10 603173 0000100201 Mah QMN RPT 000001 - 01
10 603173 0000100201 Mah QMN RPT 000001 - 01
10 603173 0000100201 Mah QMN RPT 000001 - 01
Work Order Title Spine Earthworks Lot 10-3 - CH75+500 to CH 78+000 (Coastal Desert
Region)
Document Title WO 58- Management Review Meeting Report No.01 (June 15, 2023)
-Spine Earthworks Lot 10-3 - CH75+500 to CH 78+000 (Coastal Desert
Region)
Document No. 10-603173-0000100201-MAH-QMN-RPT-000001
Revision No. 01
Date & Signature July 05, 2023 July 05, 2023 July 05, 2023
10-603173-0000100201-MAH-QMN-RPT-000001_01 Page 1 of 3
`
10-603173-0000100201-MAH-QMN-RPT-000001 – Rev. 01
Date -05/07/2023
10-603173-0000100201-MAH-QMN-RPT-000001_01 Page 2 of 3
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. - 100201
Contract Name - Spine Earthworks Lot 10-3 - CH75+500 to CH
78+000 (Coastal Desert Region)
Report
Document History
10-603173-0000100201-MAH-QMN-RPT-000001_01 Page 3 of 3
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01
WO 58 – LOT 10.3 –
MANAGEMENT REVIEW # 01
Date : 15-June-2023
10-603173-0000100201-MAH-QMN-RPT-000001_01 1 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01
9.3. 1 General
10-603173-0000100201-MAH-QMN-RPT-000001_01 2 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01
The CONTRACTOR’s project management shall ensure that project risks and
opportunities are determined, and actions are taken to address these risks and
opportunities are planned.
Within (2) weeks after the scheduled review date, the CONTRACTOR shall advise
the NEOM Representative in writing of the changes to QMS resulting from
Management review. Such changes shall be incorporated in the PQPs, with the
approval of the NEOM Representative Resource Management.
10-603173-0000100201-MAH-QMN-RPT-000001_01 3 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01
10-603173-0000100201-MAH-QMN-RPT-000001_01 4 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01
SL.
MANGEMENT REVIEW RECOMMENDATION
NO
9.3.2.a. the Status of actions from
1 This is the 1st Management Review
Previous Management Reviews
Organization Chart was reviewed and is
9.3.2.b. Changes in the internal and complied.
2 external issues that are relevant to the
Quality Management System Material Approval were reviewed for the supply
materials and are complied.
9.3.2.c. Information on Performance
and Effectiveness of the Quality
Monthly PQI were provided and reviewed.
Management System
3 Reviewed weekly quality minutes of meeting for
1. Customer Satisfaction and
the compliance of feedback and comments.
feedback from relevant interested
parties
9.3.2.c. Information on Performance The Internal Quality Audit results were reviewed
and Effectiveness of the Quality to ensures Contractor MAH is in compliance to
Management System ISO 9001: 2015, all process have been carried
4
out to meet in compliance to the international
2. The Extent to which the Quality Standard organization requirement, Schedule ’Q’
Objectives have been met requirements and Project Quality Plan.
9.3.2.c. Information on Performance
Monthly Quality Management Report were
and Effectiveness of the Quality
reviewed for the process performance.
5 Management System
Monthly PQI were provided for the conformity to
3. Process performance and
comply the customer satisfaction.
conformity of product and services
9.3.2.c. Information on Performance
and Effectiveness of the Quality
6 Management System NCR Logs were reviewed and is complied.
4. Non-Conformities and Corrective
Action
10-603173-0000100201-MAH-QMN-RPT-000001_01 5 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01
10-603173-0000100201-MAH-QMN-RPT-000001_01 6 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01
Concluded By,
WALEED SHAFIK
Sr. Project Manager
WO # 58
10-603173-0000100201-MAH-QMN-RPT-000001_01 7 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 8 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01
Attachment 1
10-603173-0000100201-MAH-QMN-RPT-000001_01 9 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01
Attachment 2
10-603173-0000100201-MAH-QMN-RPT-000001_01 10 of 95
12/6/22, 9:55 AM Aconex
Bechtel Document Management Final (WF-071878) WO 058- Project Organization Chart -… 9:25 AM
BECHTEL KSA WORKFLOW TRANSMITTAL BEC-WTRAN-144675
10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia
Final (WF-071878) WO 058- Project Organization Chart -Spine Earthworks Lot 10-3-
CH75+500 to CH 78+000 (Coastal Desert Region)
Cc (2) NEOM Quality & Excellence Document Control - NEOM - Engineering & Technical Services Dept (+1 more...)
Status N/A
(0 selected)
Revision
File Document No Revision Title Status
Date
MESSAGE
The attached documents have completed the "WO 058- Project Organization Chart -Spine Earthworks Lot 10-3-CH75+500 to CH 78+000
(Coastal Desert Region)" workflow with the following results :
https://ksa1.aconex.com/hub/index.html 1/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 11 of 95
12/6/22, 9:55 AM Aconex
10-603173-0000100201-
EPM DCC B Document Management A - Work May Proceed
MAH-CPM-CRS-000001
10-603173-0000100201-
EPM DCC B Document Management A - Work May Proceed
MAH-CPM-OCH-000001
https://ksa1.aconex.com/hub/index.html 2/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 12 of 95
NEOM - 10 SPINE INFRASTRUCTURE
Work Order Title Spine Earthworks Lot 10-3 - CH75+500 to CH 78+000 (Coastal Desert
Region)
Revision No. 02
Date Nov-27-2022
10-603173-0000100201-MAH-QMN-RPT-000001_01
10-603173-0000100201-MAH-CPM-OCH-000001_02 13 of
Page 953
1 of
`
10-603173-0000100201-MAH-QMN-RPT-000001_01
10-603173-0000100201-MAH-CPM-OCH-000001_02 Page14 of 395
2 of
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. - 100201
Contract Name - Spine Earthworks Lot 10-3 - CH75+500 to CH
78+000 (Coastal Desert Region)
Project Organization Chart
Document History
10-603173-0000100201-MAH-QMN-RPT-000001_01
10-603173-0000100201-MAH-CPM-OCH-000001_02 15 of395
Page of 3
100201/WO 58- SPINE EARTHWORKS Lot 10-3 CH 75+500 to CH 78+000
(Coastal Desert Region)
Project Organizational Chart
Waleed Shafik
Sr. PROJECT MANAGER
0502366052
[email protected]
OSAMA ELBAHNASY
PROJECT MANAGER
0552020982
[email protected]
Romejun Macalolot
DOCUMENT CONTROLLER
0542583736
[email protected]
Bonjie Goloran
H&E SUPERVISOR Ibrahim Alhawiti
0555265092 ENVIRONMENTAL ENGR. Saqlain Khader Yusop Alid
[email protected] 0563378772 Montaser Kinanah Yasser Sayed PROJECT CONTROL ENGR. DC QUALITY CONTROL
SUPERINTENDENT (TBA) SUPERINTENDENT [email protected]
0500164763
[email protected]
0553811177 SUPERINTENDENT 0509240097
[email protected] [email protected]
Moatsem Ahmed
PROJECT NURSE FARES
0559297196 ENVIRONMENTAL OFFICER
0534309128
Shirajudeen Ashath
Omar hassan QC SUPERVISOR
Haris Abdul Rehman Bandar Alanzi Ahmed Elhasary Naif Ahmed Mohd Nadeem 0557209268
elzahrani Sultan Obedallah PROJECT ENGINEER PROJECT ENGINEER PROJECT ENGINEER [email protected]
ES&H ENGIEER PROJECT ENGINEER PROJECT ENGINEER
ES&H ENGIEER 506730045 0553544636 0554678055
0558084329
0503793053 0591413369
[email protected]
0535599577 [email protected] [email protected]
10-603173-0000100201-MAH-QMN-RPT-000001_01
10-603173-0000100201-MAH-CPM-OCH-000001_02 16 of 21
1 of 95
1st Submission 2nd Submission 3rd Submission 4th Submission 5th Submission
S.N. ACONEX DOCUMENT NO. DOCUMENT DESCRIPTION TYPE DISCIPLINE Comments Remarks
Date Date Date Date Date
Date Date Date Date Date Date Date Date Date Date Present
Rev. Submitted in Status Rev. Submitted Status Rev. Submitted Status Rev. Submitted Status Rev. Submitted Status
Received Respond Received Respond Received Respond Received Respond Received Respond Status
Aconex in Aconex in Aconex in Aconex in Aconex
MATERIAL APPROVAL
WO 058 - Spine Earthworks Lot 10-3 - CH75+500 to CH 78+000 (Coastal Desert
51 10-603173-0000100201-MAH-CIV-MAT-000001 Region) - Material Approval for Chain Link Fence by BRC Industrial Saudia Co. MAT CIV 01 26-Jul-22 26-Jul-22 X X F Cancelled
Fence Division
WO 058 - Materials Approval for Galvanized Heavy Duty Steel United Wire
52 10-603173-0000100201-MAH-CIV-MAT-000002 Factories Company (ASLAK ) Chain Link Fence -Spine Earthworks Lot 10-3 - MAT CIV 01 13-Aug-22 13-Aug-22 B 15-Aug-22 02 6-Feb-23 6-Feb-23 A 11-Mar-23 A A - Work May Proceed
CH75+500 to CH 78+000 (Coastal Desert Region)
WO 058- Material Approval for Concrete Mix Design C25 & C35 By (AL
53 10-603173-0000100201-MAH-CIV-MAT-000003 MUHAILIB BP) -Spine Earthworks Lot 10-3 - CH75+500 to CH 78+000 (Coastal MAT CIV 01 17-Aug-22 17-Aug-22 C 24-Aug-22 02 22-Dec-22 22-Dec-22 B 12-Jan-23 B Incorporate Comments - Proceed
Desert Region)
WO 058- Material Approval for Gabions By (BRC) -Spine Earthworks Lot 10-3 -
54 10-603173-0000100201-MAH-CIV-MAT-000004
CH75+500 to CH 78+000 (Coastal Desert Region)
MAT CIV 01 1-Nov-22 1-Nov-22 C 28-Nov-22 02 8-Jan-23 8-Jan-23 X X F Cancelled
WO 058- Material Approval for Concrete Double face New Jersey Barrier by
55 10-603173-0000100201-MAH-CIV-MAT-000005 (Alkhozama Contracting Co.) -Spine Earthworks Lot 10-3 - CH75+500 to CH MAT CIV 01 3-Nov-22 3-Nov-22 A 22-Nov-22 A A - Work May Proceed
78+000 (Coastal Desert Region)
WO 058- Material Approval for C25 SRC for Chain link Fence Foundation-Spine
56 10-603173-0000100201-MAH-CIV-MAT-000006
Earthworks Lot 10-3 -CH75+500 to CH 78+000 (Coastal Desert Region)
MAT CIV 01 26-Nov-22 26-Nov-22 A 19-Dec-22 A A - Work May Proceed
WO 58- Material Approval for Geotextile by (ALYAF) -Spine Earthworks Lot 10-3 -
57 10-603173-0000100201-MAH-CIV-MAT-000007
CH75+500 to CH 78+000 (Coastal Desert Region)
MAT CIV 01 19-Nov-22 30-Nov-22 C 10-Jan-23 02 2-May-23 2-May-23 A 22-May-23 A A - Work May Proceed
WO 58- Material Approval for SIKA DESIGN MIX for SHOTCRETE -Spine
58 10-603173-0000100201-MAH-CIV-MAT-000008
Earthworks Lot 10-3 -CH75+500 to CH 78+000 (Coastal Desert Region)
MAT CIV 01 3-Dec-22 3-Dec-22 C 29-Dec-22 C Revise and Resubmit - Do Not Proceed
WO 58- Materials Approval for Concrete Mix Design C35 + Micro Silica By (Abdul
59 10-603173-0000100201-MAH-CIV-MAT-000009 Abdin Concrete BP) for Concrete Slab -Spine Earthworks Lot 10-3 Ch 75+500 To MAT CIV 01 7-Dec-22 7-Dec-22 C 10-Jan-23 C Revise and Resubmit - Do Not Proceed
Ch 78+000 (Coastal Desert Region)
WO 58- Materials Approval for Aggregate Base Course for Access Road -Spine
60 10-603173-0000100201-MAH-CIV-MAT-000010
Earthworks Lot10-3 Ch 75+500 To Ch 78+000 (Coastal Desert Region)
MAT CIV 01 25-Jan-23 26-Jan-23 D 28-Feb-23 02 2-Mar-23 2-Mar-23 A 18-Mar-23 A A - Work May Proceed
WO 58- Materials Approval for Shotcrete Mix Design By (Abdullah Abdin) -Spine
61 10-603173-0000100201-MAH-CIV-MAT-000011
Earthworks Lot10-3 Ch 75+500 To Ch 78+000 (Coastal Desert Region)
MAT CIV 01 16-Feb-23 16-Feb-23 C 11-Apr-23 C Revise and Resubmit - Do Not Proceed
WO 58- Materials Approval for the Shotcrete Mix Design (MAPEI) By Al-Muhaylib
63 10-603173-0000100201-MAH-CIV-MAT-000013 Batch Plant -Spine Earthworks Lot 10-3 Ch 75+500 To Ch78+000 (Coastal Desert MAT CIV 01 5-Mar-23 5-Mar-23 C 26-Mar-23 C Revise and Resubmit - Do Not Proceed
Region)
WO 58- Materials Approval for Gabion Box & Mattress By UNITED WIRE
64 10-603173-0000100201-MAH-CIV-MAT-000014 FACTORIES COMPANY (ASLAK)-Spine Earthworks Lot 10-3 Ch 75+500 To MAT CIV 01 8-Mar-23 8-Mar-23 B 23-Mar-23 B Incorporate Comments - Proceed
Ch78+000 (Coastal Desert Region)
WO 58- Materials Approval for Gabion Box & Mattress By KHALEEJ DUBAI -
65 10-603173-0000100201-MAH-CIV-MAT-000015
Spine Earthworks Lot 10-3 Ch75+500 To Ch78+000 (Coastal Desert Region)
MAT CIV 01 1-Apr-23 1-Apr-23 A 16-Apr-23 A A - Work May Proceed
WO 58- Material approval for Gabion filling for Dike -Spine Earthworks Lot 10-3 -
66 10-603173-0000100201-MAH-CIV-MAT-000016
CH75+500 to CH78+000 (Coastal Desert Region)
MAT CIV 01 19-Apr-23 19-Apr-23 B 22-May-23 B Incorporate Comments - Proceed
10-603173-0000100201-MAH-QMN-RPT-000001_01 17 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01 Document No.:
Attachment 3
10-603173-0000100201-MAH-QMN-RPT-000001_01 18 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 19 of 95
Applicable
KPI No. KPI Description Index Criteria Remarks Weightage Earned Value Score
weightage
16 16 10.3 65%
Quality System Implementation (SI)
Contractor Internal Audit Contractor Internal Audit Measured as Compliance Audits Planned VS
Contractor’s Internal Audit as per 5 NA NA NA
KPI 8 Planned Performed Actual Audits done by contractor in reporting
Schedule/Plan month .
0 0
0 0
0 0
5 5 5.0 100%
Vendor Quality Management
Submitted (1),
The Procurement (Material) List provided Not submitted (0) 2 NA NA NA
Prior to starting the procurement activities
to NEOM for all the critical materials at Not applicable (NA)
KPI 14 Submitted = 100%, Not Submitted = 0
the time of the first PQD submittal (Cumulative measurement)
(Schedule Q, Appendix B2.1)
NA
10 0 0.0 0%
CONTRACT NAME SPINE EARTHWORKS LOT 10.3 CH 75+500 TO CH 78+000 REGION SPINE INFRASTRUCTURE
REPORTING PERIOD From: 1-Mar-23 To: 31-Mar-23 Kickoff meeting with ETSD (Y/N) Y
GRADING CRITERIA
Compliant: (85% to 100%) Need Improvement: (71% to 84%) Non-Compliant: (0% to 70%)
KPI 7 9 Field Testing (Required tests for the disciplines, for example, Trial Mix, Hydro Tests, Welding tests, Lab Testing etc) 100.0%
KPI 16 2 Conducted Final Inspection/FAT and issued the release certificate prior to shipment for C2 & C3 Materials and Equipment NA
VQM Document Submittals on time ( IAP, Vendor ITP, Inspection Reports, FAT, Inspection Release Certificate, Special
KPI 17 3 NA
Process Records, Weekly Reports, IDR)
VQM Performance Score (%) NA
Provide all Aconex reports to VQM team for review.
OVERALL PROJECT QUALITY INDEX 90%
REMARKS The overall PQI score for the month of March 2023 is 90%. The PQI is increased by 5%, the contractor needs to improve in KPIs 1, 2 and 5.
(Include any initiatives)
10-603173-0000100201-MAH-QMN-RPT-000001_01 21 of 95
Applicable
KPI No. KPI Description Index Criteria Remarks Weightage Earned Value Score
weightage
16 16 12.5 78%
Quality System Implementation (SI)
Contractor Internal Audit Contractor Internal Audit Measured as Compliance Audits Planned VS
Contractor’s Internal Audit as per 5 NA NA NA
KPI 8 Planned Performed Actual Audits done by contractor in reporting
Schedule/Plan month .
0 0
0 0
0 0
Planned Preservation
per Inspection Sch.
Preservation Performed Monthly Measurement - Preservation performed 5 NA NA NA
Materials & Equipment storage, handling & on equipment or material against planned
KPI 11
preservation per procedure inspection schedules for maintaining the Quality
0 0 of the material or equipment .
5 5 5.0 100%
Vendor Quality Management
Submitted (1),
The Procurement (Material) List provided Not submitted (0) 2 NA NA NA
Prior to starting the procurement activities
to NEOM for all the critical materials at the Not applicable (NA)
KPI 14 Submitted = 100%, Not Submitted = 0
time of the first PQD submittal (Schedule (Cumulative measurement)
Q, Appendix B2.1)
NA
10 0 0.0 0%
10-603173-0000100201-MAH-QMN-RPT-000001_01 22 of 95
Project Quality Index 2023 (PQI)
Project General Information
CONTRACT NAME 10 SPINE EARTHWORKS LOT 10.3 CH 75+500 TO CH 78+000 REGION Spine Infrastructure
REPORTING PERIOD From: 1-Feb-23 To: 28-Feb-23 Kickoff meeting with ETSD (Y/N) Y
GRADING CRITERIA
Compliant: (85% to 100%) Need Improvement: (71% to 84%) Non-Compliant: (0% to 70%)
KPI 7 9 Field Testing (Required tests for the disciplines, for example, Trial Mix, Hydro Tests, Welding tests, Lab Testing etc) 100.0%
KPI 16 2 Conducted Final Inspection/FAT and issued the release certificate prior to shipment for C2 & C3 Materials and Equipment NA
VQM Document Submittals on time ( IAP, Vendor ITP, Inspection Reports, FAT, Inspection Release Certificate, Special
KPI 17 3 NA
Process Records, Weekly Reports, IDR)
VQM Performance Score (%) NA
Provide all Aconex reports to VQM team for review.
OVERALL PROJECT QUALITY INDEX 85%
REMARKS The overall PQI score for the month of Feb-23 is 85%, decreased by 7 % from the previous month of Jan-2023.
(Include any initiatives) The contractor needs to improve in KPIs 1, 2, 5, 6 and 13 to achieve the target of 85%.
10-603173-0000100201-MAH-QMN-RPT-000001_01 23 of 95
Applicable
KPI No. KPI Description Index Criteria Remarks Weightage Earned Value Score
weightage
16 16 12.4 77%
Quality System Implementation (SI)
Contractor Internal Audit Contractor Internal Audit Measured as Compliance Audits Planned VS
Contractor’s Internal Audit as per 5 NA NA NA
KPI 8 Planned Performed Actual Audits done by contractor in reporting
Schedule/Plan month .
0 0
0 0
0 0
Planned Preservation
per Inspection Sch.
Preservation Performed Monthly Measurement - Preservation performed 5 NA NA NA
Materials & Equipment storage, handling & on equipment or material against planned
KPI 11
preservation per procedure inspection schedules for maintaining the Quality
0 0 of the material or equipment .
5 5 3.3 67%
Vendor Quality Management
Submitted (1),
The Procurement (Material) List provided Not submitted (0) 2 NA NA NA
Prior to starting the procurement activities
to NEOM for all the critical materials at the Not applicable (NA)
KPI 14 Submitted = 100%, Not Submitted = 0
time of the first PQD submittal (Schedule (Cumulative measurement)
Q, Appendix B2.1)
NA
10 0 0.0 0%
10-603173-0000100201-MAH-QMN-RPT-000001_01 24 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 25 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 26 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 27 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 28 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 29 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 30 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 31 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 32 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 33 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 34 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 35 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 36 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 37 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01 Document No.:
Attachment 4
10-603173-0000100201-MAH-QMN-RPT-000001_01 38 of 95
3/26/23, 10:55 AM Aconex
100201DCC MAH WO 58- Contractor Closure Report for Internal Quality A… YESTERDAY
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-005292
Bechtel Document Management Re: WO 58- Contractor Closure Report for Internal Qualit… 10:00 AM
BECHTEL KSA QA REJECTION BEC-QAR-000692
100201DCC MAH Re: WO 58- Contractor Closure Report for Internal Qualit… 10:55 AM
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-005297
Re: WO 58- Contractor Closure Report for Internal Quality Audit No.1 (Jan. 15,
2023) -Spine Earthworks Lot 10-3 - CH75+500 to CH 78+000 (Coastal Desert
Region)
Status N/A
DETAILS
Letter Initiator
Letter Addressee
(0 selected)
https://ksa1.aconex.com/hub/index.html 1/3
10-603173-0000100201-MAH-QMN-RPT-000001_01 39 of 95
3/26/23, 10:55 AM Aconex
Revision
File Document No Revision Title Status
Date
MESSAGE
Dear Sir,
Greetings,
Please see attached corrected file WO 58- Contractor Closure Report for Internal Quality Audit No.1 (Jan. 15, 2023) -Spine
Earthworks Lot 10-3 - CH75+500 to CH 78+000 (Coastal Desert Region)
Regard
Romejun
Please note that the document FOOTER number in page 1 is incorrect, should be 000002 instead of 000001.
Regards,
From: 1 MAH
Sent: 25/03/2023 6:32:33 PM AST (GMT +03:00)
To: Bechtel Document Management
Cc: NEOM Spine DC
Mail Number: MAH-TRANSMIT-005292
Subject: WO 58- Contractor Closure Report for Internal Quality Audit No.1 (Jan. 15, 2023) -Spine Earthworks Lot 10-3 - CH75+500 to CH 78+000
https://ksa1.aconex.com/hub/index.html 2/3
10-603173-0000100201-MAH-QMN-RPT-000001_01 40 of 95
1/17/23, 3:23 PM Aconex
100201DCC MAH WO 58- Contractor Internal Audit Report (Jan. 15, 2023) -… 3:23 PM
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-004421
WO 58- Contractor Internal Audit Report (Jan. 15, 2023) -Spine Earthworks Lot 10-3
- CH75+500 to CH 78+000 (Coastal Desert Region)
Status N/A
DETAILS
Letter Initiator
Letter Addressee
(0 selected)
https://ksa1.aconex.com/hub/index.html 1/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 41 of 95
1/17/23, 3:23 PM Aconex
Revision
File Document No Revision Title Status
Date
MESSAGE
Dear Sir,
Greetings,
Please see attached file WO 58- Contractor Internal Audit Report (Jan. 15, 2023) -Spine Earthworks Lot 10-3 - CH75+500 to
CH 78+000 (Coastal Desert Region)
Regards
Romejun
https://ksa1.aconex.com/hub/index.html 2/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 42 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01 Document No.:
Attachment 5
10-603173-0000100201-MAH-QMN-RPT-000001_01 43 of 95
5/31/23, 6:09 PM Aconex
100201DCC MAH WO 058- Monthly Quality Management Report No. 010 (… 6:09 PM
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-006020
WO 058- Monthly Quality Management Report No. 010 (May 2023) -Spine
Earthworks Lot 10-3 (CH 75+500 to CH 78+000) Coastal Desert Region
Status N/A
DETAILS
Letter Initiator
Letter Addressee
(0 selected)
https://ksa1.aconex.com/hub/index.html 1/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 44 of 95
5/31/23, 6:09 PM Aconex
Revision
File Document No Revision Title Status
Date
MESSAGE
Dear Sir,
Greetings,
Please see attached file WO 058- Monthly Quality Management Report No. 010 (May 2023) -Spine Earthworks Lot 10-3 (CH
75+500 to CH 78+000) Coastal Desert Region
Regards
Romejun
https://ksa1.aconex.com/hub/index.html 2/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 45 of 95
5/3/23, 3:12 PM Aconex
100201DCC MAH WO 058- Monthly Quality Management Report No. 009 (A… 3:11 PM
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-005731
WO 058- Monthly Quality Management Report No. 009 (Apr 2023) -Spine
Earthworks Lot 10-3 (CH 75+500 to CH 78+000) Coastal Desert Region
Status N/A
DETAILS
Letter Initiator
Letter Addressee
(0 selected)
https://ksa1.aconex.com/hub/index.html 1/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 46 of 95
5/3/23, 3:12 PM Aconex
Revision
File Document No Revision Title Status
Date
MESSAGE
Dear Sir,
Greetings,
Please see attached file WO 058- Monthly Quality Management Report No. 009 (Apr 2023) -Spine Earthworks Lot 10-3 (CH
75+500 to CH 78+000) Coastal Desert Region
Regards
Romejun
https://ksa1.aconex.com/hub/index.html 2/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 47 of 95
4/1/23, 8:01 PM Aconex
100201DCC MAH WO 058- Monthly Quality Management Report No. 008 (… 8:01 PM
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-005413
WO 058- Monthly Quality Management Report No. 008 (Mar. 2023) -Spine
Earthworks Lot 10-3 (CH 75+500 to CH 78+000) Coastal Desert Region
Status N/A
DETAILS
Letter Initiator
Letter Addressee
(0 selected)
https://ksa1.aconex.com/hub/index.html 1/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 48 of 95
4/1/23, 8:01 PM Aconex
Revision
File Document No Revision Title Status
Date
MESSAGE
Dear Sir,
Greetings,
Please see attached file WO 058- Monthly Quality Management Report No. 008 (Mar. 2023) -Spine Earthworks Lot 10-3 (CH
75+500 to CH 78+000) Coastal Desert Region
Regards
Romejun
https://ksa1.aconex.com/hub/index.html 2/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 49 of 95
10-603173-0000100201-MAH-QMN-RPT-000001_01 50 of 95
Applicable
KPI No. KPI Description Index Criteria Remarks Weightage Earned Value Score
weightage
16 16 10.3 65%
Quality System Implementation (SI)
Contractor Internal Audit Contractor Internal Audit Measured as Compliance Audits Planned VS
Contractor’s Internal Audit as per 5 NA NA NA
KPI 8 Planned Performed Actual Audits done by contractor in reporting
Schedule/Plan month .
0 0
0 0
0 0
5 5 5.0 100%
Vendor Quality Management
Submitted (1),
The Procurement (Material) List provided Not submitted (0) 2 NA NA NA
Prior to starting the procurement activities
to NEOM for all the critical materials at Not applicable (NA)
KPI 14 Submitted = 100%, Not Submitted = 0
the time of the first PQD submittal (Cumulative measurement)
(Schedule Q, Appendix B2.1)
NA
10 0 0.0 0%
CONTRACT NAME SPINE EARTHWORKS LOT 10.3 CH 75+500 TO CH 78+000 REGION SPINE INFRASTRUCTURE
REPORTING PERIOD From: 1-Mar-23 To: 31-Mar-23 Kickoff meeting with ETSD (Y/N) Y
GRADING CRITERIA
Compliant: (85% to 100%) Need Improvement: (71% to 84%) Non-Compliant: (0% to 70%)
KPI 7 9 Field Testing (Required tests for the disciplines, for example, Trial Mix, Hydro Tests, Welding tests, Lab Testing etc) 100.0%
KPI 16 2 Conducted Final Inspection/FAT and issued the release certificate prior to shipment for C2 & C3 Materials and Equipment NA
VQM Document Submittals on time ( IAP, Vendor ITP, Inspection Reports, FAT, Inspection Release Certificate, Special
KPI 17 3 NA
Process Records, Weekly Reports, IDR)
VQM Performance Score (%) NA
Provide all Aconex reports to VQM team for review.
OVERALL PROJECT QUALITY INDEX 90%
REMARKS The overall PQI score for the month of March 2023 is 90%. The PQI is increased by 5%, the contractor needs to improve in KPIs 1, 2 and 5.
(Include any initiatives)
10-603173-0000100201-MAH-QMN-RPT-000001_01 52 of 95
Applicable
KPI No. KPI Description Index Criteria Remarks Weightage Earned Value Score
weightage
16 16 12.5 78%
Quality System Implementation (SI)
Contractor Internal Audit Contractor Internal Audit Measured as Compliance Audits Planned VS
Contractor’s Internal Audit as per 5 NA NA NA
KPI 8 Planned Performed Actual Audits done by contractor in reporting
Schedule/Plan month .
0 0
0 0
0 0
Planned Preservation
per Inspection Sch.
Preservation Performed Monthly Measurement - Preservation performed 5 NA NA NA
Materials & Equipment storage, handling & on equipment or material against planned
KPI 11
preservation per procedure inspection schedules for maintaining the Quality
0 0 of the material or equipment .
5 5 5.0 100%
Vendor Quality Management
Submitted (1),
The Procurement (Material) List provided Not submitted (0) 2 NA NA NA
Prior to starting the procurement activities
to NEOM for all the critical materials at the Not applicable (NA)
KPI 14 Submitted = 100%, Not Submitted = 0
time of the first PQD submittal (Schedule (Cumulative measurement)
Q, Appendix B2.1)
NA
10 0 0.0 0%
10-603173-0000100201-MAH-QMN-RPT-000001_01 53 of 95
Project Quality Index 2023 (PQI)
Project General Information
CONTRACT NAME 10 SPINE EARTHWORKS LOT 10.3 CH 75+500 TO CH 78+000 REGION Spine Infrastructure
REPORTING PERIOD From: 1-Feb-23 To: 28-Feb-23 Kickoff meeting with ETSD (Y/N) Y
GRADING CRITERIA
Compliant: (85% to 100%) Need Improvement: (71% to 84%) Non-Compliant: (0% to 70%)
KPI 7 9 Field Testing (Required tests for the disciplines, for example, Trial Mix, Hydro Tests, Welding tests, Lab Testing etc) 100.0%
KPI 16 2 Conducted Final Inspection/FAT and issued the release certificate prior to shipment for C2 & C3 Materials and Equipment NA
VQM Document Submittals on time ( IAP, Vendor ITP, Inspection Reports, FAT, Inspection Release Certificate, Special
KPI 17 3 NA
Process Records, Weekly Reports, IDR)
VQM Performance Score (%) NA
Provide all Aconex reports to VQM team for review.
OVERALL PROJECT QUALITY INDEX 85%
REMARKS The overall PQI score for the month of Feb-23 is 85%, decreased by 7 % from the previous month of Jan-2023.
(Include any initiatives) The contractor needs to improve in KPIs 1, 2, 5, 6 and 13 to achieve the target of 85%.
10-603173-0000100201-MAH-QMN-RPT-000001_01 54 of 95
Applicable
KPI No. KPI Description Index Criteria Remarks Weightage Earned Value Score
weightage
16 16 12.4 77%
Quality System Implementation (SI)
Contractor Internal Audit Contractor Internal Audit Measured as Compliance Audits Planned VS
Contractor’s Internal Audit as per 5 NA NA NA
KPI 8 Planned Performed Actual Audits done by contractor in reporting
Schedule/Plan month .
0 0
0 0
0 0
Planned Preservation
per Inspection Sch.
Preservation Performed Monthly Measurement - Preservation performed 5 NA NA NA
Materials & Equipment storage, handling & on equipment or material against planned
KPI 11
preservation per procedure inspection schedules for maintaining the Quality
0 0 of the material or equipment .
5 5 3.3 67%
Vendor Quality Management
Submitted (1),
The Procurement (Material) List provided Not submitted (0) 2 NA NA NA
Prior to starting the procurement activities
to NEOM for all the critical materials at the Not applicable (NA)
KPI 14 Submitted = 100%, Not Submitted = 0
time of the first PQD submittal (Schedule (Cumulative measurement)
Q, Appendix B2.1)
NA
10 0 0.0 0%
10-603173-0000100201-MAH-QMN-RPT-000001_01 55 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01 Document No.:
Attachment 6
10-603173-0000100201-MAH-QMN-RPT-000001_01 56 of 95
NAME OF PROJECT : SPINE EARTHWORKS Lot 10-3 CH 75+500 to CH 78+000 (Coastal Desert West Region)
CONTRACT NO. : 100201/58
CONTRACTOR : MOFARREH ALHARBI & PARTNERS (MAH)
TITLE : NON CONFORMANCE REGISTER
DATE UPDATED : 15-May-2023
NCR No. Desciption Revision Reference Location Date Issued Closed Date Status Remarks/Comments
10-603173-0000100201-MAH-QMN-RPT-000001_01 57 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01 Document No.:
Attachment 7
10-603173-0000100201-MAH-QMN-RPT-000001_01 58 of 95
NAME OF PROJECT : SPINE EARTHWORKS Lot 10-3 CH 75+500 to CH 78+000 (Coastal Desert West Region)
CONTRACT NO. : 100201/058
CONTRACTOR : MOFARREH ALHARBI & PARTNERS (MAH)INSPECTION, MEASURING AND TEST
TITLE : EQUIPMENT LOG
DATE UPDATE : 25-May-2023
1 GPS Receiver RE-5114 1491-11982 4030192824 09-Mar-23 09-Sep-23 ZAN MODERN CO. HYPER VR
2 GPS Receiver RE-5115 1491-11981 4030192824 09-Mar-23 09-Sep-23 ZAN MODERN CO. HYPER VR
10-603173-0000100201-MAH-QMN-RPT-000001_01 59 of 95
10-603173-0000100201-MAH-QMR-000011
10-603173-0000100201-MAH-QMN-RPT-000001_01 Page6036ofof95
53
10-603173-0000100201-MAH-QMR-000011
10-603173-0000100201-MAH-QMN-RPT-000001_01 Page6137ofof95
53
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01 Document No.:
Attachment 8
6. Audit Results
10-603173-0000100201-MAH-QMN-RPT-000001_01 62 of 95
3/26/23, 10:55 AM Aconex
100201DCC MAH WO 58- Contractor Closure Report for Internal Quality A… YESTERDAY
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-005292
Bechtel Document Management Re: WO 58- Contractor Closure Report for Internal Qualit… 10:00 AM
BECHTEL KSA QA REJECTION BEC-QAR-000692
100201DCC MAH Re: WO 58- Contractor Closure Report for Internal Qualit… 10:55 AM
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-005297
Re: WO 58- Contractor Closure Report for Internal Quality Audit No.1 (Jan. 15,
2023) -Spine Earthworks Lot 10-3 - CH75+500 to CH 78+000 (Coastal Desert
Region)
Status N/A
DETAILS
Letter Initiator
Letter Addressee
(0 selected)
https://ksa1.aconex.com/hub/index.html 1/3
10-603173-0000100201-MAH-QMN-RPT-000001_01 63 of 95
3/26/23, 10:55 AM Aconex
Revision
File Document No Revision Title Status
Date
MESSAGE
Dear Sir,
Greetings,
Please see attached corrected file WO 58- Contractor Closure Report for Internal Quality Audit No.1 (Jan. 15, 2023) -Spine
Earthworks Lot 10-3 - CH75+500 to CH 78+000 (Coastal Desert Region)
Regard
Romejun
Please note that the document FOOTER number in page 1 is incorrect, should be 000002 instead of 000001.
Regards,
From: 1 MAH
Sent: 25/03/2023 6:32:33 PM AST (GMT +03:00)
To: Bechtel Document Management
Cc: NEOM Spine DC
Mail Number: MAH-TRANSMIT-005292
Subject: WO 58- Contractor Closure Report for Internal Quality Audit No.1 (Jan. 15, 2023) -Spine Earthworks Lot 10-3 - CH75+500 to CH 78+000
https://ksa1.aconex.com/hub/index.html 2/3
10-603173-0000100201-MAH-QMN-RPT-000001_01 64 of 95
1/17/23, 3:23 PM Aconex
100201DCC MAH WO 58- Contractor Internal Audit Report (Jan. 15, 2023) -… 3:23 PM
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-004421
WO 58- Contractor Internal Audit Report (Jan. 15, 2023) -Spine Earthworks Lot 10-3
- CH75+500 to CH 78+000 (Coastal Desert Region)
Status N/A
DETAILS
Letter Initiator
Letter Addressee
(0 selected)
https://ksa1.aconex.com/hub/index.html 1/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 65 of 95
1/17/23, 3:23 PM Aconex
Revision
File Document No Revision Title Status
Date
MESSAGE
Dear Sir,
Greetings,
Please see attached file WO 58- Contractor Internal Audit Report (Jan. 15, 2023) -Spine Earthworks Lot 10-3 - CH75+500 to
CH 78+000 (Coastal Desert Region)
Regards
Romejun
https://ksa1.aconex.com/hub/index.html 2/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 66 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01 Document No.:
Attachment 9
10-603173-0000100201-MAH-QMN-RPT-000001_01 67 of 95
1st Submission 2nd Submission 3rd Submission 4th Submission 5th Submission
S.N. ACONEX DOCUMENT NO. DOCUMENT DESCRIPTION TYPE DISCIPLINE Comments Remarks
Date Date Date Date Date
Date Date Date Date Date Date Date Date Date Date Present
Rev. Submitted in Status Rev. Submitted Status Rev. Submitted Status Rev. Submitted Status Rev. Submitted Status
Received Respond Received Respond Received Respond Received Respond Received Respond Status
Aconex in Aconex in Aconex in Aconex in Aconex
D. PREQUALIFICATION
WO 058 - Spine Earthworks Lot 10-3 - CH75+500 to CH 78+000 (Coastal Desert
36 10-603173-0000100201-MAH-CIV-PQD-000001 Region) - SUB-CONTRACTOR PRE-QUALIFICATION APPROVAL FOR IGMT PQD CIV 01 24-Jul-22 24-Jul-22 C 5-Sep-22 02 3-Oct-22 3-Oct-22 B 6-Dec-22 03 14-Dec-22 14-Dec-22 A 1-Jan-23 A A - Work May Proceed
(THIRD PARTY LABORATORY & TESTING)
10-603173-0000100201-MAH-QMN-RPT-000001_01 68 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01 Document No.:
Attachment 10
10-603173-0000100201-MAH-QMN-RPT-000001_01 69 of 95
12/4/22, 7:05 PM Aconex
Bechtel Document Management Final (WF-071674) WO 058 - Spine Earthworks Lot 10-3 -… 4:35 PM
BECHTEL KSA WORKFLOW TRANSMITTAL BEC-WTRAN-143789
10 Spine Infrastructure
Spine Infrastructure
NEOM
Saudi Arabia
Cc (2) NEOM Quality & Excellence Document Control - NEOM - Engineering & Technical Services Dept (+1 more...)
Status N/A
(0 selected)
Revision
File Document No Revision Title Status
Date
A-
WO 058 - Spine Earthworks Lot 10-3 - CH75+500 to
10-603173-0000100201- Work
04 26/11/2022 CH 78+000 (Coastal Desert Region) - Site Offices
MAH-CON-CRS-000001 May
Layout Plan_CRS
Proceed
A-
WO 058 - Spine Earthworks Lot 10-3 - CH75+500 to
10-603173-0000100201- Work
04 26/11/2022 CH 78+000 (Coastal Desert Region) - Site Offices
MAH-CON-SHD-000001 May
Layout Plan
Proceed
A-
10-603173-0000100201- WO 058 - Spine Earthworks Lot 10-3 - CH75+500 to
Work
MAH-CON-SHD- 04 26/11/2022 CH 78+000 (Coastal Desert Region) - Site Offices
May
000001_DWG Layout Plan
Proceed
MESSAGE
https://ksa1.aconex.com/hub/index.html 1/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 70 of 95
12/4/22, 7:05 PM Aconex
The attached documents have completed the "WO 058 - Spine Earthworks Lot 10-3 - CH75+500 to CH 78+000 (Coastal Desert Region) - Site
Offices Layout Plan" workflow with the following results :
10-603173-0000100201-
EPM DCC B Document Management A - Work May Proceed
MAH-CON-SHD-000001
10-603173-0000100201-
MAH-CON-SHD- EPM DCC B Document Management A - Work May Proceed
000001_DWG
10-603173-0000100201-
EPM DCC B Document Management A - Work May Proceed
MAH-CON-CRS-000001
https://ksa1.aconex.com/hub/index.html 2/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 71 of 95
660
N
GENERAL KEY
1+6
PLAN:
QIBLA
80
R S
RIE
BAR
1+7
SEY
JER
R S
RIE
AR
00
YB
SE
JER
1+7
20
0
1+74
IERS
EY BARR RIE
RS
0
JERS BAR
EY
1+76
ERS
IERS
J
E 730642.528
1+780
R
BAR
Generator setting up location.
N 3109668.954
JERS
shared with Lot 10.2,
SEY
1+800
EY B
JER
1+820
4
582.37
A
3 0
RRIE
Lighting poles. E 7 60
9662.6
N 310
RS
Exit KIT
Entra FL-06
nce
JERS
GATE SPILL
FL-07
EY B
ARR
POIN
ASSE T
4.00
MBLY
UE
MOSQ
IERS
3.00
12.00
4.00 KIT
Point
BLY
ASSEM
Fire
Ketchen
12.00
BOX
TOOL
NG
MEETI
.476
D
GUAR
E 730500
E
HOUS
Project fice
Of
12.00
2.550
Manage
Cup Boa
N 310964
int
Fire Po
r
ASTE
rd
WALK
RAL W
WAY
GENE SKIP
PEDE
Secretary
STRIA
N
Cup Boa
FL-10 ( CLIE
FENCE
Room
LINE
rd
PARK
PARKIN NT )
G ARE
A
Cup Boa
Printer
rd
ING A
3.50
FL-01
4.10
1.50
10.00
Induct
P
14.8
3.00 0
TO
REA
FIC
ion roo
EN
OF t 1.80
TR
9.59
SS
ile en
To ch
1.39
AN
Ket
1.50 STAG
m
CE
IT
EX e E
BU
Stor
3.50 CE
ENTRAN SAFE
TY
4.10
t
ile
To
int
EXIT
E E
( CLIE
FIC FIC
OF OF
o
OFFIC
E
eP
t
ile
To
PARK
AMBU
ING OFFIC E
OFFIC
Fir
3.50 LANCE
OM E ARE
3.00
RO Toilet
G
TIN IT
1.50 MEE EX
E) A
6.00
NT
EN
Toilet
TR
FIC
AN
-11
CE
4.80
MEETIN
3.00
FL OF 14.8
0
FL-08
OFFIC
NT Store
G ROO
1.50
LIE
M
3.00
(C 3.50 Ketchen
int
3.60
o
Toilet
EA
AR ING
OK
eP
SM
E)
3.00
1.29
8.65 Toilet
No. Description
Fir
OFFIC
3.75 E
3.00
04 ETW 26-11-2022
OFFIC
E 04A-MOBILIZATION & CONSTRUCTION
3.60 03 04A-MOBILIZATION & CONSTRUCTION ETW 21-11-2022
02 ETW
EXIT
3.00
WATER
1.29
8.65
ENTRAN 01 04A-MOBILIZATION & CONSTRUCTION ETW 30-07-2022
3.75 CE
E)
3.00
TANK
FIC Store OFFIC PURPOSE OF ISSUE: FOR APPROVAL
OF 3.60 Ketchen Toilet
E
1.29
(M 8.65 Toilet
ENTR
3.75 OFFIC
AN
3.00 E EXIT
CE
-12 Toilet
12.00
OFFIC
FL IC
CLIN E
3.60
6.00
Toilet
ENTR
EXIT
1.29
3.00
OFFIC
ANCE
E EXIT
8.65
ENTRAN
EXIT Toilet E
EA G
AROKIN
SM
( MAH
OFFIC
CE
FL-02
DESIGN CONSULTANT NAME & LOGO (s): CONTRACTOR NAME & LOGO (s):
Toilet
OFFIC
E
E)
WA
TE
RT ( MAH
AN
OFFIC
K
LUP
SEPT FL-03
IC TA
NK CA
PACITY Riyadh 11414, Kingdom of Saudi Arabia
3)
(20 m MOFARREH ALHARBI & PARTNERS
DESIGN CONSULTANT / CONTRACTOR: NEOM'S REVIEW:
-13
FL DRAWN: SAE 26-11-2022
E 730655
MAH 26-11-2022
FL-04 APPROVED: ETW 26-11-2022 APPROVED:
3.165
N 310960
SCALE: AS SHOWN SHEET SIZE: A1
DISCIPLINE NAME: CONSTRUCTION
0000100201/58-Spine Earthworks Lot 10-3 CH
75+000 To 78+000
Site Office Location
Lighting poles.
PROJECT NAME:
.021
E 730596 SPINE EARTHWORKS LOT 10-3 CH 75+000 TO 78+000
Attachment 11
10-603173-0000100201-MAH-QMN-RPT-000001_01 73 of 95
5/12/23, 4:01 PM Aconex
100201DCC MAH WO 058 - Two Weeks Inspection Look Ahead No.40 (May… 4:01 PM
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-005821
WO 058 - Two Weeks Inspection Look Ahead No.40 (May 13 - May 19, 2023) -Spine
Earthworks Lot 10-3 - Ch75+500 To Ch 78+000 (Coastal Desert Region)
Status N/A
DETAILS
Letter Initiator
Letter Addressee
(0 selected)
Revision
File Document No Revision Title Status
Date
https://ksa1.aconex.com/hub/index.html 1/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 74 of 95
5/12/23, 4:01 PM Aconex
Revision
File Document No Revision Title Status
Date
MESSAGE
Dear Sir,
Greetings,
Please see attached file WO 058 - Two Weeks Inspection Look Ahead No.40 (May 13 - May 19, 2023) -Spine Earthworks Lot
10-3 - Ch75+500 To Ch 78+000 (Coastal Desert Region)
Regards
Romejun
https://ksa1.aconex.com/hub/index.html 2/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 75 of 95
TWO WEEKS INSPECTION LOOK AHEAD
Project: Spine Earthworks Lot 10-3 CH 75+500 to CH 78+000 (Coastal Desert West Region) Reference No: MAH-TWLA-040
CONTRACTOR: MOFARREH ALHARBI & PARTNERS Contract No: 100201 / 58 Date Submitted: May 11, 2023
For the Period of May 13, 2023 to May 26, 2023
No Activity Description Location Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri
13 14 15 16 17 18 19 20 21 22 23 24 25 26
√ √ √ √ √ √ √ √ √ √ √ √
1 Weak rock excavation (Zone 1, 2, 3, 4 & 5) Site Work
Backfilling and Compaction of Aggregate Base-Course at Temporary Access Road Site Work
√ √ √ √ √ √ √ √ √ √ √ √
4 01,02,03,05
Backfilling and Compaction of Fill Material for the Dike Construction Site Work
√ √ √ √ √ √ √ √ √ √ √ √
5
Legend:
√ - Planned Activity
- Holiday
10-603173-0000100201-MAH-QMN-SCD-000040_01
10-603173-0000100201-MAH-QMN-RPT-000001_01 761ofof95
1
5/5/23, 11:19 AM Aconex
100201DCC MAH WO 058 - Two Weeks Inspection Look Ahead No.39 (May… 11:19 AM
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-005748
WO 058 - Two Weeks Inspection Look Ahead No.39 (May 06 - May 19, 2023) -Spine
Earthworks Lot 10-3 - Ch75+500 To Ch 78+000 (Coastal Desert Region)
Status N/A
DETAILS
Letter Initiator
Letter Addressee
(0 selected)
Revision
File Document No Revision Title Status
Date
https://ksa1.aconex.com/hub/index.html 1/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 77 of 95
5/5/23, 11:19 AM Aconex
Revision
File Document No Revision Title Status
Date
MESSAGE
Dear Sir,
Greetings,
Please see attached file WO 058 - Two Weeks Inspection Look Ahead No.39 (May 06 - May 19, 2023) -Spine Earthworks Lot
10-3 - Ch75+500 To Ch 78+000 (Coastal Desert Region)
Regards
Romejun
https://ksa1.aconex.com/hub/index.html 2/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 78 of 95
TWO WEEKS INSPECTION LOOK AHEAD
Project: Spine Earthworks Lot 10-3 CH 75+500 to CH 78+000 (Coastal Desert West Region) Reference No: MAH-TWLA-039
CONTRACTOR: MOFARREH ALHARBI & PARTNERS Contract No: 100201 / 58 Date Submitted: May 04, 2023
For the Period of May 06, 2023 to May 19, 2023
No Activity Description Location Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri
06 07 08 09 10 11 12 13 14 15 16 17 18 19
√ √ √ √ √ √ √ √ √ √ √ √
1 Weak rock excavation (Zone 1, 2, 3, 4 & 5) Site Work
3 Backfilling and Compaction of Aggregate Base-Course at Temporary Access Road Site Work
√ √ √ √ √ √ √ √ √ √ √ √
01,02,03,05
4 Backfilling and Compaction of Fill Material for the Dike Construction Site Work
√ √ √ √ √ √ √ √ √ √ √ √
Legend:
√ - Planned Activity
- Holiday
10-603173-0000100201-MAH-QMN-SCD-000039_01
10-603173-0000100201-MAH-QMN-RPT-000001_01 791ofof95
1
4/27/23, 11:03 AM Aconex
100201DCC MAH WO 058 - Two Weeks Inspection Look Ahead No.38 (Apr.… 11:00 AM
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-005658
WO 058 - Two Weeks Inspection Look Ahead No.38 (Apr. 29 - May 12, 2023) -Spine
Earthworks Lot 10-3 - Ch75+500 To Ch 78+000 (Coastal Desert Region)
Status N/A
DETAILS
Letter Initiator
Letter Addressee
(0 selected)
Revision
File Document No Revision Title Status
Date
https://ksa1.aconex.com/hub/index.html 1/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 80 of 95
4/27/23, 11:03 AM Aconex
Revision
File Document No Revision Title Status
Date
MESSAGE
Dear Sir,
Greetings,
Please see attached file WO 058 - Two Weeks Inspection Look Ahead No.38 (Apr. 29 - May 12, 2023) -Spine Earthworks Lot
10-3 - Ch75+500 To Ch 78+000 (Coastal Desert Region)
Regards
Romejun
https://ksa1.aconex.com/hub/index.html 2/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 81 of 95
TWO WEEKS INSPECTION LOOK AHEAD
Project: Spine Earthworks Lot 10-3 CH 75+500 to CH 78+000 (Coastal Desert West Region) Reference No: MAH-TWLA-038
CONTRACTOR: MOFARREH ALHARBI & PARTNERS Contract No: 100201 / 58 Date Submitted: Apr 29, 2023
For the Period of Apr 29, 2023 to May 12, 2023
No Activity Description Location Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri
29 30 01 02 03 04 05 06 07 08 09 10 11 12
√ √ √ √ √ √ √ √ √ √ √ √
1 Weak rock excavation (Zone 1, 2, 3, 4 & 5) Site Work
√ √ √ √ √ √ √ √ √ √ √ √
2 Material Receiving, Concrete Pouring and Installation for Chain Link Site Work
4 Backfilling and Compaction of Aggregate Base-Course at Temporary Access Road Site Work
√ √ √ √ √ √ √ √ √ √ √ √
01,02,03,05
Legend:
√ - Planned Activity
- Holiday
10-603173-0000100201-MAH-QMN-SCD-000038_01
10-603173-0000100201-MAH-QMN-RPT-000001_01 821ofof95
1
1st Submission 2nd Submission 3rd Submission 4th Submission 5th Submission
S.N. ACONEX DOCUMENT NO. DOCUMENT DESCRIPTION TYPE DISCIPLINE Comments Remarks
Date Date Date Date Date
Date Date Date Date Date Date Date Date Date Date Present
Rev. Submitted in Status Rev. Submitted Status Rev. Submitted Status Rev. Submitted Status Rev. Submitted Status
Received Respond Received Respond Received Respond Received Respond Received Respond Status
Aconex in Aconex in Aconex in Aconex in Aconex
C. METHOD STATEMENT
WO 058 - Spine Earthworks Lot 10-3 - CH75+500 to CH 78+000 (Coastal Desert
18 10-603173-0000100201-MAH-SRV-MST-000001
Region) - Method Statement for Surveying Works
MS SRV 01 24-Jul-22 24-Jul-22 A 11-Aug-22 A A - Work May Proceed
WO 058- Method Statement for Clearing, Grubbing & Stripping -Spine Earthworks
22 10-603173-0000100201-MAH-CIV-MST-000004
Lot 10-3 - CH75+500 to CH78+000 (Coastal Desert Region)
MS CIV 01 15-Aug-22 15-Aug-22 B 4-Sep-22 02 27-Nov-22 27-Nov-22 A 15-Dec-22 A A - Work May Proceed
WO 58- Method Statement for Stockpile Management Plan -Spine Earthworks Lot
24 10-603173-0000100201-MAH-CIV-MST-000006
10-3 Ch 75+500 To Ch 78+000 (Coastal Desert Region)
MS CIV 01 24-Aug-22 24-Aug-22 B 25-Aug-22 02 13-Dec-22 13-Dec-22 B 19-Dec-22 03 3-Jan-23 3-Jan-23 B 7-Jan-23 04 16-Jan-23 16-Jan-23 B 11-Feb-23 05 15-Feb-23 15-Feb-23 A 21-Mar-23 A A - Work May Proceed
WO 58- Method Statement for Rock Cutting & Excavations Work -Spine
25 10-603173-0000100201-MAH-CIV-MST-000007
Earthworks Lot 10-3 - CH75+500 to CH78+000 (Coastal Desert Region)
MS CIV 01 28-Sep-22 28-Sep-22 B 12-Nov-22 02 3-Jan-23 3-Jan-23 A 7-Jan-23 A A - Work May Proceed
WO 58- Method Statement for Hauling & Disposal of Excavated Waste Materials -
26 10-603173-0000100201-MAH-CIV-MST-000008
Spine Earthworks Lot 10-3 - CH75+500 to CH78+000 (Coastal Desert Region)
MS CIV 01 29-Sep-22 29-Sep-22 B 12-Nov-22 02 8-Jan-23 8-Jan-23 A 17-Jan-23 A A - Work May Proceed
WO 58- Method Statement for Drilling & Blasting Works -Spine Earthworks Lot 10-
27 10-603173-0000100201-MAH-CIV-MST-000009
3 - CH75+500 to CH78+000 (Coastal Desert Region)
MS CIV 01 3-Oct-22 3-Oct-22 B 1-Nov-22 02 24-Dec-22 24-Dec-22 C 1-Apr-23 03 9-Apr-23 9-Apr-23 B 11-May-23 B Incorporate Comments - Proceed
WO 58- Method Statement for Shotcrete Works -Spine Earthworks Lot 10-3 -
32 10-603173-0000100201-MAH-CIV-MST-000014
CH75+500 to CH78+000 (Coastal Desert Region)
MS CIV 01 15-Feb-23 15-Feb-23 B 22-Mar-23 B Incorporate Comments - Proceed
WO 58- Method Statement for Installation of Geotextile -Spine Earthworks Lot 10-
34 10-603173-0000100201-MAH-CIV-MST-000016
3 - CH75+500 to CH78+000 (Coastal Desert Region)
MS CIV 01 5-Apr-23 5-Apr-23 A 11-May-23 A A - Work May Proceed
10-603173-0000100201-MAH-QMN-RPT-000001_01 83 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01 Document No.:
Attachment 12
10-603173-0000100201-MAH-QMN-RPT-000001_01 84 of 95
12/21/22, 9:04 AM Aconex
Status N/A
DETAILS
Letter Initiator
Letter Addressee
(0 selected)
https://ksa1.aconex.com/hub/index.html 1/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 85 of 95
12/21/22, 9:04 AM Aconex
Revision
File Document No Revision Title Status
Date
MESSAGE
Dear Sir,
Greetings,
Please see attached file WO 58- Quality Personnel Training (WIR Preparation)-Spine Earthworks Lot 10-3-Ch75+500 To Ch
78+000 (Coastal desert Region)
Regards
Romejun
https://ksa1.aconex.com/hub/index.html 2/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 86 of 95
2/15/23, 10:50 AM Aconex
100201DCC MAH WO 58- Quality Toolbox meeting No.003 (ITP for Aggrega… 10:49 AM
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-004799
WO 58- Quality Toolbox meeting No.003 (ITP for Aggregate Base-course) -Spine
Earthworks Lot10-3-CH75+500 to CH 78+000 (Coastal Desert Region)
Status N/A
DETAILS
Letter Initiator
Letter Addressee
(0 selected)
Revision
File Document No Revision Title Status
Date
10-603173- 01 14/02/2023 WO 58- Quality Toolbox meeting No.003 (ITP for For
0000100201-MAH- Aggregate Base-course) -Spine Earthworks Lot10- Information
QMN-MOM-000003
https://ksa1.aconex.com/hub/index.html 1/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 87 of 95
2/15/23, 10:50 AM Aconex
Revision
File Document No Revision Title Status
Date
MESSAGE
Dear Sir,
Greetings,
Please see attached file WO 58- Quality Toolbox meeting No.003 (ITP for Aggregate Base-course) -Spine Earthworks Lot10-
3-CH75+500 to CH 78+000 (Coastal Desert Region)
Regards
Romejun
https://ksa1.aconex.com/hub/index.html 2/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 88 of 95
1/12/23, 2:27 PM Aconex
100201DCC MAH WO 58- Quality Toolbox meeting No.001 & 002 2:26 PM
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-004366
Status N/A
DETAILS
Letter Initiator
Letter Addressee
(0 selected)
Revision
File Document No Revision Title Status
Date
https://ksa1.aconex.com/hub/index.html 1/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 89 of 95
1/12/23, 2:27 PM Aconex
Revision
File Document No Revision Title Status
Date
MESSAGE
Dear Sir,
Greetings,
Please see attached file WO 58- Quality Toolbox meeting No.001 & 002
Regards
Romejun
https://ksa1.aconex.com/hub/index.html 2/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 90 of 95
1/12/23, 2:27 PM Aconex
100201DCC MAH WO 58- Quality Toolbox meeting No.001 & 002 2:26 PM
MOFARREH ALHARBI AND PARTNERS TRANSMITTAL MAH-TRANSMIT-004366
Status N/A
DETAILS
Letter Initiator
Letter Addressee
(0 selected)
Revision
File Document No Revision Title Status
Date
https://ksa1.aconex.com/hub/index.html 1/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 91 of 95
1/12/23, 2:27 PM Aconex
Revision
File Document No Revision Title Status
Date
MESSAGE
Dear Sir,
Greetings,
Please see attached file WO 58- Quality Toolbox meeting No.001 & 002
Regards
Romejun
https://ksa1.aconex.com/hub/index.html 2/2
10-603173-0000100201-MAH-QMN-RPT-000001_01 92 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01 Document No.:
Attachment 13
Refer Attachment 12
10-603173-0000100201-MAH-QMN-RPT-000001_01 93 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01 Document No.:
Attachment 14
10-603173-0000100201-MAH-QMN-RPT-000001_01 94 of 95
MOFARREH
NEOM ALHARBI &
PARTNERS
Document Type: Management Review # 01 Document No.:
Attachment 15
10-603173-0000100201-MAH-QMN-RPT-000001_01 95 of 95