Time Line

This document provides a 3-week schedule for the rehabilitation of a public facility or space from February 12th to March 10th. It lists the project name and duration of 28 days. The project start date is February 12th and planned end date is March 10th. A schedule is provided showing the planned work for each day.

Uploaded by

es
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views1 page

Time Line

This document provides a 3-week schedule for the rehabilitation of a public facility or space from February 12th to March 10th. It lists the project name and duration of 28 days. The project start date is February 12th and planned end date is March 10th. A schedule is provided showing the planned work for each day.

Uploaded by

es
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

"Community Support Projects (public facilities/spaces)" According to Schedule below is approximately 28 days

3-Baseline Plan of Work to Complete a Community Support Projects (public facilities/spaces)


PROJECT NAME DURATION PROJECT START DATE PROJECT END DATE
Rehibiltation of (public facilities/spaces) 28 Days 12-02-24 10-03-24
‫ن‬ ‫ن‬
‫المعوقي حركيا‬ ‫اللبنان األشخاص‬
‫ي‬ ‫اإلتحاد‬
Done by Eng.Essam Alhayek
DAY MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI SAT SUN
Category

12-02-24

13-02-24

14-02-24

15-02-24

16-02-24

17-02-24

18-02-24

19-02-24

20-02-24

21-02-24

22-02-24

23-02-24

24-02-24

25-02-24

26-02-24

27-02-24

28-02-24

29-02-24

01-03-24

02-03-24

03-03-24

04-03-24

05-03-24

06-03-24

07-03-24

08-03-24

09-03-24

10-03-24
Task ID
Task

Task
Task Description Start Date End Date
Duration

Prepare PRELIMINARIES 1 12-02-24 12-02-24


0

Civil Work BLOCK WORK & PLASTER 7 13-02-24 19-02-24


1 2 3

X X X X X X X

DW DOORS & WINDOWS 5 19-02-24 23-02-24 X X X X X

Steel Steel Works 6 23-02-24 28-02-24 X X X X X X

Tiles FLOOR & WALL TILES 5 27-02-24 02-03-24


4

X X X X X

Elec ELECTRICAL WORKS 6 02-03-24 07-03-24


5

X X X X X X

Mech MECHANICAL WORKS 6 04-03-24 09-03-24


6

X X X X X X

Al+St Int Works 3 02-03-24 04-03-24


7

X X X

Conct.+Ramps EXTERNAL WORKS 5 05-03-24 09-03-24


8

X X X X X

Closing Project Cleaning and Handover 1 10-03-24 10-03-24


9