How To Assign Resource - Resource Loading
How To Assign Resource - Resource Loading
In Primavera P6, after finish creating the schedule, you may need to assign resource to activity to make the resource
plan.
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 1/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 2/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
For the Unit of Measure, if you don't see the Unit you need, Go to menu Admin -> Admin Categories
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 3/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
After finish creating resource, Go back to Activities window (Go to menu Project -> Activities)
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 4/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
Click on Display -> Filter By -> All Active Resource to see your resource
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 5/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
Select the resources you want to assign and click Assign button:
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 6/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
By default, when you assign resource to activity, the unit will be distributed linearly. For example: assign 80 m3 to 10
days activity, each day will take 08 m3.
In case you don't want distribute resource linearly, you can show the resource curve column. Right click in Resource
tab, click Customize Resource Columns:
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 7/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
Click on the Curve column and select Back Loaded for example.
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 8/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
Now we can see the resource is distributed more at the end period of activity:
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 9/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
Go to menu Project -> Resource Assignments. We can make the layout look like below picture:
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 10/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 11/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 12/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 13/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
Select Concrete resource, on the chart area Right click and select Resource Usage Profile Option:
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 14/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 15/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
Later, when we update process (having Actual data), the report will be like this:
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 16/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 17/18
2/20/24, 5:44 PM How to assign resource / resource loading / make resource plan in Primavera P6 | dedicated to Project Controls
Website Development by Hunt Data Solutions and Vit-al Interactive. CMS: Drupal THEME: Acquia Marina
www.planningplanet.com/blog/how-assign-resource-resource-loading-make-resource-plan-primavera-p6 18/18