This document provides a method statement for installing an intercom system in a residential building project. It outlines the purpose, scope of work, references, definitions, responsibilities of roles like the project manager and HSE officer. It also describes materials, equipment, procedures, health and safety considerations, and attachments for the intercom installation work. The method statement aims to ensure the job is executed according to project requirements and guidelines.

Uploaded by

rockn
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
86 views

MOS Intercom Rivan

This document provides a method statement for installing an intercom system in a residential building project. It outlines the purpose, scope of work, references, definitions, responsibilities of roles like the project manager and HSE officer. It also describes materials, equipment, procedures, health and safety considerations, and attachments for the intercom installation work. The method statement aims to ensure the job is executed according to project requirements and guidelines.

Uploaded by

rockn
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 41

Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]

Project No.: P44 [K126] Location: Erikya – Lusail City


Client Project Manager Consultant Contractor

METHOD STATEMENT
METHOD STATEMENT No: REV:

ORIGINATOR: DISCIPLINE: ELECTRICAL

Title:

METHOD STATEMENT FOR INSTALLATION OF INTERCOM

REVIEWER / APPROVER
REV DATE STATUS REVISION DETAILS
SubC Main
EXTERNAL
on Con

Status Code:
D : Draft FI : For Information FC : For Construction
* External Authorization (Client),
P : Preliminary FA : For Approval
where required

Distribution :

Method Statement for Installation of Intercom


Page 1 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

TABLE OF CONTENTS

1.0 PURPOSE

2.0 SCOPE OF WORKS

3.0 REFERENCES

4.0 DEFINITATION

5.0 RESPONSIBILITIES

6.0 MATERIALS

7.0 EQUIPMENT

8.0 PROCEDURE

9.0 HEALTH, SAFETY AND ENVIRONMENT

10.0 ATTACHMENTS

Method Statement for Installation of Intercom


Page 2 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

1.0 PURPOSE:
The purpose of this Method Statement is to define the procedure step by step to implement
the correct practices for installation of Intercom system through the guidelines contained
herein to ensure that the job execution complies with the project requirements.
2.0 SCOPE:
This Method Statement refers to various work procedures which explains and covers the
installation of Intercom system works for the Residential Building [2B+G+2P+12F+Roof].

3.0 REFERENCES

• Approved Shop Drawings.

• Approved Material Submittal

• Health, Safety and Environment reference:KBR-CEC-K126-PLN-001

4.0 DIFINATION

CLIENT : Ariane Real State

CONSULTANT : CONSEIL Engineering Consultant

CONTRACTOR : KBR Contracting and Trading Company


IR : Inspection Request

MIR : Material Inspection Request

ITP : Inspection & Test Plan

MST : Method Statement

HSE : Health, Safety & Environment

PPE : Personal Protective Equipment

QC : Quality Control

QA : Quality Assurance

Method Statement for Installation of Intercom


Page 3 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

5.0 RESPONSIBILITIES:
Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at
relevant steps in the procedure:

• Project Manager.
• Construction manager
• HSE officer
• QA/QC Engineer
• Project Engineer
• Site Engineer
• Pre-Commissioning Engineer.
• Supervisor/Foreman
• Technicians.

5.1 Project Manager:


Shall be responsible for the overall project. The Project Manager will be based on site and will
be responsible for the management of the project, both on and off site, through delegation of
duties in accordance with the organization chart and for the effective implementation of the
project management system. He shall ensure that the proper tools and tackles are available for
the timely completion of this job in a quality manner.
5.2 Construction Manager:
Organize the site work to carried out the required specification with a minimum risk to men,
equipment, and materials. Ensure that the MS are develop in consultation with workers.
Relevant frontline management must lead, facilitate and participate in the works teams in
developing MS & RA. Adhere the project specific quality management program and HSE
requirements. All responsibilities stated in the Projects Quality Assurance Plan.

5.3 HSE Officer:


Will monitor and implement all HSE related issues. He shall ensure that all necessary
requirements regarding health, safety and environment concerns are met and adhered to. The HSE
officer shall ensure that all permits and authorization are on hand prior to starting any site
operation.
5.4 QA/QC Engineer:
Shall ensure that the work is carried out ensuring that the requirement for quality control is
followed. He shall ensure that all ITP requirements are met. The QA/QC Engineer shall ensure
that all necessary requests for inspection and testing are processed and put forward to the company
Engineer for notification. He shall ensure all inspections conducted as per contract specifications,
QCP (Quality control procedures) & ITPs to ensure all inspections proper tools& tackles and
manpower are used at all stages of work to ensure all current issues of procedures, approved
materials and shop drawings and standards are available at the point of use. He shall be
responsible for the total quality of work for the installation work. Inspect for any damage during
shipping, handling and storage. Monitor the quality of works and ensure that fulfillment of

Method Statement for Installation of Intercom


Page 4 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

specified requirement and that all quality records related to work are completed. Ensure the work
is completed as per quality requirement. Main contractor shall inspect the same work prior to
initiative INR for company approval. Maintain comprehensive inspection and test record for
documentation

5.5 Project Engineer


Shall ensure that the works is carried out to according approved shop drawings. Direct supervise
of site engineer & Supervisor works and followed by all personnel taking into consideration all
relevant documents. He shall review the method statement before starting the work. Explain the
same to the subordinates and prepares program for the daily job. Aware all code of practices,
standards and specifications and HSE plan and to appreciate the work force to perform a time
bound and quality job. Originate INR for complete installation works and accompanies QA/QC
Engineer during inspection

5.6 Site Engineer:


Shall ensure that all works are carried out according to approved shop drawings, approved
material submittal and approved method statement. Ensure all safety equipment’s proper tools &
tackles are available at the point of use. Aware of all procedures, work method (instruction,
quality requirements for the timely completion of the job and explains to the task force for
execution of the job applicable code of practice and approved shop drawings.

5.7 Pre-Commissioning Engineer


He is responsible to complete all the Pre-Commissioning tasks, documentation and handovers
required for a Project to achieve Project objectives. Ensure development and implementation of
procedures, task plans, and processes within assigned scope of work and coordinating interfaces
of all disciplines involved.

5.8 Supervisor/Foreman
Follow up scope of work given by the Engineer. Understand approved shop drawing, method
statement and HSE requirements before executing the work. Assign manpower, material and
machinery for the scheduled work. Complete the work in the planned/scheduled time period.
Conduct toolbox meetings regularly to the workers before start of the work.
5.9 Technician:
Follow up scope of work given by the Engineer. Understand approved shop drawing, method
statement and HSE requirements before executing the work. Assign manpower, material and
machinery for the scheduled work. Complete the work in the planned/scheduled time period.
Conduct toolbox meetings regularly to the workers before start of the work.

Method Statement for Installation of Intercom


Page 5 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

6.0 MATERIALS (HANDLING & STORAGE)


6.1 Material Sha Materials shall be approved prior to procurement. A material approval schedule
shall be maintained by the project site Engineer.
6.2 Incoming materials shall be inspected for conformance by the project QA/QC.
6.3 The project MEP consultant shall be invited to inspect materials for conformance prior to
installation.
6.4 Relevant Certificate of conformance shall be presented at the time of inspection with the MEP
consultant.
6.5 All material inspection shall be recorded. All major items shall be inspected for each delivery.
6.6 All materials shall be stored in suitably constructed racks.
6.7 The materials shall not touch the ground. proper storage supports shall be attended.
6.8 Materials should not be exposed to sunlight and if kept open for longer periods of direct
sunlight, it should be covered by opaque sheets.
6.9 During unloading from vehicles, materials should not be dropped / mishandled from the
vehicle.
6.10 Materials should never be dragged along hard surfaces
6.11 The storage temperature should not exceed 30°C and Relative humidity must be between
15% and 40% @ 65 °C (non-condensing). The sub-contractor stores shall be constructed in a
manner that protects all stored materials from the elements.
6.12 Fittings should be stored in sheltered conditions that are protected from the weather elements
and accidental damage.
6.13 Materials segregation between new delivery and inspected/ approved shall be separated
and assign on designated areas.

7.0 EQUIPMENT
7.1 Electrical tool box
7.2 Drill Machine
7.3 Crimping tool with crimping bits for all required sizes
7.4 Base Cutter
7.5 Marker pen
7.6 Safety ladder/Scaffolding
7.7 Measurement tape/Level Bar
7.8 Multi tester or Digital Mustimeter
7.9 Measuring tape

Method Statement for Installation of Intercom


Page 6 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

7.10 Open-ended and ring spanners for all required sizes


7.11 Torque wrenches and Allen wrenches for all required sizes
7.12 Screwdrivers (Slatted/crosshead)
7.13 Battery hammer drill
7.14 Cables
7.15 Cable tie
7.16 Entrance panel
7.17 Indoor unit

8.0 PROCEDURES

8.1 Preparation

• Main & related access control items prior to receiving at site are inspected by QC inspector at the
ware house upon arrival, and shall be stored between 0 to 40°C & less than 80% humidity.
• The area in which the Intercom materials are to be placed shall be identified, cleaned and
without any loose soil.
• Upon Placing the access control material, it will also be checked physically to verify that
the items conform to the manufacturer's specifications, and is free of defects, breaks and damages
by transportation and manufacturing processes.
• The pipes shall be checked and cleaned thoroughly to ensure no foreign objects are blocked
prior to cable pulling process.
• Pipes shall have pulling ropes installed to aid in the pulling process

8.2 Precautions

• Do not install or make any wire terminate ons while power supply is plugged in. It can cause
electrical shock or damage to the unit.
• When mounting the unit on a wall, install the unit in a convenient location, but not where it could
be jarred or bumped. Injury could result.
• Before turning on power, make sure wires are not crossed or shorted. If not, fire or electric shock
could result.
• For power supply, use of intercom power supply model or model specified for use with system. If
non-specified product is used, fire or malfunction could result.
• On products with ground terminals, connect to an earth ground. Fire or malfunction could result.
• Do not put anything on the unit or cover the unit with cloth, etc. Fire or unit trouble could result.
• Do not install the unit in any of the following locations. Fire, electric shock, or unit trouble could
result.
-

Method Statement for Installation of Intercom


Page 7 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

- Places subject to oil, chemicals, hydrogen sulphide (hot spring).


- Places subject to moisture and humidity extremes, such as bathrooms, cellars, greenhouses, etc.
- Places subject to steam or smoke (near heating or cooking surfaces).
- Where noise generating devices such as dimmer switches or inverter electrical appliances are
closeby.
- Locations subject to frequent vibration or impact.

8.3 Installation
The following guidelines and procedures shall be followed in any Intercom system installation:

• Intercom Entrance Panels and indoor unit (with handset or hands-freetype) shall be securely
mounted in a convenient position for the user.
• The capacity of the power supply shall be selected to meet the largest load likely to be placed
upon it under normal operational conditions.
• The main supply shall be permanently connected via a fused outlet i.e.not by a plug and socket.
• Lower voltage cables shall not be brought into a power supply container through the same entry
point as any mains cables.
• Cables shall be installed within a controlled area where practicable, cables should be concealed.
• Where cables are exposed to possible mechanical damage or tampering, or are in public areas,
they shall be protected by suitable conduit, trunking, or armour. Where a cable point release signal
passes outside of a controlled area, metal conduit (or equivalent protection) shall be used.
• All interconnecting wiring shall be supported and its installation shall conform to good working
practice.
• Any cable joints shall be made in suitable junction boxes using either wrapped, soldered,
crimped, or screw-terminals.
• Low voltage and signal cables shall not run in close proximity to mains or other transient carrying
cables.
• Signal cables for the transmission of data or other low-level signals shall be of a type and
size compatible with the rate of data transfer and anticipated levels of electromagnetic interference.
• Low voltage cables from both mains and standby power supplies to remote equipment shall be
of sufficient size to permit satisfactory operation of the equipment at the end of any proposed length
of cable run.

Method Statement for Installation of Intercom


Page 8 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

9.0 HEALTH, SAFETY AND ENVIRONMENT


The health and safety personnel are paramount our policy is to provide what is industry
best practice. All welfare facilities will be provided for the workers linked to toilet, rest
shelters, drinking station and first aid this will be position at specified location for use during
the workscope. Refer HSE Plan (KBR-CEC-K126-PLN-001)
- Implementation of Health, Safety and Environmental (HSE). Mechanism and checks as per
contract agreement and the approved Health and Safety Manual
- The responsible contractor HSE Officer for the project will conduct routine HSE
inspections.
- All HSE related documents, standards and procedures relating to this Installation method
statement are available within the contractor Project Specific HSE Plan.
- Safe access and egress to and from the work place will be provided by the managing
contractor; KBR.
- Access and working platforms will be provided by the managing contractor; KBR for
external work related to the activity.
- Scaffolds will be inspected at least once every 7 days, after alteration or after inclement
weather conditions. This will be the responsibility of a competent & trained scaffold.
- Risk / Impact Assessment for the Installation has been attached to this method statement
and relates to the risks and associated hazards related to the activity.
- Proper TOOL BOX talk will be given to the personnel involving in the activity and PPE’s
to be used.
- Safety Equipment: Safety Shoes, Helmet, Gloves and Safety belt should be available during
this activity
- During the installation, the Safety Officer will ensure that all safety precautions are taken as
per Project Specification, Health & Safety Rules and Regulations

10.0 ATTACHEMENTS
10.1 Check list
10.2 Health & Safety Plan
10.3 Emergency Contact Numbers
10.4 Material Installation Details
10.5 Inspection Test Plan
10.6 Risk Assessment

Method Statement for Installation of Intercom


Page 9 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

10.1 INSPECTION CHECKLIST

Method Statement for Installation of Intercom


Page 10 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

CHECKLIST FOR INSTALLATION OF INTERCOM


Checklist Ref. No.: IR Ref. No.:
Level/Area/Location : Drawing Ref. No.:
Date of Inspection : Specs. Ref. No. :

S/N Checklist YES NO N/A Remarks / Comments


Items
VERIFY AND ENSURE THAT THE METHOD STATEMENT, MATERIAL
1 SUBMITTAL, SHOP DRAWINGS ARE APPROVED BY CONSULTANT
PRIOR TO INSTALLATION
ENSURE THAT THE INSTALLATION WORKS OF CONDUIT, CABLE
2 TRAY / TRUNKING, BACK BOXES AND ACCESSORIES ARE DONE
AS PER APPROVED DRAWING.
CHECK THE MARKING / SETTING OUT AND LOCATION OF FIELD
3 DEVICES IS AS PER APPROVED DRAWING / WALL COORDINATION
DRAWING
CHECK ALL MATERIALS AND ACESSORIES USED IS AS PER
4 APPROVED MATERIAL SUBMITTAL AND MATERIAL INSPECTION IS
APPROVED.
CHECK INSTALLATION OF SLEEVES OR OX OUT FOR WALLS /
5 SLAB PEBETRATION FORM CABLE TRAY OR TRUNKING WITH ITS
ACCESSORIES AS PER APPROVED DRAWING.

CHECK THAT THE CABLES, FITTINGS AND EQUIPMENTS ARE NOT


6
DAMAGE.

CHECK THE INSTALLATION OF CAT 6 CABLES WITH TESTING


7 AND TERMINATION IS DONE ASPER THE APPROVED SHOP
DRAWING

CHECK FOR ANY CLASH WITH OTHER SERVICES 9 MINIMUM


8
CLEARANCE)

ENSURE THE COMPLETE LINK PRODUCTS ARE IN PLACE SUCH


9
ASCABLE CONNECTORS ETC.

ENSURE THAT ALL INTERCOM DEVICES OUTLET, DEVICES ARE


10
INSTALLED ANDTERMINATED AS PER APPROVED DRAWING

11 ENSURE THAT ALL INCOMING CABLES ARE PROPERLY


HARNESSES AND ARANGE

ENSURE TO TEST CAT 6 CABLE TO DETERMINE THE CONTINUITY OF


12 THE START AND END TO END USING MULTIMETER

ENSURE THAT ALL INTERCOM CABLES ARE PROPERLY


13 TERMINATED IN TO PATCH PANEL

Method Statement for Installation of Intercom


Page 11 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

S/N Checklist YES NO N/A Remarks / Comments


Items
CHECK THE HEAD END EQUIPMENTS ARE INSTALLED PROPERLY
14 IN THE MAIN RACK

CHECK LABELING AD IDENTIFICATION OF COMPONENTS,


15 EQUIPMENTS AND CABLES IS DONE.

Method Statement for Installation of Intercom


Page 12 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

10.2 HEALTH & SAFETY PLAN

Method Statement for Installation of Intercom


Page 13 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

Method Statement for Installation of Intercom


Page 14 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

10.3 EMERGENCY CONTACT NO

Method Statement for Installation of Intercom


Page 15 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

Method Statement for Installation of Intercom


Page 16 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

10.4 MATERIAL INSTALLATION DETAILS

Method Statement for Installation of Intercom


Page 17 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

10.5 INSPECTION TEST PLAN

Method Statement for Installation of Intercom


Page 18 of 19
Project Logo Project Name: Residential Building [2B+G+2P+12F+Roof]
Project No.: P44 [K126] Location: Erikya – Lusail City
Client Project Manager Consultant Contractor

10.6 RISK ASSESSMENT

Method Statement for Installation of Intercom


Page 19 of 19
Power Series | ADS-26SGP-12 12024E

ADS-26SGP-12 12024E
DC12V2A Interchangeable Plug Power Adapter

Features

 Easy installation and plug interchangeable;


 Support 90~264Vac wide-range voltage input, and meet the demand of voltage fluctuation;
 Accurate overcurrent, overvoltage protection.

www.dahuasecurity.com
Power Series | ADS-26SGP-12 12024E
Technical Specifications
Model ADS-26SGP-12 12024E
Electrical Specification
Input 90~264Vac
Output 12V, 2A (+7%, -3%)
Protection/Environmental
 Surge protection, over current and voltage load protection
ESD: IEC61000-4-2
Protection ± 6kV Contact; ± 8kV Air
Surge: IEC61000-4-5
± 2KV power line; ± 4kV line to Earth
Working Temperature -10℃~+55℃(14℉~+131℉)
Working Humidity <90% RH
Physical Properties
Weight 120g(0.26lb)
Dimension(LxWxH) 84.5mmx38.5mmx30.3mm(3.33”x1.52”x1.19”)
Installation Mode Pluggable installation, need to be matched up with an extra power plug to use
Color Black
Input Plug Optional plug
Outgoing Cord 22AWG, 1500mm(59.06”), black
DC Plug Φ5.5mmxΦ2.1mmx10mm (Φ0.22”xΦ0.08”x0.39”)
Safety Standards
Certification CCC/UL/CE/FCC/RCM

Order Information
Type Part Number Description
ADS-26SGP-12 12024E DC12V 2A interchangeable plug power adapter(UL/CE/FCC/RCM)
European standard plug European standard power plug-used for plug-optional power adapter
British standard plug British standard power plug-used for plug-optional power adapter
American standard plug American standard power plug-used for plug-optional power adapter
Power
Australian standard plug Australian standard power plug-used for plug-optional power adapter
S024-1A120200HE DC12V 2A pluggable power adapter(CE)
S024-1A120200HK DC12V 2A pluggable power adapter(CE)
S024-1A120200HU DC12V 2A pluggable power adapter(UL)

www.dahuasecurity.com
Power Series | ADS-26SGP-12 12024E
Dimensions (mm/inch)

Optional Power Plug

European 2-pin American 2-pin British 2-pin Australian 2-pin

Rev 001.001 © 2018 Dahua. All rights reserved. Design and specifications are subject to change without notice.

www.dahuasecurity.com
VTH2 Series | DHI-VTH2621G-P/DHI-VTH2621GW-P

DHI-VTH2621G-P/DHI-VTH2621GW-P
IP Indoor Monitor

· 7" TFT capacitive touch screen, 1024 × 600.


· 6-channel alarm input and 1-channel alarm output.
· Standard PoE.
· Door station and IPC monitor.
· H.265 and H.264 video decoding.
· High performance & cost-effective.

Technical Specification DND Mode Do not disturb period can be set; Do not disturb mode

System Villa: 9
Number of Extensions Apartment: 4
Main Processor Embedded processor
Performance
Operating System Embedded Linux operating system
Casing PC + ABS
Interoperability ONVIF; SDK
Port
Network Protocol RTSP; RTP; SIP; DNS; SSH
Alarm Input 6
ROM 128 MB
Alarm Output 1
RAM 128 MB
Door Bell Yes (use any alarm input port)
CPU Dual core 1.2 GHz
Network One 10/100 Mbps Ethernet

Basic
General
Screen Type Capacitive touchscreen
Appearance Color Black/White
Display 7" TFT
12 VDC 1A;
Power Supply Standard PoE (36–57 V, 0.35 A)
Screen Resolution 1024 × 600
Installation Surface Mount
Audio Compression G.711a; G.711u; PCM
Certifications CE; FCC
Audio Input 1
189.6 mm × 134.6 mm × 26.0 mm (7.50" × 5.30" ×
Dimensions 1.00")
Audio Output Built-in speaker

Audio Mode 2-way Audio Operating Temperature –10 °C to +55 °C (+14 °F to 131 °F)

Audio Enhancement Echo suppression Operating Humidity 10%–95% RH (non-condensing)

Audio Bit Rate 16 kHz; 16 bit Operating Altitude Beneath 3,000 m (9,842.52 ft)

Power Consumption Standby ≤ 2 W; working ≤ 6 W


Function
Communication Mode Full digital Net Weight 0.34 kg (0.74 lb)

Receive and view text information released by the Gross Weight 0.58 kg (1.27 lb)
Information Release management center

Leave Videos Yes (SD card inserted in VTO is needed)

www.dahuasecurity.com
VTH2 Series | DHI-VTH2621G-P/DHI-VTH2621GW-P

Ordering Information Dimensions (mm[inch])

Type Model Description

IP Indoor DHI-VTH2621G-P/
Monitor IP Indoor Monitor
DHI-VTH2621GW-P

Installation

Application

Rev 002.000 © 2022 Dahua. All rights reserved. Design and specifications are subject to change without notice.
The images, specifications and information mentioned in the document are only for reference, and might differ from the actual product.

www.dahuasecurity.com
VTO Series | DHI-VTO6521H

DHI-VTO6521H
Apartment Door Station

· 4.3 inch IPS display; screen resolution 800×480


· 2MP CMOS; true WDR
· Touch button; IP65
· Operating temperature: -30°C to +60°C
· Auto light illumination reduces light pollution
· Multiple unlock modes: Password unlock, IC card unlock, and remote
unlock
· Support 20,000 users and 10,000 cards
· Support full duplex; management platform, and voice call through APP
· Support SIP server, and can manage 200 indoor monitors at most
· Support duress alarm, tamper alarm, and door sensor timeout alarm

IP65

Main Stream (720P@25fps), sub stream


Technical Specification (1080P@25fps)
Frame Rate
Main Stream (720P@30fps), sub stream
System (1080P@30fps)
Main Processor Embedded processor Video Bit Rate 256Kbps–2048Kbps

Operating System Embedded Linux operating system Light Compensation Auto white light

Button Type Touch button Audio Compression G.711u

SIP; P2P; IPv4; FTP; UPnP; DNS; DDNS; RTSP; RTP; Audio Input 1
Network Protocol
TCP; UDP
Audio Output Built-in speaker
ROM 4GB
Audio Mode Full duplex communication
RAM 1GB
Echo suppression and cancellation/digital noise
Audio Enhancement
reduction
Basic
Audio Bit Rate 16KHz, 16Bit
Display 4.3 inch IPS screen
Communication Mode Full digital
Screen Resolution 800×480

1/2.7" 2MP CMOS high definition, low illumination,


Unlock Mode Card/remote/password unlock
Camera
white illuminator and IR illuminator
Card Type IC card
Horizontal: 113.79°; vertical: 61.5°;
Field of View Motion Detection Video motion detection
diagonal: 134.45°

Focal Length 2.8mm Auto Snapshot Yes

Aperture F2.0 Leave Videos or Text Messages Yes

WDR 120dB Web Configuration Yes

Noise Reduction 3D noise reduction Performance


Video Compression H.264 Card Reading Distance 1cm–5cm

Video Resolution Main Stream: 720p, sub stream: 1080P Issue Card Locally Yes

www.dahuasecurity.com
VTO Series | DHI-VTO6521H
Casing Material PC+ABS Ordering Information
Capacity Type Model Description

Card 10, 000 Unit Door Station DHI-VTO6521H 4.3 Inch Unit Door Station

Port Flush Mounting Flush Mounting Plate for 8 Inch Face


VTM121
RS-485 1 Plate Recognition Door Station

Wiegand 1 input port, 1 output port Surface Mount Surface Mount Plate (VTM130) for 4.3 Inch
VTM130
Plate Door Station
Electric lock 1

Alarm Input 2

Alarm Output 2

Power Output 1 12V/100mA Dimensions (mm[inch])


Exit Button 1

Door Status Detection 1

Lock Control 1, normally open by default

Network 1 RJ-45 10Mbps/100Mbps self-adaptive

Alarm
Tamper Yes

General
Unlock Password Mode User password/public password/duress password

Color Silver

Power Supply Mode DC 12V2A

Power Adapter Optional

Installation Surface mount and Flush mount

Certification CE/FCC Application


Accessory Optional Community Intercom System Architecture

Product Dimensions 389 mm×145 mm×41.9 mm (15.31"×5.71"×1.65") Fence Entrance


Check and call to owner
Apartment Lobby
SIP big apartment

IP65 (silicone sealant is needed, see the quick start


Protection Grade
guide)
Visitor arriving
 Remote check through
 the IPC which is installed

Operating Temperature -30°C to +60°C (-22°F to +140°F)


at the entrance
Open the door

Operating Humidity 10%RH–90%RH (non-condensing)

Operating Altitude 86kPa–106kPa


Call

Fence VTO

Power Consumption ≤5W (standby), ≤18W (working) IPC

VTS5240B-S1 Lobby VTO


Cat5e EXPRESS

Net Weight 1.4 kg (3.09 lb)


Security Room

Gross Weight 1.68 kg (3.70 lb)

Rev 001.001 © 2020 Dahua. All rights reserved. Design and specifications are subject to change without notice.
Pictures in the document are for reference only, and the actual product shall prevail.

www.dahuasecurity.com
VTO7 Series | VTM121

VTM121
Flush Mount Plate of 8 Inch Face Recognition Outdoor Station

· Flush Mount

Technical Specification Dimensions (mm[inch])


Product Dimension 373mm×143mm×67.5mm (14.69"×5.63"×2.66")

Packaging Dimension 413mm×182mm×104mm (16.26"×7.17"×4.09")

Operatimng Temperature -30°C to +70°C (-20°F to +158°F)

Operating Humidity 10%RH–90%RH

Operating Altitude 86kPa–106kPa

Gross Weight 1.1kg(2.42lb)

Installation Method Flush Mount

Operating Environment Outdoor

Ordering Information
Type Material No. Description

Flush Mount Plate for outdoor stations


VTM121 1.0.01.15.11233
(DHI-VTO7541G and DHI-VTO7521G )

8 Inch Digital Face Recognition Outdoor


DHI-VTO7541G 1.0.01.15.11293
Station

8 Inch Digital Face Recognition Outdoor


DHI-VTO7521G 1.0.01.15.11292
Station

Rev 001.001 © 2019 Dahua . All rights reserved. Design and specifications are subject to change without notice.
Pictures in the document are for reference only, and the actual product shall prevail.

www.dahuasecurity.com
DHI-VTS5A40B

DHI-VTS5A40B
Master Station

· Highly convenient, it has a 10-inch glass touch screen with a 1024 (H) ×
600 (V) resolution and supports speaker phone and handsets.
· Supports desk mount installation, and the bracket can be adjusted
from 0°–45°.
· Offers HDMI output with a resolution up to 1024 (H) × 600 (V).
· The intercom can be set for residential areas and use in industries.
· Buidlings intercom:
Doors can be remotely unlocked during monitoring and while the
intercom is in use.
· Features two-way talk for indoor monitors and door stations.
· Monitors 4 channel door stations and IPCs at the same time.
· Records videos, takes snapshots and stores information on SD cards
during monitoring and while the intercom is in use.
· Industry intercom:
300 IP VTAs can be connected to the master station.
Technical Specification
· Supports two-way talk with emergency phone terminals and
System emergency phone terminal stations.
Main Processor Embedded Processor · Monitors 4 channel door stations and IPCs at the same time.
Operating System Android 11 · Records videos, takes snapshots and stores information on SD cards
while the emergency phone terminal and emergency terminal station
Button Type Mechanical
are performing monitoring and using the intercom.
Interoperability ONVIF; CGI; SDK; SIP
· Offers two-way talk between stations.
Network Protocol IPv4; RTSP; UDP; FTP; RTP; TCP

Basic Scene
Screen Type Capacitive Touchscreen Suitable for use in residential areas and a variety of industries.
Display Screen 10" TFT display
Storage Micro SD, Max 512 GB
Screen Resolution 1024 × 600
Web Configuration Yes
Video Compression H.264; H.265
Auto Registration Yes
Video Resolution 720p
Building mode:
Video Frame Rate 25 fps Up to 32 VTSs.
Up to 32 IPCs.
Access Device Industry mode:
Video Bit Rate 2 Mbps
Up to 300 VTAs (Added through IP).
Up to 32 IPCs.
Audio Compression G.711a; G.711u; PCM

Audio Input 2 Channels


Performance
Casing Material PC + ABS
Audio Output Built-in speaker; handset speaker

Audio Mode Two-way audio


Port
RS-485 1
Audio Enhancement Echo suppression/digital noise reduction
HDMI 1
Audio Bit Rate 16 kHz, 16 Bit
1 × USB 2.0 port
USB
Function 1 × USB 3.0 port

Communication Mode Full digital Power Output 1 channel, 12 V/200 mA

Supports splitting to 4 windows and monitoring 4-ch Network Port 1 × RJ-45 100 Mbps/1000 Mbps self-adaptive
Multi-Window Display 720p videos.

www.dahuasecurity.com
DHI-VTS5A40B

General
Appearance Color Titanium gray

Power Supply 12 VDC, 4A

Power Adapter Included

Installation Desk Mount

Certifications CE; FCC

Accessory Power adapter; power cord; handset cord

345.00mm × 224.60 mm × 64.42 mm (13.58" × 8.84"


Product Dimensions × 2.54")

Operating Temperature –10 °C to +55 °C (14 °F to +131 °F)

Operating Humidity 5%–90% (RH) (Non-condensing)

Operating Altitude 0 m–1300 m (0 ft–4265.09 ft)

Power Consumption ≤ 5 W (standby), ≤ 10 W (working)

Gross Weight 2.5 kg (5.51 lb)

Storage Temperature 0 °C to +40 °C (+32 °F to +104 °F)

Storage Humidity 30% to 75% (RH)

Application

Dimensions (mm[inch])

Rev 002.000 © 2022 Dahua. All rights reserved. Design and specifications are subject to change without notice.
The images, specifications and information mentioned in the document are only for reference, and might differ from the actual product.

www.dahuasecurity.com
Residential Building [2B+G+2P+12F+Roof]
Page Number
INSPECTION AND TEST PLAN
1 of 3

ITP NO.: P44-K126-ITP-ELV-016


INSTALLATION OF INTERCOM
SCOPE OF
WORKS: ITP REVISION NO.: 00

ITP DATE: 3-JULY-2023

ACTIVITY HOLD (H), WITNESS (W), REVIEW (R) POINTS


FREQUENCY REFERENCE TO SPECIFIED REQUIREMENTS FOR ACCEPTANCE/REJECTION CRITERIA
NO 3RD RECORDS TO BE VERIFIED
DESCRIPTION KBR SUB CON CONSIEL INSPECTION TEST APPROVAL &TOLERANCE
PARTY
``

A DOCUMENT APPROVAL

BEFORE
VERIFY APPROVAL OF SHOP DRAWING TO BE
1 R R - R COMENCEMENT OF CONTRACT DOCUMENT
DRAWING WORK APPROVED
BEFORE
APPROVED MATERIAL MATERIAL SUBMITTAL TO
2 MATERIAL APPROVAL R R - H COMENCEMENT OF
SUBMITTAL BE APPROVED
WORK
BEFORE METHOD STATEMENT REF:
VERIFY APPROVAL OF METHOD STATEMENT TO
3 R R - R COMENCEMENT OF P44-KBR-MST-ELV-016
METHOD STATEMENT. BE APPROVED
WORK

MATERIAL VERIFICATION
CHECK LIST REF.:
INSPECTION OF AFTER MATERIAL APPROVED MATERIAL MATERIAL SUBMITTAL TO
H H - H
4 MATERIAL RECEIVED AT DELIVERED TO SITE SUBMITTAL BE APPROVED
P44-KBR-MIR-001
SITE STORAGE

B INSTALLATION

BEFORE START KBR-CEC-K126-PLN-


5 SAFETY CLEARANCE AS PER CONTRACT DOCUMENT HSE PLAN
OF WORK 001
AFTER
COMPLETION OF
COAXIAL CABLE PULLING APPROVED SHOP DRAWING AS PER PROJECT CHECK LIST REF.:
6 H H - H WORK (CONDUIT,
& TERMINATION APPROVED METHOD STATEMENT REQUIREMENTS P44-KBR-ELV-023
CABLE TRY
TRUNKING)

FACEPLATE AFTER SETTING APPROVED SHOP DRAWING APPROVED SHOP CHECK LIST REF.:
7 H H - H
INSTALLATION OUT APPROVED METHOD STATEMENT DRAWING P44-KBR-ELV-023
Residential Building [2B+G+2P+12F+Roof]
Page Number
INSPECTION AND TEST PLAN
2 of 3

ITP NO.: P44-K126-ITP-ELV-016


INSTALLATION OF INTERCOM
SCOPE OF
WORKS: ITP REVISION NO.: 00

ITP DATE: 3-JULY-2023

ACTIVITY HOLD (H), WITNESS (W), REVIEW (R) POINTS


FREQUENCY REFERENCE TO SPECIFIED REQUIREMENTS FOR ACCEPTANCE/REJECTION CRITERIA
NO 3RD RECORDS TO BE VERIFIED
DESCRIPTION KBR SUB CON CONSIEL INSPECTION TEST APPROVAL &TOLERANCE
PARTY
``

AFTER APPROVED SHOP DRAWING


INSTALLATION OF APPROVED SHOP DRAWING CHECK LIST REF.:
8 H H - H COMPLETION OF APPROVED METHOD
DISHES APPROVED METHOD STATEMENT P44-KBR-ELV-023
WORK STATEMENT

AFTER APPROVED SHOP DRAWING


INSTALLATION OF THE APPROVED SHOP DRAWING CHECK LIST REF.:
9 H H - H COMPLETION OF APPROVED METHOD
PANELS APPROVED METHOD STATEMENT P44-KBR-ELV-023
WORK STATEMENT

INSTALLATION OF
AFTER APPROVED SHOP DRAWING
TRANSMITTERS, APPROVED SHOP DRAWING CHECK LIST REF.:
H H - H COMPLETION OF APPROVED METHOD
10 RECEIVERS, SPLITTERS APPROVED METHOD STATEMENT P44-KBR-ELV-023
WORK STATEMENT
AND AMPLIFIERS
AFTER AS PER PROJECT
11 LABELLING AND REQUIREMENTS
UQUIPMENT / APPROVED SHOP DRAWING CHECK LIST REF.:
IDENTIFICATION OF H H - H REFER ATTACHED
COMPONENTS APPROVED METHOD STATEMENT P44-KBR-ELV-023
COMPONENTS STANDARD AS PER EIA/TIA
CONNECTIONS 606A
AFTER
12 APPROVED SHOP DRAWING AS PER PROJECT CHECK LIST REF.:
TESTING THE SYSTEM H H - S COMPLETION OF
APPROVED METHOD STATEMENT REQUIREMENTS P44-KBR-ELV-023
WORK
Residential Building [2B+G+2P+12F+Roof]
Page Number
INSPECTION AND TEST PLAN
3 of 3

ITP NO.: P44-K126-ITP-ELV-016


INSTALLATION OF INTERCOM
SCOPE OF
WORKS: ITP REVISION NO.: 00

ITP DATE: 3-JULY-2023

ACTIVITY HOLD (H), WITNESS (W), REVIEW (R) POINTS


FREQUENCY REFERENCE TO SPECIFIED REQUIREMENTS FOR ACCEPTANCE/REJECTION CRITERIA
NO 3RD RECORDS TO BE VERIFIED
DESCRIPTION KBR SUB CON CONSIEL INSPECTION TEST APPROVAL &TOLERANCE
PARTY
``

PREPARED BY: REVIEWED BY: APPROVED BY: APPROVED BY:


NOTES HOLD (H) AND WITNESS (W) POINT PARTIES
(SCTC) (SCTC) (SCTC) (CONSEIL)
H = Hold Point (IR) QA/QC PROJECT CONSULTANT
MEP MANAGER
ENGINEER MANAGER REP:
W = Witness Point
IR= Inspection Request R = Review/Record Point
S = Surveillance Point
MIR= Material Inspection Request H1 = Hold Point (without IR)
A1 = Random Actual

CONSULTANT = CONSEIL
MAIN CONTRACTOR = KBR
SUB-CONTRACTOR = ABSOLUTE MAC GERALD
RESP. PERSON:
MAPANAO

DATE: 3-JULY-2023
Document Reference

Residential Building [2B+G+2P+12F+Roof], Erikya – Lusail City


Rev. No. Assessment Date
00
Risk Assessment Record Assessed by Titile Signature
Activity: Integration of Intercom System
Safety
Officer

Base Risk Ranking Residual Risk Ranking


IDENTIFIED CONTROL MEASURES
(Without Controls) (With Controls) Person
No ACTIVITY HAZARDS/RISKS People Involved
Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

1) Delivery/ collection drivers shall be subject


to
McLaren induction/Training with regards to
Plant and Traffic traffic management.
movement 2)Ensure exclusion zone is set up around the
-Run over by preparation work area and all plant
vehicles/plants movement and checked by supervisor.
Delivering, -Run over by 3) Always use the pedestrian access provided
unloading and vehicles/plants 4) Traffic light batons shall be provided for
storing of Cat 6 -Hit by reversing banks man at night
Cable with Equipment- 5) All plant to have a fully trained banks man
accessory Overhead present all times.
Operatives/Staf
materials using obstructions 6) No plant to reverse without banks man. Supervisor
1 f/ 3 4 12 1 3 3 Low
pickup van and - Vehicle break Medium 7) Ensure access route are sufficient and safe Engineer
unloading by down to use.
manual handling -Property damage 8) Do not take rest in or under vehicles
and shifting by - Collision with 9) Proper barricade and safety signboard
using pallet other vehicles provided on open excavation
trolley - Falling materials 10) All vehicles must be fitted with reverse
from pallet alarm/ Flashing light.
trolley 11) The work place and all access to be well
- Personal injury illuminated.
12) Ensure close supervision, Effective
Communication & Coordination with McLaren
13) Enforce Speed limit
14) Ensure all vehicles entering the site is

Approved By:

SPECIFIC RISK ASSESSMENT RECORD


Document Reference

Residential Building [2B+G+2P+12F+Roof], Erikya – Lusail City


Rev. No. Assessment Date
00
Risk Assessment Record Assessed by Titile Signature
Activity: Integration of Intercom System
Safety
Officer

Base Risk Ranking Residual Risk Ranking


IDENTIFIED CONTROL MEASURES
(Without Controls) (With Controls) Person
No ACTIVITY HAZARDS/RISKS People Involved
Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

properly maintained and reported if found


any
defect
15) Ensure materials are secured/tied in
pallet

Approved By:

SPECIFIC RISK ASSESSMENT RECORD


Document Reference

Residential Building [2B+G+2P+12F+Roof], Erikya – Lusail City


Rev. No. Assessment Date
00
Risk Assessment Record Assessed by Titile Signature
Activity: Integration of Intercom System
Safety
Officer

Base Risk Ranking Residual Risk Ranking


IDENTIFIED CONTROL MEASURES
(Without Controls) (With Controls) Person
No ACTIVITY HAZARDS/RISKS People Involved
Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

1) Eliminate the need for manual handling by


using mechanical aid.
2)Reduce the weight of a load to limit force
exertion
3) If unsure of the load weight, check with
Musculoskeletal supervisor.
disorders, Hand 5)Ensure proper manual handling procedure
Operatives Supervisor
injuries, cut, 6) Identify and eliminate sharp edges before
2 Manual Handling involved in 4 3 12 Medium 1 3 3 Low Foreman
bruises Sharp any manual lift
work Site Eng.
edges 7) Ensure adherence with sufficient and
appropriate PPE.
8) Limit load carrying to 20kg per person
9) Supervisor must make sure while manual
handling load individual task and
environment to be considered to reduce the
risk of manual handling.

Approved By:

SPECIFIC RISK ASSESSMENT RECORD


Document Reference

Residential Building [2B+G+2P+12F+Roof], Erikya – Lusail City


Rev. No. Assessment Date
00
Risk Assessment Record Assessed by Titile Signature
Activity: Integration of Intercom System
Safety
Officer

Base Risk Ranking Residual Risk Ranking


IDENTIFIED CONTROL MEASURES
(Without Controls) (With Controls) Person
No ACTIVITY HAZARDS/RISKS People Involved
Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

1) Ensure accesses are kept clear at all times.


2)Housekeeping to be carried out regularly
throughout the day when required
3)Supervisor to ensure operatives are stacking
material neatly and stacks are stable and in a
safe condition
4)Provide adequate lighting especially during
night hours
5) Appropriate space is allowed around
Operatives/ storage areas for employees to move around
Supervisor
Strips, Trips and fall Staff/Store safely without the risk being trapped between
3 Material Storing 3 4 12 Medium 1 4 4 Low Foreman
Poor house keeping keeper stacked materials.
Site Eng.
6) Maintain good housekeeping.

Approved By:

SPECIFIC RISK ASSESSMENT RECORD


Document Reference

Residential Building [2B+G+2P+12F+Roof], Erikya – Lusail City


Rev. No. Assessment Date
00
Risk Assessment Record Assessed by Titile Signature
Activity: Integration of Intercom System
Safety
Officer

Base Risk Ranking Residual Risk Ranking


IDENTIFIED CONTROL MEASURES
(Without Controls) (With Controls) Person
No ACTIVITY HAZARDS/RISKS People Involved
Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

1. Supervisor must conduct the Toolbox talks


and discuss STARRT prior to start the work.
2. Ensure all kind of electrical power supply
and utility services turned off before starting
activity.
Installation of 3. Use proper access and egress while using
Fiber Cable and Working at height Mobile scaffolding with green tag
CAT-6 cable Fall of Person 4. Work area must have enough illumination
Supervisor
using Fall of All operative arrangement.
4 3 4 12 Medium 2 4 8 Low Foreman
mobile tower for Materials/tools involved 5. Mobile scaffolding must be fixed by
Site Eng.
access. Slips, Trips and Falls, competent person and inspected by 3rd party
Cable pulling Poor illumination certified inspector.
By manual 6. Full body harness must wear while working
on height and anchored in secured place.
7) Unauthorized person not allowed
modifying the scaffolding.
8) Do not push or pull the scaffolding if person
working

Approved By:

SPECIFIC RISK ASSESSMENT RECORD


Document Reference

Residential Building [2B+G+2P+12F+Roof], Erikya – Lusail City


Rev. No. Assessment Date
00
Risk Assessment Record Assessed by Titile Signature
Activity: Integration of Intercom System
Safety
Officer

Base Risk Ranking Residual Risk Ranking


IDENTIFIED CONTROL MEASURES
(Without Controls) (With Controls) Person
No ACTIVITY HAZARDS/RISKS People Involved
Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

1. PAT test to be conduct and maintain


register.
2) All the power tools must be 110 volt and
safe to use
3.All power supplies should be installed &
Cable glanding
Physical Injuries like connected by a competent electrician.
and
laceration, foreign 4). RAMS to be briefed to the operatives
termination in to
parts in eyes, finger before start the activity and maintain the
patch panel Supervisor
injury All Operatives record.
5 (Not energized) 4 4 16 High 2 4 8 Low Foreman
Entanglement with Involved 5.Hot work permit to be obtained and work
using drill Site Eng.
sharp edge tools area must free from combustible item
machine
Noise and dust 6. Fire extinguisher in place with fire blanket.
and hole show
Spark and Fire 7. Noise protection to be use
cutter.
8) Eye protection must be used.
9) Operatives should alert while using sharp
edge tools to avoid entanglement with
clothing.
10) Close supervision and necessary PPE.

Approved By:

SPECIFIC RISK ASSESSMENT RECORD


Document Reference

Residential Building [2B+G+2P+12F+Roof], Erikya – Lusail City


Rev. No. Assessment Date
00
Risk Assessment Record Assessed by Titile Signature
Activity: Integration of Intercom System
Safety
Officer

Base Risk Ranking Residual Risk Ranking


IDENTIFIED CONTROL MEASURES
(Without Controls) (With Controls) Person
No ACTIVITY HAZARDS/RISKS People Involved
Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

1. Permit to be obtained for testing and


commissioning
2) Reflectometer must be calibrated from
Authorized testing lab.
3. Ensure all kind of electrical power supply Supervisor
6 Cable Testing Irritation of eyes Operators 4 3 12 Medium and utility services turned off before starting 2 3 6 Low Foreman
activity. Site Eng.
4. Both end operators must have
communication by using radio system.

Approved By:

SPECIFIC RISK ASSESSMENT RECORD


Document Reference

Residential Building [2B+G+2P+12F+Roof], Erikya – Lusail City


Rev. No. Assessment Date
00
Risk Assessment Record Assessed by Titile Signature
Activity: Integration of Intercom System
Safety
Officer

Base Risk Ranking Residual Risk Ranking


IDENTIFIED CONTROL MEASURES
(Without Controls) (With Controls) Person
No ACTIVITY HAZARDS/RISKS People Involved
Risk Risk Risk Risk Responsible
L S L S
Score Rating Score Rating

1. Prepare the working area for a good


working condition.
2.All workers should wear high visibility vest
Physical injuries, and PPE
Slips,trips & falls, 3. Ensure that the working area is well- Supervisor
Working in Poor All Personal in
7 Health effects-eye 3 4 12 Medium ventilated. 1 4 4 Low Foreman
visibility/dust the work area
damage/respiratory 4.Wear goggles & face mask when working in Site Eng.
condition
diseases. a dusty place
5. TBT conducted by supervisor.
6.First aider and first aid kit available on the
site
7) Ensure that work area must have proper
illumination
8) Maintain good house keeping

Approved By:

SPECIFIC RISK ASSESSMENT RECORD


RISK ASSESSMENT & CONTROL GUIDELINES

1. Executing Steps:
1.1. Planning
a) Construction and HSE team must ensure that hazard identification is complete.
b) Construction and HSE team must prioritize the hazard issues, which are of significant in nature. (It means that
risks have well established legal requirements, potentially high risks).
c) Construction and HSE team to prepare the risk assessment plan for the priorities identified hazards for these
potential high risks.

1.2. Risk Assessment


Risk is the probability of an event occurring in a given set of circumstances. The ‘event’ is an exposure to hazard. The
hazard is the potential to cause harm. The risk assessment is the technique of evaluating not just the likelihood of an
event occurring, but also the outcome will be in terms of injury, loss, damage or harm.
1.3. Risk Assessment Process
The process of carrying out a risk assessment should be as follows.
1. Identify the hazards.
2. Identify who might be harmed and how.
3. Evaluate the risk and implement the control measures.
4. Record the significant findings.
5. Review the assessment and update if necessary.

1.4. Examination of the Hazards and Risk Associated


➢ Competent staff must be used in examining the risk associated with the identified hazard.
➢ Competent staff should examine following aspect to determine the risk involved:
o Examine the existing control measures in place.
o Identify employees at risk.
o Likelihood of risk.
o Severity
o Risk level and their tolerability.

1.5. Evaluating the risk:


Once the necessary information has been obtained on the hazards encountered by work activities, next stage is to
access the risks.
1.5.1. Risk Rating Score
Risk rating score is a combination of two factors.
➢ The severity of the risk that could injure persons or cause damage to plant.
➢ The likelihood of the risk that it could happen (Probability).

RISK RATING = LIKELIHOOD X SEVERITY


NOTE: Each activity has to be assessed for the risk value for determining the level of Severity and likelihood are mentioned in
the table below.
No Injury Minor Moderate Major Catastrophic
(1) Injury (2) Injury (3) Injury (4) (5)
1 2 3 4 5
Rarely (1)
Unlikely (2) 2 4 6 8 10
LIKELIHOOD
Possible (3) 3 6 9 12 15
Likely (4) 4 8 12 16 20
Almost
5 10 15 20 25
Certain (5)
RISK LEVEL:
Low Medium High

SAF-010 (UAE) 03/18 Rev C SPECIFIC RISK ASSESSMENT RECORD