Standard Project - Cost
Standard Project - Cost
Standard Project - Cost
Saff Details
COMP.ID DESIGNATION
Estimation Manager
Electrician
Labourer / Helper
AREA / LOCATION:
Page No. of
Page No. of
Madan Electrical Contracting W.l.l. Proposed Al Salm Specialist Hospital At East Riffa
TV System
Satellite dish
LNB 3
Splitter
Tap
Multi Switcher
Satellite Amplifier
RG 6 Coaxial Cables 305 mtr
Telephone System
Cat6 UTP Cable
xx Pair DB Box
xx Pair MDF
6 pair Tephone cable
Installation testing and commissioning
Video Intercom
Guard Master
Digital audio door phone
Wall mount Video intercom receiver
Door lock strike
CAT5 Cables
Power supply
Installation testing and commissioning
Note: All Items & Quantities above are only guide to the Contractor Final quantity Should Be Obtained From The
Drawings By The Contractor
CCTV System 0
0
0
0
0
Note: All Items & Quantities above are only guide to the Contractor Final quantity Should Be Obtained From The
Drawings By The Contractor
Note: All Items & Quantities above are only guide to the Contractor Final quantity Should Be Obtained From The
Drawings By The Contractor
Brand/ Make Vendor /Subcontractor Our Qoutation Actual Cost Supplier Qoute Remarks
Actual cost
PVC Conduits Items COMAT/UAE CAPITAL 11,000.00 -11,000.00
GI Conduits Items SMART/INDIA CAPITAL 1,200.00 -1,200.00
Transformer 0.00
Busbar METCO 0.00
DB's , SMDB, & Panels VoltAmp/Hagar/France METCO 46,930.00 56,000.00 -9,070.00
LV Cables Jedda Cable/KSA METCO 72,651.00
Single Core Wire DELTA/BAHRAIN METCO 30,593.00 28,000.00 2,593.00
Internal & External Light Fitting EUROP/ GLORY 82,522.00 45,000.00 37,522.00
Cable Tray SKC/ KSA CAPITAL/ METCO 18,875.00 12,233.00 6,642.00
GI / PVC CableTrunking SKC/ KSA CAPITAL/METCO 6,303.00 8,500.00 -2,197.00
Cable Ladder SKC/ KSA CAPITAL/METCO 800.00 -800.00
Tel System METCO 4,529.00 200.00 4,329.00
Computer System Opterna/USA GLORY 17,425.00 15,000.00 2,425.00
Fire Alarm System C-tec/UK UNEECO 32,276.00 9,081.00 23,195.00
CCTV System IPTec/UK GLORY 13,061.00 16,232.00 -3,171.00
PA System RCS/GERM GLORY 4,100.00 5,360.00 -1,260.00
SMATV System KATHRINE/GERM UNEECO 336.00 550.00 -214.00
Intercom System STENTOFON/ Norway GLORY 3,248.00 10,000.00 -6,752.00
Lighting Control System QLITE/UK UNEECO 21,000.00 25,000.00 -4,000.00
Structured Cabling CLIPSAL/AUST UNEECO 12,000.00 -12,000.00
Ceremoniational Lighting OTHERS 5,400.00 1,200.00 4,200.00
Traffic Barrier 1,400.00 950.00 450.00
Display System Vivteck/USA UNEECO 8,130.00 -8,130.00
Multimedia Projectors UNEECO 4,000.00 12,000.00 -8,000.00
SPN/TPN Isolator SCAME/ITLY CAPITAL/METCO 3,906.00 5,000.00 -1,094.00
Power Skirting HALWATCHI 18,716.50 25,000.00 -6,283.50
Substation METCO 1,000.00 -1,000.00
Generator Set & ATS CATERPILLER /USA METCO 8,000.00 1,500.00 6,500.00
HV Works OTHERS 5,000.00 -5,000.00
Earthing & lightning Protection FURSE/ METCO 4,300.00 4,000.00 300.00
Tools & Equipment 2,000.00
Labour Charge 43,200.00
Accessories 6,000.00 6,984.50
399,571.50 358,936.00
PROJECT NO. #NAME?
PROJECT STATEMENT OF ACCOUNT
PROJECT STATEMENT OF ACCOUNT
% RETENTION TOTAL RECIVABLES % TOTAL RETENTION
Contract Value BHD 102,200.000 BHD 10,220.000 BHD 91,980.000 10.00%
Variation 1 BHD 14,181.750 BHD 1,418.175 BHD 12,763.575
Variation 2 BHD 950.000 BHD 95.000 BHD 855.000
Variation 3 BHD 0.000 BHD 0.000 BHD 0.000
Variation 4 BHD 0.000 BHD 0.000 BHD 0.000
Variation 5 BHD 0.000 BHD 0.000 BHD 0.000
Variation 6 BHD 0.000 BHD 0.000 BHD 0.000
Variation 7 BHD 0.000 BHD 0.000 BHD 0.000
Variation 8 BHD 0.000 BHD 0.000 BHD 0.000
Total Variation BHD 15,131.750 BHD 11,733.175 ACTUAL RECIVABLES
Total Contract Value BHD 117,331.750 BHD 105,598.575
Basic Completion % 90.00% BHD 105,598.58
Variation 1 Completion % 90.00% 90.00%
Variation 2 Completion % 0.00%
Variation 3 Completion % 0.00% Till the Project End All Recivable with Retention
Variation 4 Completion % 0.00% BHD 21,637.35
Variation 5 Completion % 0.00%
Variation 6 Completion % 0.00% Balance Recivable
Variation 7 Completion % 0.00% BHD 9,904.18
Variation 8 Completion % 0.00%
Variation Completion % 100.00%
Total Completion % 90.00% ACTUAL RECIVABLES- TOTAL PAID BHD 9,904.175
% 0.62%
PAYMENT DETAILS
Base Value BHD 91,980.000 BHD 12,763.575 BHD 10,220.00
Balance BHD 1,395.600 BHD 12,763.575 BHD 5,110.000
BASIC VARIATION BASIC RETENTION
2012 BHD 20,701.000 BHD 0.000 BHD 0.00
2013 BHD 69,883.400 BHD 0.000 BHD 5,110.000
2014 BHD 0.000 BHD 0.000 BHD 0.000
2015 BHD 0.000 BHD 0.000 BHD 0.000
SUB TOTAL BHD 90,584.400 BHD 0.000 BHD 5,110.000
GRAND TOTAL BHD 95,694.400
% 90.62% PAID OUT OF TOTAL RECIVABLES
% 0.00% PAID OUT OF TOTAL RETENTION
PAGE 1 OF 5
Payment details Payment details
2013 2012
BHD 3,969.000
BHD 7,500.000
BHD 1,418.18
PAGE 3 OF 5
PROJECT NO. #NAME?
PROJECT STATEMENT OF ACCOUNT
ACTUAL COSTS
ACTUAL ACTUAL TOTAL TOTAL ACC
% revinew TOTAL PROFIT % ON
MONTH AMOUNT AMOUNT AMOUNT MATERIAL LABOUR OVERHEAD COST/ TOTAL
invoiced PROFIT COST
INVOICED RECEIVED RECEIVED MONTH COST
Jun-12 1.96% 2,300 0 0 500 1,250 0 1,750 1,750 -1,750 -100.00%
Jul-12 2.98% 3,500 5,800 5,800 600 1,257 42 1,899 3,649 3,901 106.91%
Aug-12 4.01% 4,700 4,700 10,500 650 1,125 209 1,984 5,633 2,716 48.22%
Sep-12 1.28% 1,500 10,500 700 1,556 188 2,444 8,077 -2,444 -30.26%
Oct-12 2.81% 3,300 5,500 16,000 700 2,426 230 3,356 11,433 2,144 18.76%
Nov-12 2.30% 2,701 16,000 1,500 2,400 213 4,113 15,546 -4,113 -26.46%
Dec-12 2.30% 2,695 4,701 20,701 1,700 2,017 317 4,034 19,580 667 3.41%
Jan-13 6.87% 8,065 3,969 24,670 3,259 1,223 420 4,902 24,482 -933 -3.81%
Feb-13 16.11% 18,900 7,500 32,170 1,364 1,763 213 3,339 27,821 4,161 14.96%
Mar-13 7.39% 8,669 13,946 46,116 14,350 1,780 268 16,398 44,219 -2,452 -5.55%
Apr-13 8.14% 9,551 8,668 54,784 2,167 1,278 248 3,692 47,912 4,976 10.39%
May-13 0.00% 0 9,552 64,336 7,516 1,697 242 9,456 57,367 96 0.17%
Jun-13 17.44% 20,462 10,508 74,844 6,556 1,382 206 8,144 65,511 2,364 3.61%
Jul-13 12.09% 14,189 11,466 86,310 12,972 718 206 13,896 79,407 -2,430 -3.06%
Aug-13 0.00% 0 0 86,310 397 204 222 824 80,230 -824 -1.03%
Sep-13 0.00% 0 3,175 89,485 567 12 227 806 81,036 2,369 2.92%
Oct-13 1.41% 1,650 1,100 90,585 624 197 821 81,857 279 0.34%
Nov-13 12.90% 15,132 0 90,585 0 216 216 82,073 -216 -0.26%
Dec-13 0.00% 0 90,585 195 195 82,268 -195 -0.24%
90,585 162 162 82,430 -162 -0.20%
99.98% 117,313 90,585 56,121 22,088 4,221 82,430 8,155 9.89%
PAGE 4 OF 5
PROJECT NO. #NAME?
PROJECT STATEMENT OF ACCOUNT
PLANING MANANGMENT
PAGE 3 OF 5
BHD 40,000.00
Total Value %
BHD 3,000.00 2.56%
BHD 8,000.00 6.82% BHD 35,000.00
BHD 13,000.00 11.08%
BHD 15,000.00 12.78% BHD 30,000.00
BHD 18,500.00 15.77%
BHD 21,500.00 18.32% BHD 25,000.00
BHD 24,500.00 20.88%
BHD 31,500.00 26.85% BHD 20,000.00
BHD 47,500.00 40.48%
BHD 55,500.00 47.30% BHD 15,000.00
BHD 64,831.75 55.26%
BHD 67,331.75 57.39% BHD 10,000.00
BHD 82,331.75 70.17%
BHD 96,331.75 82.10% BHD 5,000.00
BHD 99,331.75 84.66%
BHD 100,331.75 85.51%
BHD 0.00
BHD 102,331.75 87.22% Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12
BHD 117,331.75 100.00%
BHD 117,331.75 100.00%
BHD 117,331.75 100.00%
BHD 117,331.75
Total Value %
BHD 1,500.00 1.60%
BHD 3,300.00 3.51%
BHD 10,300.00 10.97%
BHD 19,800.00 21.09%
BHD 21,950.00 23.38%
BHD 25,950.00 27.64%
BHD 29,950.00 31.90%
BHD 33,950.00 36.16%
BHD 37,450.00 39.88%
BHD 54,450.00 57.99%
BHD 58,250.00 62.03%
BHD 68,250.00 72.68%
BHD 76,250.00 81.20%
BHD 90,250.00 96.11%
BHD 91,250.00 97.18%
BHD 92,250.00 98.24%
BHD 93,250.00 99.31%
BHD 93,500.00 99.57%
BHD 93,700.00 99.79%
BHD 93,900.00 100.00%
BHD 93,900.00 BHD 93,900.00
Total Value %
BHD 0.00 0.00%
BHD 6,000.00 5.11%
BHD 11,000.00 9.38%
BHD 35,000.00
BHD 21,000.00 17.90%
BHD 27,000.00 23.01%
BHD 30,000.00
BHD 37,000.00 31.53%
BHD 42,000.00 35.80% BHD 25,000.00
BHD 46,000.00 39.21%
BHD 53,500.00 45.60% BHD 20,000.00
BHD 68,500.00 58.38%
BHD 77,500.00 66.05% BHD 15,000.00
BHD 87,000.00 74.15%
BHD 97,500.00 83.10% BHD 10,000.00
BHD 109,500.00 93.33%
BHD 112,331.75 95.74% BHD 5,000.00
BHD 116,331.75 99.15%
BHD 117,331.75 100.00% BHD 0.00
2 2 2 2 2 2 2
BHD 117,331.75 100.00% n-1 l-1 g-1 p-1 ct-1 v-1 c-1
Ju Ju u Se O o De
A N
BHD 117,331.75 100.00%
BHD 117,331.75 100.00%
BHD 117,331.75 BHD 117,331.75
ACTUAL REVENUE
Com
BHD 550.00 BHD 25,000.00
BHD 1,601.00
BHD 2,716.00
-BHD 230.60
-BHD 55.74 BHD 20,000.00
-BHD 1,412.21
-BHD 1,333.66
BHD 3,162.41
BHD 15,560.95 BHD 15,000.00
-BHD 7,729.42
BHD 5,858.70
-BHD 9,455.54
BHD 10,000.00
BHD 12,318.70
BHD 292.74
-BHD 823.76
-BHD 805.72 BHD 5,000.00
BHD 129.00
BHD 14,915.75
-BHD 195.00
BHD 0.00
1 2 3 4 5 6 7 8
Invoicing Process Planning
AC Invo
PV to be
-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13
Payable Process Planning
BHD 40,000.00
BHD 35,000.00
BHD 30,000.00
BHD 25,000.00
BHD 20,000.00
BHD 15,000.00
BHD 10,000.00
BHD 5,000.00
BHD 0.00
Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-1
Recivable Process Planning
Actual Recived
Planned to be recived
12 12 t-1
2 12 c-1
2 13 13 r-1
3
r-1
3 13 -1
3
l-1
3
-1
3
-1
3
t-1
3
-1
3
-1
3
ug- ep- c ov- e an- eb- a p ay- n u ug ep c ov ec
A S O N D J F M A M Ju J A S O N D
Actual Spent to
Actual Paid
Ratio
#DIV/0!
0.63
0.54
0.77
0.71
0.97
0.95
0.99
0.86
0.96
0.87
0.89
0.88
0.92
0.93
0.91
0.90
0.91
0.91
0.91
0.91
Earned Value(EV)
Planned Value (PV)
Actual Value(AC)
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
AC Invoiced
PV to be Invoiced
Nov-13 Dec-13
nning
AC Spent
Planeed to be Spent
TOTAL COST BHD 93,900 BHD 84,510 BHD 82,430 BHD 2,080 BHD 11,470 BHD 9,390 BHD 11,470
Material BHD 55,200 BHD 49,680 BHD 56,121 -BHD 6,441 -BHD 921 BHD 5,520 -BHD 921
Labour BHD 32,500 BHD 29,250 BHD 22,088 BHD 7,162 BHD 10,412 BHD 3,250 BHD 10,412
Overheads BHD 6,200 BHD 5,580 BHD 4,221 BHD 1,359 BHD 1,979 BHD 620 BHD 1,979
REVENUE BHD 117,332 BHD 105,599 BHD 90,585 BHD 15,014
NET PROFIT BHD 23,432 BHD 21,089 BHD 8,155 BHD 12,934
PROFIT MARGIN 16.83% 16.83% 9.00%
PAGE 2 OF 5
VARIABLE COST
AMOUNT TOTAL AMOUNT FIXED COST PROJECT CASH
MONTH (MATERIAL + TOTAL COST PROFIT % ON COST
RECEIVED RECEIVED (OVERHEADS) POSITION
LABOUR)
4 BAC BAC - Budget at completion (Total Estimated Cost)Total Estimated Dry Cost at starting of the project(Project budget ) BHD 93,900.00
5 PV PV/BCWS - Planned Value (Planned Budget ) AS OF NOW / Planned Value to be Spent (from Project starting till this month) BHD 93,900.00
6 Actual Value to be invoiced (from Project starting till this month)-Actual Value invoiced (from Project starting till this month) BHD 117,331.75
7 EV EV/BCWP - Earned Value -We should spend Value BD till this month as per buget values BHD 84,510.00
8 Planned Cost of Work Performed (Planned cost to be spent till this month)-Planned cost to be spent on project till this month BHD 93,900.00
9 AC Actual Cost of Work Performed (Cost incurred to date)Actual Value spent till this month for Performed Works BHD 82,430.16
10 CV CV - Cost Variance (Cost Saved)under or over budget by BD Value BHD 2,079.84
11 CPI CPI - Cost Performance Index As of now the Value of One BD we spend Equal to 1.03 BD
12 SPI SPI - Schedual Performance Index The Project excuted by Value from the orignal time 0.90
13 EAC EAC - Estimate at Completion Expected Total Cost if we Continue at Same Performance BHD 91,589.07
14 ETC ETC - Estimate To Complete (The Remaining works will cost us) BHD 9,158.91
15 VAC VAC - Variance at Completion (Total Cost Expected to be Saved) BHD 93,566.67
TCPI - To-Complete Performance Index (Remaining Budget Index) IF we continue on the same performance the project will
16 TCPI cost us Extra /Less Value BD BHD 0.77 (EAC-EV)/ (EAC-AC)
17 Estimated GrossProfit of now BHD 21,088.58
18 Expected Gross Profit at the End of the Project (based on EAC) BHD 23,431.75
19 Finance Cost (EAC x Interest Rate) @ 7% Interest Rate BHD 6,411.23
Predicted Profit BHD 25,742.68
Rredicted Rate of Profit 21.94%
20 Estimated Net Profit BHD 34,901.59 38%
Estimated Net Profit Per day BHD 157.93
Project 1044 - ZALLAQ
Revenues Variable Cost Contribution Fixed Cost
Reset
BHD 117,331.75 BHD 78,209.16 BHD 39,122.59 BHD 200.00
Breakeven
BHD 140,000
BHD 120,000
BHD 100,000
Revenue
BHD 80,000
BHD 60,000
BHD 40,000
BHD 20,000
BHD 0
0
10
20
30
40
50
60
70
80
90
100
Completion Percentage
REVENUE FIXED COSTS TOTAL COSTS
Total Sales: BHD 117,331.75 What-if Sales: 100% Value of Sales: BHD 117,332
BAC BHD 93,900
PV BHD 93,900
EV-AC CV/EV EV-PV
% Work Done PV AC EV CV %CV SV
90.00% 14 BHD 93,900 BHD 82,430 BHD 84,510 BHD 2,080 2.46% (BHD 9,390)
SV/PV EV/AC EV/PV BAC/CPI EAC-AC BAC-( (BACXAC)/EV)
%SV CPI SPI EAC ETC
-10.00% 1.03 0.90 BHD 91,589 BHD 9,159 BHD 2,311
(EAC-EV)/ (EAC-AC)
TCPI
0.77
Project Performance Index
(PPI)
Electrical Installation Manpower Histogram
24
22
20
18
16 15 15
14
12
10 10
10
8 8 8 8 8
8
6 5 5
4 3 3
2 2 2 2
2 1 1
0
Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13
Months Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13
ELECTRICAL WORKS 1 2 2 3 5 8 8 10 15 15 10 8 8 8 5 3 2 2 1
TOTAL 1 2 2 3 5 8 8 10 15 15 10 8 8 8 5 3 2 2 1
Project Actual Start Date
6/7/2013
BHD 5.00
BHD 6.00
BHD 7.00
BHD 8.00
BHD 9.00
BHD 10.00
BHD 11.00
BHD 12.00
BHD 13.00
BHD 14.00
BHD 15.00
BHD 16.00
BHD 17.00
18.00
19.00
20.00
21.00
Issue of Major
Material
Purchase Order
Last PO Date
1/15/2013
Ranges Gauge
Start 0 Value 99
Red 15 Pointer 1
Yellow 45 End 177
Green 40
End 100
KPI
Sample
Sample
1
BAC $500
PV $100
EV-AC CV/EV EV-PV SV/PV EV/AC
% Work Done PV AC EV CV %CV SV %SV CPI
24% 1 $100 $80 $120 $40 33.33% $20 20.00% 1.50
24% 2 $100 $100 $120 $20 16.67% $20 20.00% 1.20
20% 3 $100 $80 $100 $20 20.00% $0 0.00% 1.25
28% 4 $100 $120 $140 $20 14.29% $40 40.00% 1.17
24% 5 $100 $120 $120 $0 0.00% $20 20.00% 1.00
20% 6 $100 $100 $100 $0 0.00% $0 0.00% 1.00
16% 7 $100 $60 $80 $20 25.00% ($20) -20.00% 1.33
20% 8 $100 $120 $100 ($20) -20.00% $0 0.00% 0.83
16% 9 $100 $80 $80 $0 0.00% ($20) -20.00% 1.00
24% 10 $100 $140 $120 ($20) -16.67% $20 20.00% 0.86
12% 11 $100 $80 $60 ($20) -33.33% ($40) -40.00% 0.75
16% 12 $100 $100 $80 ($20) -25.00% ($20) -20.00% 0.80
16% 13 $100 $120 $80 ($40) -50.00% ($20) -20.00% 0.67
EV/PV BAC/CPI EAC-AC BAC-( (BACXAC)/EV) (EAC-EV)/ (EAC-AC)
SPI EAC ETC TCPI
1.20 $333.33 $253.33 $166.67 0.84
1.20 $416.67 $316.67 $83.33 0.94
1.00 $400.00 $320.00 $100.00 0.94
1.40 $428.57 $308.57 $71.43 0.94
1.20 $500.00 $380.00 $0.00 1.00
1.00 $500.00 $400.00 $0.00 1.00
0.80 $375.00 $315.00 $125.00 0.94
1.00 $600.00 $480.00 ($100.00) 1.04
0.80 $500.00 $420.00 $0.00 1.00
1.20 $583.33 $443.33 ($83.33) 1.05
0.60 $666.67 $586.67 ($166.67) 1.03
0.80 $625.00 $525.00 ($125.00) 1.04
0.80 $750.00 $630.00 ($250.00) 1.06
Project Performance Index
(PPI)
Good. Work ahead of schedule & with cost savings on work done, as well as an apparent cost under-run on the budget.
Good. Work is ahead of schedule, with cost savings even though the budget has been spent as planned.
Good. Work is on schedule, with cost savings.
Good. Work is ahead of schedule, with costs savings. [But may have a cash flow problem if funds are released incrementally.
V. Good. Work is ahead of schedule, with costs as planned for work done. [But may have a cash flow problem if funds are relea
“Ideal”. Everything going according to plan – On Schedule & Spending. [Extremely Rare!]
Mixed – Good & Bad. Saving money on the work performed; but work is behind schedule
Mixed – Good & Bad. Work on schedule, but cost overrun incurred. [May have a cash flow problem if funds are released increm
Mixed – Good & Bad. Spending as planned; but work is behind schedule.
Mixed – Good & Bad. Work ahead of schedule, but a cost overrun has been incurred. [May have a cash flow problem if funds re
BAD. Spending is slower than planned, but the Value is low — indicating a cost overrun; and the work is also behind schedule.
BAD. Although the spending rate is as planned, since the Value is low, there is a cost overrun; and the work is also behind sche
V.BAD. Work behind schedule, cost overrun [and possible cash flow problem.]
KPI'S
LIQUIDITY INDICATOR
BACKLO INDICATOR
UNDER BILLINGS:
IF THE BILL AMOUNT IS LESS THAN THE EARNED VALUE OF JOB, IT IS UNDER BILLING.
THE COMPANY WILL BE AT LOSS AS IT MAY FORGET TO SUBMIT A BILL.
OVER BILLING:
IF THE BILL AMOUNT IS MORE THAN THE EARNED VALUE IT IS OVERBILLING.
THE COMPANY WILL HAVE LIQUIDITY.
PI'S
CASH FUNDING
1,200.000
365 DAYS
365.000
REVISED DURATION(DAYS)
REMAINING DURATION (DAYS)
ER BILLING.
AZ
KPI
SPI
Schedule Performance Index
Value more than One , we are behind the schedule , Value equal One ,
we are on schedule and Value less than One, we are ahead of
1
schedule
Ranges Gauge
Start 0 Value 97
Red 295 Pointer 1
Yellow 0 End 177
Green 55
End 350
KPI
266
SPI
30
Schedule Performance Index
Value more than One , we are behind the schedule , Value equal One ,
we are on schedule and Value less than One,1we are ahead of
schedule
Ranges Gauge
Project Start
ProjectConduit
Start and Piping
Wiring DB insta
DB installation Cable Pulling
onduit
tart and Piping
Wiring DB installation SMP installation Cable Pulling DB Dressing
Install Switch
Light fittingEarthing
inst Install
witch
Earthing Install
witch
Light fittingEarthing
inst Install Project Handover
Project Name #NAME?
EDESON Projects
Days Remaining
Duration (Days)
Days Complete
Working Days
% Complete
10/13/14
10/20/14
10/27/14
11/10/14
11/17/14
11/24/14
12/15/14
12/22/14
12/29/14
4/28/14
5/12/14
5/19/14
5/26/14
6/16/14
6/23/14
6/30/14
7/14/14
7/21/14
7/28/14
8/11/14
8/18/14
8/25/14
9/15/14
9/22/14
9/29/14
10/6/14
11/3/14
12/1/14
12/8/14
1/12/15
1/19/15
1/26/15
2/16/15
2/23/15
3/16/15
3/23/15
5/5/14
6/2/14
6/9/14
7/7/14
8/4/14
9/1/14
9/8/14
1/5/15
2/2/15
2/9/15
3/2/15
3/9/15
WBS Tasks Task Lead Start End
24-Nov-13
25-Nov-13
26-Nov-13
27-Nov-13
28-Nov-13
29-Nov-13
30-Nov-13
1-Dec-13
2-Dec-13
3-Dec-13
4-Dec-13
5-Dec-13
6-Dec-13
7-Dec-13
DATE
DURATION FORECAST % COMPLETION
ID ACTIVITY DESCRIPTION START DATE
(days) FINISH DATE CURRENT REMARKS
SS M T W TH F S SS M T W TH F S
P
1 24-Nov-13 14 7-Dec-13 10.00%
A
P
A
P
A
P
A
P
A
P
A
P
A
P
A
P
A
P
A
P
A
P
A
P
A
P
A
P
A
P
S/n Sub Contractor List Tel No. Fax No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Contact Person Mobile
S/n Vendor List Tel . No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Fax No. Contact Person Mobile
HCDC 001 MAT A/1
Status
Status
Actual Rec.Date from Submittal Rec. from Submittal Rec. from required at site Remark
Reference Ref.No. As Per Tender & Concept Report Proposed Submittal Status date
Submittal Date Consultant Date Consultant Date Consultant
Date
EL -01 PVC CONDUITS & FITTINGS MA/EL/006 DECODUCT/ CLIPSAL CLIPSAL 26-Dec-07 26-Dec-07 5-Mar-08 B 1-Dec-07 Material recived@site
EL -02 UPVC DUCT MA/EL/007 GULF PLASTIC GULF PLASTIC 10-Feb-08 10-Feb-08 5-Mar-08 A 12-Feb-08 Material recived@site
EL -03 FLEXIBLE METALLIC CONDUITS MA/EL/011 ADAPTAFLEX ADAPTAFLEX 16-Jul-08 12-Aug-08 21-Aug-08 A 3-Dec-09 Needs Details DWG's
EL -04 CABLE TRAYS, &LADDERS AND GI TRUNKING & ACCESSORIES MA/EL/012 KRUPPSMETAL KRUPPSMETAL 15-Dec-08 18-Aug-08 21-Aug-08 B 2-Apr-08 Material recived@site
EL -05 CABLE TRAYS, &LADDERS AND GI TRUNKING & ACCESSORIES MA/EL/012/2 CLIPSAL CLIPSAL 15-Dec-08 13-Aprl-09 32-Aprl-09 A 2-Apr-08 Material recived@site
EL -06 GI CONDUIT AND ACCESSORIES MA/EL/020 BARTON/MARSHAL/SMARTr SMARTr 8-Jan-09 8-Jan-09 26-Jan-09 A 3-Dec-09 Needs Details DWG's
EL -07 GI BOXES MA/EL/010 VOLEX / BARTON BARTON 15-Mar-08 15-Mar-08 23-Mar-08 A 2-Jan-09 Material ordered Partially
EL -08 LV CABLES,WIRES,MV CABLES AND CABLE GLANDS MA/EL/004 DUCAB/RIADH/SAUDI CABLES DUCAB 26-Dec-07 26-Dec-07 12-Feb-08 B 8-May-09 Material recived@site
EL -09 BRASS CABLE GLANDS MA/EL/29 BIAX BIAX 16-Mar-09 16-Mar-09 22-Mar-09 B 9-Dec-09
EL -10 HV CABLES MA/EL/23 DUCAB DUCAB 25-Feb-09 25-Feb-09 1-Mar-09 A 10-Oct-09 DWG's on progress
BBI,ITALY/ZUCCHINI,ITALY/ LG LS
EL -11 BUSBAR TRUNKING MA/EL/25 BBI 25-Feb-09 3-Aug-09 31/3/09 B 5-Dec-09 Needs Details DWG's
KOREA/ SEMINS,CHINA/EAE,TURKEY
EL -12 SWITCHES AND SOCKETS (WIRING DEVICES& ACCESSORIES) MA/EL/013 CLIPSAL/MK/LEGRAND-PLASTIC WHITE CLIPSAL 29-Oct-08 29-Oct-08 30-Nov-08 B 8-Nov-08 30-Nov-08 B 1-Feb-10 Material recived@site
EL -13 ISOLATORS MA/EL/24 CLIPSAL/ABB/MEM/GE CLIPSAL 3-Feb-09 3-Feb-09 4-Mar-09 B 1-Feb-10 DWG's on progress
EDWARD,CANADA/SIMPEX,USA/
EL -14 FIRE ALARM SYSTEM MA/EL/014 SIMPLEX 24-Sep-08 24-Sep-08 28-Sep-08 B 14-Feb-10 Material ordered
THORN,UK/GENT,UK/CO
EL -15 FIRE ALALRM CABLES MA/EL/015 DATWYLER PRYSMIAN 21-Oct-08 21-Oct-08 29-Oct-08 B 8-May-09 Material recived@site
EL -16 AUDIO INTERCOM SYSTEM MA/EL/17/01 BPT / ITALY GOLMAR/GERMANY BPT/ ITALY 5-Jan-09 6-Jan-09 27-Jan-09 C 13-May-09 2-Jun-09 A&B 14-Feb-10 Options to be fininlize
C.D.V.,UK/SIMPLEX,USA/MC-TAK,UK
EL -17 ACCESS CONTROL SYSTEM(PARKING BARRIER SYSTEM) MA/EL/28 GE SEQURITY 12-Mar-09 14-Mar-09 4-May-09 B 31-May-09 25-Jun-09 B 14-Feb-10 Material ordered
HID,MAXXESS,GE,SIEMENS
EL -18 ICT SYSTEM (CONTAINMENT ONLY) TO BE CONFIRMED NOT IN SCOPE NOT IN SCOPE
EL -19 CCTV SYSTEM MA/EL/27 BOSCH,PELCO,GE,I-LAX CBC GROUP-UK 14-Mar-09 14-Mar-09 21-Aprl-09 B 19-May-10 Material ordered
SDMO,FRANCE/CUMMINS,UK/
EL -20 STAND BY GENERATORS MA/EL/18 AKASA 5-Jan-09 5-Feb-09 11-Feb-09 B 10-Oct-09 Material ordered
F.G.WELSON,UK/CATERPILLAR/USA
EL -21 MAIN PANEL BOARD,MDB,EMDB,SMDB,ESMDB,DB,EDB MA/EL/26 ABB/GE/MG/LEGRAND ABB / BSLI 15-Feb-09 3-Aug-09 23/3/09 B 30-May-09 2-Jun-09 C 8-May-09
EL -22/1 LIGHT FITIINGS MA/EL/22/1 SEGMA-CHINA SEGMA-CHINA 20-Jan-09 18/02/09 3-Mar-09 B 20/6/09 14-Jul-09 C 25-Oct-09 5-Dec-09
EL -23 FACAD LIGHTING MA/EL/38 SEGMA-CHINA SEGMA-CHINA 28-Jul-09 28/7/09 23-Aug-09 B 5-Dec-09
EL -24 AVIATION LIGHTING(AIRCRAFT WARNING LIGHT) MA/EL/021 HONEWELL/ LIGHTINGPOINT/SILL HONEWELL 4-Feb-09 4-Feb-09 7-Feb-09 B 14-Feb-09 18-Feb-09 A 1-Feb-10 Material ordered
EL -25 EARTHING & LIGHTNING PROTECTION SYSTEM(LPS) MA/EL/005 FURSE, UK /WALLIS,UK FURSE 26-Dec-07 26-Dec-07 12-Feb-08 A 25-Dec-07 Material recived@site
EL -26 SELF CONTAINES EMERGENCY LIGHT FITTING MA/EL/22/1 ECC-TURKY ECC-TURKY 20-Jan-09 18/02/09 3-Mar-09 B 5-Dec-09 Options to be fininlize
TAMCO,MALYSIA/RUNHIL,MALYSIA/ AL
EL -27 HV SWITCHGEAR MA/EL/36 AL AHLIA,KWAIT 4-Jun-09 20-Jun-09 27-Jul-09 B 10-Oct-09
AHLIA,KWAIT
EL -28 TRANSFORMER MA/EL/31 MG,SAUDI TRANSFORMER/ ABB ZENNARO-ITALY 4-Jun-09 4-Jun-09 11-Apr-09 C 31-May-09 15/6/09 C 28-Dec-09
EL -29 PAMENT POOTH SYSTEM FOR SUPER MARKET MA/EL/32 CEDAMATIC/ ITALY CEDAMATIC/ ITALY 29-Mar-09 29-Mar-09 21-Apr-09 B 6-May-09 3-Jun-09 B 22/6/09 23/7/09 B 19-May-10
RINGGRIP PTY
EL -30 DOOR CHIME MA/EL/35 RINGGRIP PTY /AUSTRALIA 6-May-09 6-May-09 14-May-09 C 22-Aug-09 23-Aug-09 R 5-Dec-09
/AUSTRALIA
EL -31 RING MAIN UMIT MA/EL/ SCHNEIDR ELECTRIC/ FRANCE
EL -32 DB SPLIT W/ 3MA, 0030MA ELCB 4+4 WAY FLUSH MOUNTED MA/EL/ VOLTAMP
ERP MAF-CATLOGE
QTY APPPROVED
DESCRIPTION QTY BOQ
CODE NO SHOP DWGS
RACTING W.L.L.
DATE:
Project: #NAME?
Issue 1
Issue 1
Issue 1
Issue 1
Issue 1
Issue 1
Issue 1
Issue 1
Issue 1
Issue 1
Issue 1
Assigned to Comments
Engineering Dept
Purchasing Dept.
Vendor
Purchasing Dept.
Purchasing Dept.
Purchasing Dept.
Store Keeper
Vendor
Vendor
Accounts Dept
Vendor
Variation Order Log
Job Name Job Number
AREA / LOCATION:
Page No. of
Page No. of
Construction Schedule