0% found this document useful (0 votes)
151 views4 pages

Inspection & Test Plan

1. The document outlines an inspection and test plan for various construction processes including incoming/outgoing materials, setting out, piling, excavation/backfilling, and reinforced concrete structure. 2. It lists items to be checked, characteristics/conditions, frequency of inspection, applicable standards/specifications, and testing methods for each process. 3. Inspections include checking quantities, quality, arrangement of materials; boundary pegs, control points, and orientation for setting out; pile position, hammering, welding, penetration for piling; excavation levels and materials for excavation/backfilling.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
151 views4 pages

Inspection & Test Plan

1. The document outlines an inspection and test plan for various construction processes including incoming/outgoing materials, setting out, piling, excavation/backfilling, and reinforced concrete structure. 2. It lists items to be checked, characteristics/conditions, frequency of inspection, applicable standards/specifications, and testing methods for each process. 3. Inspections include checking quantities, quality, arrangement of materials; boundary pegs, control points, and orientation for setting out; pile position, hammering, welding, penetration for piling; excavation levels and materials for excavation/backfilling.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 4

INSPECTION AND TEST PLAN Rev.

: 0
Page : 1 of 4

Standards / Testing
Things To Be Checks Characteristics /
Process Responsibility Frequency Specification / Method / Remark
Checked Conditions
Reference Equipment

Incoming / Project Manager / 1. All Goods 1. Quantity & Type As Per Every Delivery. 1. Drawings / 1. Visual; PO & DO
Outgoing Received; DO; Specification / 2. Calculatio
Material Civil Engineer / 2. Storing/ 2. Quality - Approved As BQ. n;
Site Supervisor Stacking. Accordance To Sample 2. PO / COA. 3. Measuring
Or Specification, Clean, Tape.
Tidy & Rigidity;
3. Arrangement - Safe,
Traceable & Working
Distance.

Setting Out Project Manager / 1. Boundary Peg.; 1. Level; Every Block, 1. Licensed 1. Theodolite
2. Control Point / 2. Coordinate Point; Every Floor. Surveyor. ;
Civil Engineer / Profile Board. 3. Orientation. 2. Dumpy
Site Supervisor Level;
3. Measuring
Tape;
4. Plumb
Bub.

Piling Project Manager / 1. Pile Point; 1. Pile Position & Pitching; Every Pile Point 1. Drawings- 1. Visual &
2. Machine; 2. Hammer & Verticality; Or As Per Foundation Counting;
Civil Engineer / 3. Join; 3. Welding Thickness / Engineer’s Layout & Pile 2. Spirit
Site Supervisor 4. Pile Set; Sizes Of Sleeve; Instruction. Group Detail. Level
5. Load Testing. 4. Penetration per No. Of Rule;
Blows; 3. Pressure
5. Correct Load Test Gauge,
Equipment Testing; Ruler &
6. Correct Calibration Dumpy
Requirement As Per Level;
Proposal. 4. Measuring
Tape.

Excavation Project Manager / 1. Excavated / 1. To Require Reduce Every Unit. 1. Dumpy


1. Drawings;
/ Back Back Filled Level; Level &
2. Specifications.
Filling Civil Engineer / Level; 2. Correct Material; Staff.
Site Supervisor 3. Shoring / Slopes /
Gradient;
INSPECTION AND TEST PLAN Rev.: 0
Page : 2 of 4

RC Project Manager / 1. Setting Out; 1. Control Point As Per Before / After 1. Measuring
1. Contract
Structure 2. Formwork; Construction Drawings; Casting. Tape;
Specification;
Civil Engineer / 3. Reinforcement; 2. Surface Of Formwork & 2. Water
2. Drawings. Pre-
Site Supervisor 4. M&E Services; Apply Mould Oil (For Ply Spirit
Arrange
5. Concrete Wood); Level;
With COW
Placing; 3. Dimensions, Level & 3. Plum Bulb;
For Joint
6. Dismantling Verticality; 4. Visualizing
Inspection.
Formwork; 4. Joints Tight; &
7. Cube Testing. 5. Stability, Rigidity & Counting;
Cleanliness; 5. Slump;
6. Grade, Size, Nos. Of 6. Cube
Bar, Spacing & Lapping; Mould;
7. Concrete Cover / 7. Lab
Spacer; Testing.
8. Clean;
9. Piping / Wiring Are
Installed Accordingly;
10. Services Opening Size;
11. Concrete Sources &
Suitability-Grade,
Slump, Time Limit (Btw.
Batching & Placing);
12. Vibration Poker (Enough
Vibration);
13. Proper Curing;
14. No Damage To
Concrete;
15. Achieve Required
Strength.

Common Project Manager / 1 Setting Out; 1. Correct Position & Every Unit. 1. Sprit Level
1. Specification;
Brickwork / 2 Quality Of Alignment; / Plumb;
2. Drawings.
Block Work Civil Engineer / Material 2. Appropriate Cement 2. Measuring
Site Supervisor Preparation; Mortar Mixing Ratio As Tape.
3 Quality Of Per Contract;
Craftsmanship. 3. Type Of Bonding /
Jointing, Reinforcement
(Exmet @4 Course,
INSPECTION AND TEST PLAN Rev.: 0
Page : 3 of 4

Dowel Bars, Stiffener &


Lintel) & dpc;.
4. Verticality.

Wall Project Manager / 1. Quality of 1. At Least 3 Days After 1. Before 1. Long


1. Specification;
Plastering Craftsmanship. Completion Of Wall; Commencing Ruler.
2. Drawings.
Civil Engineer / 2. All Concealed Piping & Work;
Site Supervisor Wiring Are Installed; 2. Every Unit.
3. Cement Mortar Mixing
Ratio As Per Contract
Specification;
4. Applying First & Finishing
Coat Technique;
5. Thickness;
6. Surface Leveling & Towel
To Evenness;
7. Plastering Joint If Area
Too Substantial;
8. Groove Line.
1. Specification;
Wall Project Manager / 1. Quality of 1. At least 1 Days after 1. Before 1. Long
2. Drawings
Skimcoat Craftsmanship Completion Work; Commencing Ruler.
Civil Engineer / . Work;
2. Conner Bead are place
Site Supervisor
align to structure 2. Every Unit.
(beam/column) ;
3. Skim coat mixing ratio as
per Method of statement;
4. Thickness;
5. Surface Leveling &
smooth surface.

External Project Manager / 1. Parameter 1. Cement Mortar Mixing Every Unit. 1. Specification; Nil DE-QC-IT-
Work Drain & Apron. Ratio; 2. Shop Drawing; F15_Perim
Civil Engineer / 2. Chain Link 2. Gradient / Lay To Fall; 3. Detail eter Drain
Site Supervisor Fencing. 3. Approved PC Drain; Drawing; And Apron
4. Level; 4. Architect’s Inspection
5. Approved Fencing - Type, Approved Form
Size & Color; Sample.
6. Approved Gate;
7. Stanchion Size As Per
INSPECTION AND TEST PLAN Rev.: 0
Page : 4 of 4

Drawing & Depth Below


The Earth;
8. Angle Bracing;
9. Welding.

Prepared By: Reviewed & Approved By:

Name: TS Chin (QMR) Name: Ir. Lew Choon Keong


Date: 05 / 05 / 2016 Date: 05 / 05 / 2016

You might also like