Engineering Change Management - How It Works For Material Master - SAP Blogs

Engineering change management (ECM) in SAP allows controlled changes to be made to production master data like bills of material (BOMs) and material masters. ECM works through change master records that document changes and control effectivity. Changes made through ECM are saved with date or parameter effectivity and revision history. ECM helps control losses by providing authorization for changes and documentation of changes to key master data like valuation class and profit center to avoid unintended issues.

Uploaded by

sapppqmmanlo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
272 views7 pages

Engineering Change Management - How It Works For Material Master - SAP Blogs

Engineering change management (ECM) in SAP allows controlled changes to be made to production master data like bills of material (BOMs) and material masters. ECM works through change master records that document changes and control effectivity. Changes made through ECM are saved with date or parameter effectivity and revision history. ECM helps control losses by providing authorization for changes and documentation of changes to key master data like valuation class and profit center to avoid unintended issues.

Uploaded by

sapppqmmanlo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Community

Follow

Ask a QuestionWrite a Blog Post


 Like

 RSS Feed

raghavendra sai
June 10, 2013 | 4 minute read

Engineering Change Management –


How it works for Material Master
 2  9  51,230

Introduction :

1. Engineering Change Management:

Engineering Change Management in SAP is a process given for to change various


aspects of production Basic Data ( For Example BOMs, Task Lists ,Materials, and
Documents) with history ( with date effectivity ) or depending upon specific
Conditions (with parameter effectivity )

A change with history has the following distinctive characteristics:

è It takes effect under precisely defined conditions (precise date or specific


effectivity

è Parameter value).

è The changed object is saved twice: in its state before and after the changes.

è A change master record or ECR/ECO controls and documents the changes.

2. How It works: A demo:

ECM works through a Change Master Record

Definition:
The change master record is a master record that contains information
necessary for the

Management and control of changes.

The change master record contains data of a descriptive character (such as the
reason for the Change) and control data (such as effectivity data, object type
indicators). Besides this data that the user maintains, there is also data that is
automatically updated by the system (management Data).

Structure:

The most important change master record data is grouped as follows:

è Change header (description, affectivity data, status information)

è Object type indicators (for example, BOMs, task lists, documents)

è Object overviews for the different object types

è Detail screens for the different objects (object management records)

Exactly which data is maintained depends on the function that the change
master record adopts in the change process. For example, you do not need to
maintain object type indicators for a Change master record that has been created
with the Leading change master record function .

Integration

In the R/3 System, change master records are identified by a change number. is
made according to defined criteria. In the change process, a change number can
identify change master records with the following tasks:

è Simple change master record (with or without release procedure)

è ECR / ECO

è Change master record of an engineering change hierarchy

è Change leader (Leading change master record)

A sample Change Master Record Creation:

Use the Transaction Code CC01.


When Save
Assigning the Change Master Record to the Material Master during a New
Material Creation

For Creating the Material Master Use the Transaction Code MM01 and here
assign the change number

Once saving the material the material will get created with the change number.

Soon after getting the material this material can be changed with the change
number assigned or can be scheduled for change at a later stage.

All the changes will get saved for display to have the change history of the record.
3 Material Master Control through ECM

AMaterial Master which had been created with a Change Control Record or a
material Master which has been changed with a Change Control Record can have
many usages when compared with a material master which is crated or changed
without a change control record. For Example Control of the Master Data:

è Master Data like Material Master serves as a central data for various applications
like External and Internal Purchasing documents , BOMs, Scheduling , Sale
Orders etc and hence the changes which are being planned or which are being
changed needed to get documented. This Documented data will serves in
controlling the change.

è The material data like Valuation Class, Profit Center, Tax Classifications,
Classification data, etc are termed to be most important and the change to the
values leads to application to run erratically. And hence the change Records will
provide provision for controlled change of the material master.

è Change records authorization will provide a controlled atmosphere for the


changes

è Material master though it contains the changes record will just serve as just a
Data , but when created or changed through Change Master Record will contain
the history of the changes for Past and present , and can give a way to plan for
the flow of the changes for present and for future.

è Once the materials are created or changed through change control records,
automatically in a course of time the duplicity will get reduced.

Revision Level : Through the Change Number Assignment concept for the material
master we can have the Revision level for the change .

A Brief Demo for the same . AT CC11 screen


Once Press Enter

Once Press Enter

Once save the record , Revision level gets assigned to the material.

4.How the Process helps in controlling losses:

The below Examples will depict how a loss can be raised:

è An unwanted change in the material master for a valuation class can lead to
configuration issue for a GL account, thereby loosing time in a goods Receipt
entry which in turn might cause a shortage leading to production down time or a
late goods issue for the delivery might cause a customer loss.

è An unwanted or un authorized change in the Profit center can cause a


Controlling and Profitability (COPA) issue.
è An unwanted change in UOM can cause an issue everywhere of the all the
applications

To name these are few are the losses created by an unwanted change for the
master data like material master. Through controlled changes of the master
using the ECM can improve the margins in a phased manner.

5. Conclusion

Though Engineering Change Management applies to many areas, Material Master


is one such, which needed to get controlled for the changes as the change applies
to many areas of application .The Controlled change through ECM leads to proper
documentation of the changes and provides a controlled environment for the
changes.

Alert Moderator

Assigned Tags

MM (Materials Management)

SAP ERP

enterprise resource planning

sap erp logistics materials management

Similar Blog Posts 


S/4HANA Extended Production Engineering and Operations (PEO) Part 1 - Configuration Settings
By Lingaiah Vanam Apr 05, 2020

S/4HANA Extended Production Engineering and Operations (PEO) Part 4 – 1909 Release Updates
By Lingaiah Vanam Jun 10, 2020

Usage of Revision Level for PP Masters -BOM and Routing


By Ramagiri Srinivas Rao Feb 25, 2014

Related Questions 
Material master and Engineering change management
By P H Aug 02, 2012

How to apply the ECN apply on the followup material in material master MRP4

You might also like