Aluminium Dome Roof Installation
Aluminium Dome Roof Installation
Aluminium Dome Roof Installation
Each worker shall complete the necessary general and site-specific safety
orientations required for the particular facility in which the dome will be
installed.
1. All necessary work permits, job hazard analysis (JHA) or job safety
the project.
includes hard hats, safety glasses, cut resistant gloves, fire retardant
clothing as required, safety toe footwear, long sleeved shirts and long
protection.
resistant footwear.
precautions.
an emergency.
8. If a wind girder is present and will be used for access during dome
start-up of the project. High winds may cause the dome to sway
Floating Roof
support brackets, etc.) that would impede the vertical path of the
3. If a door sheet is not present, all panels will need to be lifted and set
inside tank.
operate crane.
6. Allow enough daylight hours to perform the lift and set of dome.
mechanism.
engineering.
and tank.
Checklist
understood.
tank.
Lifting Methods
• Verify tank shell and wind girder can support loads imposed during
lift.
1. Mark the davit locations at the top of the tank and windgirder per the
3. Lower lifting device rigging down to tension ring hubs. Attach rigging
at each hub. Ensure the rigging is looped around both the upper and
4. One at a time take the slack out of the rigging with lifting device and
structure.
necessary.
6. With a minimum of one (1) person at each lifting point, begin to raise
dome is level throughout the lift. Stopping at the top of each shell
8. Raise the dome until it is sufficiently above the tank shell to install
Illustration 7-3).
10. Once the lifting devices/davits have been removed, the remaining
Lift or set the dome to a sufficient height above the tank and install support
pedestals. Ensure that dome is properly orientated with the tank. The dome
may be rotated at this time to ensure proper alignment with the tank. When
performing a crane lifting from inside the tank, support beams will need to
be installed after lifting dome above the tank and prior to attaching mounting
welded/bolted to tank and attached to support beams, the crane rigging can
be released.
drawings.
• If lifting dome from outside of the tank, support beams and slide
pods :
2. The floating roof must be at highest possible position when using this
method.
3. Using quad-pods/tri-pods, lift the dome uniformly and level until the
components.