Labour Schedule
Labour Schedule
BLOCK WALL
4 Masonry Man 10,010.00 nr 70.00 700,700.00
STAGE 1
Carried to Collection 902,200.00
BLOCK WALL
5 Masonry Man 10,010.00 nr 70.00 700,700.00
STAGE 2
Carried to Collection 902,200.00
BLOCK WALL
7 Masonry Man 10,010.00 nr 70.00 700,700.00
ROOF BEAM
8 Caster 45.00 cum 10,000.00 90,000.00
9 Iron bender 9.20 tons 45,000.00 414,000.00
10 carpenter 733.00 sqm 2,000.00 1,466,000.00
STAGE 3
Carried to Collection 3,618,000.00
STAGE 4
Carried to Collection 1,826,000.00
E STAGE 5 ( DOORS)
1 Fixing 91.00 nr 25,000.00 2,275,000.00
STAGE 5
Carried to Collection 2,275,000.00
F STAGE 6 ( WINDOWS)
1 Fixing sum 650,000.00
STAGE 6
Carried to Collection 650,000.00
STAGE 7
Carried to Collection 700,000.00
STAGE 8
1 Carried to Collection 889,100.00
K STAGE 10 ( FINISHING)
FLOOR TILING
1 Tiler 2,830.00 sqm 1,000.00 2,830,000.00
2 skirting 995.00 lm 200.00 199,000.00
WALL TILING
3 Tiler 618.00 sqm 1,000.00 618,000.00
WALL PLASTERING
4 Mansonry Man 6,399.00 sqm 1,000.00 6,399,000.00
CEILING FINISHING
5 Screeder 904.00 sqm 2,000.00 1,808,000.00
6 carpenter 182.00 sqm 1,000.00 182,000.00
PAINTING
7 Painter 6,867.00 sqm 500.00 3,433,500.00
15,469,500.00
SUMMARY
A STAGE 1 902,200.00
B STAGE 2 902,200.00
C STAGE 3 3,618,000.00
D STAGE 4 1,826,000.00
E STAGE 5 2,275,000.00
F STAGE 6 650,000.00
G STAGE 7 700,000.00
H STAGE 8 889,100.00
J STAGE 9 1,500,000.00
K STAGE 10 15,469,500.00