1.B . SUPER – STRUCTURE
1.B.12.Electro Mechanical Work

1 TOILET AIR EXTRACTION SYSTEM


Fan installation
Supply, Fix,test and commision DYNAIR or Equivalent fans as shown

on the drawing, complete with all accessories including control

systems for alternate operation of the flow fans.

1.1 Exhaust Air Fans


I) Toilet Exhaust Air Fan (TEF-1)
Model: TW-D
Type = Dynair or equivalent
Power input : Kw
Discharge = 490 lt/sec / 1764 m3/hr No 2.00 135,000.00 270,000.00
Head = 564 Pa
Altitude = 2355m.a.s.l

II) Toilet Exhaust Air Fan (TEF-2)


Model: TW-D
Type = Dynair or equivalent
Power input : Kw
Discharge = 225 lt/sec / 810 m3/hr No 2.00 95,000.00 190,000.00
Head = 564 Pa
Altitude = 2355m.a.s.l

III) Toilet Exhaust Air Fan (TEF-3)


Model: TW-D
Type = Dynair or equivalent
Power input : Kw
Discharge = 500 lt/sec / 1800 m3/hr No 2.00 140,000.00 280,000.00
Head = 572 Pa
Altitude = 2355m.a.s.l

1.2 Exhaust Air Duct


Supply, fix, test and commision rectangular exhaust air ducts
made of galvanized steel sheet complete with dampers and
fittings including all acessories. All duct works connection
should be done as per SMACNA Standard and using
Flanges, corners gasket and Silcon.
* All connection to be made using Flange, Gasket
and Corners only.

Duct longer size (mm) Sheet metal thickness (mm)


Up to 600 mm 0.6 mm
600 to 800 mm 0.8 mm
800 to 1000 mm 0.9 mm
1000 to 1200 mm 1.0 mm
1200 to 1500 mm 1.3 mm
1500 to 2100 mm 1.5 mm

__________________ 1 of 23
Consulting Architects and Engineers
CMC Site Apartment Building Project
Specification and Bill of Quantities 3B+G+16 Floors Structural Work
For Zeta Construction PLC
Exhaust Air Duct
100X100mm ml 275.00 1,850.00 508,750.00
150X100mm ml 10.00 1,900.00 19,000.00
150X150mm ml 14.00 2,150.00 30,100.00
200X150mm ml 23.00 2,350.00 54,050.00
250X150mm ml 3.00 2,450.00 7,350.00
300X150mm ml 7.00 2,650.00 18,550.00
300X200mm ml 7.00 2,800.00 19,600.00
350X200mm ml 7.00 2,950.00 20,650.00
400X200mm ml 3.00 3,450.00 10,350.00
400X250mm ml 10.00 3,600.00 36,000.00

1.3 Ceilling mounted Exhaust Fans/Grills


Fix, test and commision VENTS, DYNAIR or Equivalent Ceilling

Exhaust Air Fans. The frame and blade be made from high
quality extrude alluminium pofile. Price shall include fixing foam

gasket seal around the back of the frame and flexible duct
connector as reqired; and all the necessary adaptor and
fixings to make the system complet shown on the drawing,
complete with all fixing accessories

1.3.1 Exhaust Air Ceilling Fans (EG)


Exhaust Air Ceilling Fan
Type= VENTS, DYNAIR or Equivalent
Exhaust Flow rate = 15 lt/sec
Size:150X150mm No 64.00 4,850.00 310,400.00

1.3.2 Grills (EAG-1)


Type= made of aluminium
Exhaust Flow rate = 20 - 25 lt/sec
grill Size:200X200mm No 16.00 5,400.00 86,400.00
1.3.2 Grills (EAG-1)
Type= made of aluminium
Exhaust Flow rate = 15 lt/sec
grill Size:150X150mm No 3.00 3,850.00 11,550.00
1.4 Dampers and accessories :
All dampers and accessories shall be manufactured
as per recognized codes,standards & and full fill the
requirments specified in the technical specification.

1.4.1 Volume Dampers


Fix, test and commision volume dampers of AIRMASTER or

approved quality as where shown on the drawings. Price shall


include all the necessary accessories and connecting pieces.

For duct Size: 100X100 VD No 106.00 4,850.00 514,100.00


For duct Size: 300X200 VD No 2.00 14,500.00 29,000.00
For duct Size: 400X250 VD No 4.00 18,500.00 74,000.00

__________________ 2 of 23
Consulting Architects and Engineers
CMC Site Apartment Building Project
Specification and Bill of Quantities 3B+G+16 Floors Structural Work
For Zeta Construction PLC
1.4.2 Sound Attenuator
Fix, test and commision sound Attenuator of AIRMASTER or
Approved quality as where shown on the drawings.
Price shall include all the necessary accessories and
connecting pieces.

For duct Size: 300X200 SA No 2.00 28,500.00 57,000.00


For duct Size: 400X250 SA No 4.00 38,500.00 154,000.00

ANTITIES
ITEM D E S C R I P T I O N

2 Extracting Kitchen Hood, fan and accessories


Supply,Fix, test and commission stainless steel Grade SS-304 /

aluminium thickness 1mm kitchen hoods of approved quality as per

the manufacturer's instruction and shown on the drawing. Including :


* Final Kitchen hood size will be decided after the kitchen is furnished
by the kitchen specialist.
- Grease filter with trap
- Condensate water trap
- Hangers / Support structures
- Booster fan
- Canopy light made Flourcent
2.1 TYPE : i. SIZE = (0.9mX0.6mX0.4m) No 86.00 28,500.00 2,451,000.00
2.2 TYPE : i. SIZE = (1.20mX0.8mX0.4m) No 1.00 85,500.00 85,500.00

2.2 Exhaust Air Duct


Supply,fix.test and commission galvanized steel air exhaust
ducts as where shown on the drawing. All duct construction &
installation shall follow the technical specification of this
project,standardes and recommendations conditioning given
on SMACNA (Sheet Metal and Air Contractors National
Association,INC) and EBCS11.

Price shall also include all the necessary duct reinforcement,


fixing clamps to slabs,walls, vanes, flange,corner,gasket etc
and all the necessary fittings and civil assistance works.
Galvanization coating should be 0.2mm thick.

Duct longer size (mm) Sheet metal thickness (mm)


Up to 600 mm 0.6 mm
600 to 800 mm 0.8 mm
800 to 1000 mm 0.9 mm
1000 to 1200 mm 1.0 mm
1200 to 1500 mm 1.3 mm

Exhaust duct

150x150mm mm 215.00 2,150.00 462,250.00


200x150mm mm 48.00 2,450.00 117,600.00
__________________ 3 of 23
Consulting Architects and Engineers
CMC Site Apartment Building Project
Specification and Bill of Quantities 3B+G+16 Floors Structural Work
For Zeta Construction PLC
350x200mm mm 8.00 2,950.00 23,600.00
400x200mm mm 8.00 3,450.00 27,600.00
400X250mm mm 8.00 3,600.00 28,800.00
450X250mm mm 8.00 3,800.00 30,400.00
500X250mm mm 8.00 3,850.00 30,800.00
500X350mm mm 8.00 4,250.00 34,000.00
550X300mm mm 8.00 4,250.00 34,000.00
550X350mm mm 8.00 4,400.00 35,200.00
600X350mm mm 8.00 5,200.00 41,600.00
700X350mm mm 8.00 5,600.00 44,800.00

2.3 Kitchen Exhaust Air Fan


i) Kitchen Exhaust Air Fan (KEF-1)
Type: DYNAIR or Approved Equivalent
Model: PR-L-
Exaust Fan Capacity =2100 lt/sec / 7560 m3/hr No 1.00 365,000.00 365,000.00
Power input = KW
Total Pressure = 572 pa
Altitude = 2355 m.a.s.l.

ii) Kitchen Exhaust Air Fan (KEF-2)


Type: DYNAIR or Approved Equivalent
Model: PR-L-
Exaust Fan Capacity =2100 lt/sec / 7560 m3/hr No 1.00 365,000.00 365,000.00
Power input = KW
Total Pressure = 572 pa
Altitude = 2355 m.a.s.l.

iii) Kitchen Exhaust Air Fan (KEF-3)


Type: DYNAIR or Approved Equivalent
Model: PR-L-
Exaust Fan Capacity =2250 lt/sec / 8100 m3/hr No 1.00 365,000.00 365,000.00
Power input = KW
Total Pressure = 572 pa
Altitude = 2355 m.a.s.l.

iV) Kitchen Exhaust Air Fan (KEF-4)


Type: DYNAIR or Approved Equivalent
Model: PR-L-
Exaust Fan Capacity =4350 lt/sec / 15664 m3/hr No 1.00 650,000.00 650,000.00
Power input = KW
Total Pressure = 562 pa
Altitude = 2355 m.a.s.l.
V) Kitchen Exhaust Air Fan (KEF-5)
Type: DYNAIR or Approved Equivalent
Model: PR-L-
Exaust Fan Capacity =755 lt/sec / 2718 m3/hr No 1.00 125,000.00 125,000.00
Power input = KW
Total Pressure = 350 pa
Altitude = 2355 m.a.s.l.

2.4 Dampers and accessories :


__________________ 4 of 23
Consulting Architects and Engineers
CMC Site Apartment Building Project
Specification and Bill of Quantities 3B+G+16 Floors Structural Work
For Zeta Construction PLC
All dampers and accessories shall be manufactured as per recognized
codes, standards & and full fill the requirements specified in the
technical specification.

2.4.1 Volume Dampers


Supply, Fix, test and commission volume dampers of approved quality
as where shown on the drawings. Price shall include all the necessary
accessories and connecting pieces.
Model: AIR MASTER or Equivalent
For duct Size: 150x150mmxmm/ VD No 115.00 5,600.00 644,000.00
For duct Size: 200x150mmxmm/ VD No 14.00 6,580.00 92,120.00
For duct Size: 550x300mmxmm/ VD No 2.00 7,800.00 15,600.00
For duct Size: 550x350mmxmm/ VD No 1.00 8,200.00 8,200.00
For duct Size: 700 x 350 mmxmm/ VD No 1.00 12,500.00 12,500.00

2.4.2 Sound Attenuator


Supply, Fix.test and commission Sound Attenuator of approved quality

as specified and/or shown on the drawings. Price shall include all the

necessary accessories and connecting pieces.

For duct Size: 550x300mmxmm/ SA No 2.00 45,000.00 90,000.00


For duct Size: 550x350mmxmm/ SA No 1.00 48,500.00 48,500.00
For duct Size: 700 x 350 mmxmm/ SA No 1.00 55,000.00 55,000.00

2.4.3 Fire Damper


Supply, Fix.test and commission Sound Attenuator of approved quality

as specified and/or shown on the drawings. Price shall include all the

necessary accessories and connecting pieces.

For duct Size: 550x300mmxmm/ FD No 2.00 45,000.00 90,000.00


For duct Size: 550x350mmxmm/ FD No 1.00 48,500.00 48,500.00
For duct Size: 700 x 350 mmxmm/ FD No 1.00 55,000.00 55,000.00
3 BASEMENT VENTILATION SYSTEM BILL OF QUANTITIES
3.1 Basement Exhaust Air Fan
i) Exhaust Air Fan (EAF-1)
Type: DYNAIR or Approved Equivalent
Model: double belt driven
Exaust Fan Capacity =3750 lt/sec / 13500 m3/hr No 1.00 365,000.00 365,000.00
Power input = KW
Total Pressure = 350 pa
Altitude = 2355 m.a.s.l.

ii) Supply Air Fan (SAF-1)


Type: DYNAIR or Approved Equivalent
Model: double belt driven
Exaust Fan Capacity =3750 lt/sec / 13500 m3/hr No 1.00 365,000.00 365,000.00
Power input = KW
__________________ 5 of 23
Consulting Architects and Engineers
CMC Site Apartment Building Project
Specification and Bill of Quantities 3B+G+16 Floors Structural Work
For Zeta Construction PLC
Total Pressure = 350 pa
Altitude = 2355 m.a.s.l.

3.2 Dampers and accessories :


All dampers and accessories shall be manufactured as per recognized
codes, standards & and full fill the requirements specified in the
technical specification.

2.3.1 Volume Dampers


Supply, Fix, test and commission volume dampers of approved quality
as where shown on the drawings. Price shall include all the necessary
accessories and connecting pieces.
Model: AIR MASTER or Equivalent
For duct Size: 600x400mmxmm/ VD No 4.00 25,800.00 103,200.00

2.3.2 Sound Attenuator


Supply, Fix.test and commission Sound Attenuator of approved quality

as specified and/or shown on the drawings. Price shall include all the

necessary accessories and connecting pieces.

For duct Size: 600 x 400 mmxmm/ SA No 2.00 65,000.00 130,000.00

2.3.3 Fire Damper


Supply, Fix.test and commission Sound Attenuator of approved quality

as specified and/or shown on the drawings. Price shall include all the

necessary accessories and connecting pieces.

For duct Size: 600 x 400 mmxmm/ FD No 4.00 65,000.00 260,000.00


Exhaust duct
600x400mm ml 10.00 7,700.00 77,000.00
Supply duct
600x400mm ml 10.00 77,000.00 770,000.00
3 Garbage chute system
General
Supply , Install and fix,test and commission stainless steel(SS304) /
aluminium indoor garbage chute collection ducts with
ventilation system included and vent tube with insect screen
and exhaust fan as where shown on the drawing. All duct
construction,duct thickness and installation shall follow the
technical specification of this project, standards and
recommendations given on BS1703:1977/ BS 5906:1980.
Price shall include all the necessary duct fittings, reinforcement, hot

dipped galvanized steel support roads, brackets,fixing clamps

angle,iron walls, vanes, sound insulations etc and all the necessary

fittings and civil assistance works.

__________________ 6 of 23
Consulting Architects and Engineers
CMC Site Apartment Building Project
Specification and Bill of Quantities 3B+G+16 Floors Structural Work
For Zeta Construction PLC
3.1 CHUTE Ventilation
Trash chute vent and exhaust fan in inhibiting unwanted smell in the
chute according to NFPA 82, ASHRAE 62.1 2007 standard. The vent
unit is shaped from stainless steel parts such as weather proof cap,
insect screen and vent duct.
For the flat roof with a cap on top to guard against rain
Size: Diameter Ø300mm, 1.2m long above roof level NR 1.00 3,500.00 3,500.00
3.2 AXIAL CENTRIFUGAL FAN EXTRACTOR -
Flow: 5,00lps @ 250pa, per manufacturer standard -
Power: 220V/50Hz/0.85Kw, per manufacturer standard NR 1.00 65,000.00 65,000.00
3.3 INSPECTION ACCESS DOOR -
Manufacture and fix The Inspection Access Door and is situated on

the top most floor, kept above the Intake Garbage Chute door. -
Size: 500x500mm -
Material: Stainless steel 304 / aluminium NR 1.00 6,500.00 6,500.00
3.4 CHUTE HEAD PLATE -
Manufacture and installation of the chute head plate is with all
necessary connections and holes for the flushing spray head and air
vent. The plate is also removed for maintenance reason of the chute
system. NR 1.00 6,500.00 6,500.00
3.5 CHUTE TUBE/DUCT -
Manufacturing & install Chute Duct extends from the garbage

collection room to the top floor where the highest intake is located.

The tubes are continuously TIG welded which ensures watertight

system without any bolts, rivets or other projections inside the chute. -
Size: 500 x 500mm, 1mm thick -
Material: Stainless steel 304 / aluminium lm 56.00 8,500.00 476,000.00
3.6 CHUTE SUPPORTING FRAME & CLAMP RINGS -
Supply and install Hot Dip Galvanized Chute Support Frames are
fixed around to chute and bolted to SSL and to wall by 4 Nos Rawl
plugs. The wing is shaped from 5mm Mild Steel and welded to
50x50x5mm angle bars. The interior of the rings are covered with
3mm anti vibration rubber pad as a sound isolator and protects the
chute from corrosion. The frames are fixed to slab at each floor. NR 17.00 3,500.00 59,500.00
3.7 INTAKE THROAT/Chute Intake -
Manufacturing & install Chute intakes are Stainless Steel (Grade 304)
and designed to suit the bottom hinged hopper doors for proper
disposal of the trash bags. The intake sections are continuously
welded, rectified inside and sealed externally with mastic to be free
from obstructions. NR 15.00 6,500.00 97,500.00
3.8 ALUMINIUM DOOR -
Manufacturing & install Aluminium hinged doors, with cladding panel.

The size : 400 x 800 mm, noiseless, self sealing, self closing with door

Interlocking device with led indicator lamps which operates One Door

at a time & lock Cleaning and Maintenance time. -


Shaped from 1mm Stainless Steel Sheet, including its latch, indicator
lamps and handle are made out of stainless steel. NR 15 13500 202,500.00
3.9 OFFSET FOR CHUTE BOTTOM -
__________________ 7 of 23
Consulting Architects and Engineers
CMC Site Apartment Building Project
Specification and Bill of Quantities 3B+G+16 Floors Structural Work
For Zeta Construction PLC
Manufacturing & install offset with a diameter 500 mm fabricated from
Stainless Steel to suit the site conditions, continuously welded chute
offset is a 45° angled discharge unit reinforced and separately
supported at the area of impact. NR 1 6500 6,500.00

-
Total Carried to Summary 12,171,120.00

__________________ 8 of 23
Consulting Architects and Engineers
C-37 Concrete Formwork
From 1st
basment -
From 3rd-2nd From 2nd- ground
basment 1st basment floor Unit m2
In elevation column 8.32 8.32 8.32 m3 163.58
In lift shaft shear wall 15.35 15.35 15.35 m3 370.76
In shear wall 41.00 41.00 41.00 m3 693.82
In 250mm thick retaining wall 49.59 49.59 49.59 m2 1,157.17
C-30 Concrete
In mat beam 226.04 m3 515.19
In mat slab 436.24 m3 80.78
In 2nd basment floor Beam 1.44 m3 30.90
In 1st basment floor Beam 1.26 m3 29.73
In ground floor Beam 0.90 m3 25.46
In 100mm thick basment floor 27.13 m3
In 220mm thick 2nd basment floor flat slab 81.34 m3 369.72
In 220mm thick 1st basment floor flat slab 83.82 m3 381.00
In 220mm thick ground floor flat slab 75.70 m3 344.11
From 3rd-2nd basment Stair 2.89 m3 19.67
From 2nd-1st basment Stair 2.89 m3 19.67
From 1st basment - ground floor Stair 2.89 m3 19.67
Rebar Post Tension Masonry Work 4mm Water Proffing

Kg m2 m3 m2
5,411.79 1,094.83 12.00 1,257.32

41,351.00

15,799.01

41,211.44
39,233.01

1,301.18

18,946.43

1,183.14
2nd - 3rd
ground - 1st 1st - 2nd 3rd - 4th 4th - 5th 5th - 6th
In elevation column 8.16 6.46 5.81 5.81 5.81 4.13
In shear wall 55.51 43.95 40.69 40.69 40.69 40.69
In lift shaft shear wall 20.78 16.25 16.25 16.25 16.25 16.25
In Beam 5.63 7.27 7.27 7.27 7.27 7.27
In 220mm thick flat slab. 99.51 97.21 95.80 97.21 95.80 97.21
In Stair 3.40 2.89 2.89 2.89 2.89 2.89
In elevation column 48.96 38.76 36.18 36.18 36.18 31.01
In shear wall 308.37 244.12 242.02 242.02 242.02 242.02
In lift shaft 161.48 129.90 129.90 129.90 129.90 129.90
In Beam 37.11 49.00 49.00 49.00 49.00 49.00
In 220mm thick flat slab. 471.22 460.09 453.47 460.09 453.47 460.09
In Stair 23.50 19.67 19.67 19.67 19.67 19.67
In elevation column 1,291.25 1,035.52 1,011.70 1,011.70 1,011.70 712.82
In lift shaft shear wall 14,084.52 11,199.78 6,950.56 6,950.56 6,950.56 6,950.56
In Beam 937.33 1,285.13 1,285.13 1,285.13 1,285.13 1,285.13
In 220mm thick flat slab.
In Stair 451.16 407.01 407.01 407.01 407.01 407.01
PT 452.69 452.69 452.69 452.69 452.69 452.69
6th - 7th 7th - 8th 8th - 9th 9th - 10th 10th -11th 11th - 12th 12th - 13th
4.13 4.13 3.62 3.62 3.62 3.62 3.10
40.69 40.69 35.02 35.02 35.02 35.02 35.02
16.25 16.25 16.25 16.25 16.25 16.25 16.25
7.27 7.27 7.27 7.27 7.27 7.27 7.27
95.80 97.21 95.80 97.21 95.80 97.21 95.80
2.89 2.89 2.89 2.89 2.89 2.89 2.89
31.01 31.01 28.42 28.42 28.42 28.42 25.84
242.02 242.02 238.96 238.96 238.96 238.96 238.96
129.90 129.90 129.90 129.90 129.90 129.90 129.90
49.00 49.00 49.00 49.00 49.00 49.00 49.00
453.47 460.09 453.47 460.09 453.47 460.09 453.47
19.67 19.67 19.67 19.67 19.67 19.67 19.67
712.82 712.82 690.13 690.13 690.13 690.13 569.42
6,787.48 7,178.33 6,345.32 6,345.32 6,345.32 6,345.32 6,300.51
1,285.13 1,285.13 1,285.13 1,285.13 1,285.13 1,285.13 1,285.13

407.01 407.01 407.01 407.01 407.01 407.01 407.01


452.69 452.69 452.69 452.69 452.69 452.69 452.69
roof -
13th - 14th 14th - 15th 15th - 16th 16th - roof upper roof
3.10 3.10 3.10 1.55
35.02 35.02 29.69 18.36 10.80
16.25 16.25 16.25 16.25 11.70
Concrete
7.27 7.27 12.03 4.35 2.42
97.21 100.47 81.24 50.25 6.76
2.89 2.89 2.89 2.89
25.84 25.84 25.84 12.92
238.96 238.96 223.45 119.35 73.08
129.90 129.90 129.90 129.90 98.30 Form
49.00 49.00 82.88 29.49 17.22 work
460.09 475.58 378.80 238.48 30.71
19.67 19.67 19.67 19.67
569.42 569.42 565.94 271.17
6,300.51 6,274.37 5,166.48 5,741.72
1,285.13 1,285.13 1,583.47 650.04 296.41
Kg
108,096.27
407.01 407.01 407.01 407.01
452.69 452.69 452.69
HCB
Sub Structure Supper Structure
20cm 22.33 4,111.00
15cm 68.73 6,431.26
10cm 0.00 978.90
2, ROOFING

2.1 Average 7cm thick light weight concrete spread and leveled over R.C.roof slab
and balcony, cement pumice and sand mix in the proportion of 1:4:3.with a
slope of 2% towards down pipe. m2

2.2 3cm thick cement screed a ratio of 1:3 on top of light weight concrete keeping
the slope as indicated. m2

2.3 Apply APP modified & thickness not less than 4mm slated finish water
proofing membrane or compatible equivalent material for concrete roof slab as
per the manufacturer's instruction. m2

2.4 Supply and fix wire dome leaf strainer ml

TOTAL CARRIED TO SUMMARY


440.00 0.00 0.00

440.00 0.00 0.00

440.00 0.00 0.00

10.00 220.00 2,200.00

2,200.00
3. Metal and Aluminum WORK
3.1.1 Window.
W 1 Size - 348x150cm Nº 1.00
W 2 Size - 415x200cm Nº 1.00
W 3 Size - 530x200cm Nº 1.00
W 4 Size - 250x200cm Nº 1.00
W 5 Size - 230x200cm Nº 1.00
W 6 Size - 150x190cm Nº 45.00
W 7 Size - 90x190cm Nº 16.00
W 8 Size - 100x190cm Nº 16.00
W 9 Size - 110x190cm Nº 1.00
W 10 Size - 135x190cm Nº 16.00
W 11 Size - 120x80cm Nº 28.00
W 12 Size - 70x80cm Nº 14.00

3.1.2 Top Window.


TW 1 Size - 500x70cm Nº 1.00
TW 2 Size - 490x70cm Nº 1.00
TW 3 Size - 725x70cm Nº 1.00
TW 4 Size - 250x70cm Nº 1.00
TW 5 Size - 315x110cm Nº 1.00
TW 6 Size - 80x60cm Nº 88.00
TW 7 Size - 45x60cm Nº 14.00
TW 8 Size - 60x60cm Nº 14.00

3.1.3 Window Door.


WD 1 Size - 286x451x170x286cm Nº 1.00
WD 2 Size - 200x310cm Nº 1.00
WD 3 Size - 150x260cm Nº 29.00
WD 4 Size - 200x260cm Nº 29.00
WD 5 Size - 110x190cm Nº 14.00
WD 6 Size - 531x260cm Nº 1.00
WD 7 Size - 365x181x260cm Nº 1.00

3.1.4 Door.
D 2 Size - 80x210cm Nº 1.00
D 3 Size - 70x210cm Nº 3.00

3.2 Metal doors fabricated with LTZ black steel profile 38mm wide price
includes all necessary iron mongery, one coat of primer, two coats of
synthetic enamel paint & cylindrical lock doors. (glazing measured
separately)
NB-All dimensions shall be verified on-site prior to production. All
locks, handles, springs& lashes shall be of the best quality &
approved by the Arch.
D1 Size - 90x210cm No 1.00

3.3
Supply & fix in position Aluminum railing for stair case in
accordance with drawing & technical specifications. Price shall
include & all necessary fixing accessories including but not limited
to : brackets, flanges, anchors, fasteners, grouting and anchoring
cement. ml 128.40
3.4
Supply & fix in position 80cm high Aluminum railing for balcony in
accordance with drawing & technical specifications. Price shall
include & all necessary fixing accessories including but not limited
to : brackets, flanges, anchors, fasteners, grouting and anchoring
cement. ml 198.70

TOTAL CARRIED TO SUMMARY


4. CARPENTARY AND JOINERY

4.1 Supply and fix flush wooden doors both sides covered with 4mm
thick good quality kerrero ply wood with sides, top and bottom lipped
and edged with hard wood complete work with all the necessary
accessories. Price includes three coats of varnish paint, locks, hinges
& stopper.

Doors
D4 Size - 120x210cm Nº 60.00
D5 Size - 90x210cm Nº 101.00
D6 Size - 90x210cm Nº 126.00
D7 Size - 80x210cm Nº 104.00

4.2 construct built in cupbourd made of semi solid wooden corewith


walnut veneer facing fixed in place as shown in the drawing. Price
shall include varnish paint and necessary iron mongery all as per the
architectural detail drawing.

BCB1 size 150 x 60 x 260cm No. 14.00


BCB2 size 200 x 60 x 260cm No. 14.00
BCB3 size 120 x 60 x 260cm No. 84.00

BCB4 size 190 x 60 x 260cm No. 1.00


BCB5 size 220 x 60 x 260cm No. 1.00
BCB6 size 250 x 60 x 260cm No. 2.00

4.3 Construct kitchen cabinet made of semi solid MDF wooden core top
and side finish with walnut veneer with drawer, double bowel kitchen
sink, shelves and cupboard all asper the architectural detail drawing.
price shall include the necessary iron mongery. And marble top on
sink area

KCB1 size (220 x 60 x 90 + 220 x 40 x 80)cm No. 14.00


KCB2 size (240 x 60 x 90 + 240 x 40 x 80)cm No. 28.00
KCB3 size (280 x 60 x 90 + 280 x 40 x 80)cm No. 56.00
KCB4 size (180 x 60 x 90 + 180 x 40 x 80)cm No. 14.00
KCB5 size (260 x 60 x 90 + 260 x 40 x 80)cm No. 28.00

KCB6 size (300 x 60 x 90 + 300 x 40 x 80)cm No. 1.00


KCB6 size (160 x 60 x 90 + 160 x 40 x 80)cm No. 1.00
KCB6 size (350 x 60 x 90 + 350 x 40 x 80)cm No. 1.00

TOTAL CARRIED TO SUMMARY


5. FINISHING
5.1 Wall finishing
5.1.1 Apply two coats of plaster in cement-sand mortar mix 1:3 and
smooth finish to internal HCB wall, column and beam surface.
All wall-concrete structure joints shall be recessed to avoid hairline
cracks. The proportioning of the first two coats (Base Coats) shall be
1:3 cement sand ratio. Portland Cement Shall comply with the
requirements of ASTM C 150, Type I. Sand 00 Aggregates for Base
Coats shall comply with the requirements of ASTM C 897.

m2 28,148.69

5.1.2 Apply two coats of plaster in cement-sand mortar mix 1:3


concrete ceiling and stair soffit surface. All wall-concrete structure
joints shall be recessed to avoid hairline cracks. The proportioning of
the first two coats (Base Coats) shall be as indicated on the specs.
Portland Cement Shall comply with the requirements of ASTM C
150, Type I. Sand 00 Aggregates for Base Coats shall comply with
the requirements of ASTM C 897.
m2 7,038.52

5.1.3 Apply three coats of plaster in cement-sand mortar mix 1:3 to the
external HCB wall column and beam surface as located in the
drawings. m2 5,103.54
0.00
5.1.4 Apply fine coat Gypsum chuck plastering above second coat
cement plastering to internal wall surface, slab sofit and stair case
sofit. m2 30,139.96

5.1.5 Supply and fix 300 x 600 x 60mm RAK or equivalent ceramic wall
cladding, of matching color to floor, stuck to wall with cement sand
mortar 1:3 backing and grouting with white cement wash. Mortar
backing measured separately with two coat plastering. Price shall
include rod anchors to backing. Color and pattern according to
architect's drawings.
m2 5,047.26

5.2 Floor Finishing

5.2.1 Apply 40mm thick fine finish epoxy flooring price includes all the
necessary materials and civil work required m2 1,195.38

6.2.3 300x300x10mm RAK or equivalent Non-slippery ceramic floor tiles


bedded in 3cm thick cement sand mortar mix (1:3) price includes
cement sand mortar. Match colour with wall ceramic for bathrooms
and kitchen.
m2 1,681.70
5.2.4 Prepare the surface, supply and fix best quality SFT 60 x 60cm non-
slip porcelain floor tiles bedded in 40mm thick cement sand mortar
backing mix (1:3). Color and pattern is subject to Architect's
approval price includes cement sand mortar backing and filler.
m2 5,167.76

5.2.5 10cm high porcelain skirting of matching color to floor tiles.Color


and type to be approved by the Architect. Price shall include all
necessary materials for fixing the skirting. ml 4,932.15

5.3 Supply & lay granite steps thread & riser bedded in cement mortar
1:3

5.3.1 a) Thread size average 28/3 mm ML 549.60

5.3.2 b) Riser size 16/2 cm ML 549.60

5.3.3 Supply and fix 10cm approved standard Granite skirting match
colour with floor tile bedded in 3cm thick cement sand mortar mix
(1:3) price includes cement sand mortar. ML 231.20

5.3.4 Supply and fix 400*400*2mm thick Granite floor tile for stair case
landing beded in 3cm thick cement sand mortar mix. price includes
cement sand mortar. m2 60.00

5.3.5 Supply and fix 30 mm thick granite window sill, price shall include
cement and sand mortar bedding. ml 428.37

5.3.6 supply and fix 2 x 20mm thick granite threshold for doors, edge of
stair case, balcony & suspended slab, price shall include cement and
sand mortar bedding. ml 363.30

5.4 Ceiling Finish


5.4.1 Supply and fix suspended perforated aluminum ceiling price to
include all the necessary accessories and civil works required. m2 1,031.20

5.4.2 Supply and install 9mm thick gypsum board ceiling with tapered and rounded

edges fixed on 75mm galvanised metal channel framing suspended from slab sofit.

Unit prices shall include all materials, accessories, equipment, labor and all

preparation works necessary for performance of the work. (CL-02) m² 6,360.41


TOTAL CARRIED TO SUMMARY
6, PAINTING

Pricing Note:-

6.1 Apply 3 coats of approved plastic paint to all internal plastered, ceiling
slab & all concrete wall structure surfaces. m2 30,139.96

6.2 Apply approved type quartz paint to all external plastered HCB &
structure surfaces as located in the drawing. Price shall one coat of
prime. m2 5,103.54

TOTAL CARRIED TO SUMMARY


7. GLAZING

7.1 6mm thick clear glass glazed to


windows with putty. m2 3,418.06

TOTAL CARRIED TO
SUMMARY