Notes
Notes
Even after you’ve established the project’s scope, some stakeholders may want to discuss adjusting
it. They may feel that the project’s current scope will require too much work with too few resources,
that the timeline isn’t realistic given the scope, or that the project requires additional tasks and
objectives. When your stakeholders ask to revisit a project’s scope, you should meet with them so
they can raise their concerns. Knowing how to effectively facilitate scope negotiations will allow you
to reach solutions that are suitable for everyone.
1.
Question 1
As a project manager working on a new project, you need to identify potential tasks for the
team. For this project, there are many roles that require specific expertise and many distinct tasks.
Additionally, some team members will have similar tasks. You’d like to have the team generate a full list
of detailed tasks and get agreement on the tasks and owners. What interaction should you have?
1 / 1 point
Correct
With a group brainstorm, you can get the team to think through tasks together and establish a
group consensus. You can also save time by talking with the team at once instead of having one-on-one
conversations.
2.
Question 2
As a project manager working on a new project, you need to select a graphic designer on your
team to work on a marketing campaign. You’re unsure of each designer’s background and skill set. Which
type of interaction would be best to learn more about each teammate's background and identify
potential tasks?
1 / 1 point
Correct
You should have one-on-one conversations with the team members to learn their background
and if they can help you better understand how to complete the task.
3.
Question 3
As a project manager working on a new project, you need to identify potential tasks for the
team. For a deliverable, you need to create marketing materials, but your team’s primary expertise is
product development. Which type of interaction would be best to identify marketing-related tasks?
1 / 1 point
Correct
You may need to consult with other people in your organization who are not on your team. They
can provide valuable expertise and help fill in knowledge gaps.
4.
Question 4
As a project manager working on a new project, you need to identify potential tasks for the
team. For this project, you plan to get input from the team’s leadership about tasks. Which type of
interaction would be best to identify tasks?
1 / 1 point
Correct
Stakeholders with high- or medium-level interest or influence in the project are most likely to
provide the information you need.
5.
Question 5
As a project manager, you’re going to meet with a stakeholder to discuss potential project tasks.
What are two best practices to prepare for the meeting?
1 / 1 point
When meeting with a stakeholder, you should prepare clear and well-defined questions about
the project and its tasks.You should also gather as much task information as possible before the meeting
to help you craft meaningful questions.
Wait to gather task information so you can be more open minded during the meeting.
Correct
When meeting with a stakeholder, you should have as much information about the project as
you can gather. This will help you ask informed questions about the project and its tasks.
Coursera
SEARCH IN COURSE
Search in course
Ungraded Plugin: Activity: Part 1: Identify time estimates for your project plan
Practice Quiz: Activity: Part 2: Identify time estimates for your project plan
Module 2
Receive grade
Your grade
80%
1.
Question 1
What are the benefits of providing accurate time estimates for individual tasks? Select all that apply.
1 / 1 point
Correct
If a milestone is likely to go over an important deadline, you can quickly make adjustments to the size of
the tasks or team members' workloads to fit within a required deadline. Accurate estimates also help to
establish a better sense of the project timeline and track task progress.
Correct
By adding up each task’s duration, you get an informed idea of when you and your team will complete
the project. Accurate estimates also clarify if a milestone may go over deadline and help to track task
progress.
Correct
Knowing tasks’ time estimates allows you to better understand how far along a team is with a particular
phase of a project. Accurate estimates also help to establish a better sense of the project timeline and
clarify if a milestone may go over deadline.
2.
Question 2
As a project manager, you try to get an accurate time estimate for a task by communicating with an
expert. After considering their time estimate, you are unsure if it includes all steps of a task, so you ask
them to explain each step in detail.
What strategy for getting an accurate time estimate did you choose?
0 / 1 point
Ask the expert how likely they think it is that an assumption might not work out and how it would affect
their estimate.
Check the expert's understanding of the task.
Check the expert’s estimates against the actual time spent on similar tasks in previous work.
Incorrect
You ask the expert to explain the steps not to assess how likely it is that their assumptions might not
work out, but to check their understanding of the task. This strategy helps an expert arrive at a time
estimate by thoroughly thinking through each step in a task.
3.
Question 3
As a project manager, you try to get an accurate time estimate for a task by communicating with an
expert. After receiving their time estimate, you ask questions like, “What equipment do you suppose
you’ll have?” and “How many people do you expect to work on the task?”
What strategy for getting an accurate time estimate did you choose?
1 / 1 point
Check the expert’s estimates against the actual time spent on similar tasks in previous work.
Discuss the assumptions the expert may be making when they give an estimate.
Correct
Asking the expert about their specific assumptions can help uncover areas where they may be misguided
in the project.
4.
Question 4
As a project manager, you try to get an accurate time estimate for a task by communicating with an
expert. You ask them to think back to a task that resembles the one for this project and describe what
was the same, what was different, and if thinking about this previous task changes their estimate.
What strategy for getting an accurate time estimate did you choose?
1 / 1 point
Ask the expert how likely they think it is that their assumptions might not work out and how it would
affect their estimate.
Check the expert’s estimates against the actual time spent on similar tasks.
Discuss the assumptions the expert may be making when they give an estimate.
Correct
You can estimate task time by reviewing the time it took an expert to complete a similar task on a
previous project.
5.
Question 5
What type of time estimate considers how long it takes to complete a task, plus the time it takes to test
the product?
1 / 1 point
Conservative estimate
Effort estimate
Timeline estimate
Correct
There are two types of time estimates: effort estimates and total duration estimates. The main difference
between effort estimate and total duration estimate is adding time for factors such as prep, approvals,
and testing.
The three-point estimating technique can be used to help determine the most realistic time estimate for
a task. It uses optimistic, pessimistic, and most likely calculations, meaning calculations are based on the
“best case” (optimistic), “worst case” (pessimistic), and most probable scenarios.
Three-point estimation
In this technique, each task receives three estimates: optimistic, most likely, and pessimistic. Each of
these three estimates is then associated with the corresponding amount of time that task is expected to
take.
See definitions:Optimistic
Assumes the best case scenario that issues will not occur
Most Likely
Assumes some issues might occur and based on how long the task usually takes under normal
circumstances
Pessimistic
Assumes the worst case scenario that issues will definitely occur
For each task, add a duration estimate in each category: optimistic, most likely, and pessimistic. You can
get these estimates by doing research on the task or by asking a task expert. As a best practice, add
notes about the conditions that determine each estimate.
4 Hours
Most Likely = Vendor is qualified but might not have all the materials;
Vendor is new and needs extra time
6 Hours
Staff no-shows or turnover right before the training; Equipment isn’t delivered
6 Days
To determine your final estimate—the estimate you’re going to use in your project plan—examine the
optimistic and pessimistic timing, then compare it with the most likely timing. Consider the conditions
that are likely to exist while the task is being completed. Does it seem reasonable that the most likely
time can be met? If your team has never completed this task before, or if dependencies for the task are
unknown, then the final estimate should be closer to the pessimistic estimate. If your team is familiar
with the task and you’re able to confirm the conditions for an optimistic estimate, then the final estimate
can be closer to the optimistic estimate. Alternatively, simply use the most likely estimate, especially if
the difference between the optimistic and pessimistic estimates is minimal (a few hours or no more than
one or two days). A good practice is to build in a “buffer” that accounts for risks that are likely but still
keeps the project progressing at an efficient rate.
Some projects will require you to calculate specific numeric values for task time estimates. There are
many online resources that provide more instruction for how to calculate estimates, but we’ve provided
two popular formulas: the Triangular Distribution and the Beta (PERT) Distribution.
For each formula: E is Estimate (the final estimate you’ll assign to the task), o = optimistic estimate, p =
pessimistic estimate, and m = most likely estimate.
E = estimate (the final estimate) o = optimistic estimate m = most likely estimate P = pessimistic
The weight of each estimate in this equation is identical, which means the most likely case does not
affect the final estimate more than the optimistic or pessimistic estimates.
The Beta (PERT) distribution is a weighted average. The most likely estimate receives a multiplier of four,
while the overall divisor is increased to six.
This method takes into account that the most likely case is more likely to occur, so it’s given more weight.
The added weight is reflected in the multiplier of four.
Placing more weight on the most likely estimate increases the accuracy of the estimate. In most cases,
the Beta (PERT) Distribution has been proven to be more accurate than three-point estimating and is
often used to calculate both cost and time estimates.