Spontaneous Potential, 3) Neutron, 4) Resistivity, 5) Temperature and 6) Caliper in
the whole depth of borehole immediately after the completion of the each stage of
drilling. Before the commencement of logging, the viscosity, the electrical
conductivity, apparent resistivity and the temperature of the filtered drilling fluid and
the water used in the drilling fluid was measured.
After interpretation of borehole logging results, data regarding lost circulation zones and
the drilling log, the lengths and positioning of screens and blank sections of casings (6")
were determined. Casing was lowered down the borehole by their own weight and no
force was allowed to push the casing down. All the casing pipes, from the bottom of
the hole up to 15 m below ground level had to be centralized using carbon steel
centralizers spaced at a minimum of 10 m intervals.
The bottom of the casing (6") was completely closed by a bottom-plug of the same
material as used for the casing. Where the cement grout or full hole cementing was to
be installed, the string of connected casings had to be suspended from the surface
without resting the column on the bottom of the hole until after the cementation have
been completed.
All welding joints for casing and/or screens had to comply with the standard for welding
as described in SABS 044. The welding joints outside of the casing and screens were
painted with epoxy tar.
7) Development
After the casing and screen pipes have been installed, the development work was
conducted by air lifting, or by bailing or surging in case of very low yielding boreholes.
The water level in the borehole prior to the commencement of air-lift operations was
measured and recorded.
After installing a test pump, surging of the borehole was achieved by starting and
stopping the pump, or by changing the discharge rate in order to induce reversal of
water flow through the screen openings. The development was carried out until the
borehole was adequately developed.
6 - 12